PLAN SEMANAL LOOKAHEAD Nro 01

Desde el 09 dic @ 04 mar

L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J ANÁLISIS RESTRICCIONES

ITEM PARTIDAS UND.

10-Feb

11-Feb

12-Feb

13-Feb

14-Feb

15-Feb

16-Feb

17-Feb

18-Feb

19-Feb

20-Feb

21-Feb

22-Feb

23-Feb

24-Feb

25-Feb

26-Feb

27-Feb

28-Feb

29-Feb

10-Mar

11-Mar

12-Mar

13-Mar

14-Mar

15-Mar

16-Mar

17-Mar

18-Mar

19-Mar

20-Mar

21-Mar

22-Mar

23-Mar

24-Mar

25-Mar

26-Mar

27-Mar

28-Mar

29-Mar

30-Mar

31-Mar
27-Jan

28-Jan

29-Jan

30-Jan

31-Jan

10-Apr

11-Apr

12-Apr

13-Apr

14-Apr

15-Apr

16-Apr
Fecha

1-Feb

2-Feb

3-Feb

4-Feb

5-Feb

6-Feb

7-Feb

8-Feb

9-Feb

1-Mar

2-Mar

3-Mar

4-Mar

5-Mar

6-Mar

7-Mar

8-Mar

9-Mar

1-Apr

2-Apr

3-Apr

4-Apr

5-Apr

6-Apr

7-Apr

8-Apr

9-Apr
Restricción Responsable
Levantamiento

OBRAS PRELIMINARES GLB.


INSTALACIÓN DE CAMPAMENTOS DEL PROYECTO (ALMACÉN, OFICINA DE CAMPO,
GLB. X
VESTIDORES)

INSTALACIÓN DE ZAI TEMPORAL, SEÑALIZACIÓN DE ZONAS PEATONALES,


GLB. X X
ESTACIONAMIENTO DE MAQUINARIA DEL PROYECTO, BAÑOS QUÍMICOS, LAVAMANOS

ATERRAMIENTO DE INSTALACIONES DE CAMPAMENTO GLB. X


EJECUCIÓN DE CALICATAS EN ZONAS DE REUBICACIÓN PAT 01 Y PAT 02 GLB. X X X
TRAZO Y REPLANTEO DE LAS ZONAS DE EXCAVACIÓN DONDE SE INSTALARÁN LOS
GLB. X X X X
PAT 01 Y 02
1.00 PAT 01 GLB.
1.01 EXCAVACIÓN PARA CIMENTACIÓN M3 X X X X X X X
1.02 HABILITACIÓN ACERO, ENCOFRADO Y CONCRETO EN LOSAS M3 X X X X X X X X X X X X X X
1.03 SUMINISTRO E INSTALACIÓN DE GROUT LT. X
1.04 DESMONTAJE DE COBERTURA DE TECHO M2 X X X X X X X X
1.05 DESMONTAJE DE ESTRUCTURA Y COBERTURA DE PARED M2 X X X X X X X X

1.06 DESMONTAJE DE ESTRUCTURAS METÁLICAS (COLUMNAS Y TIJERALES) GLB. X X X X X X X X

1.07 REINSTALACIÓN DE ESTRUCTURAS METÁLICAS GLB. X X X X


1.08 REINSTALACIÓN DE COBERTURA DE TECHO M2 X X X X X X
1.09 REINSTALACIÓN DE ESTRUCTURA Y COBERTURA DE PARED M2 X X X X X X
1.10 PINTURA TRÁFICO EN PISO DE CONCRETO M2 X X X X X
1.11 REUBICACIÓN DE LETREROS EXISTENTES UND. X X
1.12 DEMOLICIÓN DE LOSA Y CIMENTACIÓN DE CONCRETO M3 X X X X X X
2.00 PAT 02 GLB.
2.01 EXCAVACIÓN PARA CIMENTACIÓN M3 X X X X X X X
2.02 SUMINISTRO E INSTALACIÓN DE GEOMEMBRANA M2 X X X
2.03 HABILITACIÓN ACERO, ENCOFRADO Y CONCRETO EN LOSAS M3 X X X X X X X X X X X X X X
2.04 SUMINISTRO E INSTALACIÓN DE GROUT LT. X
2.05 DESMONTAJE DE COBERTURA DE TECHO Y PARED M2 X X X X X X X X X X X

2.06 DESMONTAJE DE ESTRUCTURAS METÁLICAS (COLUMNAS Y TIJERALES) GLB. X X X X X X X X X X X

2.07 REINSTALACIÓN DE ESTRUCTURAS METÁLICAS GLB. X X X X X X


2.08 REINSTALACIÓN DE COBERTURA DE TECHO Y PARED M2 X X X X X
2.09 PINTURA TRÁFICO EN PISO DE CONCRETO M2 X X X X X X
2.10 DEMOLICIÓN DE LOSA Y CIMENTACIÓN DE CONCRETO M3 X X X X
2.11 ELIMINACIÓN Y DISPOSICIÓN FINAL DE COBERTURAS DE ASBESTO M2 X X
2.12 REINSTALACIÓN DE TECHO TRANSLÚCIDA M2 X X X X X
3.00 PAT 01 SIN TECHAR GLB.
3.01 EXCAVACIÓN PARA CIMENTACIÓN M3
3.02 HABILITACIÓN ACERO, ENCOFRADO Y CONCRETO EN LOSAS M3 X X X X X X X X X X X X X X
3.03 DESMONTAJE DE CERCO PERIMÉTRICO M2 X X X
3.04 REINSTALACIÓN DE CERCO PERIMÉTRICO M2 X X X X X
3.05 PINTURA DE TRÁFICO EN SARDINEL M2 X X
3.06 DEMOLICIÓN DE SARDINEL Y CIMENTACIÓN DE CONCRETO M3 X X
4.00 ELIMINACIÓN DE INDIVIDUOS EXISTENTES GLB.
4.01 LIMONEROS UND. X X X X X
4.02 GRANADA UND. X X X X X
4.03 TAMARIZ UND. X X X X X
5.00 PLANTACIÓN DE NUEVOS INDIVIDUOS GLB.
5.01 OLIVOS UND. X X X X X X X X X X X X X X X X X X
5.02 PINOS UND. X X X X X X X X X X X X X X X X X X
5.03 PALMERAS UND. X X X X X X X X X X X X X X X X X X
5.04 MONITOREO DE INDIVIDUOS PLANTADOS Y TRANSPLANTADOS UND. X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X
6.00 RIEGO TECNIFICADO GLB.
6.01 RETIRO Y REUBICACIÓN DE RIEGO TECNIFICADO UND. X X X X X X X X
6.02 INSTALACIÓN DE NUEVA LÍNEA DE RIEGO TECNIFICADO UND. X X X X X X X X X X X X X X

Informar avance y/o cumplimiento los todos los viernes