Fecha: 12/1/2018
Hecho por: Molina Masias, Nataly Patricia ARQUITECTURA
ELEMENTO ABERTURAS O DESCUENTOS
UBICACIÓN UNIDAD TOTAL
Cantidad Long. Alto Ancho Subtotal Cantidad Clase Long. Ancho Alto Subtotal
OE.1 OBRAS PROVICIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD.
OE.3 ARQUITECTURA
OE.3.1 MUROS Y TABIQUES DE ALBAÑILERIA
OE.3.1.1 MUROS DE LADRILLO CORRIENTE DE ARCILLA-CABEZA m2 29.70
PRIMER NIVEL
EJE C-C
ENTRE 1-2 1 1.2500 2.4000
ENTRE 2-3 1 3.0000 2.4000 7.2000 m2 7.20
EJE 1-1
ENTRE C-B 1 4.5000 2.6000 11.7000 m2 11.70
EJE 3-3
ENTRE C-B 1 4.5000 2.4000 10.8000 m2 10.80
OE.3.1.2 MUROS DE LADRILLO CORRIENTE DE ARCILLA-SOGA m2 135.27
PRIMER NIVEL
EJE 1-1
ENTRE A-B 1 3.2100 2.4000 7.7040 m2 7.70
EJE 2-2
ENTRE A-B 1 3.2100 2.4500 7.8645 m2 7.86
ENTRE B-C 1 4.5000 2.6000 11.7000 m2 11.70
EJE 3-3
ENTRE A-B 1 2.8500 2.4000 6.8400 m2 6.84
SEGUNDO NIVEL
EJE A-A
ENTRE 2-3 1 3.0000 2.4300 7.2900 m2 7.29
EJE B-B 2.4300
ENTRE 1-2 2 4.2500 2.4300 20.6550 m2 20.66
EJE C-C
ENTRE 1-2 2 3.1500 2.4300 15.3090 m2 15.31
ENTRE 2-3 2 3.0000 2.4300 14.5800 m2 14.58
EJE 1-1
ENTRE A-B 1 3.2100 2.2300 7.1583 m2 7.16
ENTRE B-C 1 4.5000 2.2300 10.0350 m2 10.04
EJE 2-2
ENTRE B-C 1 4.0000 2.4300 9.7200 m2 9.72
EJE 3-3
ENTRE A-B 1 2.8600 2.2300 6.3778 m2 6.38
ENTRE B-C 1 4.5000 2.2300 10.0350 m2 10.04
TERCER NIVEL
EJE A-A
ENTRE 2-3 1 3.0000 2.6000 7.8000 m2 7.80
EJE B-B
ENTRE 1-2 2 3.1500 2.6000 16.3800 m2 16.38
ENTRE 2-3 3 3.0000 2.6000 23.4000 m2 23.40
EJE C-C
ENTRE 1-2 1 3.1500 2.6000 8.1900 m2 8.19
ENTRE 2-3 1 3.0000 2.6000 7.8000 m2 7.80
EJE 1-1
ENTRE A-B 1 0.8500 2.2000 1.8700 m2 1.87
ENTRE B-C 2 4.5000 2.2000 19.8000 m2 19.80
EJE 2-2
ENTRE B-C 1 4.5000 2.6000 11.7000 m2 11.70
EJE 3-3
ENTRE A-B 1 3.0000 2.2000 6.6000 m2 6.60
ENTRE B-C 1 4.5000 2.6000 11.7000 m2 11.70
OE.3.1.3 BARANDAS Y PARAPE 2.2000
BARANDAS m 3.50
BARANDA DE TOTAL 3.5000 m 3.50
BARANDA DE TOTAL 6.1200 m 6.12
BARANDA DE TOTAL 5.4000 m 5.40
PARAPETOS m2 6.66
TODO 1 7.4000 0.9000 6.6600 m2 6.66
SEGUNDO NIVEL
EJE A-A 2.6000
ENTRE 2-3 1 1.7800 2.6000 4.6280 m2 4.63
EJE C-C
ENTRE 1-2 1 1.7800 2.6000 4.6280 m2 4.63
EJE 1-1
ENTRE A-B 1 3.7500 2.6000 11.0625 m2 11.06
ENTRE B-C 1 2.2000 2.6000 6.4900 m2 6.49
EJE 3-3
ENTRE A-B 1 2.1000 2.6000 5.7750 m2 5.78
ENTRE B-C 1 1.8000 2.6000 4.9500 m2 4.95
TERCER NIVEL
EJE A-A
ENTRE 2-3 1 1.7800 2.6500 4.6280 m2 4.63
EJE C-C
ENTRE 1-2 1 4.5000 2.6500 4.6280 m2 4.63
ENTRE 2-3 1 3.0000 2.6500 4.6280 m2 4.63
EJE 1-1
ENTRE A-B 1 3.7500 2.6500 11.0625 m2 11.06
ENTRE B-C 1 2.2000 2.6500 6.4900 m2 6.49
EJE 3-3
ENTRE A-B 1 2.1000 2.6500 5.7750 m2 5.78
ENTRE B-C 1 1.8000 2.6500 4.9500 m2 4.95
OE.3.3 CIELORRASOS
OE.3.3.1 CIELORRASO CON YESO m2 173.44
PRIMER PISO
TODO 1 8.00 10.8400 86.7200 m2 86.72
SEGUNDO PISO
TODO 1 8.00 10.8400 86.7200 m2 86.72
TERCER PISO
TODO 1 8.00 10.8400 86.7200 m2 86.72
OE.3.4.2 PISOS
OE.3.4.2.2 MAYOLICA m2 10.66
SSHH 01 1.50 1.2 1.800 m2 5.52
SSHH 02 1.50 1.2 1.800 m2 3.57
SSHH 03 3.2 1.4 4.480 m2 1.58
COCINA 3.83 1.81 6.932 m2 6.93
LAVANDERIA 3.35 3.02 0.844 m2 0.84
OE.3.5.2 CONTRAZOCALOS
OE.3.5.2.1 CERAMICO m 5.52
COCINA 1 5.52 m 5.52
OE.3.8 CERRAJERIA
OE.3.8.1 BISAGRAS Pza. 18.00
1er NIVEL 10 0 pza 10.00
2do NIVEL 8 0 pza 8.00
3er NIVEL 4 4.00
OE.3.8.2 CERRADURAS unid 11.00
TOTAL 11 unid 11.00
OE.3.10 PINTURA
OE.3.10.1 PINTURA DE CIELOS RAZOS, VIGAS, COLUMNAS Y PAREDES m2 659.89
CIELOS RAZOS
PRIMER PISO
TODO 1 8.00 10.8400 86.7200 m2 86.72
SEGUNDO PISO
TODO 1 8.00 10.8400 86.7200 m2 86.72
TERCER PISO
TODO 1 8.00 10.8400 86.7200 m2 86.72
PAREDES INTERIORES
PRIMER NIVEL
EJE 1-1
ENTRE A-B 1 3.2100 2.4000 7.7040 m2 7.70
ENTRE C-B 1 4.5000 2.6000 11.7000 m2 11.70
EJE 2-2
ENTRE A-B 1 3.2100 2.4500 7.8645 m2 7.86
ENTRE B-C 1 4.5000 2.6000 11.7000 m2 11.70
EJE 3-3
ENTRE A-B 1 2.8500 2.4000 6.8400 m2 6.84
ENTRE C-B 1 4.5000 2.4500 11.0250 m2 11.03
EJE C-C
ENTRE 1-2 1 1.2500 2.4500 3.0625 m2 3.06
SEGUNDO NIVEL
EJE A-A
ENTRE 2-3 1 3.0000 2.4300 7.2900 m2 7.29
EJE B-B 2.4300
ENTRE 1-2 2 4.2500 2.4300 20.6550 m2 20.66
EJE C-C
ENTRE 1-2 2 3.1500 2.4300 15.3090 m2 15.31
ENTRE 2-3 2 3.0000 2.4300 14.5800 m2 14.58
EJE 1-1
ENTRE A-B 1 3.2100 2.2300 7.1583 m2 7.16
ENTRE B-C 1 4.5000 2.2300 10.0350 m2 10.04
EJE 2-2
ENTRE B-C 1 4.0000 2.4300 9.7200 m2 9.72
EJE 3-3
ENTRE A-B 1 2.8600 2.2300 6.3778 m2 6.38
ENTRE B-C 1 4.5000 2.2300 10.0350 m2 10.04
TERCER NIVEL
EJE A-A
ENTRE 2-3 1 3.0000 2.6000 7.8000 m2 7.80
EJE B-B
ENTRE 1-2 2 3.1500 2.6000 16.3800 m2 16.38
ENTRE 2-3 3 3.0000 2.6000 23.4000 m2 23.40
EJE C-C
ENTRE 1-2 1 3.1500 2.6000 8.1900 m2 8.19
ENTRE 2-3 1 3.0000 2.6000 7.8000 m2 7.80
EJE 1-1
ENTRE A-B 1 0.8500 2.2000 1.8700 m2 1.87
ENTRE B-C 2 4.5000 2.2000 19.8000 m2 19.80
EJE 2-2
ENTRE B-C 1 4.5000 2.6000 11.7000 m2 11.70
EJE 3-3
ENTRE A-B 1 3.0000 2.2000 6.6000 m2 6.60
ENTRE B-C 1 4.5000 2.6000 11.7000 m2 11.70
PAREDES EXTERIORES
PRIMER NIVEL
EJE C-C
ENTRE 1-2 1 3.7500 2.8000 11.0625 m2 11.06
ENTRE 2-3 1 3.1700 2.6500 9.3515 m2 9.35
EJE 1-1
ENTRE A-B 1 3.7500 2.9500 11.0625 m2 11.06
ENTRE B-C 1 2.2000 2.9500 6.4900 m2 6.49
EJE 3-3
ENTRE A-B 1 2.1000 2.6500 5.7750 m2 5.78
ENTRE B-C 1 1.8000 2.6500 4.9500 m2 4.95
SEGUNDO NIVEL
EJE A-A 2.6000
ENTRE 2-3 1 1.7800 2.6000 4.6280 m2 4.63
EJE C-C
ENTRE 1-2 1 1.7800 2.6000 4.6280 m2 4.63
EJE 1-1
ENTRE A-B 1 3.7500 2.6000 11.0625 m2 11.06
ENTRE B-C 1 2.2000 2.6000 6.4900 m2 6.49
EJE 3-3
ENTRE A-B 1 2.1000 2.6000 5.7750 m2 5.78
ENTRE B-C 1 1.8000 2.6000 4.9500 m2 4.95
TERCER NIVEL
EJE A-A
ENTRE 2-3 1 1.7800 2.6500 4.6280 m2 4.63
EJE C-C
ENTRE 1-2 1 4.5000 2.6500 4.6280 m2 4.63
ENTRE 2-3 1 3.0000 2.6500 4.6280 m2 4.63
EJE 1-1
ENTRE A-B 1 3.7500 2.6500 11.0625 m2 11.06
ENTRE B-C 1 2.2000 2.6500 6.4900 m2 6.49
EJE 3-3
ENTRE A-B 1 2.1000 2.6500 5.7750 m2 5.78
ENTRE B-C 1 1.8000 2.6500 4.9500 m2 4.95
OE.3.11.2 LIMPIEZA DE VIDRIOS m2 42.97
V-1 1 0.60 1.70 1.020 m2 1.02
V-2 1 1.25 0.50 0.625 m2 0.63
V-3 1 2.30 1.20 2.760 m2 2.76
V-4 1 2.35 1.20 2.820 m2 2.82
V-5 1 3.00 2.45 7.350 m2 7.35
V-6 1 3.20 2.10 6.720 m2 6.72
V-7 1 2.05 1.70 3.485 m2 3.49
V-8 1 2.90 1.70 4.930 m2 4.93
V-9 1 2.10 1.70 3.570 m2 3.57
V-10 1 0.70 1.70 1.190 m2 1.19
V-11 1 2.00 1.70 3.400 m2 3.40
V-12 1 3.00 1.70 5.100 m2 5.10
V-13 1 2.05 1.70 3.485 m2 3.49
V-14 1 2.90 1.70 4.930 m2 4.93
V-15 1 2.10 1.70 3.570 m2 3.57
V-16 1 0.70 1.70 1.190 m2 1.19
V-17 1 2.00 1.70 3.400 m2 3.40
V-18 1 3.00 1.70 5.100 m2 5.10
OE.2 ESTRUCTURAS
OE.2.1 MOVIMIENTO DE TIERRAS
OE.2.1.1 NIVELACION DEL TERRENO
OE.2.1.1.1 NIVELACION m2 200.00
TODO 1 20.0000 10.0000 200.0000 m2 200.00
OE.2.1.2 EXCAVACIONES
OE.2.1.2.2 EXCAVACIONES SIMPLES m3 67.06
EJE A - A
ENTRE EJE 6 - 7 1 3.5800 0.4000 1.1000 1.5752 m3 1.58
ENTRE EJE 5 - 6 1 3.4500 0.5000 1.1000 1.8975 m3 1.90
ENTRE EJE 3 - 4 1 3.9900 0.5000 1.1000 2.1945 m3 2.19
ENTRE EJE 2 - 3 1 2.0200 0.5000 1.1000 1.1110 m3 1.11
1 0.3800 0.5000 1.1000 0.2090 m3 0.21
ENTRE EJE 1 - 2
1 3.6000 0.4000 1.1000 1.5840 m3 1.58
EJE B - B
ENTRE EJE 4 - 5 2 1.9500 0.5000 1.1000 2.1450 m3 2.15
ENTRE EJE 3 - 4 1 2.9200 0.5000 1.1000 1.6060 m3 1.61
1 2.1200 0.5000 0.5000 0.5300 m3 0.53
ENTRE EJE 5 - 6
1 0.9800 1.0600 0.1000 0.1039 m3 0.10
EJE C - C
1 2.9200 0.5000 1.1000 1.6060 m3 1.61
ENTRE EJE 3 - 4 1 1.8200 0.8500 1.1000 1.7017 m3 1.70
1 1.6000 0.5000 1.1000 0.8800 m3 0.88
EJE D - D
ENTRE EJE 6 - 7 1 3.5800 0.4000 1.1000 1.5752 m3 1.58
ENTRE EJE 5 - 6 1 3.4500 0.5000 1.1000 1.8975 m3 1.90
ENTRE EJE 4 - 5 1 2.4500 0.5000 1.1000 1.3475 m3 1.35
ENTRE EJE 3 - 4 1 3.9900 0.5000 1.1000 2.1945 m3 2.19
ENTRE EJE 2 - 3 1 2.0200 0.5000 1.1000 1.1110 m3 1.11
1 0.3800 0.5000 1.1000 0.2090 m3 0.21
ENTRE EJE 1 - 2
1 3.6000 0.4000 1.1000 1.5840 m3 1.58
EJE 3 - 3
ENTRE EJE A - B 1 3.0800 0.5000 1.1000 1.6940 m3 1.69
1 1.2000 0.5000 1.1000 0.6600 m3 0.66
1 0.3800 1.1500 1.1000 0.4807 m3 0.48
ENTRE EJE B - C
1 0.7300 0.7000 1.1000 0.5621 m3 0.56
ENTRE EJE B - C
EJE 6 - 6
ENTRE EJE A - B 1 2.1300 0.5000 0.5000 1.0650 m2 1.07
ENTRE EJE B - C 1 3.7200 1.0600 0.1000 3.9432 m2 3.94
ENTRE EJE C - D 1 1.9300 1.0600 0.1000 2.0458 m2 2.05
EJE 4 - 4
ENTRE EJE A - C 1 5.8800 0.2500 0.3000 0.4410 m3 0.44
ENTRE EJE C - D 1 2.6200 0.5000 0.3000 0.3930 m3 0.39
EJE 5 - 5
ENTRE EJE A - C 1 5.8800 0.2500 0.3000 0.4410 m3 0.44
ENTRE EJE C - D 1 2.6200 0.5000 0.3000 0.3930 m3 0.39
OE.2.2.4 SOBRECIMIENTOS
OE.2.2.4.1 PARA EL CONCRETO m3 8.83
EJE A - A
ENTRE EJE 6 - 7 1 3.5800 0.1500 0.5000 0.2685 m3 0.27
ENTRE EJE 5 - 6 1 3.4500 0.2500 0.6000 0.5175 m3 0.52
ENTRE EJE 3 - 4 1 3.9900 0.2500 0.6000 0.5985 m3 0.60
ENTRE EJE 2 - 3 1 2.0200 0.2500 0.6000 0.3030 m3 0.30
1 0.3800 0.2500 0.6000 0.0570 m3 0.06
ENTRE EJE 1 - 2
1 3.6000 0.1200 0.5000 0.2160 m3 0.22
EJE B - B
ENTRE EJE 4 - 5 1 2.2000 0.2500 0.6000 0.3300 m3 0.33
ENTRE EJE 4' - 5' 1 1.4000 0.1500 0.6000 0.1260 m3 0.13
EJE C - C
ENTRE EJE 3 - 4 1 2.2700 0.1500 0.6000 0.2043 m3 0.20
1 2.2700 0.1500 0.6000 0.2043 m3 0.20
ENTRE EJE 3' - 4'
1 0.9000 0.1500 0.6000 0.0810 m3 0.08
ENTRE EJE 4 - 5 1 1.7600 0.1500 0.6000 0.1584 m3 0.16
EJE D - D
ENTRE EJE 6 - 7 1 3.5800 0.1500 0.6000 0.3222 m3 0.32
ENTRE EJE 5 - 6 1 3.4500 0.2500 0.6000 0.5175 m3 0.52
ENTRE EJE 4 - 5 1 2.4500 0.5000 0.6000 0.7350 m3 0.74
ENTRE EJE 3 - 4 1 3.9900 0.2500 0.6000 0.5985 m3 0.60
ENTRE EJE 2 - 3 1 2.0200 0.2500 0.6000 0.3030 m3 0.30
1 0.3800 0.2500 0.6000 0.0570 m3 0.06
ENTRE EJE 1 - 2
1 3.6000 0.1200 0.6000 0.2592 m3 0.26
EJE 3 - 3
ENTRE EJE A - B 1 2.3000 0.2500 0.6000 0.3450 m3 0.35
ENTRE EJE B - C 1 1.8000 0.2500 0.6000 0.2700 m3 0.27
EJE 4 - 4
ENTRE EJE A - C 1 2.3500 0.2500 0.6000 0.3525 m3 0.35
ENTRE EJE C - D 1 2.7600 0.5000 0.6000 0.8280 m3 0.83
EJE 5 - 5
ENTRE EJE A - C 1 2.1000 0.2500 0.6000 0.3525 m3 0.35
ENTRE EJE C - D 1 1.6200 0.1500 0.6000 0.8280 m3 0.83
EJE 4 - 4
ENTRE EJE A - C 1 5.0000 0.6000 3.0000 m2 3.00
ENTRE EJE C - D 1 5.8200 0.6000 3.4920 m2 3.49
EJE 5 - 5
ENTRE EJE A - C 1 4.7000 0.6000 2.8200 m3 2.82
ENTRE EJE C - D 1 3.5400 0.6000 2.1240 m2 3.49
OE.2.3.2 COLUMNAS
OE.2.3.2.1 PARA EL CONCRETO m3 11.28
PARA EL 1ER PISO
C1 3 0.3500 0.3500 6.1000 1.7607 m3 1.76
C2 17 0.2500 0.2500 6.1000 6.4813 m3 6.48
C3 1 0.2500 0.2500 6.1000 0.3813 m3 0.38
C7 10 0.2500 0.1500 6.1000 2.2875 m3 2.29
PARA EL 2DO PISO
C5 3 0.1500 0.1500 2.7500 0.1856 m3 0.19
C6 1 0.2500 0.1500 2.7500 0.1031 m3 0.10
PARA LA AZOTEA
C5 2 0.1500 0.1500 1.8000 0.0810 m3 0.08
OE.2.3.3 VIGAS
OE.2.3.3.1 PARA EL CONCRETO m3 13.76
PRIMER PISO
EJE 6-6 1 10.0000 0.2500 0.5000 1.2500 4.0000 ENCUENTRO 0.2500 0.2500 0.5000 0.1250 m3 1.13
EJE 6'-6' 1 8.0500 0.1500 0.2000 0.2415 m3 0.24
EJE 5-5 1 10.0000 0.2500 0.5000 1.2500 5.0000 ENCUENTRO 0.2500 0.2500 0.5000 0.1563 m3 1.09
1 6.2000 0.2500 0.2000 0.3100 m3 0.31
EJE 4-4
1 2.8000 0.2500 0.5000 0.3500 m3 0.35
EJE 3-3 1 10.0000 0.2500 0.2000 0.5000 4.0000 ENCUENTRO 0.2500 0.2500 0.2000 0.0500 m3 0.45
EJE 3'-3' 1 3.0000 0.1500 0.2000 0.0900 m3 0.09
EJE 2-2 1 10.0000 0.2500 0.2000 0.5000 4.0000 ENCUENTRO 0.2500 0.2500 0.2000 0.0500 m3 0.45
EJE 2'-2' 1 6.9600 0.1500 0.2000 0.2088 5.0000 ENCUENTRO 0.2500 0.2500 0.2000 0.0625 m3 0.15
EJE A-A
ENTRE 2-4 1 5.5800 0.2500 0.2000 0.2790 3.0000 ENCUENTRO 0.2500 0.2500 0.2000 0.0375 m3 0.24
ENTRE 5-6 1 5.1100 0.2500 0.2000 0.2555 2.0000 ENCUENTRO 0.2500 0.2500 0.2000 0.0250 m3 0.23
EJE B-B
ENTRE 2-3 1 2.2900 0.2500 0.2000 0.1145 1.0000 ENCUENTRO 0.3500 0.3500 0.2000 0.0245 m3 0.09
ENTRE 3-5 1 5.6200 0.2500 0.2000 0.2810 1.0000 ENCUENTRO 0.2500 0.2500 0.2000 0.0125 m3 0.27
ENTRE 5-6 1 3.7500 0.2500 0.2000 0.1875 m3 0.19
ENTRE 6-6' 1 1.1400 0.2500 0.2000 0.0570 m3 0.06
EJE C-C
ENTRE 2'-2 1 1.1200 0.2500 0.2000 0.0560 m3 0.06
ENTRE 2-4 1 5.1900 0.2500 0.2000 0.2595 1.0000 ENCUENTRO 0.2500 0.2500 0.2000 0.0125 m3 0.25
ENTRE 4-5 1 2.2000 0.2500 0.2000 0.1100 m3 0.11
ENTRE 5-6 1 3.7500 0.2500 0.2000 0.1875 m3 0.19
ENTRE 6-6' 1 0.8000 0.2500 0.2000 0.0400 m3 0.04
EJE D-D 1
ENTRE 2'-2 1 1.1200 0.2500 0.5000 0.1400 m3 0.14
ENTRE 2-6 1 11.6400 0.2500 0.2000 0.5820 3.0000 ENCUENTRO 0.2500 0.2500 0.2000 0.0375 m3 0.54
ENTRE A-B/4-5 1 2.2000 0.1500 0.2000 0.0660 m3 0.07
ENTRE C-D/4-3 1 2.7400 0.1500 0.2000 0.0822 m3 0.08
SEGUNDO PISO
EJE 6-6 1 9.5000 0.2500 0.5000 1.1875 2.0000 ENCUENTRO 0.2500 0.2500 0.5000 0.0625 m3 1.13
EJE 6'-6' 1 10.0000 0.1500 0.2000 0.3000 m3 0.30
EJE 5-5 1 9.5000 0.2500 0.2000 0.4750 2.0000 ENCUENTRO 0.2500 0.2500 0.2000 0.0250 m3 0.45
1 6.2000 0.2500 0.2000 0.3100
EJE 4-4
1 2.8000 0.2500 0.5000 0.3500 m3 0.35
EJE 3'-3'
EJE A-D 1 9.0000 0.1500 0.2000 0.2700 m3 0.27
EJE 3-3 1 9.0000 0.2500 0.2000 0.4500 m3 0.45
EJE 2-2 1 9.0000 0.2500 0.2000 0.4500 m3 0.45
EJE 2'-2'
EJE A-B 1 4.4700 0.1500 0.2000 0.1341 m3 0.13
EJE B-C 1 2.8000 0.1500 0.2000 0.0840 m3 0.08
EJE B'-C' 1 3.2000 0.1500 0.5000 0.2400 m3 0.24
EJE C-D 1 3.0000 0.1500 0.2000 0.0900 m3 0.09
EJE C'-D' 1 3.0000 0.1500 0.5000 0.2250 m3 0.23
EJE A-A
ENTRE 2-6 1 10.1500 0.2500 0.2000 0.5075 m3 0.51
ENTRE 4-5 1 2.2000 0.1500 0.2000 0.0660 m3 0.07
EJE B-B
ENTRE 1-3 1 3.3500 0.2500 0.2000 0.1675 m3 0.17
ENTRE 3-4 1 3.1700 0.2500 0.2000 0.1585 m3 0.16
ENTRE 4-5 1 2.2000 0.2500 0.2000 0.1100 m3 0.11
ENTRE 5-6 1 4.9000 0.2500 0.2000 0.2450 m3 0.25
EJE C-C
ENTRE 1-6 1 14.8700 0.2500 0.2000 0.7435 5.0000 ENCUENTRO 0.2500 0.2500 0.2000 0.0625 m3 0.68
EJE C'-C'
EJE 3-4 1 2.7500 0.1500 0.2000 0.0825 m3 0.08
EJE 4-5 1 3.0700 0.1500 0.2000 0.0921 m3 0.09
EJE D-D
ENTRE 1-6 1 14.8700 0.2500 0.2000 0.7435 5.0000 ENCUENTRO 0.2500 0.2500 0.2000 0.0625 m3 0.68
OE.2.3.4 LOSAS
OE.2.3.4.1 LOSAS ALIGERADAS CONVENCIONALES
OE.2.3.4.1.1 PARA EL CONCRETO m3 21.65
PRIMER PISO
TODO 1 1.0000 120.8500 0.2000 24.1700 1208.5000 BLOQUETAS 0.2500 0.3000 0.1500 13.5956 m3 10.57
SEGUNDO PISO
TODO 1 1.0000 126.5370 0.2000 25.3074 1265.3700 BLOQUETAS 0.2500 0.3000 0.1500 14.2354 m3 11.07
OE.2.3.5 ESCALERAS
OE.2.3.5.1 PARA EL CONCRETO m3 1.728
DADO DE Cº 1 1.0000 0.4000 0.6000 0.2400 m3 0.24
GRADAS 15 1.0000 0.1700 0.2400 0.3060 m3 0.31
LOSA SUP. E INF. 2 1.0000 2.6900 0.1500 0.8070 m3 0.81
LOSA DE DESCANZO 1 2.0000 1.2500 0.1500 0.3750 m3 0.38
OE.2.5.3 COBERTURAS
OE.2.5.3.1. CON PLANCHAS CORRUGADAS PLASTICAS m2 6.67
COBER.DE LA ESCALE. 2.9 2.3000 6.6700 m2 6.67
OE.3.3 CIELORRASOS
OE.3.3.1 CIELORRASO CON YESO m2 247.39
PRIMER PISO area
TODO 1 1.00 120.8500 120.8500 m2 120.85
SEGUNDO PISO
TODO 1 1.00 126.5370 126.5370 m2 126.54
OE.3.4.2 PISOS
OE.3.4.2.1 LOSETA CORRIENTE m2 10.66
SSHH 01 2.40 2.30 5.520 m2 5.52
SSHH 02 2.30 1.55 3.565 m2 3.57
SSHH 03 0.9 1.75 1.575 m2 1.58
OE.3.8 CERRAJERIA
OE.3.8.1 BISAGRAS Pza. 45.00
1er NIVEL 3 6 18 pza 18.00
2do NIVEL 3 9 27 pza 27.00
OE.3.10 PINTURA
OE.3.10.1 PINTURA DE CIELOS RAZOS, VIGAS, COLUMNAS Y PAREDES m2 1171.45
CIELOS RAZOS
PRIMER PISO area
TODO 1 1.00 131.04 131.040 m2 131.04
SEGUNDO PISO
TODO 1 1.00 139.30 139.300 m2 139.30
VIGAS
TODO 1 29.20 0.85 24.820 m2 24.82
TODO 1 6.45 0.75 4.838 m2 4.84
COLUMNAS
TODO RECT 18 1.00 4.4 79.200 m2 79.20
TODO CIRC 3 1.10 4.4 14.514 m2 14.51
PAREDES INTERIORES
PRIMER NIVEL
EJE A-A
ENTRE 5-6 1 3.75 2.75 10.313 m2 10.31
ENTRE 3-4 1 3.17 2.75 8.718 m2 8.72
EJE B-B
ENTRE 4-5 2 2.20 2.75 12.100 m2 12.10
EJE C-C
EJE D-D
ENTRE 5-6 1 3.75 2.75 10.313 m2 10.31
ENTRE 4-5 1 2.20 2.75 6.050 m2 6.05
ENTRE 3-4 1 3.17 2.75 8.718 m2 8.72
ENTRE 2-3 1 1.78 2.75 4.895 m2 4.90
EJE 5-5
ENTRE A-B 1 2.1 2.75 5.775 m2 5.78
EJE 3-3
ENTRE B-C 1 1.8 2.75 4.950 m2 4.95
SEGUNDO NIVEL
EJE A-A
ENTRE 2-3 1 1.78 2.6 4.628 m2 4.63
ENTRE 3-4 1 3.17 2.6 8.242 m2 8.24
EJE B-B 0.000
ENTRE 2-3 2 1.78 2.6 9.256 m2 9.26
ENTRE 3-4 2 0.42 2.6 2.184 m2 2.18
EJE C-C
ENTRE 3-4 2 0.42 2.6 2.184 m2 2.18
ENTRE 2-3 2 1.78 2.6 9.256 m2 9.26
ENTRE 1-2 2 1.27 2.6 6.604 m2 6.60
EJE D-D
ENTRE 3-4 1 3.17 2.6 8.242 m2 8.24
ENTRE 2-3 1 1.78 2.6 4.628 m2 4.63
ENTRE 1-2 1 1.27 2.6 3.302 m2 3.30
EJE 4-4
ENTRE B-C 2 1.8 2.6 9.360 m2 9.36
PRIMER NIVEL
EJE A-A
ENTRE 6-7 1 4.00 2.75 11.000 m2 11.00
ENTRE 4-5 1 2.20 2.75 6.050 m2 6.05
ENTRE 2-3 1 1.78 2.75 4.895 m2 4.90
ENTRE 1-2 1 4.27 2.75 11.743 m2 11.74
EJE B-B
EJE C-C
EJE D-D
ENTRE 6-7 1 4.00 2.75 11.000 m2 11.00
ENTRE 1-2 1 4.27 2.75 11.743 m2 11.74
EJE 7-7
ENTRE A-B 1 10 2.75 27.500 m2 27.50
EJE 6-6
ENTRE A-B 2 3.2 1.2 7.680 m2 7.68
ENTRE B-C 2 3.0 1.2 7.200 m2 7.20
EJE 5-5
ENTRE B-C 2 2.8 2.75 15.400 m2 15.40
EJE 4-4
ENTRE A-B 2 2.35 1.2 5.640 m2 5.64
ENTRE B-C 2 2.8 2.75 15.400 m2 15.40
EJE 3-3
ENTRE A-B 2 3.2 1.2 7.680 m2 7.68
ENTRE B-C 2 3.0 1.2 7.200 m2 7.20
ENTRE C-D 2 3.0 1.2 7.200 m2 7.20
EJE 2-2
ENTRE A-B 2 2.3 1.2 5.520 m2 5.52
EJE 1-1
1 8.8 2.75 24.200 m2 24.20
SEGUNDO NIVEL
EJE A-A
ENTRE 6-7 1 0.85 2.6 2.210 m2 2.21
ENTRE 5-6 1 3.75 2.6 9.750 m2 9.75
ENTRE 4-5 1 2.20 2.6 5.720 m2 5.72
EJE B-B
ENTRE 4-5 2 2.20 2.6 11.440 m2 11.44
ENTRE 3-4 2 0.90 2.6 4.680 m2 4.68
EJE C-C
ENTRE 5-6 2 2.85 2.6 14.820 m2 14.82
EJE D-D 0.000
ENTRE 5-6 1 3.75 2.6 9.750 m2 9.75
ENTRE 4-5 1 2.20 2.6 5.720 m2 5.72
EJE 6-6
1 2.85 2.6 7.410 m2 7.41
1 7.80 1.2 9.360 m2 9.36
EJE 5-5
2 12.6 2.6 65.520 m2 65.52
2 1.00 1.7 3.400 m2 3.40
EJE 4-4
2 3.15 2.6 16.380 m2 16.38
2 1.25 0.5 1.250 m2 1.25
EJE 2-2
1 2.35 2.6 6.110 m2 6.11
1 7.82 1.2 9.384 m2 9.38
PAREDES EXTERIORES
EJE A-A
ENTRE 5-6 1 3.75 2.90 10.875 m2 10.88
ENTRE 3-4 1 3.17 2.90 9.193 m2 9.19
EJE D-D
ENTRE 5-6 1 3.75 2.90 10.875 m2 10.88
ENTRE 4-5 1 2.20 2.90 6.380 m2 6.38
ENTRE 3-4 1 3.17 2.90 9.193 m2 9.19
ENTRE 2-3 1 1.78 2.90 5.162 m2 5.16
EJE 5-5
ENTRE A-B 1 2.1 2.75 5.775 m2 5.78
EJE 3-3
ENTRE B-C 1 1.8 2.75 4.950 m2 4.95
SEGUNDO NIVEL
EJE A-A
ENTRE 2-3 1 1.78 2.6 4.628 m2 4.63
ENTRE 3-4 1 3.17 2.6 8.242 m2 8.24
EJE D-D
ENTRE 3-4 1 3.17 2.6 8.242 m2 8.24
ENTRE 2-3 1 1.78 2.6 4.628 m2 4.63
ENTRE 1-2 1 1.27 2.6 3.302 m2 3.30
PRIMER NIVEL
EJE A-A
ENTRE 6-7 1 4.00 2.90 11.600 m2 11.60
ENTRE 4-5 1 2.20 2.90 6.380 m2 6.38
ENTRE 2-3 1 1.78 2.90 5.162 m2 5.16
ENTRE 1-2 1 4.27 2.90 12.383 m2 12.38
EJE D-D
ENTRE 6-7 1 4.00 2.90 11.600 m2 11.60
ENTRE 1-2 1 4.27 2.90 12.383 m2 12.38
EJE 7-7
ENTRE A-B 1 10 2.75 27.500 m2 27.50
EJE 1-1
1 8.8 2.75 24.200 m2 24.20
SEGUNDO NIVEL
EJE A-A
ENTRE 6-7 1 0.85 2.6 2.210 m2 2.21
ENTRE 5-6 1 3.75 2.6 9.750 m2 9.75
ENTRE 4-5 1 2.20 2.6 5.720 m2 5.72
EJE D-D 0.000
ENTRE 5-6 1 3.75 2.6 9.750 m2 9.75
ENTRE 4-5 1 2.20 2.6 5.720 m2 5.72
EJE 6-6
1 2.85 2.6 7.410 m2 7.41
1 7.80 1.2 9.360 m2 9.36
EJE 2-2
1 2.35 2.6 6.110 m2 6.11
1 7.82 1.2 9.384 m2 9.38