Gantt Mata 50
Gantt Mata 50
17 ago '20 24 ago '20 31 ago '20 07 sep '20 14 sep '20 21 sep '20 28 sep '20 05 oct '20 12 oct '20 19 oct '20 26 oct '20 02 nov '20 09 nov '20 16 nov '20 23 nov '20 30 nov '20 07 dic '20 14 dic '20 21 dic '20 28 dic '20 04 ene '21 11 ene '21 18 ene '21 25 ene '21 01 feb '21 08 feb '21 15 feb '21 22 feb '21 01 mar '21 08 mar '21 15 mar '21 22 mar '21 29 mar '21 05 abr '21 12 abr '21 19 abr '21
tarea L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V
1 PROYECTO MATA 50 196,13 días mié 19-08-20 mié 21-04-21
2 OBRAS PRELIMINARES. 18 días mié 19-08-20 jue 10-09-20
3 INSTALACIÓN DE FAENAS. 10 días mié 19-08-20 lun 31-08-20
4 Cierro Provisorio. 2 días mié 19-08-20 jue 20-08-20
5 Construcciones Provisorias 4 días mié 19-08-20 lun 24-08-20 4CC
105 Barras para cortinas de duchas 1 día lun 01-02-21 mar 02-02-21 101CC+12 días
Proyecto: CARTA GANTT MATA Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual
Fecha: mar 21-07-20
Página 1