CRONOGRAMA VALORIZADO DE OBRA

PROYECTO
: MEJORAMIENTO DE LA OFERTA DE SERVICIOS EDUCATIVOS EN LA I.E N°88128 ALFONSO UGARTE DEL CENTRO POBLADO DE CALPOC, DISTRITO DE
YAUTAN, PROVINCIA DE CASMA ANCASH
UBICACIÓN : Distrito: YAUTAN, Provincia: CASMA, Departamento : ANCASH
FECHA : ABRIL 2013

210 DIAS CALENDARIOS


ITEM DESCRIPCION PARCIAL
1° MES 2° MES 3° MES 4° MES 5° MES 6° MES 7° MES

01.00.00 TRABAJOS PRELIMINARES 116,136.30 116,136.30 232,272.60###


02.00.00 ESTRUCTURAS 357,976.36 357,976.36 357,976.36 357,976.36 357,976.36 357,976.36 2,147,858.16###
03.00.00 ARQUITECTURA 141,717.14 141,717.14 141,717.14 141,717.14 141,717.14 141,717.14 850,302.86###
04.00.00 INSTALACIONES ELECTRICAS 49,445.16 49,445.16 49,445.16 148,335.47###
05.00.00 INSTALACIONES SANITARIAS 19,252.69 19,252.69 19,252.69 57,758.06###
06.00.00 PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES 49,389.49 49,389.49 98,778.98###
07.00.00 FLETE 40,000.00 40,000.00 ###
80,000.00

COSTO DIRECTO 563502.15 675082.49 598528.15 518946.19 499693.50 549138.66 ###


210415.00 3,615,306.13

GASTOS GENERALES (7.34%) 41382.34 49576.55 43954.57 38110.25 36696.37 40327.51 15452.41 ###
265499.98
UTILIDADES (10%) 56350.22 67508.25 59852.82 51894.62 49969.35 54913.87 21041.50 ###
361,530.61
SUB TOTAL 661234.70 792167.28 702335.53 608951.05 586359.23 644380.04 ###
246908.90 4,242,336.73
I.G.V. (18%) 119,022.25 142,590.11 126,420.40 109,611.19 105,544.66 115,988.41 44,443.60 ###
763,620.61

TOTAL PRESUPUESTO 780,256.95 934,757.40 828,755.93 718,562.24 691,903.89 760,368.45 291,352.50 5,005,957.33###
CRONOGRAMA DE AVANCE FISICO EN OBRA

PROYECTO : MEJORAMIENTO DE LA OFERTA DE SERVICIOS EDUCATIVOS EN LA I.E N°88128 ALFONSO UGARTE DEL CENTRO POBLADO DE CALPOC, DISTRITO DE YAUTAN, PROVINCIA DE CASMA ANCASH
UBICACIÓN : Distrito: YAUTAN, Provincia: CASMA, Departamento : ANCASH
FECHA : ABRIL 2013

180 Dias Calendarios


ITEM DESCRIPCION
1° MES 2° MES 3º MES 4º MES 5º MES 6º MES 7º MES
01.00.00 TRABAJOS PRELIMINARES
02.00.00 ESTRUCTURAS
03.00.00 ARQUITECTURA
04.00.00 INSTALACIONES ELECTRICAS
05.00.00 INSTALACIONES SANITARIAS
06.00.00 PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES
07.00.00 FLETE
120 DIAS CALENDARIOS
ITEM DESCRIPCION
1° MES 2° MES 3° MES 4° MES
01.00.00 OBRAS PROVISIONALES. 11,750.00
02.00.00 OBRAS PRELIMINARES. 37,960.39
03.00.00 MOVIMIENTO DE TIERRAS.
03.01.00 EXCAVACION DE ZANJA 37,887.68 63,146.14 63,146.14 63,146.14
03.02.00 NIVELACION Y REFINE 910.52 1,517.53 1,517.53 1,517.53
03.03.00 CONFORMACION DE CAMA DE APOY 794.19 1,323.66 1,323.66 1,323.66
03.04.00 RELLENO DE ZANJA. 43,386.50 72,310.84 72,310.84 72,310.84
03.05.00 ELIMINACION DE MATERIAL EXEDENTE. 811.41 811.41 1,217.12
04.00.00 TUBERIAS.
04.01.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 13,110.77 32,776.93 32,776.93 32,776.93
04.01.02 SUMINISTRO E INSTALACION DE TUBERIA PVC ISO4435 DN315MM S-20 1,043.89 1,391.85
04.01.03 SUMINISTRO E INSTALACION DE TUBERIA PVC ISO4435 DN4 9,203.03 13,804.55 13,804.55
04.02.01 ALINEAMIENTO Y AJUSTE DE TUBERIA PVC ISO 164.81 412.02 412.02 412.02
04.02.02 ALINEAMIENTO Y AJUSTE DE TUBERIA PVC ISO 234.45 586.12 586.12 586.12
04.02.03 ALINEAMIENTO Y AJUSTE DE TUBERIA PVC ISO 4435 DN 315 MM 11.20 14.93
04.02.04 ALINEAMIENTO Y AJUSTE DE TUBERIA PVC ISO 4435 DN 400 80.87 121.31 121.31
04.03.01 DESVIO DE AGUAS SERVIDAS HASTA Q=60L/S 1,791.33 2,985.56 2,388.44 2,985.56
05.00.00 CAMARAS DE INSPECCION
05.01.01 ENCOFRADO Y DESENCOFRADO P/C 6,389.72 15,974.31 15,974.31 15,974.31
05.02.01 CONCRETO F'C = 140 Kg/cm² P/MEDI 490.24 1,225.59 1,225.59 1,225.59
05.02.02 CONCRETO F'C = 175 Kg/cm² P/CAM 3,867.42 9,668.54 9,668.54 9,668.54
05.02.03 CONCRETO F'C = 210 Kg/cm² P/ T 818.03 2,045.07 2,045.07 2,045.07
05.03.01 ACERO DE REFUERZO F'Y=4200 P/C 3,878.78 9,696.95 9,696.95 9,696.95
05.04.01 SUMINISTRO DE MARCO DE F°F° Y T 3,082.26 7,705.66 7,705.66 7,705.66
05.05.01 ENCOFRADO Y DESENCOFRADO DE DADOS DE 441.18 661.77 661.77
05.05.02 CONCRETO F'C = 140 Kg/cm² P/DADOS DE EMPA 777.65 1,166.47 1,166.47
06.00.00 CONEXIONES DOMICILIARIAS.
06.01.0 CONEXION DOMICILIARIA DN 160MM ISO4435 S-20 A TUBERI 46,598.80 77,664.67 31,065.87
07.00.00 PRUEBA HIDRAULICA 3,016.41 3,016.41 2,585.50
08.00.00 ROTURA Y REPOSICION DE PAVIME ### ### ### ###
09.00.00 ROTURA Y REPOSICION DE VEREDA 3,250.10 4,333.47 4,333.47 4,333.47
COSTO DIRECTO 285344.56 440740.88 477516.09 431840.89
GASTOS GENERALES (15%) 42801.68 66111.13 71627.41 64776.13
UTILIDADES (10%) 28534.46 44074.09 47751.61 43184.09
SUB TOTAL 356680.70 550926.10 596895.12 539801.11
I.G.V. (19%) 67,769.33 ### ### ###
TOTAL PRESUPUESTO ### ### ### ###
ARIOS
PARCIAL
5° MES
11,750.00
37,960.39

25,258.46 ###
607.01 6,070.10
529.46 5,294.63
28,924.34 ###
1,217.12 4,057.06

19,666.16 ###
1,043.89 3,479.62
9,203.03 46,015.17
247.21 1,648.08
351.67 2,344.48
11.20 37.34
80.87 404.37
1,791.33 11,942.22

9,584.59 63,897.24
735.35 4,902.35
5,801.12 38,674.15
1,227.04 8,180.27
5,818.17 38,787.80
4,623.40 30,822.64
441.18 2,205.90
777.65 3,888.24

###
8,618.32
### ###
5,416.84 21,667.34
315986.04 ###
47397.91 ###
31598.60 ###
394982.55 ###
75,046.69 ###
### ###
PROGRAMACION DE PROYECTOS
VIVIENDA 3 PISOS , 200 M2

DURACION(DIAS)
ARQUITECTURA 15
ESTRUCTURAS 25
INSTALACIONES ELECTRICAS 10
INSTALACIONES SANITARIAS 12
62
RECURSOS
MANO OBRA
MATERIALES CONTROL Y SEGUIMIENTO DEL PROYECTO
EQUIPOS

DURACION(DIAS)
ARQUITECTURA 15
ESTRUCTURAS
INSTALACIONES ELECTRICAS
INSTALACIONES SANITARIAS
INICIO DE TRABAJ FINAL DE ENTREGACOSTOS
8/8/2020 8/9/2020 S/ 2,000.00
S/ 5,000.00
S/ 3,000.00
S/ 2,500.00
###

INICIO DE TRABAJ FINAL DE ENTREGACOSTOS


26 9