Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Activity ID Activity Name Original Remaining Start Finish BLProject BLProject Remaining Total Float
Duration Duration Start Finish Labor Units
868al 25oct19)
K-172 GyM Concentradora Quellaveco Cronograma Linea Base Rev1 (Corte 485 15-Feb-19 A 21-Feb-21 15-Feb-19 05-Feb-21 1867981 107
3000 Planta General 860 150 20-Mar-19 A 24-Mar-20 23-Feb-19 16-Jun-20 0 185
3010 Papujune Plant Area General Worksw 860 150 20-Mar-19 A 24-Mar-20 23-Feb-19 16-Jun-20 0 185
A13620 30101030000-U/G Plant Utilities andAncillary Buildings (Include common Areas)- Civil Works
0 0 20-Mar-19 A 08-Jul-19 0
A13640 30101030005-U/G Plant Utilities andAncillary Buildings (Include common Areas) - Piping Works
0 0 20-Mar-19 A 23-Feb-19 0
A13650 30101040000-U/G Flotation & Overflow Launder/ Grinding & Regrinding Area (less than 3m0 deep)- Civil Works
0 20-Mar-19 A 18-Apr-19 0
A13660 30101040001-U/G Flotation & Overflow Launder/ Grinding & Regrinding Area (less than 3m0 deep)- Concrete
0 Works
20-Mar-19 A 19-Aug-19 0
A13680 30101040005-U/G Flotation & Overflow Launder/ Grinding & Regrinding Area (less than 3m0 deep) - Piping 0Works
20-Mar-19 A 19-Apr-19 0
A13710 30101260001-U/G Papujune South Area (Ducts Bank & grounding) - Concrete Works 0 0 20-Mar-19 A 21-May-19 0
A13790 30101330005-U/G Pipeline RO Water to Salveani Camp from Tie in CWP-3010124000 to 0
Tie xx - Piping Works
0 17-Apr-19 A 12-Jul-19 0
A13610 30101020005-U/G Tailings Thickeners & Substation Areas - Piping Works 0 0 18-Apr-19 A 05-Jun-19 0
A13810 30101350000-Masive & Structural Backfill in Tailings Area- Civil Works 0 0 26-May-19 A 29-Aug-19 0
A13830 30101360000-Final Grading Area 3000 (North)- Civil Works 0 0 04-Jun-19 A 17-May-20 0
A13850 30101380000-Final Grading Area 3000 (South)( Exclude Building Platform Area 3800)- Civil
0 Works 0 04-Jun-19 A 16-Jun-20 0
A13600 30101010005-U/G Molybdenum Plant / Copper Filtering / Concentrate Thickeners Tanks - Piping
0 Works 0 01-Aug-19 A 30-Oct-19 0
A13760 30101300005-U/G OverlandArea - Piping Works 0 0 01-Aug-19 A 05-Mar-20 0
A13690 30101040006-U/G Flotation & Overflow Launder/ Grinding & Regrinding Area (less than 3m0 deep) - Electrical
0 Works
26-Oct-19 06-Oct-19 0 155
A13750 30101300000-U/G OverlandArea- Civil Works 0 0 26-Oct-19 06-Sep-19 0 45
A13800 30101340000-Masive & Structural Backfill in Stockpile Area- Civil Works 0 0 14-Dec-19 25-Oct-19 0 129
A13730 30101270000-Yards Pipes Papujune Plant Area General - Civil Works 0 0 25-Dec-19 05-Nov-19 0 129
A13770 30101320000-U/G Sewage Pipeline Colector at South of Papujune Area- Civil Works 0 0 21-Jan-20 02-Dec-19 0 129
A13820 30101350001-Masive & Structural Backfill in Tailings Area- Concrete Works 0 0 13-Feb-20 18-Oct-19 0 45
A13740 30101270005-Yards Pipes Papujune Plant Area General - Piping Works 0 0 24-Mar-20 24-Mar-20 0 185
3100 Mineral Recuperado Stockpile a Molienda 490 121 28-Mar-19 A 26-Mar-20 31-Aug-19 02-Jan-21 0 90
3130 Reclaim Tunnel 0 0 27-Apr-19 A 27-Apr-19 A 31-Aug-19 31-Aug-19 0
A13930 31300010001-Reclaim Tunnels: Concrete Works - Fundacion 0 0 27-Apr-19 A 31-Aug-19 0
3120 Stockpile Building 411 0 28-Mar-19 A 30-Aug-19 A 22-Dec-19 02-Jan-21 0
A13870 31200010000-Stockpile Building:Local Earthworks - Civil Works 0 0 28-Mar-19 A 22-Dec-19 0
A13910 31200030004-Stockpile Building Dome - Mechanical Works 0 0 15-Jun-19 A 02-Jan-21 0
A23830 Stockpile Building Dome - Electrical Works 0 0 30-Aug-19 A 12-Oct-20 0
3140 Feeders and Feeding CV´s to Stockpile 235 121 28-Mar-19 A 26-Mar-20 07-Nov-19 18-Jul-20 0 90
A14150 31400040004-Conveyor to SAG Mill #2: Mechanical Works 0 0 28-Mar-19 A 05-Apr-20 0
A13960 31400010004-Conveyor feeders Line #1: - Mechanical Works 0 0 28-Mar-19 A 11-Jan-20 0
A14010 31400020004-Conveyor feeders Line #2: - Mechanical Works 0 0 28-Mar-19 A 26-Apr-20 0
A14080 31400030004-Conveyor to SAG Mill #1: Mechanical Works 0 0 28-Mar-19 A 05-Apr-20 0
A14160 31400040006-Conveyor to SAG Mill #2: Electrical Works 0 0 14-May-19 A 03-Jul-20 0
A13980 31400010006-Conveyor feeders Line #1: - Electrical Works 0 0 14-May-19 A 19-May-20 0
A14020 31400020006-Conveyor feeders Line #2: - Electrical Works 0 0 14-May-19 A 18-Jul-20 0
A13950 31400010002-Conveyor feeders Line #1: - Steel Works 0 0 15-May-19 A 25-Jan-20 0
A14000 31400020002-Conveyor feeders Line #2: - Steel Works 0 0 15-May-19 A 04-Apr-20 0
A14120 31400040001-Conveyor to SAG Mill #2: Concrete Works 0 0 26-Nov-19 07-Nov-19 0 55
A14180 31400050001-Emergency Exit - Concrete Works 0 0 26-Nov-19 07-Nov-19 0 55
A14050 31400030001-Conveyor to SAG Mill #1: Concrete Works 0 0 26-Nov-19 07-Nov-19 0 55
A14110 31400040000-Conveyor to SAG Mill #2: Civil Works 0 0 19-Feb-20 07-Feb-20 0 76
A14060 31400030002-Conveyor to SAG Mill #1: Steel Works 0 0 24-Mar-20 24-Mar-20 0 92
A14040 31400030000-Conveyor to SAG Mill #1: Civil Works 0 0 26-Mar-20 14-Mar-20 0 80
3200 Molienda y Molienda de Pebbles 666 63 07-Mar-19 A 19-Mar-20 08-Mar-19 02-Jan-21 0 27
3210 SAG and Ball Mills Grinding General 666 0 07-Mar-19 A 16-Jan-20 08-Mar-19 02-Jan-21 0 41
A14730 32100390002-Grinding Building Axis 1-3 & A-H - Steel Works 0 0 07-Mar-19 A 21-Jul-19 0
A14740 32100410002-Grinding Building Axis 3-7 & A-H - Steel Works 0 0 07-Mar-19 A 21-Jul-19 0
A14750 32100400002-Grinding Building Axis 1-3 & H-M - Steel Works 0 0 07-Mar-19 A 16-Sep-19 0
© Oracle Corporation
K-172 GyM Concentradora Quellaveco Classic Schedule Layout 29-Jan-20 22:51
Activity ID Activity Name Original Remaining Start Finish BLProject BLProject Remaining Total Float
Duration Duration Start Finish Labor Units
A14760 32100420002-Grinding Building Axis 3-7 & H-M - Steel Works 0 0 07-Mar-19 A 16-Sep-19 0
A14770 32100430002-Grinding Building Axis 7-8 & A-H - Steel Works 0 0 07-Mar-19 A 21-Jul-19 0
A14780 32100440002-Grinding Building Axis 7-8 & H-M - Steel Works 0 0 07-Mar-19 A 16-Sep-19 0
A14310 32100040001-Ball Mill # 1 Foundation - Concrete Works 0 0 16-Mar-19 A 04-Apr-19 0
A14320 32100050001-Ball Mill # 2 Foundation - Concrete Works 0 0 16-Mar-19 A 08-Mar-19 0
A14290 32100030000-SAG Mill #2 Foundations - Civil Works 0 0 17-Mar-19 A 09-Apr-19 0
A14650 32100320001-Foundation Grinding Building Axis 3-7 & A-H - Concrete Works 0 0 20-Mar-19 A 08-Mar-19 0
A14660 32100330001-Foundation Grinding Building Axis 3-7 & H-M - Concrete Works 0 0 20-Mar-19 A 28-Mar-19 0
A14670 32100340001-Foundation Grinding Building Axis 1-2 & A-M - Concrete Works 0 0 20-Mar-19 A 02-Apr-19 0
A14680 32100350001-Foundation Grinding Building Axis 8 & A-M - Concrete Works 0 0 20-Mar-19 A 07-May-19 0
A14250 32100010001-Mill Area Interior Works (Box & Found. Pulp Pumps, Drainage Trench, Found.
0 Pipe Support)0- Concrete
29-Mar-19
Works
A 06-Aug-19 0
A14450 32100130002-Grinding Building & Mill - Steel Works 0 0 29-Mar-19 A 04-Dec-19 0
A14280 32100020001-SAG Mill #1 Foundations - Concrete Works 0 0 02-Apr-19 A 20-Apr-19 0
A14300 32100030001-SAG Mill #2 Foundations - Concrete Works 0 0 02-Apr-19 A 22-Mar-19 0
A14550 32100210000-Cooling Towers- Civil Works 0 0 17-Apr-19 A 18-Apr-19 0
A14240 32100010000-Mill Area (Backfill) - Civil Works 0 0 17-Apr-19 A 14-Apr-19 0
A14270 32100020000-SAG Mill #1 Foundations - Civil Works 0 0 17-Apr-19 A 14-Mar-19 0
A14590 32100210006-Cooling Towers - Electrical Works 0 0 30-Apr-19 A 11-Mar-20 0
A14470 32100170006-Grinding Electrical Room - Electrical Works 0 0 30-Apr-19 A 29-Feb-20 0
A14610 32100230002-Mill Area Pipe Racks - Steel Works 0 0 01-May-19 A 01-Sep-19 0
A14620 32100270004-Piping A/G Sag and Ball Mills - Mechanical Works 0 0 15-May-19 A 22-May-20 0
A14640 32100300004-Ball Feeding System for Ball Mills - Mechanical Works 0 0 15-May-19 A 02-Jan-21 0
A14260 32100010004-Mill Area -Mechanical Works 0 0 15-May-19 A 17-Jun-20 0
A14330 32100070004-SAG Mill #1 - Mechanical Works 0 0 15-May-19 A 02-Mar-20 0
A14360 32100080004-SAG Mill #2 - Mechanical Works 0 0 15-May-19 A 01-Feb-20 0
A14390 32100090004-Ball Mill #1 - Mechanical Works 0 0 15-May-19 A 28-Mar-20 0
A14420 32100100004-Ball Mill #2 - Mechanical Works 0 0 15-May-19 A 02-Feb-20 0
A14460 32100130004-Grinding Building & Mill - Mechanical Works 0 0 15-May-19 A 09-Dec-19 0
A14340 32100070006-SAG Mill #1 - Electrical Works 0 0 17-May-19 A 31-Aug-20 0
A14370 32100080006-SAG Mill #2 - Electrical Works 0 0 17-May-19 A 08-Jul-20 0
A14400 32100090006-Ball Mill #1 - Electrical Works 0 0 17-May-19 A 18-Jul-20 0
A14430 32100100006-Ball Mill #2 - Electrical Works 0 0 17-May-19 A 24-May-20 0
A14580 32100210004-Cooling Towers - Mechanical Works 0 0 26-May-19 A 17-May-19 0
A14630 32100270005-Piping A/G Sag and Ball Mills - Piping Works 0 0 27-May-19 A 27-Jul-20 0
A14690 32100360001-Radier & Losas Colaborantes - Concrete Works 0 0 29-May-19 A 21-Jun-20 0
A14700 32100370001-Retaining Walls (External) & ERoom Foundations - Concrete Works 0 0 30-Aug-19 A 03-Jun-19 0
A14560 32100210001-Cooling Towers- Concrete Works 0 0 16-Jan-20 18-Jan-20 0 41
3220 Pebble Crusher 277 10 17-May-19 A 19-Mar-20 06-Feb-20 10-Nov-20 0 27
A14860 32200030006-Pebble Crusher & Mech / Elect Feeders / Magneto & Hoppers - Electrical Works
0 0 17-May-19 A 14-Oct-20 0
A14930 32200040006-Pebbles Conveyor Belts - Electrical Works 0 0 17-May-19 A 03-Nov-20 0
A14970 32200050006-Transformers Yard and Pebbles Crusher Electrical Room - Electrical Works0 0 17-May-19 A 14-Sep-20 0
A14820 32200020004-Pebble Crusher Building - Mechanical Works 0 0 15-Jun-19 A 13-Sep-20 0
A14890 32200040001-Pebbles Conveyor Belts- Concrete Works 0 0 15-Jun-19 A 06-Apr-20 0
A14920 32200040004-Pebbles Conveyor Belts - Mechanical Works 0 0 15-Jun-19 A 05-May-20 0
A14790 32200010000-Pebble Crusher Building Civil & Backfill- Civil Works 0 0 12-Jul-19 A 06-Feb-20 0
A14840 32200030004-Pebble Crusher & Mech / Elect Feeders / Magneto & Hoppers - Mechanical0Works 0 27-Aug-19 A 10-Nov-20 0
A14800 32200010001-Pebble Crusher Building - Concrete Works 0 0 09-Mar-20 07-Mar-20 0 27
A14880 32200040000-Pebbles Conveyor Belts- Civil Works 0 0 19-Mar-20 17-Mar-20 0 27
3300 Flotación y Remolienda 664 76 04-May-19 A 10-Jan-20 15-Feb-19 10-Dec-20 0 167
3310 Copper Flotation 664 76 23-May-19 A 10-Jan-20 15-Feb-19 10-Dec-20 0 167
A15000 33100010001-Flotation Area Buildings - ConcreteWorks (Piperacks) 0 0 23-May-19 A 28-Apr-19 0
A15030 33100020001-Flotation Cells - Rougher/Scavenger/First cleaning - Concrete Works 0 0 25-May-19 A 26-Apr-19 0
A15080 33100020006-Flotation Cells - Rougher/Scavenger/First cleaning - Electrical Works 0 0 27-May-19 A 18-Sep-20 0
A15120 33100030006-Flotation Columns - Second cleaning - Electrical Works 0 0 27-May-19 A 14-Oct-20 0
A15160 33100040006-Miscellaneous Equipment and Concentrate Launders - Electrical Works 0 0 27-May-19 A 13-Jun-19 0
A15200 33100050006-Flotation Electrical Room - Electrical Works 0 0 27-May-19 A 30-Aug-20 0
A15250 33100100006-Piping A/G FlotationArea - Electrical Works 0 0 27-May-19 A 29-Aug-20 0
A15020 33100020000-Flotation Cells - Rougher/Scavenger/First cleaning - Civil Works 0 0 05-Jun-19 A 15-Feb-19 0
A17180 33100010000-Flotation Area Buildings Local Earthworks & Backfill- Civil Works 0 0 05-Jun-19 A 26-Apr-19 0
A15040 33100020002-Flotation Cells - Rougher/Scavenger/First cleaning - Steel Works 0 0 17-Jul-19 A 15-Jun-20 0
A15100 33100030002-Flotation Columns - Second cleaning - Steel Works 0 0 17-Jul-19 A 14-Oct-20 0
A15140 33100040002-Miscellaneous Equipment and Concentrate Launders - Steel Works 0 0 17-Jul-19 A 10-Jan-20 0
A15010 33100010002-Flotation Area Buildings - Steel Works 0 0 17-Jul-19 A 10-Jan-20 0
A15070 33100020005-Flotation Cells - Rougher/Scavenger/First cleaning - Piping Works 0 0 19-Jul-19 A 22-May-20 0
A15110 33100030004-Flotation Columns - Second cleaning - Mechanical Works 0 0 19-Jul-19 A 30-Aug-20 0
A15230 33100100004-Piping A/G FlotationArea - Mechanical Works 0 0 19-Jul-19 A 10-Dec-20 0
A15240 33100100005-Piping A/G FlotationArea - Piping Works 0 0 19-Jul-19 A 15-Aug-20 0
A15060 33100020004-Flotation Cells - Rougher/Scavenger/First cleaning - Mechanical Works 0 0 27-Aug-19 A 15-Nov-19 0
A15150 33100040004-Miscellaneous Equipment and Concentrate Launders - Mechanical Works 0 0 27-Aug-19 A 30-May-19 0
A15180 33100050000-Flotation Electrical Room- Civil Works 0 0 26-Oct-19 23-Oct-19 0 184
A484820 33100010001-Flotation Area Buildings - ConcreteWorks (Piperacks) Pipe Racks Lado Este
0 0 01-Dec-19* 0 0
A15190 33100050001-Flotation Electrical Room- Concrete Works 0 0 24-Dec-19 21-Dec-19 0 184
A15220 33100100002-Piping A/G FlotationArea - Steel Works 0 0 10-Jan-20 10-Jan-20 0 60
3320 Regrind 479 0 05-Jun-19 A 27-Oct-19 18-Jul-19 26-Sep-20 0 41
A15260 33200010000-Regrind Area Buildings Local Earthworks & Backfill- Civil Works 0 0 05-Jun-19 A 18-Jul-19 0
A15300 33200020004-Regrind Circuit - Mechanical Works 0 0 09-Jul-19 A 19-Jan-20 0
A15310 33200020006-Regrind Circuit - Electrical Works 0 0 19-Jul-19 A 26-Sep-20 0
© Oracle Corporation
K-172 GyM Concentradora Quellaveco Classic Schedule Layout 29-Jan-20 22:51
Activity ID Activity Name Original Remaining Start Finish BLProject BLProject Remaining Total Float
Duration Duration Start Finish Labor Units
© Oracle Corporation
K-172 GyM Concentradora Quellaveco Classic Schedule Layout 29-Jan-20 22:51
Activity ID Activity Name Original Remaining Start Finish BLProject BLProject Remaining Total Float
Duration Duration Start Finish Labor Units
A17090 51103050001-Emergency Generators , Electrical Room (5110-ER-003) and Transformers-0Concrete Works0 22-Dec-19 21-Dec-19 0 298
A17050 51103030002-22.9 kV Electrical Yard (Includes Underground) and Electrical Room (5110-ER-002)-
0 Steel Works
0 31-Jan-20 11-Dec-19 0 298
A17130 51103110001-60 KV Electrical Yard and Electrical Room (5110-ER-004)- Concrete Works 0 0 31-Jan-20 10-Jan-20 0 395
A17060 51103030006-22.9 kV Electrical Yard (Includes Underground) and Electrical Room (5110-ER-002)
0 - Electrical0Works
03-Feb-20 28-Dec-19 0 298
A17140 51103110006-60 KV Electrical Yard and Electrical Room (5110-ER-004) - Electrical Works 0 0 03-Mar-20 26-Jan-20 0 298
A17070 51103030007-22.9 kV Electrical Yard (Includes Underground) and Electrical Room (5110-ER-002)
0 - I&C Works
0 11-Mar-20 03-Feb-20 0 315
A17150 51103120001-Harmonic Filters- Concrete Works 0 0 11-Mar-20 20-Jan-20 0 298
A17160 51103120006-Harmonic Filters - Electrical Works 0 0 18-Mar-20 10-Feb-20 0 298
Procura 242 151 25-Jun-19 A 24-Mar-20 24-Jul-19 24-Mar-20 0 411
3100 Mineral Recuperado Stockpile a Molienda 17 17 23-Feb-20 10-Mar-20 23-Feb-20 10-Mar-20 0 306
3130 Reclaim Tunnel 0 0 23-Feb-20 23-Feb-20 23-Feb-20 23-Feb-20 0 0
Structural 0 0 23-Feb-20 23-Feb-20 23-Feb-20 23-Feb-20 0 0
A2840 Reclaim Conveyors - Feeder Support - Line 1 (p/modular) 0 0 23-Feb-20* 23-Feb-20 0 0
A2850 Reclaim Conveyors - Feeder Support - Line 2 (p/modular) 0 0 23-Feb-20* 23-Feb-20 0 0
3140 Feeders and Feeding CV´s to Stockpile 1 1 10-Mar-20 10-Mar-20 10-Mar-20 10-Mar-20 0 306
Mechanical 1 1 10-Mar-20 10-Mar-20 10-Mar-20 10-Mar-20 0 306
A3330 408011 Belt feeders CWP 3140-002 0 0 10-Mar-20* 10-Mar-20 0 307
A3320 408011 Belt feeders CWP 3140-001 0 0 10-Mar-20* 10-Mar-20 0 201
3200 Molienda y Molienda de Pebbles 172 137 16-Sep-19 A 10-Mar-20 16-Sep-19 10-Mar-20 0 0
3210 SAG and Ball Mills Grinding General 172 137 16-Sep-19 A 10-Mar-20 16-Sep-19 10-Mar-20 0 0
Structural 145 110 16-Sep-19 A 13-Feb-20 16-Sep-19 13-Feb-20 0 0
A2890 Grinding Bldg. -Axis 1-3/ A-H - Modules & Stick-built (80%) (p/modular) 0 0 16-Sep-19 A 16-Sep-19 0
A2900 Grinding Bldg. -Axis 3-7/ A-H - Modules & Stick-built (80%) (p/modular) 0 0 16-Sep-19 A 16-Sep-19 0
A3710 Acopio y selección de material para 1er pre-ensamble 3 0 16-Sep-19 A 18-Sep-19 A 16-Sep-19 18-Sep-19 0
A2950 Grinding Bldg. -Axis 1-3/ A-H - Stick-built (20%) 0 0 26-Oct-19 16-Oct-19 0 39
A2960 Grinding Bldg. -Axis 3-7/ A-H - Stick-built (20%) 0 0 26-Oct-19 16-Oct-19 0 39
A3010 Grinding Bldg. - Pipe Racks 0 0 31-Oct-19* 31-Oct-19 0 0
A2910 Grinding Bldg. -Axis 1-3/ H-M - Modules & Stick-built (80%) (p/modular) 0 0 15-Nov-19* 15-Nov-19 0 0
A2920 Grinding Bldg. -Axis 3-7/ H-M -Modules & Stick-built (80%) (p/modular) 0 0 15-Nov-19* 15-Nov-19 0 0
A2930 Grinding Bldg. -Axis 7-8/ A-H - Stick-built (80%) 0 0 15-Nov-19* 15-Nov-19 0 0
A2970 Grinding Bldg. -Axis 1-3/ H-M - Stick-built (20%) 0 0 15-Dec-19* 15-Dec-19 0 0
A2980 Grinding Bldg. -Axis 3-7/ H-M - Stick-built (20%) 0 0 15-Dec-19* 15-Dec-19 0 0
A2990 Grinding Bldg. -Axis 7-8/ A-H - Stick-built (20%) 0 0 15-Dec-19* 15-Dec-19 0 0
A2940 Grinding Bldg. -Axis 7-8/ H-M -Stick-built (80%) 0 0 14-Jan-20* 14-Jan-20 0 0
A3000 Grinding Bldg. -Axis 7-8/ H-M - Stick-built (20%) 0 0 13-Feb-20* 13-Feb-20 0 0
Mechanical 130 130 02-Nov-19 10-Mar-20 02-Nov-19 10-Mar-20 0 0
A3360 406010 - Bba Booster Agua Recuperada TAG 3210-PU-022@024 0 0 02-Nov-19* 02-Nov-19 0 0
A3370 406010 - Horizontal Process Pumps TAG 3210-PU-007@010 * 0 0 02-Nov-19* 02-Nov-19 0 0
A3380 407004-01 Cyclones TAG 3210-CY-003/004 (Line #1) 0 0 25-Nov-19* 25-Nov-19 0 0
A3390 407004-01 Cyclones TAG 3210-CY-001/002 (Line #2) 0 0 25-Dec-19* 25-Dec-19 0 0
A3580 700402- Stream Analyzers CWP 3210-019 0 0 10-Jan-20* 10-Jan-20 0 0
A3391 408002-RQ-EPCM - Trunnion Bearing Soleplates and Bearing Pedestal Ball 2 0 0 13-Jan-20* 13-Jan-20 0 0
A3470 409001- Bridge cranes CWP 3210-007 (3210-CN-005) - Bolas 0 0 20-Jan-20* 20-Jan-20 0 0
A3480 409001- Bridge cranes CWP 3210-009 (3210-CN-004) - SAG 0 0 20-Jan-20* 20-Jan-20 0 33
A3393 408002-RQ-EPCM - Trunnion Bearing Soleplates and Bearing Pedestal Ball 1 0 0 29-Jan-20* 29-Jan-20 0 0
A3460 409001- Bridge cranes CWP 3210-019 (3210-CN-003) - Ciclones 0 0 22-Feb-20* 22-Feb-20 0 0
A3392 408002-RQ-EPCM - Trunnion Bearing Soleplates and Bearing Pedestal SAG 2 0 0 29-Feb-20* 29-Feb-20 0 0
A3340 406001 - Slurry pumps TAG 3210-PU-001/002 0 0 04-Mar-20* 04-Mar-20 0 0
A3350 406001 - Slurry pumps TAG 3210-PU-003/006/021 0 0 04-Mar-20* 04-Mar-20 0 0
A3394 408002-RQ-EPCM - Trunnion Bearing Soleplates and Bearing Pedestal SAG 1 0 0 10-Mar-20* 10-Mar-20 0 0
3300 Flotación y Remolienda 242 144 25-Jun-19 A 24-Mar-20 24-Jul-19 24-Mar-20 0 354
3310 Copper Flotation 227 129 25-Jun-19 A 09-Mar-20 24-Jul-19 09-Mar-20 0 369
Structural 0 0 09-Mar-20 09-Mar-20 09-Mar-20 09-Mar-20 0 173
A3050 Copper Flotation - General 0 0 09-Mar-20* 09-Mar-20 0 35
A3060 Copper Flotation - Rougher/Scavenger/Cleaner & Distributor Support Steel 0 0 09-Mar-20* 09-Mar-20 0 173
A3090 Copper Flotation - Pipe Racks 0 0 09-Mar-20* 09-Mar-20 0 60
Mechanical 222 124 25-Jun-19 A 04-Mar-20 24-Jul-19 04-Mar-20 0 374
A3720 409006 Tower Crane CWP 3310-003 TAG 3310-CN-001 0 0 25-Jun-19 A 24-Jul-19 0
A3750 700412 - Metallurgical Samplers CWP 3310-002 0 0 01-Nov-19* 01-Nov-19 0 498
A3700 407006- Cuerpo Celda Columna 2da Limpieza de CU-Componente TAG 3310-FT-071@074
0 * 0 11-Nov-19* 11-Nov-19 0 369
A3680 407005 Celda Scavenger/ ConjuntoAgitador Celda Scavenger Filas 1 y 2 ** 0 0 10-Jan-20* 10-Jan-20 0 160
A3690 407005 Celda Primera Limpieza / Conjunto Agitador Celda 1ra LimpiezaFila 1 y 2 ** 0 0 10-Jan-20* 10-Jan-20 0 227
A3740 700402- Stream Analyzers CWP 3310-002 0 0 10-Jan-20* 10-Jan-20 0 428
A3670 407005 Celdas Rougher/ Conjunto Agitador Celda Rougher Filas 1,2,3 y 4 ** 0 0 13-Jan-20* 13-Jan-20 0 24
A3660 406001 - Slurry pumps TAG 3310-PU-001@005 0 0 04-Mar-20* 04-Mar-20 0 361
3320 Regrind 20 20 04-Mar-20 24-Mar-20 04-Mar-20 24-Mar-20 0 326
Structural 0 0 24-Mar-20 24-Mar-20 24-Mar-20 24-Mar-20 0 148
A3100 Regrind Circuit - Regrind Bldg. & Miscel. 0 0 24-Mar-20* 24-Mar-20 0 148
Mechanical 6 6 04-Mar-20 10-Mar-20 04-Mar-20 10-Mar-20 0 340
A3760 406001 - Slurry pumps TAG 3320-PU-001@003 Y005 0 0 04-Mar-20* 04-Mar-20 0 101
A3770 407004-01 Cyclones TAG 3320-CY-001@003 0 0 10-Mar-20* 10-Mar-20 0 340
3400 Planta de Molibdeno 141 141 01-Nov-19 21-Mar-20 01-Nov-19 21-Mar-20 0 414
3410 Molybdenum Plant 141 141 01-Nov-19 21-Mar-20 01-Nov-19 21-Mar-20 0 414
Structural 21 21 29-Feb-20 21-Mar-20 29-Feb-20 21-Mar-20 0 46
A3120 Molybdenum Plant Bldg. & Area 0 0 29-Feb-20* 29-Feb-20 0 42
A3130 Molybdenum Plant - Pipe Rack 0 0 21-Mar-20* 21-Mar-20 0 46
Mechanical 70 70 01-Nov-19 10-Jan-20 01-Nov-19 10-Jan-20 0 485
A3940 700412 - Metallurgical Samplers CWP 3410-002 0 0 01-Nov-19* 01-Nov-19 0 555
© Oracle Corporation
K-172 GyM Concentradora Quellaveco Classic Schedule Layout 29-Jan-20 22:51
Activity ID Activity Name Original Remaining Start Finish BLProject BLProject Remaining Total Float
Duration Duration Start Finish Labor Units
A3820 406010 - Bba Recuperada Plta Moly TAG 3410-PU-015/016 0 0 02-Nov-19* 02-Nov-19 0 25
A3830 406010 - Horizontal Process Pumps (3530-PU-006/007) - CWP 3410-002 0 0 02-Nov-19* 02-Nov-19 0 128
A3850 407006- Moly Third & Fourth cleaning colimn TAG 3410-FT-031-032 * 0 0 11-Nov-19* 11-Nov-19 0 425
A3930 700402- Stream Analyzers CWP 3410-002 0 0 10-Jan-20* 10-Jan-20 0 455
3500 Planta de Cal y Reactivos (Rx) 149 149 26-Oct-19 22-Mar-20 29-Aug-19 22-Mar-20 0 313
3510 Lime Plant 0 0 22-Mar-20 22-Mar-20 22-Mar-20 22-Mar-20 0 293
Mechanical 0 0 22-Mar-20 22-Mar-20 22-Mar-20 22-Mar-20 0 293
A3970 407013 Planta Lechada de Cal (Lime Plant) CWP 3510-002 * 0 0 22-Mar-20* 22-Mar-20 0 293
3520 Reagents and Flocculants Plant 0 0 26-Oct-19 26-Oct-19 29-Aug-19 29-Aug-19 0 462
Mechanical 0 0 26-Oct-19 26-Oct-19 29-Aug-19 29-Aug-19 0 462
A4010 407012 Planta de Floculante CWP 3520-002/004 * 0 0 26-Oct-19* 29-Aug-19 0 462
3530 Sodium Sulphide Plant 0 0 02-Nov-19 02-Nov-19 02-Nov-19 02-Nov-19 0 329
Mechanical 0 0 02-Nov-19 02-Nov-19 02-Nov-19 02-Nov-19 0 329
A4020 406010 - Horizontal centrifugal pump TAG 3530-PU-001@003 0 0 02-Nov-19* 02-Nov-19 0 329
3600 Espesamiento Filtrado y Almacenamiento Moly 124 124 02-Nov-19 04-Mar-20 02-Nov-19 04-Mar-20 0 210
3620 Cu Concentrate Thickening 123 123 02-Nov-19 04-Mar-20 02-Nov-19 04-Mar-20 0 131
Mechanical 123 123 02-Nov-19 04-Mar-20 02-Nov-19 04-Mar-20 0 131
A4040 406010 - Bba Recuperada Espesadores TAG 3620-PU-005/006 0 0 02-Nov-19* 02-Nov-19 0 254
A4030 406001 - Slurry pumps TAG 3620-PU-001@004 0 0 04-Mar-20* 04-Mar-20 0 131
3630 Cu Concentrate Filtering and Storage 83 83 02-Nov-19 23-Jan-20 02-Nov-19 23-Jan-20 0 251
Structural 0 0 23-Jan-20 23-Jan-20 23-Jan-20 23-Jan-20 0 68
A3220 Cu Concentrate Filtering and Storage 0 0 23-Jan-20* 23-Jan-20 0 68
Mechanical 0 0 02-Nov-19 02-Nov-19 02-Nov-19 02-Nov-19 0 334
A4060 406010 - Bba RecirculacionAgua Filtrado TAG 3630-PU-204/205/208/209 0 0 02-Nov-19* 02-Nov-19 0 334
3700 Espesador de Colas 114 114 01-Nov-19 23-Feb-20 01-Nov-19 23-Feb-20 0 164
3710 Tailings Thickeners 114 114 01-Nov-19 23-Feb-20 01-Nov-19 23-Feb-20 0 138
Structural 0 0 23-Feb-20 23-Feb-20 23-Feb-20 23-Feb-20 0 0
A3250 Tailing Thickeners - PipeRacks 0 0 23-Feb-20* 23-Feb-20 0 0
Mechanical 70 70 01-Nov-19 10-Jan-20 01-Nov-19 10-Jan-20 0 182
A4130 700412 - Metallurgical Samplers CWP 3710-003 0 0 01-Nov-19* 01-Nov-19 0 0
A4110 407022-RQ Tailings Thickeners - Espesador De Relaves 2 (High Rate) TAG 3710-TH-0020 0 26-Dec-19* 26-Dec-19 0 152
A4100 407022-RQ Tailings Thickeners Espesador De Relaves 1 (High Rate) TAG 3710-TH-001 0 0 10-Jan-20* 10-Jan-20 0 182
A4120 700402- Stream Analyzers CWP 3710 0 0 10-Jan-20* 10-Jan-20 0 26
3720 Water Recovery System 113 113 02-Nov-19 23-Feb-20 02-Nov-19 23-Feb-20 0 164
Structural 0 0 23-Feb-20 23-Feb-20 23-Feb-20 23-Feb-20 0 164
A3270 Tailing Water Recovery 0 0 23-Feb-20* 23-Feb-20 0 164
Mechanical 0 0 02-Nov-19 02-Nov-19 02-Nov-19 02-Nov-19 0 277
A4140 406010 - BbaAgua Recuperada deEspesadores TAG 3720-001@006 0 0 02-Nov-19* 02-Nov-19 0 277
3900 Servicios Planta Papujune 101 101 02-Nov-19 11-Feb-20 02-Nov-19 11-Feb-20 0 392
3940 Potable Water System 0 0 11-Feb-20 11-Feb-20 11-Feb-20 11-Feb-20 0 333
Mechanical 0 0 11-Feb-20 11-Feb-20 11-Feb-20 11-Feb-20 0 333
A4160 407010 Potable water plant CWP 3940-003 TAG 3940-WT-001/ 3990-WT-001 0 0 11-Feb-20* 11-Feb-20 0 333
3950 Plant Area Sewage Treatment Plant 0 0 02-Nov-19 02-Nov-19 02-Nov-19 02-Nov-19 0 493
Mechanical 0 0 02-Nov-19 02-Nov-19 02-Nov-19 02-Nov-19 0 493
A4170 406010 - Bba DescargaAgua TratadaTAG 3950-PU-005/006 0 0 02-Nov-19* 02-Nov-19 0 493
5100 Subestación de Potencia Principal 80 80 04-Nov-19 23-Jan-20 04-Nov-19 23-Jan-20 0 396
5110 Papujune Main Substation 80 80 04-Nov-19 23-Jan-20 04-Nov-19 23-Jan-20 0 396
Structural 0 0 23-Jan-20 23-Jan-20 23-Jan-20 23-Jan-20 0 366
A3290 22.9 kV Electrical Yard (Includes Underground) and Electrical Room (5110-ER-002) 0 0 23-Jan-20* 23-Jan-20 0 366
Mechanical 0 0 04-Nov-19 04-Nov-19 04-Nov-19 04-Nov-19 0 476
A4190 600004 GIS 22.9 KV & Room TAG 5110-ER-002 + Componentes 0 0 04-Nov-19* 04-Nov-19 0 476
Preensamble y Modularización 197 165 19-Sep-19 A 07-Apr-20 19-Sep-19 07-Apr-20 159860 175
© Oracle Corporation
K-172 GyM Concentradora Quellaveco Classic Schedule Layout 29-Jan-20 22:51
Activity ID Activity Name Original Remaining Start Finish BLProject BLProject Remaining Total Float
Duration Duration Start Finish Labor Units
A22010 (3630008S239) S.S.PRE-ASS.- PIPE RACK 3410-YDA-004 - 2D TRUSS 4 4 24-Jan-20 27-Jan-20 24-Jan-20 27-Jan-20 92 68
A22020 (3630008S249) S.S.PRE-ASS.- PIPE RACK 3630-YDA-001 - 2D TRUSS 4 4 28-Jan-20 31-Jan-20 28-Jan-20 31-Jan-20 69 68
A22030 (3630008S289) S.S.PRE-ASS.- PIPE RACK 3630-YDA-001 - 2D TRUSS 4 4 01-Feb-20 04-Feb-20 01-Feb-20 04-Feb-20 89 68
3D Trusses 53 53 05-Feb-20 28-Mar-20 05-Feb-20 28-Mar-20 2292 68
A22040 (3630008S319) S.S.PRE-ASS.- PIPE RACK 3410-YDA-004 - 3D TRUSS 6 6 05-Feb-20 10-Feb-20 05-Feb-20 10-Feb-20 242 68
A22050 (3630008S329) S.S.PRE-ASS.- PIPE RACK 3410-YDA-004 - 3D TRUSS 6 6 11-Feb-20 16-Feb-20 11-Feb-20 16-Feb-20 242 68
A22060 (3630008S339) S.S.PRE-ASS.- PIPE RACK 3410-YDA-004 - 3D TRUSS 6 6 17-Feb-20 22-Feb-20 17-Feb-20 22-Feb-20 232 68
A22070 (3630008S359) S.S.PRE-ASS.- PIPE RACK 3630-YDA-001 - 3D TRUSS 6 6 23-Feb-20 28-Feb-20 23-Feb-20 28-Feb-20 184 68
A22080 (3630008S369) S.S.PRE-ASS.- PIPE RACK 3630-YDA-001 - 3D TRUSS 6 6 29-Feb-20 05-Mar-20 29-Feb-20 05-Mar-20 207 68
A22090 (3630008S379) S.S.PRE-ASS.- PIPE RACK 3630-YDA-001 - 3D TRUSS 6 6 06-Mar-20 11-Mar-20 06-Mar-20 11-Mar-20 184 68
A22100 (3630008S389) S.S.PRE-ASS.- PIPE RACK 3630-YDA-001 - 3D TRUSS 6 6 12-Mar-20 17-Mar-20 12-Mar-20 17-Mar-20 207 68
A22110 (3630008S399) S.S.PRE-ASS.- SUPPORT DISTRIBUTION BOX 360-DB-001 - 3D TRUSS
11 11 18-Mar-20 28-Mar-20 18-Mar-20 28-Mar-20 794 68
Piperack Modules 63 63 05-Feb-20 07-Apr-20 05-Feb-20 07-Apr-20 13603 89
A18360 (3630002PR19) CONCENTRATE FILTER PLANT PIPERACKS 14 14 05-Feb-20 18-Feb-20 05-Feb-20 18-Feb-20 1633 89
A18370 (3630002PR29) CONCENTRATE FILTER PLANT PIPERACKS 14 14 12-Feb-20 25-Feb-20 12-Feb-20 25-Feb-20 2122 89
A18380 (3630002PR39) CONCENTRATE FILTER PLANT PIPERACKS 14 14 19-Feb-20 03-Mar-20 19-Feb-20 03-Mar-20 758 89
A18390 (3630002PR49) CONCENTRATE FILTER PLANT PIPERACKS 14 14 26-Feb-20 10-Mar-20 26-Feb-20 10-Mar-20 1297 89
A18400 (3630002PR59) CONCENTRATE FILTER PLANT PIPERACKS 14 14 04-Mar-20 17-Mar-20 04-Mar-20 17-Mar-20 1667 89
A18410 (3630002PR69) CONCENTRATE FILTER PLANT PIPERACKS 14 14 11-Mar-20 24-Mar-20 11-Mar-20 24-Mar-20 2197 89
A18420 (3630002PR79) CONCENTRATE FILTER PLANT PIPERACKS 14 14 18-Mar-20 31-Mar-20 18-Mar-20 31-Mar-20 2003 89
A18430 (3630002PR89) CONCENTRATE FILTER PLANT PIPERACKS 14 14 25-Mar-20 07-Apr-20 25-Mar-20 07-Apr-20 1926 89
3210 SAG and Ball Mills Grinding General 195 163 19-Sep-19 A 05-Apr-20 19-Sep-19 17-Mar-20 35332 31
Structural Steel Pre-Assemblies 170 138 19-Sep-19 A 11-Mar-20 19-Sep-19 11-Mar-20 30295 38
3D Trusses 32 32 30-Nov-19 31-Dec-19 31-Oct-19 01-Dec-19 2290 71
A13460 (3210021S319) S.S.PRE-ASS.- PIPE RACK 3210-YDA-001 - 3D TRUSS 4 4 30-Nov-19 03-Dec-19 31-Oct-19 03-Nov-19 320 31
A13470 (3210021S329) S.S.PRE-ASS.- PIPE RACK 3210-YDA-001 - 3D TRUSS 4 4 04-Dec-19 07-Dec-19 04-Nov-19 07-Nov-19 232 31
A13480 (3210021S339) S.S.PRE-ASS.- PIPE RACK 3210-YDA-001 - 3D TRUSS 4 4 08-Dec-19 11-Dec-19 08-Nov-19 11-Nov-19 0 31
A13490 (3210021S349) S.S.PRE-ASS.- PIPE RACK 3210-YDA-002 - 3D TRUSS 4 4 12-Dec-19 15-Dec-19 12-Nov-19 15-Nov-19 232 31
A13500 (3210021S359) S.S.PRE-ASS.- PIPE RACK 3210-YDA-002 - 3D TRUSS 4 4 16-Dec-19 19-Dec-19 16-Nov-19 19-Nov-19 320 31
A13510 (3210021S269) S.S.PRE-ASS.- PIPE RACK 3210-YDA-002 - 2D TRUSS 4 4 20-Dec-19 23-Dec-19 20-Nov-19 23-Nov-19 0 31
A13520 (3210021S379) S.S.PRE-ASS.- PIPE RACK 3210-YDA-002 - 3D TRUSS 4 4 24-Dec-19 27-Dec-19 24-Nov-19 27-Nov-19 705 31
A22850 (3210021S369) S.S.PRE-ASS.- PIPE RACK 3210-YDA-002 - 3D TRUSS 4 4 28-Dec-19 31-Dec-19 28-Nov-19 01-Dec-19 481 71
Stair Boxes 55 55 28-Dec-19 20-Feb-20 28-Nov-19 21-Jan-20 6865 31
A13540 (3210013SB49) S.S.PRE-ASS.-MILLING BUILDING-STAIRS BOX AXIS B-UPPER PART
11 11 28-Dec-19 07-Jan-20 28-Nov-19 08-Dec-19 1293 31
A13550 (3210013SB59) S.S.PRE-ASS.-MILLING BUILDING-STAIRS BOX 11 11 08-Jan-20 18-Jan-20 09-Dec-19 19-Dec-19 1159 31
A13560 (3210013SB19) S.S.PRE-ASS.-MILLING BUILDING-STAIRS BOX AXIS M-LOWER PART
11 11 19-Jan-20 29-Jan-20 20-Dec-19 30-Dec-19 1567 31
A13570 (3210013SB29) S.S.PRE-ASS.-MILLING BUILDING-STAIRS BOX AXIS M-UPPER PART
11 11 30-Jan-20 09-Feb-20 31-Dec-19 10-Jan-20 1567 31
A13530 (3210013SB39) S.S.PRE-ASS.-MILLING BUILDING-STAIRS BOX AXIS B-LOWER PART
11 11 10-Feb-20 20-Feb-20 11-Jan-20 21-Jan-20 1280 31
2D Trusses- Roof 77 75 18-Oct-19 A 08-Jan-20 22-Nov-19 02-Mar-20 4837 92
A18880 (3210041S2K9) S.S.PRE-ASS.-MILLING BLDG-ROOF 2D TRUSS-AXIS 6-7/B-C 6 21 18-Oct-19 A 15-Nov-19 04-Dec-19 09-Dec-19 197 53
A18890 (3210041S279) S.S.PRE-ASS.-MILLING BLDG-ROOF 2D TRUSS-AXIS 3-5/E-F 6 6 18-Oct-19 A 31-Oct-19 10-Dec-19 15-Dec-19 269 91
A18920 (3210041S269) S.S.PRE-ASS.-MILLING BLDG-ROOF 2D TRUSS-AXIS 3-5/G-H 6 6 18-Oct-19 A 31-Oct-19 28-Dec-19 02-Jan-20 269 91
A18870 (3210041S2G9) S.S.PRE-ASS.-MILLING BLDG-ROOF 2D TRUSS-AXIS 5-6/B-C 6 21 18-Oct-19 A 15-Nov-19 28-Nov-19 03-Dec-19 245 54
A18860 (3210041S289) S.S.PRE-ASS.-MILLING BLDG-ROOF 2D TRUSS-AXIS 3-5/B-C 6 6 09-Nov-19 14-Nov-19 22-Nov-19 27-Nov-19 315 35
A18900 (3210041S2F9) S.S.PRE-ASS.-MILLING BLDG-ROOF 2D TRUSS-AXIS 5-6/E-F 6 6 16-Nov-19 21-Nov-19 16-Dec-19 21-Dec-19 344 53
A18910 (3210041S2J9) S.S.PRE-ASS.-MILLING BLDG-ROOF 2D TRUSS-AXIS 6-7/E-F 6 6 16-Nov-19 21-Nov-19 22-Dec-19 27-Dec-19 284 53
A18930 (3210041S2E9) S.S.PRE-ASS.-MILLING BLDG-ROOF 2D TRUSS-AXIS 5-6/G-H 6 6 22-Nov-19 27-Nov-19 03-Jan-20 08-Jan-20 344 61
A18940 (3210041S2I9) S.S.PRE-ASS.-MILLING BLDG-ROOF 2D TRUSS-AXIS 6-7/G-H 6 6 22-Nov-19 27-Nov-19 09-Jan-20 14-Jan-20 284 61
A18950 (3210039S249) S.S.PRE-ASS.-MILLING BLDG-ROOF 2D TRUSS-AXIS 2-3/B-C 6 6 28-Nov-19 03-Dec-19 15-Jan-20 20-Jan-20 311 69
A18960 (3210039S239) S.S.PRE-ASS.-MILLING BLDG-ROOF 2D TRUSS-AXIS 2-3/E-F 6 6 28-Nov-19 03-Dec-19 21-Jan-20 26-Jan-20 334 92
A18970 (3210039S229) S.S.PRE-ASS.-MILLING BLDG-ROOF 2D TRUSS-AXIS 2-3/G-H 6 6 04-Dec-19 09-Dec-19 27-Jan-20 01-Feb-20 334 92
A18980 (3210042S2H9) S.S.PRE-ASS.-MILLING BLDG-ROOF 2D TRUSS-AXIS 6-7/K-L 6 6 10-Dec-19 15-Dec-19 02-Feb-20 07-Feb-20 264 92
A18990 (3210042S2D9) S.S.PRE-ASS.-MILLING BLDG-ROOF 2D TRUSS-AXIS 5-6/K-L 6 6 16-Dec-19 21-Dec-19 08-Feb-20 13-Feb-20 318 92
A19000 (3210042S259) S.S.PRE-ASS.-MILLING BLDG-ROOF 2D TRUSS-AXIS 3-4/K-L 6 6 22-Dec-19 27-Dec-19 14-Feb-20 19-Feb-20 315 92
A19010 (3210040S219) S.S.PRE-ASS.-MILLING BLDG-ROOF 2D TRUSS-AXIS 2-3/K-L 6 6 28-Dec-19 02-Jan-20 20-Feb-20 25-Feb-20 311 92
A22840 (3210021S239) S.S.PRE-ASS.- PIPE RACK 3210-YDA-001 - 2D TRUSS 6 6 03-Jan-20 08-Jan-20 26-Feb-20 02-Mar-20 98 92
VerticalAxis 170 138 19-Sep-19 A 11-Mar-20 19-Sep-19 11-Mar-20 16303 38
EjesA-H 170 138 19-Sep-19 A 11-Mar-20 19-Sep-19 11-Mar-20 9121 38
A17420 (3210041SVO9) S.S.PRE-ASS.-MILLING BLDG-VERTICALAXIS 5/F-E-LOWER PART
7 0 19-Sep-19 A 26-Oct-19 03-Oct-19 09-Oct-19 -764 43
A17440 (3210041SVM9) S.S.PRE-ASS.-MILLING BLDG-VERTICALAXIS 5/H-G-LOWER PART
7 0 20-Sep-19 A 26-Oct-19 17-Oct-19 23-Oct-19 -879 79
A17450 (3210041SVN9) S.S.PRE-ASS.-MILLING BLDG-VERTICALAXIS 5/H-G-UPPER PART
7 0 26-Sep-19 A 26-Oct-19 24-Oct-19 30-Oct-19 -634 79
A17430 (3210041SVP9) S.S.PRE-ASS.-MILLING BLDG-VERTICALAXIS 5/F-E-UPPER PART7 0 26-Sep-19 A 26-Oct-19 10-Oct-19 16-Oct-19 -635 39
A17540 (3210039SV89) S.S.PRE-ASS.-MILLING BLDG-VERTICALAXIS 2/F-E-LOWER PART7 0 27-Sep-19 A 26-Oct-19 31-Oct-19 06-Nov-19 -167 119
A17560 (3210039SV69) S.S.PRE-ASS.-MILLING BLDG-VERTICALAXIS 2/H-G-LOWER PART
7 0 27-Sep-19 A 26-Oct-19 14-Nov-19 20-Nov-19 -166 119
A17480 (3210041SVG9) S.S.PRE-ASS.-MILLING BLDG-VERTICALAXIS 3/F-E-LOWER PART
7 0 01-Oct-19 A 26-Oct-19 14-Nov-19 20-Nov-19 -687 84
A17490 (3210041SVH9) S.S.PRE-ASS.-MILLING BLDG-VERTICALAXIS 3/F-E-UPPER PART7 0 01-Oct-19 A 26-Oct-19 21-Nov-19 27-Nov-19 -168 84
A17500 (3210041SVE9) S.S.PRE-ASS.-MILLING BLDG-VERTICALAXIS 3/H-G-LOWER PART
7 0 01-Oct-19 A 26-Oct-19 28-Nov-19 04-Dec-19 -223 92
A17510 (3210041SVF9) S.S.PRE-ASS.-MILLING BLDG-VERTICALAXIS 3/H-G-UPPER PART
7 0 01-Oct-19 A 26-Oct-19 04-Dec-19 10-Dec-19 -168 92
A17460 (3210041SVI9) S.S.PRE-ASS.-MILLING BLDG-VERTICALAXIS 3/C-B-LOWER PART7 7 20-Oct-19 A 01-Nov-19 31-Oct-19 06-Nov-19 709 23
A17470 (3210041SVJ9) S.S.PRE-ASS.-MILLING BLDG-VERTICALAXIS 3/C-B-UPPER PART7 7 20-Oct-19 A 01-Nov-19 07-Nov-19 13-Nov-19 486 0
A17520 (3210039SVA9) S.S.PRE-ASS.-MILLING BLDG-VERTICALAXIS 2/C-B-LOWER PART
7 14 20-Oct-19 A 08-Nov-19 17-Oct-19 23-Oct-19 781 89
A17530 (3210039SVB9) S.S.PRE-ASS.-MILLING BLDG-VERTICALAXIS 2/C-B-UPPER PART
7 7 20-Oct-19 A 01-Nov-19 24-Oct-19 30-Oct-19 495 96
A17550 (3210039SV99) S.S.PRE-ASS.-MILLING BLDG-VERTICALAXIS 2/F-E-UPPER PART7 14 22-Oct-19 A 08-Nov-19 07-Nov-19 13-Nov-19 551 105
A17570 (3210039SV79) S.S.PRE-ASS.-MILLING BLDG-VERTICALAXIS 2/H-G-UPPER PART7 14 22-Oct-19 A 08-Nov-19 21-Nov-19 27-Nov-19 562 105
A17610 (3210041SVX9) S.S.PRE-ASS.-MILLING BLDG-VERTICALAXIS 7/F-E-UPPER PART7 14 22-Oct-19 A 08-Nov-19 12-Dec-19 18-Dec-19 508 47
A17630 (3210041SVV9) S.S.PRE-ASS.-MILLING BLDG-VERTICALAXIS 7/H-G-UPPER PART
7 21 22-Oct-19 A 15-Nov-19 20-Dec-19 26-Dec-19 527 40
A17400 (3210041SVQ9) S.S.PRE-ASS.-MILLING BLDG-VERTICALAXIS 5/C-B-LOWER PART
7 7 26-Oct-19 01-Nov-19 19-Sep-19 25-Sep-19 932 0
A17600 (3210041SVW9) S.S.PRE-ASS.-MILLING BLDG-VERTICALAXIS 7/F-E-LOWER PART
7 7 02-Nov-19 08-Nov-19 05-Dec-19 11-Dec-19 1061 35
© Oracle Corporation
K-172 GyM Concentradora Quellaveco Classic Schedule Layout 29-Jan-20 22:51
Activity ID Activity Name Original Remaining Start Finish BLProject BLProject Remaining Total Float
Duration Duration Start Finish Labor Units
© Oracle Corporation
K-172 GyM Concentradora Quellaveco Classic Schedule Layout 29-Jan-20 22:51
Activity ID Activity Name Original Remaining Start Finish BLProject BLProject Remaining Total Float
Duration Duration Start Finish Labor Units
A20020 (3310002MRJ9) ROUGHER FLOTATION CELLS ROW 2- TAG 3310-FT-012 14 14 25-Feb-20 09-Mar-20 25-Feb-20 09-Mar-20 1940 40
A20030 (3310002MRI9) ROUGHER FLOTATION CELLS ROW 2 - TAG 3310-FT-011 14 14 03-Mar-20 16-Mar-20 03-Mar-20 16-Mar-20 1940 40
Plataforma Rougher - Eje 2 52 52 28-Jan-20 19-Mar-20 28-Jan-20 19-Mar-20 6477 37
A15440 (3310002MGP9) ROUGHER FLOTATION CELLS ROW 2- TAG 3310-FT-018 - PLATFORM
11 11 28-Jan-20 07-Feb-20 28-Jan-20 07-Feb-20 810 37
A15450 (3310002MGO9) ROUGHER FLOTATION CELLS ROW 2- TAG 3310-FT-017 - PLATFORM
11 11 03-Feb-20 13-Feb-20 03-Feb-20 13-Feb-20 810 37
A15460 (3310002MGN9) ROUGHER FLOTATION CELLS ROW 2- TAG 3310-FT-016 - PLATFORM
11 11 09-Feb-20 19-Feb-20 09-Feb-20 19-Feb-20 810 37
A15470 (3310002MGM9) ROUGHER FLOTATION CELLS ROW 2 - TAG 3310-FT-015 - PLATFORM
11 11 15-Feb-20 25-Feb-20 15-Feb-20 25-Feb-20 810 37
A15480 (3310002MGL9) ROUGHER FLOTATION CELLS ROW 2- TAG 3310-FT-014 - PLATFORM
11 11 21-Feb-20 02-Mar-20 21-Feb-20 02-Mar-20 810 37
A15490 (3310002MGK9) ROUGHER FLOTATION CELLS ROW 2- TAG 3310-FT-013 - PLATFORM
11 11 27-Feb-20 08-Mar-20 27-Feb-20 08-Mar-20 810 37
A20390 (3310002MGJ9) ROUGHER FLOTATION CELLS ROW 2- TAG 3310-FT-012 - PLATFORM
11 11 04-Mar-20 14-Mar-20 04-Mar-20 14-Mar-20 810 37
A20400 (3310002MGI9) ROUGHER FLOTATION CELLS ROW 2- TAG 3310-FT-011 - PLATFORM
11 11 09-Mar-20 19-Mar-20 09-Mar-20 19-Mar-20 810 37
Celdas Rougher - Eje 1 54 54 11-Feb-20 04-Apr-20 11-Feb-20 04-Apr-20 13578 37
A20040 (3310002MRH9) ROUGHER FLOTATION CELLS ROW 1- TAG 3310-FT-008 14 14 11-Feb-20 24-Feb-20 11-Feb-20 24-Feb-20 1940 37
A20050 (3310002MRG9) ROUGHER FLOTATION CELLS ROW 1- TAG 3310-FT-007 14 14 18-Feb-20 02-Mar-20 18-Feb-20 02-Mar-20 1940 37
A20060 (3310002MRF9) ROUGHER FLOTATION CELLS ROW 1- TAG 3310-FT-006 14 14 25-Feb-20 09-Mar-20 25-Feb-20 09-Mar-20 1940 37
A20070 (3310002MRE9) ROUGHER FLOTATION CELLS ROW 1- TAG 3310-FT-005 14 14 03-Mar-20 16-Mar-20 03-Mar-20 16-Mar-20 1940 37
A20080 (3310002MRD9) ROUGHER FLOTATION CELLS ROW 1- TAG 3310-FT-004 14 14 10-Mar-20 23-Mar-20 10-Mar-20 23-Mar-20 1940 37
A20090 (3310002MRC9) ROUGHER FLOTATION CELLS ROW 1- TAG 3310-FT-003 14 14 16-Mar-20 29-Mar-20 16-Mar-20 29-Mar-20 1940 37
A20100 (3310002MRB9) ROUGHER FLOTATION CELLS ROW 1- TAG 3310-FT-002 14 14 22-Mar-20 04-Apr-20 22-Mar-20 04-Apr-20 1940 37
Plataforma Rougher - Eje 1 47 47 18-Feb-20 04-Apr-20 18-Feb-20 04-Apr-20 5667 37
A20410 (3310002MGH9) ROUGHER FLOTATION CELLS ROW 1- TAG 3310-FT-008 - PLATFORM
11 11 18-Feb-20 28-Feb-20 18-Feb-20 28-Feb-20 810 37
A20420 (3310002MGG9) ROUGHER FLOTATION CELLS ROW 1- TAG 3310-FT-007 - PLATFORM
11 11 24-Feb-20 05-Mar-20 24-Feb-20 05-Mar-20 810 37
A20430 (3310002MGF9) ROUGHER FLOTATION CELLS ROW 1- TAG 3310-FT-006 - PLATFORM
11 11 01-Mar-20 11-Mar-20 01-Mar-20 11-Mar-20 810 37
A20440 (3310002MGE9) ROUGHER FLOTATION CELLS ROW 1- TAG 3310-FT-005 - PLATFORM
11 11 07-Mar-20 17-Mar-20 07-Mar-20 17-Mar-20 810 37
A20450 (3310002MGD9) ROUGHER FLOTATION CELLS ROW 1- TAG 3310-FT-004 - PLATFORM
11 11 13-Mar-20 23-Mar-20 13-Mar-20 23-Mar-20 810 37
A20460 (3310002MGC9) ROUGHER FLOTATION CELLS ROW 1- TAG 3310-FT-003 - PLATFORM
11 11 19-Mar-20 29-Mar-20 19-Mar-20 29-Mar-20 810 37
A20470 (3310002MGB9) ROUGHER FLOTATION CELLS ROW 1- TAG 3310-FT-002 - PLATFORM
11 11 25-Mar-20 04-Apr-20 25-Mar-20 04-Apr-20 810 37
3710 Tailings Thickeners 84 84 10-Jan-20 02-Apr-20 10-Jan-20 02-Apr-20 4164 8
Mechanical Pre-Ass at Yard 26 26 10-Jan-20 04-Feb-20 10-Jan-20 04-Feb-20 2556 26
A22150 (3710003ME19) CAJON TRASPASO RELAVES FINALES 8 8 10-Jan-20 17-Jan-20 10-Jan-20 17-Jan-20 708 26
A22160 (3710003ME29) CAJON TRASPASO RELAVES FINALES 8 8 18-Jan-20 25-Jan-20 18-Jan-20 25-Jan-20 848 26
A22170 (3710003ME39) CAJON TRASPASO RELAVES FINALES 10 10 26-Jan-20 04-Feb-20 26-Jan-20 04-Feb-20 1000 26
Structural Steel Pre-Assemblies 40 40 23-Feb-20 02-Apr-20 23-Feb-20 02-Apr-20 1608 8
3D Trusses 40 40 23-Feb-20 02-Apr-20 23-Feb-20 02-Apr-20 1608 8
A22180 (3710006S319) S.S.PRE-ASS.- PIPE RACK 3520-YDA-001 - 3D TRUSS 8 8 23-Feb-20 01-Mar-20 23-Feb-20 01-Mar-20 470 8
A22190 (3710006S329) S.S.PRE-ASS.- PIPE RACK 3520-YDA-001 - 3D TRUSS 8 8 02-Mar-20 09-Mar-20 02-Mar-20 09-Mar-20 349 8
A22200 (3710006S339) S.S.PRE-ASS.- PIPE RACK 3520-YDA-001 - 3D TRUSS 8 8 10-Mar-20 17-Mar-20 10-Mar-20 17-Mar-20 349 8
A22210 (3710006S349) S.S.PRE-ASS.- PIPE RACK 3710-YDA-001 - 3D TRUSS 8 8 18-Mar-20 25-Mar-20 18-Mar-20 25-Mar-20 220 8
A22220 (3710006S359) S.S.PRE-ASS.- PIPE RACK 3710-YDA-001 - 3D TRUSS 8 8 26-Mar-20 02-Apr-20 26-Mar-20 02-Apr-20 220 8
3720 Water Recovery System 40 40 23-Feb-20 02-Apr-20 23-Feb-20 02-Apr-20 9979 180
Structural Steel Pre-Assemblies 40 40 23-Feb-20 02-Apr-20 23-Feb-20 02-Apr-20 3584 180
3D Trusses 40 40 23-Feb-20 02-Apr-20 23-Feb-20 02-Apr-20 2697 180
A22640 (3720002S369) S.S.PRE-ASS.- PIPE RACK 3720-YDA-001 - 3D TRUSS 8 8 23-Feb-20 01-Mar-20 23-Feb-20 01-Mar-20 692 180
A22650 (3720002S379) S.S.PRE-ASS.- PIPE RACK 3720-YDA-001 - 3D TRUSS 8 8 02-Mar-20 09-Mar-20 02-Mar-20 09-Mar-20 671 180
A22660 (3720002S389) S.S.PRE-ASS.- PIPE RACK 3720-YDA-001 - 3D TRUSS 8 8 10-Mar-20 17-Mar-20 10-Mar-20 17-Mar-20 339 180
A22630 (3720002S349) S.S.PRE-ASS.- PIPE RACK 3720-YDA-002 - 3D TRUSS 8 8 18-Mar-20 25-Mar-20 18-Mar-20 25-Mar-20 497 180
A22620 (3720002S339) S.S.PRE-ASS.- PIPE RACK 3720-YDA-002 - 3D TRUSS 8 8 26-Mar-20 02-Apr-20 26-Mar-20 02-Apr-20 497 180
Stair Boxes 8 8 23-Feb-20 01-Mar-20 23-Feb-20 01-Mar-20 887 212
A22600 (3720002SB19) S.S.PRE-ASS.-RECLAIM WATER SYSTEM OVERFLOW TANK 3720-K-001-STAIRS
8 8BOX
23-Feb-20 01-Mar-20 23-Feb-20 01-Mar-20 887 212
Piperack Modules 40 40 23-Feb-20 02-Apr-20 23-Feb-20 02-Apr-20 6395 164
A22710 (3720002PR19) TAILINGS THICKENERS PIPERACKS 10 10 23-Feb-20 03-Mar-20 23-Feb-20 03-Mar-20 1803 164
A22720 (3720002PR29) TAILINGS THICKENERS PIPERACKS 8 8 04-Mar-20 11-Mar-20 04-Mar-20 11-Mar-20 949 164
A22730 (3720002PR39) TAILINGS THICKENERS PIPERACKS 12 12 12-Mar-20 23-Mar-20 12-Mar-20 23-Mar-20 1954 164
A22740 (3720002PR49) TAILINGS THICKENERS PIPERACKS 10 10 24-Mar-20 02-Apr-20 24-Mar-20 02-Apr-20 1689 164
3000 Planta General 504 343 13-Sep-19 A 02-Oct-20 20-Jul-19 05-Feb-21 151517 249
3010 Papujune Plant Area General Works 504 343 13-Sep-19 A 02-Oct-20 20-Jul-19 05-Feb-21 151517 249
Underground Pipe 504 279 13-Sep-19 A 30-Jul-20 10-Sep-19 05-Feb-21 94092 313
Sector Z4S02 (Planta Concentradora a Salviani) 239 279 14-Sep-19 A 30-Jul-20 10-Sep-19 16-May-20 55359 313
A23800 Caminos y Accesos Z4S02 60 53 14-Sep-19 A 17-Dec-19 10-Sep-19 08-Nov-19 0 539
A23670 Excavación Z4S02 125 150 14-Sep-19 A 07-May-20 20-Sep-19 08-Dec-19 17952 397
A23680 Instalación de tubería Z4S02 166 250 16-Sep-19 A 01-Jul-20 19-Nov-19 16-Feb-20 27087 342
A23690 Relleno y Compactado Z4S02 229 229 01-Oct-19 A 30-Jul-20 18-Jan-20 16-May-20 10320 178
Sector Z5S01 (Planta Concentradora a Caracoles) 504 153 13-Sep-19 A 02-Jun-20 04-May-20 05-Feb-21 38733 157
Z5S01 - TRAMO I 504 0 13-Sep-19 A 26-Oct-19 A 04-May-20 05-Feb-21 0
A23700 Excavación Z5S01 90 0 13-Sep-19 A 26-Oct-19 A 04-May-20 01-Aug-20 0
A23710 Instalación de tubería Z5S01 120 0 18-Sep-19 A 26-Oct-19 A 13-Jul-20 09-Nov-20 0
A23720 Relleno y Compactado Z5S01 486 0 09-Oct-19 A 26-Oct-19 A 29-Sep-20 05-Feb-21 0
Z5S01 - TRAMO II 153 153 02-Jan-20 02-Jun-20 26383 157
A485190 Excavación Z5S01 30 30 02-Jan-20 31-Jan-20 7482 157
A485200 Instalación de tubería Z5S01 90 90 05-Mar-20 02-Jun-20 18901 157
Z5S01 - TRAMO IV 30 30 02-Mar-20 31-Mar-20 12350 217
A485250 Excavación Z5S01 30 30 02-Mar-20 31-Mar-20 12350 217
Earthwork & Civil 283 283 25-Dec-19 02-Oct-20 06-Sep-19 13-Aug-20 22787 129
C2140703566 Trabajos Enterrados Overland Area 120 120 25-Dec-19 22-Apr-20 05-Nov-19 03-Mar-20 870 45
C3010105125 Relleno Masivo en AreaEspesadores de Relaves 180 180 02-Feb-20 31-Jul-20 28-Oct-19 24-Apr-20 853 141
C3010102500 Túnel de Emergencia - Acopio de Mineral - Relleno local 234 234 12-Feb-20 02-Oct-20 24-Dec-19 13-Aug-20 0 129
C3010108156 Yards Pipes Papujune Plant Area General Civil Works -Earthwork & Civil 120 120 23-Feb-20 21-Jun-20 04-Jan-20 02-May-20 6018 129
© Oracle Corporation
K-172 GyM Concentradora Quellaveco Classic Schedule Layout 29-Jan-20 22:51
Activity ID Activity Name Original Remaining Start Finish BLProject BLProject Remaining Total Float
Duration Duration Start Finish Labor Units
C2140703556 Trabajos Enterrados Edificios - Civil Works 120 120 16-Mar-20 13-Jul-20 06-Sep-19 03-Jan-20 6018 120
C3010108200 Colectora deAguas Servidas al Sur del Area Papujune 180 180 21-Mar-20 16-Sep-20 31-Jan-20 28-Jul-20 9027 129
Concrete 140 140 25-Dec-19 12-May-20 20-Jul-19 15-Jan-20 31882 105
C3010657986 Duct Bank Concrete - Norte 102 102 25-Dec-19 04-Apr-20 20-Jul-19 17-Oct-19 10627 45
C3010657987 Duct Bank Concrete - Sur 94 94 19-Jan-20 21-Apr-20 18-Oct-19 15-Jan-20 10627 126
C80 Trabajos Enterrados (<3m) - Area Concentradora - Concrete Works 90 90 13-Feb-20 12-May-20 18-Oct-19 15-Jan-20 10628 45
Electrical and Instrumentation 90 90 25-Dec-19 23-Mar-20 05-Dec-19 03-Mar-20 2755 155
U/G Flotation & Overflow Launder/ Grinding & Regrinding Area (less than 3m deep) 90 90 25-Dec-19 23-Mar-20 05-Dec-19 03-Mar-20 2755 155
C3010653625 Trabajos enterrados (<3m) - Area Concentrado - Electricidad - Norte (Conduit) 90 90 25-Dec-19 23-Mar-20 05-Dec-19 03-Mar-20 2755 155
3100 Mineral Recuperado Stockpile a Molienda 430 267 16-May-19 A 18-Jul-20 03-May-19 18-Jul-20 356431 325
3120 Stockpile Building 100 100 02-Nov-19 09-Feb-20 30-Oct-19 02-Jan-20 5279 182
Underground Pipe 100 100 02-Nov-19 09-Feb-20 30-Oct-19 02-Jan-20 5279 182
Sector Z1S03 100 100 02-Nov-19 09-Feb-20 30-Oct-19 02-Jan-20 5279 182
A8320 Excavación Z1S03 20 20 02-Nov-19 21-Nov-19 30-Oct-19 18-Nov-19 0 172
A8330 Instalación de tubería Z1S03 60 60 22-Nov-19 20-Jan-20 19-Nov-19 13-Dec-19 4846 182
A8340 Relleno y Compactado Z1S03 20 20 21-Jan-20 09-Feb-20 14-Dec-19 02-Jan-20 432 182
3130 Reclaim Tunnel 430 267 16-May-19 A 18-Jul-20 03-May-19 18-Jul-20 346700 325
Earthwork & Civil 424 261 16-May-19 A 12-Jul-20 03-May-19 03-Jul-20 45175 331
A4955 Excavación a nivel de fondo de túnel 60 0 16-May-19 A 26-Oct-19 03-May-19 01-Jul-19 0 592
A4960 Rellenos - Linea 1 (Norte) 62 182 07-Oct-19 A 24-Apr-20 17-Nov-19 31-Jan-20 11648 22
A4970 Rellenos - Linea 2 (Sur) Incluye Tunel de Emergencia 147 147 29-Dec-19 23-May-20 07-Dec-19 20-Feb-20 12222 22
A5000 Muro TEM - Sector Oeste (Earthwork) 161 161 03-Feb-20 12-Jul-20 20-Feb-20 03-Jul-20 17976 43
A4980 Relleno nivel fondo Tuberia Multiplate 15 15 10-Mar-20 24-Mar-20 27-Feb-20 12-Mar-20 3329 55
Concrete 422 267 26-May-19 A 18-Jul-20 21-May-19 18-Jul-20 301525 325
Túneles Mayor Sección 370 215 26-May-19 A 27-May-20 21-May-19 19-May-20 201354 377
Túnel Norte - Linea 1 370 215 26-May-19 A 27-May-20 21-May-19 19-May-20 120663 377
Losa de cimentación 90 0 26-May-19 A 28-Aug-19 A 21-May-19 13-Sep-19 0
A2005 Etapa 1 - Losa de cimentación 23 0 26-May-19 A 01-Aug-19 A 21-May-19 18-Jun-19 0
A2010 Etapa 2 Norte - Losa de cimentación 65 0 19-Jun-19 A 24-Aug-19 A 19-Jun-19 17-Jul-19 0
A2115 Etapa 4 - Losa de cimentación 21 0 29-Jun-19 A 21-Aug-19 A 16-Aug-19 13-Sep-19 0
A2015 Etapa 3 - Losa de cimentación 24 0 17-Jul-19 A 28-Aug-19 A 18-Jul-19 15-Aug-19 0
Muros 241 112 19-Jun-19 A 14-Feb-20 01-Aug-19 14-Feb-20 52668 480
A2020 Etapa 01-A - Muros 22 0 19-Jun-19 A 10-Sep-19 A 01-Aug-19 04-Sep-19 0
A2045 Etapa 04-A - Muros 22 44 27-Jun-19 A 01-Jan-20 15-Aug-19 18-Sep-19 1417 378
A2035 Etapa 03-A - Muros 28 0 10-Aug-19 A 26-Oct-19 02-Nov-19 06-Dec-19 0 592
A483830 Etapa 02'-A - Muros 28 0 10-Aug-19 A 26-Oct-19 0 592
A2025 Etapa 02-A - Muros 31 0 12-Aug-19 A 29-Sep-19 A 04-Sep-19 08-Oct-19 0
A483800 Muro Salida de EmergenciaA 34 27 15-Aug-19 A 10-Jan-20 820 55
A482470 Etapa 01-B - Muros 24 41 24-Aug-19 A 25-Dec-19 1526 429
A2175 Etapa 10 - Muros 35 0 29-Aug-19 A 15-Oct-19 A 22-Dec-19 25-Jan-20 0
A482490 Etapa 03-B - Muros 35 0 21-Sep-19 A 01-Nov-19 A 0
A2055 Etapa 5-1a - Muros 32 46 21-Sep-19 A 10-Dec-19 11-Sep-19 15-Oct-19 1653 97
A482480 Etapa 02'-B - Muros 33 16 26-Sep-19 A 10-Nov-19 2822 91
A483090 Etapa 5-2a - Muros 31 38 27-Sep-19 A 02-Dec-19 2419 70
A483080 Etapa 02-B - Muros 35 53 20-Oct-19 A 17-Dec-19 3055 539
A2185 Etapa 10 - Muros (Ensanche Concreto) 21 27 20-Oct-19 A 21-Nov-19 26-Jan-20 14-Feb-20 20599 47
A483110 Etapa 5-2b - Muros 44 44 03-Dec-19 15-Jan-20 7815 70
A482510 Etapa 5-1b - Muros 45 45 15-Dec-19 28-Jan-20 5576 97
A482500 Etapa 04-B - Muros 44 44 02-Jan-20 14-Feb-20 4966 378
Losa de techo 215 215 26-Oct-19 27-May-20 06-Oct-19 19-May-20 67995 375
A483120 Prearmado deAlzaprimado 14 14 26-Oct-19 08-Nov-19 0 47
A2075 Etapa 1 - Losa de techo 67 67 15-Nov-19 20-Jan-20 06-Oct-19 18-Dec-19 17867 41
A483930 Etapa 1 - Losa de techo (Insertos/Embebidos) 1 1 08-Dec-19 08-Dec-19 9826 545
A2095 Etapa 3 - Losa de techo 64 64 21-Jan-20 24-Mar-20 06-Jan-20 10-Mar-20 15497 41
A483940 Etapa 3 - Losa de techo (Insertos/Embebidos) 1 1 29-Jan-20 29-Jan-20 8523 494
A2205 Etapa 5 - Losa de techo 64 64 25-Mar-20 27-May-20 11-Mar-20 19-May-20 16282 41
Túnel Sur - Linea 2 233 158 12-Aug-19 A 01-Apr-20 09-Sep-19 14-Apr-20 80691 434
Losa de cimentación 25 0 12-Aug-19 A 26-Oct-19 09-Sep-19 07-Oct-19 0 592
A482460 Etapa 2 Sur - Losa de cimentación 12 0 12-Aug-19 A 24-Aug-19 A 0
A2125 Etapa 5 - Losa de cimentación 19 0 25-Aug-19 A 26-Oct-19 09-Sep-19 07-Oct-19 0 592
Muros 157 90 20-Aug-19 A 23-Jan-20 01-Oct-19 26-Dec-19 28995 502
A2155 Etapa 08-A - Muros 28 0 20-Aug-19 A 26-Sep-19 A 22-Nov-19 26-Dec-19 0
A2145 Etapa 07'-A - Muros 38 0 29-Aug-19 A 30-Sep-19 A 12-Nov-19 16-Dec-19 0
A483070 Etapa 07-A - Muros 33 0 03-Oct-19 A 25-Oct-19 A 0
A2065 Etapa 06-A - Muros 30 36 11-Oct-19 A 30-Nov-19 08-Oct-19 11-Nov-19 796 445
A482530 Etapa 08-B - Muros 33 10 11-Oct-19 A 04-Nov-19 1026 61
A483100 Etapa 07'-B - Muros 28 21 18-Oct-19 A 15-Nov-19 706 571
A2165 Etapa 09-A - Muros 41 41 08-Nov-19 18-Dec-19 01-Oct-19 04-Nov-19 7087 432
A482520 Etapa 07-B - Muros 43 43 11-Nov-19 23-Dec-19 6787 270
A482550 Etapa 06-B - Muros 45 45 27-Nov-19 10-Jan-20 7629 445
A482540 Etapa 09-B - Muros 46 46 09-Dec-19 23-Jan-20 4964 432
Losa de techo 136 136 17-Nov-19 01-Apr-20 12-Nov-19 14-Apr-20 51696 432
A2085 Etapa 2 - Losa de techo 68 68 17-Nov-19 23-Jan-20 12-Nov-19 15-Jan-20 17864 239
A483970 Etapa 2 - Losa de techo (Insertos/Embebidos) 1 1 09-Dec-19 09-Dec-19 9824 544
A2105 Etapa 4 - Losa de techo 64 64 28-Jan-20 01-Apr-20 05-Feb-20 14-Apr-20 15490 234
A483980 Etapa 4 - Losa de techo (Insertos/Embebidos) 1 1 01-Feb-20 02-Feb-20 8519 491
Túneles Menor Sección 187 162 07-Oct-19 A 04-Apr-20 08-Oct-19 04-Apr-20 88716 430
Túnel Norte - Linea 1 162 137 07-Oct-19 A 10-Mar-20 08-Oct-19 10-Mar-20 42371 43
A2245 Losa de cimentación 25 2 07-Oct-19 A 27-Oct-19 08-Oct-19 16-Nov-19 0 43
© Oracle Corporation
K-172 GyM Concentradora Quellaveco Classic Schedule Layout 29-Jan-20 22:51
Activity ID Activity Name Original Remaining Start Finish BLProject BLProject Remaining Total Float
Duration Duration Start Finish Labor Units
© Oracle Corporation
K-172 GyM Concentradora Quellaveco Classic Schedule Layout 29-Jan-20 22:51
Activity ID Activity Name Original Remaining Start Finish BLProject BLProject Remaining Total Float
Duration Duration Start Finish Labor Units
© Oracle Corporation
K-172 GyM Concentradora Quellaveco Classic Schedule Layout 29-Jan-20 22:51
Activity ID Activity Name Original Remaining Start Finish BLProject BLProject Remaining Total Float
Duration Duration Start Finish Labor Units
© Oracle Corporation
K-172 GyM Concentradora Quellaveco Classic Schedule Layout 29-Jan-20 22:51
Activity ID Activity Name Original Remaining Start Finish BLProject BLProject Remaining Total Float
Duration Duration Start Finish Labor Units
© Oracle Corporation
K-172 GyM Concentradora Quellaveco Classic Schedule Layout 29-Jan-20 22:51
Activity ID Activity Name Original Remaining Start Finish BLProject BLProject Remaining Total Float
Duration Duration Start Finish Labor Units
© Oracle Corporation
K-172 GyM Concentradora Quellaveco Classic Schedule Layout 29-Jan-20 22:51
Activity ID Activity Name Original Remaining Start Finish BLProject BLProject Remaining Total Float
Duration Duration Start Finish Labor Units
© Oracle Corporation
K-172 GyM Concentradora Quellaveco Classic Schedule Layout 29-Jan-20 22:52
Activity ID Activity Name Original Remaining Start Finish BLProject BLProject Remaining Total Float
Duration Duration Start Finish Labor Units
© Oracle Corporation
K-172 GyM Concentradora Quellaveco Classic Schedule Layout 29-Jan-20 22:52
Activity ID Activity Name Original Remaining Start Finish BLProject BLProject Remaining Total Float
Duration Duration Start Finish Labor Units
© Oracle Corporation
K-172 GyM Concentradora Quellaveco Classic Schedule Layout 29-Jan-20 22:52
Activity ID Activity Name Original Remaining Start Finish BLProject BLProject Remaining Total Float
Duration Duration Start Finish Labor Units
© Oracle Corporation
K-172 GyM Concentradora Quellaveco Classic Schedule Layout 29-Jan-20 22:52
Activity ID Activity Name Original Remaining Start Finish BLProject BLProject Remaining Total Float
Duration Duration Start Finish Labor Units
Celdas Scavenger 3310-FT-064/1° Limpieza 3310-FT-053 103 103 26-Oct-19 05-Feb-20 18-Oct-19 26-Dec-19 5094 489
A9665 Fundación 13 13 26-Oct-19 07-Nov-19 18-Oct-19 28-Oct-19 1263 67
Muros 24 24 03-Jan-20 26-Jan-20 03-Nov-19 26-Dec-19 3668 491
A9675 Muro de Octogono Este 3310-FT-053 12 12 03-Jan-20 14-Jan-20 03-Nov-19 23-Nov-19 1928 491
A9695 Muro de Octogono Oeste 3310-FT-064 12 12 03-Jan-20 14-Jan-20 28-Nov-19 17-Dec-19 1600 25
A9685 Muro Destaje Octogono Este 3310-FT-053 8 8 19-Jan-20 26-Jan-20 06-Dec-19 10-Dec-19 70 491
A9705 Muro Destaje Octogono Oeste 3310-FT-064 8 8 19-Jan-20 26-Jan-20 22-Dec-19 26-Dec-19 70 489
Losas 8 8 29-Jan-20 05-Feb-20 163 489
A483450 Losa de Piso Oeste 3310-FT-064 8 8 29-Jan-20 05-Feb-20 81 489
A483460 Losa de Piso Este 3310-FT-053 8 8 29-Jan-20 05-Feb-20 81 489
Celdas Scavenger 3310-FT-065/066 113 113 26-Oct-19 15-Feb-20 16-Sep-19 15-Nov-19 4898 479
A9485 Fundación 3310-FT-065/066 13 13 26-Oct-19 07-Nov-19 16-Sep-19 26-Sep-19 1263 83
Muros 24 24 15-Jan-20 07-Feb-20 27-Sep-19 15-Nov-19 3472 479
A9495 Muro de Octogono Este 3310-FT-065 12 12 15-Jan-20 26-Jan-20 27-Sep-19 17-Oct-19 1838 479
A9515 Muro de Octogono Oeste 3310-FT-066 12 12 15-Jan-20 26-Jan-20 18-Oct-19 06-Nov-19 1493 479
A9525 Muro Destaje Octogono Oeste 3310-FT-066 8 8 31-Jan-20 07-Feb-20 11-Nov-19 15-Nov-19 70 479
A9505 Muro Destaje Octogono Este 3310-FT-065 8 8 31-Jan-20 07-Feb-20 22-Oct-19 26-Oct-19 70 479
Losas 8 8 08-Feb-20 15-Feb-20 163 479
A483410 Losa de Piso Oeste 3310-FT-066 8 8 08-Feb-20 15-Feb-20 81 479
A483420 Losa de Piso Este 3310-FT-065 8 8 08-Feb-20 15-Feb-20 81 479
Celda Scavenger 3310-FT-067 47 47 05-Jan-20 20-Feb-20 18-Aug-19 24-Sep-19 2947 474
A9385 Fundación 3310-FT-067 13 13 05-Jan-20 17-Jan-20 18-Aug-19 26-Aug-19 1061 25
Muros 24 24 18-Jan-20 10-Feb-20 26-Aug-19 24-Sep-19 1805 472
A9395 Muro de Octogono 3310-FT-067 12 12 18-Jan-20 29-Jan-20 26-Aug-19 15-Sep-19 1735 472
A9405 Muro Destaje Octogono 3310-FT-067 8 8 03-Feb-20 10-Feb-20 20-Sep-19 24-Sep-19 70 472
Losas 8 8 13-Feb-20 20-Feb-20 81 474
A483390 Losa de Piso Este 3310-FT-067 8 8 13-Feb-20 20-Feb-20 81 474
Celda Scavenger 3310-FT-068 47 47 05-Jan-20 20-Feb-20 1374 474
A483530 Fundación 3310-FT-068(FUTURA) 13 13 05-Jan-20 17-Jan-20 1009 25
A483540 Muro de Octogono 3310-FT-068 (FUTURA) 12 12 18-Jan-20 29-Jan-20 365 25
A484810 Losa de Piso 3310-FT-068 (FUTURA) 8 8 13-Feb-20 20-Feb-20 0 474
Celdas 1° Limpieza 3310-FT-047/048 49 49 12-Nov-19 30-Dec-19 15-Dec-19 23-Feb-20 5882 477
A9935 Fundación 11 11 12-Nov-19* 22-Nov-19 15-Dec-19 25-Dec-19 1386 0
Muros 24 24 23-Nov-19 16-Dec-19 05-Jan-20 23-Feb-20 4333 477
A9965 Muro de Octogono Oeste 3310-FT-048 12 12 23-Nov-19 04-Dec-19 26-Jan-20 14-Feb-20 1866 25
A9945 Muro de Octogono Este 3310-FT-047 12 12 23-Nov-19 04-Dec-19 05-Jan-20 25-Jan-20 2326 25
A9975 Muro Destaje Octogono Oeste 3310-FT-048 8 8 09-Dec-19 16-Dec-19 19-Feb-20 23-Feb-20 70 477
A9955 Muro Destaje Octogono Este 3310-FT-047 8 8 09-Dec-19 16-Dec-19 02-Feb-20 06-Feb-20 70 477
Losas 8 8 23-Dec-19 30-Dec-19 163 477
A483510 Losa de Piso Oeste 3310-FT-048 8 8 23-Dec-19 30-Dec-19 81 477
A483520 Losa de Piso Este 3310-FT-047 8 8 23-Dec-19 30-Dec-19 81 477
Celdas Scavenger 3310-FT-059/1° Limpieza 3310-FT-049 54 54 15-Nov-19 07-Jan-20 08-Nov-19 15-Jan-20 5288 518
A9755 Fundación 13 13 15-Nov-19 27-Nov-19 08-Nov-19 18-Nov-19 1457 28
Muros 24 24 05-Dec-19 28-Dec-19 24-Nov-19 15-Jan-20 3668 510
A9785 Muro de Octogono Oeste 3310-FT-059 12 12 05-Dec-19 16-Dec-19 18-Dec-19 06-Jan-20 1600 25
A9765 Muro de Octogono Este 3310-FT-049 12 12 05-Dec-19 16-Dec-19 24-Nov-19 14-Dec-19 1928 510
A9795 Muro Destaje Octogono Oeste 3310-FT-059 8 8 21-Dec-19 28-Dec-19 11-Jan-20 15-Jan-20 70 25
A9775 Muro Destaje Octogono Este 3310-FT-049 8 8 21-Dec-19 28-Dec-19 26-Dec-19 30-Dec-19 70 510
Losas 8 8 31-Dec-19 07-Jan-20 163 518
A483470 Losa de Piso Oeste 3310-FT-059 8 8 31-Dec-19 07-Jan-20 81 510
A483480 Losa de Piso Este 3310-FT-049 8 8 31-Dec-19 07-Jan-20 81 518
Celdas Scavenger 3310-FT-060/061 49 49 28-Nov-19 15-Jan-20 07-Oct-19 06-Dec-19 5091 510
A9575 Fundación 12 12 28-Nov-19 09-Dec-19 07-Oct-19 17-Oct-19 1457 28
Muros 27 27 10-Dec-19 05-Jan-20 18-Oct-19 06-Dec-19 3472 510
A9585 Muro de Octogono Este 3310-FT-060 12 12 10-Dec-19 21-Dec-19 18-Oct-19 07-Nov-19 1838 513
A9605 Muro de Octogono Oeste 3310-FT-061 12 12 10-Dec-19 21-Dec-19 08-Nov-19 27-Nov-19 1493 28
A9615 Muro Destaje Octogono Oeste 3310-FT-061 8 8 29-Dec-19 05-Jan-20 02-Dec-19 06-Dec-19 70 25
A9595 Muro Destaje Octogono Este 3310-FT-060 8 8 29-Dec-19 05-Jan-20 15-Nov-19 19-Nov-19 70 510
Losas 8 8 08-Jan-20 15-Jan-20 163 510
A483430 Losa de Piso Oeste 3310-FT-061 8 8 08-Jan-20 15-Jan-20 81 510
A483440 Losa de Piso Este 3310-FT-060 8 8 08-Jan-20 15-Jan-20 81 510
Celda Scavenger 3310-FT-062 47 47 10-Dec-19 25-Jan-20 27-Aug-19 15-Oct-19 3113 500
A9435 Fundación 13 13 10-Dec-19 22-Dec-19 27-Aug-19 04-Sep-19 1227 500
Muros 24 24 23-Dec-19 15-Jan-20 16-Sep-19 15-Oct-19 1805 500
A9445 Muro de Octogono 3310-FT-062 12 12 23-Dec-19 03-Jan-20 16-Sep-19 06-Oct-19 1735 500
A9455 Muro Destaje Octogono 3310-FT-062 8 8 08-Jan-20 15-Jan-20 11-Oct-19 15-Oct-19 70 500
Losas 8 8 18-Jan-20 25-Jan-20 81 500
A483400 Losa de Piso Este 3310-FT-062 8 8 18-Jan-20 25-Jan-20 81 500
Celda Scavenger 3310-FT-063 47 47 10-Dec-19 25-Jan-20 1374 500
A483550 Fundación 3310-FT-063(FUTURA) 13 13 10-Dec-19 22-Dec-19 1009 500
A483560 Muro de Octogono 3310-FT-063 (FUTURA) 12 12 23-Dec-19 03-Jan-20 365 500
A484780 Muro Destaje Octogono 3310-FT-063 (FUTURA) 8 8 08-Jan-20 15-Jan-20 0 500
A484790 Losa de Piso 3310-FT-063 (FUTURA) 8 8 18-Jan-20 25-Jan-20 0 500
Piperack y Fundaciones Miscelaneas 84 84 15-Jan-20 08-Apr-20 20-Dec-19 07-Apr-20 18723 426
A355 Concreto Piperacks y Misc - Lado Norte 40 40 15-Jan-20 24-Feb-20 28-Feb-20 07-Apr-20 3569 73
A485150 Puente Vehicular 40 40 25-Jan-20 05-Mar-20 4793 460
A345 Concreto Piperacks y Misc - Lado Este 50 50 18-Feb-20 08-Apr-20 20-Dec-19 07-Feb-20 10362 236
Muros en Celdas de Flotación 167 144 08-Sep-19 A 17-Mar-20 17-Oct-19 09-Apr-20 11264 448
Muro Lado Sur (De Oeste a Este) 71 71 03-Nov-19 12-Jan-20 28-Nov-19 19-Mar-20 9011 464
Muro 1 35 35 03-Nov-19 07-Dec-19 28-Nov-19 28-Dec-19 1802 444
© Oracle Corporation
K-172 GyM Concentradora Quellaveco Classic Schedule Layout 29-Jan-20 22:52
Activity ID Activity Name Original Remaining Start Finish BLProject BLProject Remaining Total Float
Duration Duration Start Finish Labor Units
© Oracle Corporation
K-172 GyM Concentradora Quellaveco Classic Schedule Layout 29-Jan-20 22:52
Activity ID Activity Name Original Remaining Start Finish BLProject BLProject Remaining Total Float
Duration Duration Start Finish Labor Units
© Oracle Corporation
K-172 GyM Concentradora Quellaveco Classic Schedule Layout 29-Jan-20 22:52
Activity ID Activity Name Original Remaining Start Finish BLProject BLProject Remaining Total Float
Duration Duration Start Finish Labor Units
© Oracle Corporation
K-172 GyM Concentradora Quellaveco Classic Schedule Layout 29-Jan-20 22:52
Activity ID Activity Name Original Remaining Start Finish BLProject BLProject Remaining Total Float
Duration Duration Start Finish Labor Units
Pipe RacksArea Espesadores deRelave 30 30 05-Dec-19 03-Jan-20 02-Aug-20 31-Aug-20 4056 307
A7830 Fundación Lado Sur (Entre Espesadores) 30 30 05-Dec-19 03-Jan-20 02-Aug-20 31-Aug-20 4056 307
Mechanical 88 88 26-Dec-19 23-Mar-20 26-Dec-19 24-Mar-20 7485 152
Espesador de Relave 3710-TH-002 44 44 26-Dec-19 08-Feb-20 26-Dec-19 08-Feb-20 3742 152
C2000 Labores de Preensamble 44 44 26-Dec-19 08-Feb-20 26-Dec-19 08-Feb-20 3742 152
Espesador de Relave 3710-TH-001 44 44 08-Feb-20 23-Mar-20 09-Feb-20 24-Mar-20 3742 152
C320 Labores de Preensamble 44 44 08-Feb-20 23-Mar-20 09-Feb-20 24-Mar-20 3742 152
3900 Servicios Planta Papujune 436 300 21-May-19 A 20-Aug-20 12-Jun-19 18-Oct-20 355 292
3810 Edificios de Soporte yAdministración 62 25 21-May-19 A 19-Nov-19 12-Jun-19 15-Aug-19 355 567
Underground Pipe 62 25 21-May-19 A 19-Nov-19 12-Jun-19 15-Aug-19 355 567
Sector Z2S11 62 25 21-May-19 A 19-Nov-19 12-Jun-19 15-Aug-19 355 567
A23310 Excavación Z2S11 20 11 21-May-19 A 05-Nov-19 12-Jun-19 01-Jul-19 28 581
A23320 Instalación de tubería Z2S11 25 17 30-May-19 A 11-Nov-19 02-Jul-19 26-Jul-19 236 575
A23330 Relleno y Compactado Z2S11 20 25 24-Jun-19 A 19-Nov-19 27-Jul-19 15-Aug-19 91 567
3930 Fresh Water Tank and System 150 150 24-Mar-20 20-Aug-20 22-May-20 18-Oct-20 0 182
Earthwork & Civil 150 150 24-Mar-20 20-Aug-20 22-May-20 18-Oct-20 0 182
A5300 Excavaciones Estructurales - EstanqueAgua Fresca 150 150 24-Mar-20 20-Aug-20 22-May-20 18-Oct-20 0 182
5100 Subestación de Potencia Principal 392 150 11-May-19 A 13-May-20 18-Apr-19 18-Apr-20 65475 391
5110 Papujune Main Substation 392 150 11-May-19 A 13-May-20 18-Apr-19 18-Apr-20 65475 391
Underground Pipe 115 0 11-May-19 A 07-Sep-19 A 18-Apr-19 10-Aug-19 0
Sector Z2S10 115 0 11-May-19 A 07-Sep-19 A 18-Apr-19 10-Aug-19 0
A23340 Excavación Z2S10 35 0 11-May-19 A 29-Jun-19 A 18-Apr-19 22-May-19 0
A23350 Instalación de tubería Z2S10 40 0 19-May-19 A 29-Jun-19 A 23-May-19 01-Jul-19 0
A23360 Relleno y Compactado Z2S10 40 0 12-Jun-19 A 07-Sep-19 A 02-Jul-19 10-Aug-19 0
Earthwork & Civil 130 130 16-Dec-19 23-Apr-20 01-Dec-19 08-Apr-20 6382 395
C5110115260 Patio Electrico 22,9kV - Banco Ductos/Obras Civiles y Construcción SE 5110-ER-002 90 90 16-Dec-19 14-Mar-20 01-Dec-19 28-Feb-20 2127 298
C2140703856 Emergency Generators , Electrical Room (5110-ER-003) and Transformers- Civil Works90 90 05-Jan-20 03-Apr-20 21-Dec-19 19-Mar-20 2127 319
C2140703866 60 KV Electrical Yard and Electrical Room (5110-ER-004)- Civil Works 90 90 25-Jan-20 23-Apr-20 10-Jan-20 08-Apr-20 2127 395
Concrete 130 130 01-Jan-20 09-May-20 30-Jan-20 18-Apr-20 56709 298
C2140703876 Patio Electrico 22,9kV - Banco Ductos/Obras Civiles y Construcción SE 5110-ER-002 90 90 01-Jan-20 30-Mar-20 30-Jan-20 29-Mar-20 45663 298
C5110115010 Generadores de Emergencia - Obra Civil 80 80 20-Feb-20 09-May-20 19-Feb-20 18-Apr-20 11046 298
Electrical 60 60 15-Mar-20 13-May-20 2384 391
C2140706976 Puesta a Tierra 60 60 15-Mar-20 13-May-20 2384 391
© Oracle Corporation
K-172 GyM Concentradora Quellaveco Classic Schedule Layout 29-Jan-20 22:52
Activity ID Activity Name Original Remaining Start Finish BLProject BLProject Remaining Total Float
Duration Duration Start Finish Labor Units
© Oracle Corporation