VALORIZACIÓN EVALUACIÓN DE SECTORES CRÍTICOS EN LOS PAVIMENTOS DE PLATAFORMA LADO ALFA DEL AEROPUERTO INTERNACIONAL CAPITÁN FAP DAVID ABENZUR RENGIFO – PUCALLPA
PRESUPUESTO BASE AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMUL. SALDO
% AVANCE % AVANCE % POR
ITEM DESCRIPCION UND
MET. P. UNIT. P. TOTAL MET. MONTO S/. % MET. MONTO S/ ACTUAL MET. MONTO S/. ACUMUL. MET. MONTO VAL.

EVALUACIÓN DE SECTORES CRITICOS EN LOS PAVIMENTOS DE


PLATAFORMA LADO ALFA
OBRAS PRELIMINARES
MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPOS glb 1.00 7518.19 7518.19 0.33 2481.00 0.50 3759.10 50.00% 0.83 6240.10 83.00% 0.17 1278.09 17.00%
TRAZO Y REPLANTEO m2 640.00 0.53 339.20 211.20 111.94 320.00 169.60 50.00% 531.20 281.54 83.00% 108.80 57.66 17.00%
PARCHADO CON LOSA DE CONCRETO HIDRAULICO
REMOCION DE CARPETA ASFALTICA EXISTENTE m3 83.20 67.61 5625.15 27.46 1856.30 41.60 2812.58 50.00% 69.06 4668.88 83.00% 14.14 956.01 17.00%
EXCAVACIÓN DE MATERIAL GRANULAR m3 416.00 14.94 6215.04 137.28 2050.96 208.00 3107.52 50.00% 345.28 5158.48 83.00% 70.72 1056.56 17.00%
COMPACTACIÓN DE SUBRASANTE m2 640.00 4.32 2764.80 211.20 912.38 320.00 1382.40 50.00% 531.20 2294.78 83.00% 108.80 470.02 17.00%
MATERIAL GRANULAR m3 192.00 178.78 34325.76 63.36 11327.50 96.00 17162.88 50.00% 159.36 28490.38 83.00% 32.64 5835.38 17.00%
BASE GRANULAR m3 96.00 178.78 17162.88 31.68 5663.75 48.00 8581.44 50.00% 79.68 14245.19 83.00% 16.32 2917.69 17.00%
LOSA DE CONCRETO HIDRÁULICO F'C=350 KG/CM2 m3 211.00 969.03 204465.33 69.63 67473.56 105.50 102232.67 50.00% 175.13 169706.23 83.00% 35.87 34759.11 17.00%
JUNTA DE CONTRACCIÓN m 151.00 65.45 9882.95 49.83 3261.37 75.50 4941.48 50.00% 125.33 8202.85 83.00% 25.67 1680.10 17.00%
JUNTA DE AISLAMIENTO m 124.00 52.12 6462.88 40.92 2132.75 62.00 3231.44 50.00% 102.92 5364.19 83.00% 21.08 1098.69 17.00%
JUNTA DE CONTRACCIÓN (INSERCIÓN DE DOWELL) m 131.00 56.90 7453.90 43.23 2459.79 65.50 3726.95 50.00% 108.73 6186.74 83.00% 22.27 1267.16 17.00%
TRANSPORTE
TRANSPORTE DE MATERIAL GRANULAR D<= 1KM m3-km 253.44 10.02 2,539.47 83.64 838.02 126.72 1269.73 50.00% 210.36 2107.75 83.00% 43.08 431.66 17.00%
TRANSPORTE DE MATERIAL GRANULAR D> 1KM m3-km 3147.84 2.02 6,358.64 1038.79 2098.35 1573.92 3179.32 50.00% 2612.71 5277.67 83.00% 535.13 1080.96 17.00%
TRANSPORTE DE EXCEDENTES A DME PARA D<= 1KM m3-km 58.24 10.41 606.28 19.22 200.07 29.12 303.14 50.00% 48.34 503.21 83.00% 9.90 103.06 17.00%
TRANSPORTE DE EXCEDENTES (CARPETA ASFÁLTICA) A DME PARA D< m3-km 11.65 10.41 121.28 3.84 40.02 5.83 60.64 50.00% 9.67 100.66 83.00% 1.98 20.61 17.00%
COSTO
1KMDIRECTO 311,841.74 102,907.76 155,920.89 258,828.65 53,013.09
GASTOS GENERALES 8.00% 24,947.34 8,232.62 12,473.67 20,706.29 4,241.05
UTILIDAD 7.00% 21,828.92 7,203.54 10,914.46 18,118.01 3,710.91
SUB TOTAL 358,618.00 118,343.92 179,309.02 297,652.95 60,965.05
1.0000 358,618.00 118,343.92 179,309.02 297,652.95 60,965.05
IMPUESTO (IGV) 18.00% 64,551.24 21,301.91 32,275.62 53,577.53 10,973.71
TOTAL PRESUPUESTO CONTRATADO 423,169.24 139,645.83 211,584.64 351,230.48 71,938.76
PORCENTAJE DE AVANCE (%) 100.00% 33.00% 50.00% 83.00% 17.00%
ABRIL JUNIO
MONOMIO DESCRIPCIÓN SIMBOLO I.U. C.I. % Io Ir K
MANO DE OBRA 47 72.15 600.4 600.4
0.241
1 GAS MG 53 0.24 27.85 825.22 838.47
MINICARGADOR 70HP 49 48.3 309.08 311.91
SELLANTE ELASTICO POLIUTERANO MS 13 34.2 1792.19 1792.19 0.105
2 SELLADOR DE FISURAS 30 0.105 17.5 489.59 496.36
3 LOSA DE CONCRETO L 21 0.509 100 449.56 449.56 0.509
4 INDICE GENERAL DE PRECIOS AL CONSUMIDOR I 39 0.145 100 457.08 457.36 0.145
1.001

REINTEGRO
132.7922358
CUADRO RESUMEN DE REAJUSTE- LADO ALFA
MONTO CONTRATADO SIN VALORIZACIÓN % DE AVANCE
DESCRIPCIÓN IGV ANTERIOR S/. ACTUAL S/. ACUMULADO S/. ACUMULADO SALDO POR VALORIZAR
179309.02
VALORIZACIÓN (V)

TOTAL CONTRACTUAL
Avances en Porcentajes

132.79
REAJUSTES

DEDUCCIONES(R) 0
POR ADELANTO DIRECTO POR
ADELANTO DE MATERIALES

TOTAL DE DEDUCCIONES 0

VALORIZACIÓN BRUTA(VB=V-R-D) 179176.23

AMORTIZACIONES(A) 0
AMORTIZACIÓN POR ADELANTO DIRECTO
AMORTIZACIÓN POR ADELANTO DE MATERIALES

TOTAL AMORTIZACIONES(A) 0

VALORIZACIÓN NETA(VN=VB-A) 179176.23

RETENCIONES(R)
FONDOS DE GARANTÍA(5% x VB) 0
GASTOS DE LICITACIÓN
MULTA POR ATRASO DE OBRA
TOTAL

MONTO A PAGAR AL CONTRATISTA


EN EFECTIVO (VN-C) 179176.23
MONTO POR IGV (VN x 0.18) 32251.721
MONTO TOTAL CON IGV 211427.95