Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Programacion Combapata
Programacion Combapata
7/16/2018
7/17/2018
7/18/2018
7/19/2018
7/20/2018
7/21/2018
7/22/2018
7/23/2018
7/24/2018
7/25/2018
7/26/2018
7/27/2018
7/28/2018
7/29/2018
7/30/2018
7/31/2018
8/1/2018
8/2/2018
8/3/2018
8/4/2018
8/5/2018
LINEA BASE (Base CONTROL DE AVANCE
ACTIVIDADES (Activities) Line) REPROGRAMADO (Rescheduled) (Advance Control) ESTATUS RESTRICCIONES (To Do List)
DURACIÓN (Duration
DÍAS DE RETRASO EN
DIAS COMPLETADOS
Días Restantes
DIAS PENDIENTES
RUTA CRITICA
(Days Remaining)
% COMPLETADO
(Days Complete)
(Remaining
PRIORIDAD
A (Adelantado)
(Critical Path)
ITEM (WBS)
EL PROYECTO
E (Finalizado)
METRADO
P (Progreso)
(Priority)
(Complete)
D (Retraso)
Fecha de
Days)
(Days))
RESPONSABLE Estatus
TAREA (Task) UND Start End Start End SEMANA 01 SEMANA 02 SEMANA 03 DESCRIPCION (Notes)
(Owner)
Cumplimiento
(Status)
(Due Date)
1.7 DESMONTAJE Y TRASLADO DE ESTRUCTURAS METÁLICAS, MADERA U OTROS ton 146.97 28/08/18 22/09/18 26 0% 0 26
1.8 DESBROCE Y LIMPIEZA EN ZONA NO BOSCOSA ha 0.03 12/07/18 15/07/18 4 0% 0 4
1.9 PLATAFORMA PARA EXCAVACION DE PILOTES 23/07/18 26/07/18 4 0% 0 4
1.10 REUBICACIÓN DE INTERFERENCIAS glb 1.00 06/07/18 24/07/18 19 20% 3 16
2 DESVÍO PROVISIONAL 12/07/18 08/10/18 89 0% 0 89
2.1 LIMPIEZA, MANTENIMIENTO Y CONSERVACIÓN DEL DESVÍO glb 1.00 20/08/18 08/10/18 50 0% 0 50
2.2 DESBROCE Y LIMPIEZA EN ZONA NO BOSCOSA Ha 0.17 12/07/18 17/07/18 6 50% 3 3
2.3 EXCAVACIÓN PARA EXPLANACIONES (SIN CLASIFICAR) m3 459.05 12/07/18 17/07/18 6 50% 3 3
2.4 EXCAVACIÓN PARA ESTRUCTURAS EN MATERIAL COMUN SECO m3 514.56 13/07/18 17/07/18 5 50% 2 3
2.5 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO m3 105.36 06/08/18 06/08/18 1 0% 0 1
2.6 TERRAPLEN CON MATERIAL PROPIO m3 1,136.66 07/08/18 11/08/18 5 0% 0 5
2.7 AFIRMADOS m3 258.66 12/08/18 16/08/18 5 0% 0 5
2.8 TRATAMIENTO SUPERFICIAL BICAPA m2 19.73 17/08/18 19/08/18 3 0% 0 3
2.9 CONCRETO (CLASE G) F'C=100 kg/cm2 (FALSA ZAPATA DE ESTRIBOS) m3 61.00 20/07/18 20/07/18 1 0% 0 1
2.10 CONCRETO ESTRUCTURAL (CLASE D) F'C=210 kg/cm2 m3 274.96 29/07/18 30/07/18 2 0% 0 2
2.11 ACERO DE REFUERZO FY=4200 KG/CM2 kg 2,321.75 21/07/18 24/07/18 4 0% 0 4
2.12 ENCOFRADO Y DESENCOFRADO NORMAL m2 241.50 25/07/18 28/07/18 4 0% 0 4
3.2 CONCRETO ESTRUCTURAL (CLASE C) F'C=280 kg/cm2 EN PILOTES BAJO AGUA m3 141.73 27/07/18 30/07/18 4 0% 0 4
3.3 ACERO DE REFUERZO FY=4200 kg/cm2 EN PILOTES kg 17,230.64 27/07/18 30/07/18 4 0% 0 4
3.4 CORTE DE CABEZALES und 4.00 06/08/18 09/08/18 4 0% 0 4
3.5 PRUEBA DE INTEGRIDAD DE PILOTES und 4.00 10/08/18 13/08/18 4 0% 0 4
3.6 MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPOS DE PILOTAJE Glb 1.00 25/06/18 25/06/18 1 0% 0 1
PROGRAMACION - 4 WEEKS
CONSTRUCCION DE PUENTES POR REMPLAZO EN CUSCO - PUENTE COMBAPATA
3/10/2019
3/11/2019
3/12/2019
3/13/2019
3/14/2019
3/15/2019
3/16/2019
3/17/2019
3/18/2019
3/19/2019
3/20/2019
3/21/2019
3/22/2019
3/23/2019
3/24/2019
3/25/2019
3/26/2019
3/27/2019
3/28/2019
3/29/2019
3/30/2019
3/31/2019
4/10/2019
4/11/2019
4/12/2019
4/13/2019
4/14/2019
4/15/2019
4/16/2019
4/17/2019
4/18/2019
4/19/2019
4/20/2019
4/21/2019
4/22/2019
4/23/2019
4/24/2019
4/25/2019
4/26/2019
4/27/2019
4/28/2019
4/29/2019
4/30/2019
5/10/2019
5/11/2019
5/12/2019
5/13/2019
3/4/2019
3/5/2019
3/6/2019
3/7/2019
3/8/2019
3/9/2019
4/1/2019
4/2/2019
4/3/2019
4/4/2019
4/5/2019
4/6/2019
4/7/2019
4/8/2019
4/9/2019
5/1/2019
5/2/2019
5/3/2019
5/4/2019
5/5/2019
5/6/2019
5/7/2019
5/8/2019
5/9/2019
ACTIVIDADES REPROGRAMADO CONTROL DE AVANCE ESTATUS
DÍAS DE RETRASO EN
DIAS COMPLETADOS
DIAS PENDIENTES
% COMPLETADO
A (Adelantado)
EL PROYECTO
E (Finalizado)
P (Progreso)
D (Retraso)
DURACIÓN
ITEM
TAREA Inicio Fin SEMANA 62 SEMANA 63 SEMANA 64 SEMANA 65 SEMANA 66 SEMANA 67 SEMANA 68 SEMANA 69 SEMANA 70 SEMANA 71 SEM
3.2 CONCRETO ESTRUCTURAL (CLASE C) F'C= 280 kg/cm2 EN LOSA DE APROXIMACION 10/06/19 13/06/19 4 0% 0 4 P
4.1 CONCRETO ESTRUCTURAL (CLASE C) F'C= 280 kg/cm2 EN MURO NEW JERSEY 15/06/19 21/06/19 7 0% 0 7 P
4.2 ACERO DE REFUERZO FY=4200 KG/CM2 27/05/19 02/06/19 7 0% 0 7 P
4.3 ENCOFRADO Y DESENCOFRADO CARAVISTA EN MURO NEW JERSEY 02/06/19 15/06/19 14 0% 0 14 P
4.4 PINTADO DE MUROS NEW JERSEY 05/07/19 11/07/19 7 0% 0 7 P
4.5 JUNTA EN MURO NEW JERSEY 21/06/19 27/06/19 7 0% 0 7 P
20/06/18 11/07/19
5/14/2019
5/15/2019
5/16/2019
SEMANA 72
5/17/2019
5/18/2019
5/19/2019
5/20/2019
5/21/2019
5/22/2019
5/23/2019
SEMANA 73
5/24/2019
5/25/2019
5/26/2019
5/27/2019
5/28/2019
5/29/2019
SEMANA 74 5/30/2019
5/31/2019
6/1/2019
6/2/2019
6/3/2019
6/4/2019
6/5/2019
6/6/2019
SEMANA 75
6/7/2019
6/8/2019
6/9/2019
6/10/2019
6/11/2019
6/12/2019
6/13/2019
SEMANA 76
6/14/2019
6/15/2019
6/16/2019
6/17/2019
6/18/2019
6/19/2019
6/20/2019
SEMANA 77
6/21/2019
6/22/2019
6/23/2019
6/24/2019
6/25/2019
6/26/2019
6/27/2019
SEMANA 78
6/28/2019
6/29/2019
6/30/2019
7/1/2019
7/2/2019
7/3/2019
7/4/2019
SEMANA 79
7/5/2019
7/6/2019
7/7/2019
7/8/2019
7/9/2019
7/10/2019
7/11/2019
SEMANA 80
7/12/2019
7/13/2019
7/14/2019
7/15/2019
7/16/2019
7/17/2019
7/18/2019
SEMANA 81
7/19/2019
7/20/2019
7/21/2019
7/22/2019
7/23/2019
7/24/2019
7/25/2019
SEMANA 82
7/26/2019
7/27/2019
7/28/2019
7/29/2019
7/30/2019
7/31/2019
8/1/2019
SEMANA 83
8/2/2019
8/3/2019
8/4/2019
8/5/2019
8/6/2019
8/7/2019
8/8/2019
SEMANA 84
8/9/2019
8/10/2019
8/11/2019
8/12/2019
8/13/2019
8/14/2019
8/15/2019
SEMANA 85
8/16/2019
8/17/2019
8/18/2019
8/19/2019
8/20/2019
8/21/2019
8/22/2019
SEMANA 86
8/23/2019
8/24/2019
8/25/2019
8/26/2019
8/27/2019
8/28/2019
8/29/2019
SEMANA 87
8/30/2019
8/31/2019
9/1/2019
9/2/2019
9/3/2019
9/4/2019
9/5/2019
SEMANA 88
SEMANA 88
9/6/2019
9/7/2019
9/8/2019
9/9/2019
9/10/2019
9/11/2019
9/12/2019
SEMANA 89
9/13/2019
9/14/2019
9/15/2019
9/16/2019
9/17/2019
9/18/2019
9/19/2019
SEMANA 90
9/20/2019
9/21/2019
9/22/2019
9/23/2019
9/24/2019
9/25/2019
9/26/2019
SEMANA 91
9/27/2019
9/28/2019
9/29/2019
9/30/2019
10/1/2019
10/2/2019
10/3/2019
SEMANA 92
10/4/2019
10/5/2019
10/6/2019
10/7/2019
10/8/2019
10/9/2019
10/10/2019
SEMANA 93
10/11/2019
10/12/2019
10/13/2019
10/14/2019
10/15/2019
10/16/2019
10/17/2019
SEMANA 94
10/18/2019
10/19/2019
10/20/2019
10/21/2019
10/22/2019
10/23/2019
10/24/2019
SEMANA 95
10/25/2019
10/26/2019
10/27/2019
10/28/2019
10/29/2019
10/30/2019
10/31/2019
SEMANA 96
11/1/2019
11/2/2019
11/3/2019
DESCRIPCION
RESTRICCIONES
ESTATUS
PRIORIDAD
RESPONSABLE
BAJA
ALTA
PRIORIDAD
MEDIA
Atrasado
Ejecutado
B
A
En Progreso
Fecha de
Cumplimiento
P
D
O
Días Restantes
Estatus