Documentos de Académico
Documentos de Profesional
Documentos de Cultura
PRESUPUESTO MODIFICADO POR ADICIONALES DE OBRA POR MAYORES METRADOS, PARTIDAS NUEVAS Y DEDUCTIVOS DEL PROYECTO: "CREACION DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE BOLOGNESI DEL CC.PP. URBANO DE LIVITACA - DITRTITO DE LIVITACA - CHUMBIVILCAS - CUSCO"
PRESUPUESTO MODIFICADO APROBADO N° PRESUPUESTO MODIFICADO APROBADO N° PRESUPUESTO MODIFICADO APROBADO N° PRESUPUESTO POR MAYOR PRESUPUESTO MODIFICADO SOLICITADO
PRESUPUESTO PROGRAMADO PRESUPUESTO POR BAJO RENDIMIENTO PRESUPUESTO POR DEDUCTIVOS
ITEM DESCRIPCION DE PARTIDA UND 01 02 03 METRADO N° 04
Metrado Precio S/. Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Precio S/. Parcial S/. Metrado Parcial S/. Metrado Parcial S/.
1 COMPONENTE 01: INFRAESTRUCTURA VEHICULAR 630,913.24 690,238.95 699,342.76 699,342.76 - 55,256.41 - 754,599.12
1.1 OBRAS PROVISIONALES 3,008.01 3,008.01 3,008.01 3,008.01 3,008.01
1.2 TRABAJOS PRELIMINARES 15,052.98 15,052.98 - 15,052.98 - 15,052.98 - 15,052.98
1.3 SEGURIDAD Y SALUD 3,103.60 3,103.60 - 6,103.60 - 6,103.60 - - 6,103.60
1.4 MOVIMIENTO DE TIERRAS 127,479.29 163,816.83 - 163,816.85 - 163,816.85 - - 163,816.83
1.5 PAVIMENTO RIGIDO 356,031.61 306,432.33 - 307,231.46 - 307,231.46 - 37,047.28 - - 344,278.74
1.6 ENCIMADO DE BUZON 5,063.80 6,599.29 6,599.29 6,599.29 - 6,599.29
1.7 INFRAESTRUCTURA DE EVACUACION DE AGUAS FLUVIALES 58,655.83 82,483.65 83,348.30 83,348.30 - 7,843.77 - - 91,192.06
1.8 REPOSICION DE REDES MATRICES DE AGUA Y DESAGUE 26,821.80 55,860.40 - 55,860.39 - 55,860.39 - 10,365.36 - - 66,225.74
1.9 SEÑALIZACION 2,548.91 20,734.45 - 20,734.45 - 20,734.45 - - - - 20,734.45
1.1 PRUEBAS DE CONTROL DE CALIDAD 2,376.80 2,376.80 - 6,816.80 - 6,816.80 - - - 6,816.80
1.11 MITIGACION DE IMPACTO AMBIENTAL 30,770.61 30,770.61 30,770.62 30,770.62 - 30,770.61
2 COMPONENTE 02: INFRAESTRUCTURA PEATONAL 131,424.90 159,425.03 293,370.04 293,370.04 - 55,218.35 - 348,588.40
2.1 SARDINELES 38,628.94 38,628.94 38,628.94 38,628.94 4,765.51 - 43,394.44
2.2 VEREDAS 92,795.96 106,894.40 117,174.78 117,174.78 - 33,285.16 - 150,459.94
2.3 MURO DE CONCRETO CICLOPEO 13,901.69 - 120,312.88 - 120,312.88 17,167.68 - 137,480.57
2.4 BARANDA METALICA 17,253.44 17,253.44 - - 17,253.45
3 COMPONENTE O3:AREAS VERDES Y VARIOS 18,362.70 18,362.70 40,862.70 58,658.70 - - 58,658.70
3.1 AREAS VERDES 13,198.46 13,198.46 13,198.46 13,198.46 - 13,198.46
3.2 VARIOS 5,164.24 5,164.24 - 27,664.24 - 45,460.24 - - 45,460.24
COSTO TOTAL S/. 939,938.99 S/. 1,079,344.82 S/. 1,327,185.13 S/. 1,356,906.13 S/. 1,549,362.32
INCREMENTO DEL EXPEDIENTE MODIFICADO CON REFERENCIA AL EXPEDIENTE TECNICO S/. 470,017.49
INCREMENTO DEL EXPEDIENTE MODIFICADO CON REFERENCIA AL EXPEDIENTE TECNICO % 50.01%