12
UTILIDAD (8%CT) S/1,121.27
COSTO TOTAL DEL PROYECTO S/14,015.85
RESERVADE GESTION (2.5%CD) S/341.85
LINEA BASE DEL COSTO S/13,674.00
RESERVA DE CONTINGENCIA S/100.00
COSTO DIRECTO PROYECTO MURO S/13,574.00
Zanja S/5,954.00
Muro de concreto armado S/7,620.00