DIPLOMADO EN CARRETERAS

MODULO VII: ADMINISTRACION VIAL

DOCENTE: ING. MSC. REYNALDO TAPIA OROSCO


ALUMNO: IVAN WALTER GALLARDO PONCE

Datos de Areas de Corte y Relleno

Ac1= 3.95 m2 Ar1= 4.25 m2


Ac2= 7.25 m2 Ar2= 5.25 m2
Ac3= 4.38 m2 Ar3= 5.1 m2
Ac4= 6.32 m2 Ar4= 2.85 m2

Calculo de Volumenes : Vr= 〖𝐴𝑟〗 ^2/ Vc= 〖𝐴𝑐〗 ^2/


Vr 𝑦 𝑉𝑐=(𝐴1+𝐴2)/2∗𝑑
(𝐴𝑐+𝐴𝑟)∗𝑑/2 (𝐴𝑐+𝐴𝑟)∗𝑑/2
Seccion 1 y 2
Ac1= 3.95 m2 Ar1= 4.25 m2
Ar2= 5.25 m2 Ar3= 5.1 m2

Vc1= 〖 3.95 〗 ^2 Vr1= 〖 5.25 〗 ^2/ Vr1=(4.25+5.10)/2


/(3.95+5.25)∗20/2 (3.95+5.25)∗20/2 ∗20

Vc1= 16.96 m3 Vr1= 29.96 m3 Vr1= 93.5 m3

Seccion 2 y 3
Ar3= 5.1 Ar2= 5.25
Ac2= 7.25 Ar4= 2.85

Vr2= 〖 5.10 〗 ^2/ Vc2= 〖 7.25 〗 ^2/ Vr2=(5.25+2.85)/2


(5.10+7.25)∗20/2 (5.10+7.25)∗20/2 333 ∗20

Vr1= 21.06 m3 Vc1= 42.56 m3 Vr3= 81.00 m3

Seccion 3 y 4
Ar4= 2.85 Ac2= 7.25
Ac3= 4.38 Ac4= 6.32

Vc3= 〖 4.38 〗 ^2 Vc3=(7.25+6.32)/2


/(2.85+4.38)∗20/2 ∗20
Vc3= 〖 4.38 〗 ^2 Vc3=(7.25+6.32)/2
Vr3= 〖 2.85 〗 ^2/ ∗20
(2.85+4.38)∗20/2 /(2.85+4.38)∗20/2
Vr3= 11.23 m3 Vc3= 26.53 m3 Vc3= 135.7 m3

VOLUMENES TOTALES

VOLUMEN TOTAL DE VOLUMEN TOTAL DE


CORTE RELLENO
16.96 29.96
42.56 93.5
26.53 81
21.06
135.7 11.23
TOTALES 221.75 236.75
CALCULO DE MATERIAL PRESTAMO

DATOS:

Sw= 15 % Porcentaje de Esponjamiento


Sh= 10 % porcentaje de Compactacion
Vol. Corte= 221.75
Vol. Relleno= 236.75

* Ecuacion para calculo de Volumen en Banco * Ecuacion para calculo de Volumenes Sueltos

Vb=(1/ Vs=(1+𝑆𝑤/100)∗𝑉𝑏
(1−𝑆ℎ/100))∗𝑉𝑐

Vs=(1+15/100)∗41.3
Vb=(1/ 1
(1−10/100))∗236.75

Vb= 263.06 m3 Vs= 47.50 m3


Material de Prestamo necesario p/ la conformacion del Terraplen
Quitamos el Material de Corte para tener el volumen necesario
para la conformacion del Terraplen
Vb= 26 3.06- 221.75

Vb = 41.31 m3

Volumen Necesario en Banco para realizar el Terraplen