CRONOGRAMA VALORIZADO

OBRA: "CREACION DEL SERVICIO DE PROTECCION DEL RIO LACRAMARCA VULNERABLE ANTE EL PELIGRO, EN EL SECTOR

ITEM PARTIDAS UNIDAD METRADO PRECIO

1.00 OBRAS PROVISIONALES


1.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 4.80 X 3.60 und 2.00 1,286.79
1.02 ALMACEN DE OBRA (ALQUILER) MES 3.00 550.00
1.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPO, MAQU GLB 1.00 66,320.00
1.04 TRAZO NIVELACION Y REPLANTEO DE OBRA KM 1.00 1,592.61
1.05 CONTROL, TRAZO Y REPLANTEO TOPOGRAFICO DURANTEDIA 90.00 319.83
1.06 CAMINO DE ACCESO TROCHA KM 5.00 6,387.46
1.07 CAMINO DE ACCESO MEJORAMIENTO CANTERA KM 6.00 5,589.95
1.08 DESVIO DE RIO M3 1,200.00 4.34
1.09 GUARDIANIA DE OBRA MES 3.00 6,500.00
2.00 SEGURIDAD Y SALUD
2.01 ELABORACION E IMPLEMENTACION DEL PLAN DE SEGURIUND 1.00 5,000.00
2.02 EQUIPOS DE PROTECCION INDIVIDUAL GLB 1.00 7,020.00
2.03 EQUIPOS DE PROTECCION COLECTIVA GLB 1.00 2,050.00
2.04 SEÑALIZACION TEMPORAL EN OBRA UND 6.00 2,080.00
2.05 CAPACITACION EN SEGURIDAD Y SALUD UND 2.00 5,205.00
3.00 MOVIMIENTO DE TIERRAS
3.01 CORTE CE CAUCE Y BORDOS EXISTENTES M3 81,900.00 3.87
3.02 EXCAVACION DE UÑA M3 24,167.50 4.84
3.03 CONFORMACION DE TERRAPLENES M3 60,625.36 5.39
3.04 PERFILADO DE TALUD PARA DIQUE M2 10,114.16 3.51
3.05 ACABADO DE CORONA CON MATERIAL DE PRESTAMO M3 2,160.00 35.71
3.06 ELIMINACION DE MATERIAL EXCEDENTE M3 97,480.33 16.22
4.00 ENROCADO
4.01 EXTRACCION Y PREPARACION DE ROCA M3 31,546.36 49.91
4.02 SELECCION Y ACOPIO DE ROCA M3 31,546.36 13.45
4.03 TRANSPORTE DE ROCA M3 31,546.36 19.24
4.04 ACOMODO DE ROCA EN TALUD M3 10,984.86 16.73
4.05 ACOMODO DE ROCA EN UÑA M3 20,561.50 13.98
4.06 GEOTEXTIL NO TEJIDO 300 GR/M2 M2 18,044.88 6.13
6.00 MITIGACION DE IMPACTO AMBIENTAL
6.01 PLAN DE MANEJO AMBIENTAL GLB 1.00 30,000.00

COSTO DIRECTO
GASTOS GENERALES (10%)
UTILDADES (10%)
SUB TOTAL
IGV (18%)
SUB TOTAL S/.
AVANCE MENSUAL (%)
RONOGRAMA VALORIZADO DE OBRA

ANTE EL PELIGRO, EN EL SECTOR CURVA EL MILAGRO - DISTRITO DE CHIMBOTE - PROVINCIA DEL SANTA - ANCASH"

1 MES 2DO MES 3 MES


PRESUPUESTO( S/
METRADO MONTO (S/.) METRADO MONTO (S/.) METRADO MONTO (S/.)
191,105.89 71,157.71 70,143.28 49,804.90
2,573.58 2.00 2,573.58 - - -
1,650.00 1.00 550.00 1.00 550.00 1.00 550.00
66,320.00 0.20 13,264.00 0.30 19,896.00 0.50 33,160.00
1,592.61 1.00 1,592.61 - - -
28,784.70 30.00 9,594.90 30.00 9,594.90 30.00 9,594.90
31,937.30 3.00 19,162.38 2.00 12,774.92 - -
33,539.70 3.00 16,769.85 3.00 16,769.85 - -
5,208.00 265.066 1,150.39 934.93 4,057.61 - -
19,500.00 1.00 6,500.00 1.00 6,500.00 1.00 6,500.00
36,960.00 22,005.00 12,875.00 2,080.00
5,000.00 1.00 5,000.00 - - -
7,020.00 1.00 7,020.00 - - -
2,050.00 1.00 2,050.00 - - -
12,480.00 2.00 4,160.00 3.69 7,670.00 0.31 650.00
10,410.00 0.73 3,775.00 1.00 5,205.00 0.27 1,430.00
2,454,459.64 632,694.64 910,882.49 910,882.52
316,953.00 28,091.05 108,712.35 53,808.95 208,240.65 - -
116,970.70 - 24,167.50 116,970.70 - -
326,770.69 - - 60,625.36 326,770.69
35,500.70 - - 10,114.16 35,500.70
77,133.60 - - 2,160.00 77,133.60
1,581,130.95 32,304.70 523,982.29 36,107.96 585,671.14 29,067.67 471,477.53
3,187,570.93 868,576.45 1,159,497.24 1,159,497.24
1,574,478.83 17,402.85 868,576.45 14,143.51 705,902.38 - 0.00
424,298.54 - 31,546.36 424,298.54 - -0.00
606,951.97 - 1,522.68 29,296.32 30,023.68 577,655.65
183,776.71 - - 10,984.86 183,776.71
287,449.77 - - 20,561.50 287,449.77
110,615.11 - - 18,044.88 110,615.11
30,000.00 15,000.00 9,000.00 6,000.00
30,000.00 0.50 15,000.00 0.30 9,000.00 0.20 6,000.00
1,609,433.79 2,162,398.01 2,128,264.66
5,900,096.46 1,609,433.79 2,162,398.01 2,128,264.63
590,009.65 160,943.38 216,239.80 212,826.46
590,009.65 160,943.38 216,239.80 212,826.46
7,080,115.76 1,931,320.55 2,594,877.62 2,553,917.55
1,274,420.84 347,637.70 467,077.97 459,705.16
8,354,536.59 2,278,958.25 3,061,955.59 3,013,622.72
27.28 36.65 36.07
TA - ANCASH"

TOTAL

191,105.89

36,960.00

2,454,459.64

3,187,570.93

30,000.00

5,900,096.46
590,009.65
590,009.65
7,080,115.76
1,274,420.84
8,354,536.59
100.00