LOOKAHEAD - 3 WEEKS A

CONSTRUCCION DE PUENTES POR REMPLAZO EN CUSCO - PUENTE CUSIPATA PRIORIDAD


(Priority) ALTA
PROGRAMADO TAREA MEDIA M
FRENTE DE TRABAJO (PROJECT): (Scheduled) SUB-TAREA BAJA B
FECHA DE FIN DE
OBRA 3/19/2019 AVANCE
CONTRATISTA (CONTRACTOR): (Progress) TAREA Estatus (Status) En Progreso (Progress) P
22-Jun 19-Mar SUB-TAREA Atrasado (Outdated) O
Residente (Project Lead): JORGE UBILLUS Ejecutado (Done) D
Ininicio 3W (Start Date): lunes 7/16/2018
Fecha actual (Today): Friday 03/07/20

7/16/2018

7/17/2018

7/18/2018

7/19/2018

7/20/2018

7/21/2018

7/22/2018

7/23/2018

7/24/2018

7/25/2018

7/26/2018

7/27/2018

7/28/2018

7/29/2018

7/30/2018

7/31/2018

8/1/2018

8/2/2018

8/3/2018

8/4/2018

8/5/2018
LINEA BASE (Base CONTROL DE AVANCE
ACTIVIDADES (Activities) Line) REPROGRAMADO (Rescheduled) (Advance Control) ESTATUS RESTRICCIONES (To Do List)

DURACIÓN (Duration

DÍAS DE RETRASO EN
DIAS COMPLETADOS

Días Restantes
DIAS PENDIENTES
RUTA CRITICA

(Days Remaining)
% COMPLETADO

(Days Complete)

(Remaining
PRIORIDAD
A (Adelantado)
(Critical Path)
ITEM (WBS)

EL PROYECTO
E (Finalizado)
METRADO

P (Progreso)

(Priority)
(Complete)

D (Retraso)
Fecha de

Days)
(Days))
RESPONSABLE Estatus
TAREA (Task) UND Start End Start End SEMANA 01 SEMANA 02 SEMANA 03 DESCRIPCION (Notes)
(Owner)
Cumplimiento
(Status)
(Due Date)

1 TRABAJOS PRELIMINARES 22/06/18 14/05/19 327 1% 2 325


1.1 MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPO (3) glb 1.00 22/06/18 27/06/18 6 15% 0 6
1.2 TOPOGRAFIA PERMANENTE DE OBRA mes 9.00 22/06/18 13/03/19 265 0% 0 265
1.3 MANTENIMIENTO DE TRÁNSITO TEMPORAL Y SEGURIDAD VIAL mes 9.00 20/08/18 14/05/19 268 0% 0 268
1.4 ACCESOS A CANTERAS, DME, PLANTAS Y FUENTES DE AGUA km 0.57 02/01/00 4 0% 0 4
1.5 DEMOLICIÓN DE ESTRUCTURAS DE CONCRETO m3 525.40 23/09/18 28/09/18 6 0% 0 6
1.6 DEMOLICIÓN DE PAVIMENTOS, SARDINELES Y VEREDAS DE CONCRETO m3 55.10 20/08/18 27/08/18 8 0% 0 8

1.7 DESMONTAJE Y TRASLADO DE ESTRUCTURAS METÁLICAS, MADERA U OTROS ton 146.97 28/08/18 22/09/18 26 0% 0 26
1.8 DESBROCE Y LIMPIEZA EN ZONA NO BOSCOSA ha 0.03 12/07/18 15/07/18 4 0% 0 4
1.9 PLATAFORMA PARA EXCAVACION DE PILOTES 23/07/18 26/07/18 4 0% 0 4
1.10 REUBICACIÓN DE INTERFERENCIAS glb 1.00 06/07/18 24/07/18 19 20% 3 16
2 DESVÍO PROVISIONAL 12/07/18 08/10/18 89 0% 0 89
2.1 LIMPIEZA, MANTENIMIENTO Y CONSERVACIÓN DEL DESVÍO glb 1.00 20/08/18 08/10/18 50 0% 0 50
2.2 DESBROCE Y LIMPIEZA EN ZONA NO BOSCOSA Ha 0.17 12/07/18 17/07/18 6 50% 3 3
2.3 EXCAVACIÓN PARA EXPLANACIONES (SIN CLASIFICAR) m3 459.05 12/07/18 17/07/18 6 50% 3 3
2.4 EXCAVACIÓN PARA ESTRUCTURAS EN MATERIAL COMUN SECO m3 514.56 13/07/18 17/07/18 5 50% 2 3
2.5 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO m3 105.36 06/08/18 06/08/18 1 0% 0 1
2.6 TERRAPLEN CON MATERIAL PROPIO m3 1,136.66 07/08/18 11/08/18 5 0% 0 5
2.7 AFIRMADOS m3 258.66 12/08/18 16/08/18 5 0% 0 5
2.8 TRATAMIENTO SUPERFICIAL BICAPA m2 19.73 17/08/18 19/08/18 3 0% 0 3
2.9 CONCRETO (CLASE G) F'C=100 kg/cm2 (FALSA ZAPATA DE ESTRIBOS) m3 61.00 20/07/18 20/07/18 1 0% 0 1
2.10 CONCRETO ESTRUCTURAL (CLASE D) F'C=210 kg/cm2 m3 274.96 29/07/18 30/07/18 2 0% 0 2
2.11 ACERO DE REFUERZO FY=4200 KG/CM2 kg 2,321.75 21/07/18 24/07/18 4 0% 0 4
2.12 ENCOFRADO Y DESENCOFRADO NORMAL m2 241.50 25/07/18 28/07/18 4 0% 0 4

MOVILIZACIÓN, DESMOVILIZACIÓN, MONTAJE Y DESMONTAJE DE ESTRUCTURA


2.13 METÁLICA Glb 1.00 31/07/18 09/08/18 10 10% 1 9

3 PILOTAJE 25/07/18 13/08/18 20 0% 0 20 P


3.1 EXCAVACIÓN DE PILOTES Y COLOCACIÓN DE ARMADURA ml 80.20 26/07/18 29/07/18 4 0% 0 4

3.2 CONCRETO ESTRUCTURAL (CLASE C) F'C=280 kg/cm2 EN PILOTES BAJO AGUA m3 141.73 27/07/18 30/07/18 4 0% 0 4
3.3 ACERO DE REFUERZO FY=4200 kg/cm2 EN PILOTES kg 17,230.64 27/07/18 30/07/18 4 0% 0 4
3.4 CORTE DE CABEZALES und 4.00 06/08/18 09/08/18 4 0% 0 4
3.5 PRUEBA DE INTEGRIDAD DE PILOTES und 4.00 10/08/18 13/08/18 4 0% 0 4
3.6 MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPOS DE PILOTAJE Glb 1.00 25/06/18 25/06/18 1 0% 0 1
PROGRAMACION - 4 WEEKS
CONSTRUCCION DE PUENTES POR REMPLAZO EN CUSCO - PUENTE COMBAPATA

FRENTE DE TRABAJO (PROJECT):


CONTRATISTA: FECHA DE FIN DE OBRA 7/11/2019
20-Jun 12-Sep
Residente: DAVID FLORES LAU
Ininicio 4W: 30-Jul
Fecha actual: 3-Jul

3/10/2019

3/11/2019

3/12/2019

3/13/2019

3/14/2019

3/15/2019

3/16/2019

3/17/2019

3/18/2019

3/19/2019

3/20/2019

3/21/2019

3/22/2019

3/23/2019

3/24/2019

3/25/2019

3/26/2019

3/27/2019

3/28/2019

3/29/2019

3/30/2019

3/31/2019

4/10/2019

4/11/2019

4/12/2019

4/13/2019

4/14/2019

4/15/2019

4/16/2019

4/17/2019

4/18/2019

4/19/2019

4/20/2019

4/21/2019

4/22/2019

4/23/2019

4/24/2019

4/25/2019

4/26/2019

4/27/2019

4/28/2019

4/29/2019

4/30/2019

5/10/2019

5/11/2019

5/12/2019

5/13/2019
3/4/2019

3/5/2019

3/6/2019

3/7/2019

3/8/2019

3/9/2019

4/1/2019

4/2/2019

4/3/2019

4/4/2019

4/5/2019

4/6/2019

4/7/2019

4/8/2019

4/9/2019

5/1/2019

5/2/2019

5/3/2019

5/4/2019

5/5/2019

5/6/2019

5/7/2019

5/8/2019

5/9/2019
ACTIVIDADES REPROGRAMADO CONTROL DE AVANCE ESTATUS

DÍAS DE RETRASO EN
DIAS COMPLETADOS

DIAS PENDIENTES
% COMPLETADO

A (Adelantado)

EL PROYECTO
E (Finalizado)
P (Progreso)
D (Retraso)
DURACIÓN
ITEM

TAREA Inicio Fin SEMANA 62 SEMANA 63 SEMANA 64 SEMANA 65 SEMANA 66 SEMANA 67 SEMANA 68 SEMANA 69 SEMANA 70 SEMANA 71 SEM

1 TRABAJOS PRELIMINARES 20/06/18 27/06/19 373 56% 209 164


2 DESVÍO PROVISIONAL 12/07/18 11/07/19 365 100% 365 0
3 PILOTAJE 17/09/18 19/11/18 64 100% 64 0 P

4 ESTRIBOS 20/11/18 13/03/19 114 85% 97 17 P

1 TABLERO 25/02/19 28/06/19 124 37% 46 78


1.1 PAVIMENTO DE CONCRETO ASFÁLTICO EN CALIENTE 24/06/19 28/06/19 5 0% 0 5 P
1.2 RIEGO DE LIGA 23/06/19 24/06/19 2 0% 0 2 P
1.3 CONCRETO ESTRUCTURAL (CLASE A) F'C= 350 kg/cm2 EN TABLERO 23/05/19 27/05/19 5 0% 0 5 P
1.4 ACERO DE REFUERZO FY= 4200 kg/cm2 EN TABLERO 19/05/19 28/05/19 10 0% 0 10 P
1.5 ENCOFRADO Y DESENCOFRADO CARAVISTA EN TABLERO 18/05/19 24/05/19 7 0% 0 7 P
1.6 PRELOSA 25/02/19 25/05/19 89 50% 44 45 P
1.7 CONCRETO ESTRUCTURAL (CLASE D) F'C= 210 kg/cm2 EN VEREDAS 27/05/19 27/05/19 1 0% 0 1 P
2 SUPERESTRUCTURA DE ACERO ESTRUCTURAL 20/11/18 11/05/19 173 27% 45 128 P
2.1 FABRICACIÓN DE ESTRUCTURA METÁLICA 20/11/18 18/01/19 60 100% 60 0 P
2.2 TRANSPORTE DE ESTRUCTURA METÁLICA A OBRA 23/12/18 28/02/19 67 100% 67 0 P
2.3 MONTAJE DE ESTRUCTURA METÁLICA 13/03/19 03/05/19 52 0% 0 52 P
2.4 PÉNDOLAS NETWORK Ø 36mm 13/03/19 11/05/19 60 0% 0 60 P
2.5 PÉNDOLAS NETWORK Ø 42mm 13/03/19 11/05/19 60 0% 0 60 P
2.6 PÉNDOLAS NETWORK Ø 45mm 13/03/19 11/05/19 60 0% 0 60 P
2.7 PÉNDOLAS NETWORK Ø 48mm 13/03/19 11/05/19 60 0% 0 60 P
2.8 PÉNDOLAS NETWORK Ø 52mm 13/03/19 11/05/19 60 0% 0 60 P

3 LOSA DE APROXIMACIÓN 27/05/19 13/06/19 18 0% 0 18 P

3.1 CONCRETO (CLASE G) F'C= 100 kg/cm2 27/05/19 29/05/19 3 0% 0 3 P

3.2 CONCRETO ESTRUCTURAL (CLASE C) F'C= 280 kg/cm2 EN LOSA DE APROXIMACION 10/06/19 13/06/19 4 0% 0 4 P

3.3 ACERO DE REFUERZO FY=4200 KG/CM2 29/05/19 04/06/19 7 0% 0 7 P

3.4 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSA DE APROXIMACION 04/06/19 10/06/19 7 0% 0 7 P

4 MUROS NEW JERSEY 27/05/19 11/07/19 46 0% 0 46 P

4.1 CONCRETO ESTRUCTURAL (CLASE C) F'C= 280 kg/cm2 EN MURO NEW JERSEY 15/06/19 21/06/19 7 0% 0 7 P
4.2 ACERO DE REFUERZO FY=4200 KG/CM2 27/05/19 02/06/19 7 0% 0 7 P
4.3 ENCOFRADO Y DESENCOFRADO CARAVISTA EN MURO NEW JERSEY 02/06/19 15/06/19 14 0% 0 14 P
4.4 PINTADO DE MUROS NEW JERSEY 05/07/19 11/07/19 7 0% 0 7 P
4.5 JUNTA EN MURO NEW JERSEY 21/06/19 27/06/19 7 0% 0 7 P

5 DETALLES VARIOS 02/03/19 04/07/19 125 0% 0 125 P

5.1 JUNTA DE DILATACIÓN DE PUENTE 20/05/19 26/05/19 7 0% 0 7 P


5.2 APOYO DE NEOPRENO 600mm x 600mm x 157 mm 30/04/19 02/05/19 3 0% 0 3 P
5.3 TOPES DE NEOPRENO 25/04/19 01/05/19 7 0% 0 7 P
5.4 BARANDA METÁLICA 21/06/19 04/07/19 14 0% 0 14 P
5.10 PRUEBA DE CARGA TIPO II 01/07/19 01/07/19 1 0% 0 1 P

6 MOVIMIENTO DE TIERRAS 29/04/19 10/05/19 12 0% 0 12 P

7 SUB BASE Y BASE GRANULAR 10/05/19 16/05/19 7 0% 0 7 P

7.1 SUBBASE GRANULAR 10/05/19 13/05/19 4 0% 0 4 P


7.2 BASE GRANULAR 13/05/19 16/05/19 4 0% 0 4 P
8 PAVIMENTOS 21/06/19 24/06/19 4 0% 0 4 P
8.1 IMPRIMACIÓN ASFÁLTICA 21/06/19 22/06/19 2 0% 0 2 P
8.2 RIEGO DE LIGA 22/06/19 23/06/19 2 0% 0 2 P
8.3 PAVIMENTO DE CONCRETO ASFÁLTICO EN CALIENTE 23/06/19 24/06/19 2 0% 0 2 P

9 OBRAS DE ARTE Y DRENAJE 25/05/19 24/06/19 31 0% 0 31 P

9.1 EXCAVACIÓN MANUAL PARA ESTRUCTURAS EN MATERIAL COMUN 25/05/19 30/05/19 6 0% 0 6 P


9.2 CONCRETO (CLASE G) F'C=100 kg/cm2 30/05/19 31/05/19 2 0% 0 2 P
9.3 CONCRETO ESTRUCTURAL (CLASE D) F'C=210 kg/cm2 EN OBRAS DE ARTE 15/06/19 21/06/19 7 0% 0 7 P
9.4 ACERO DE REFUERZO FY=4200 KG/CM2 31/05/19 07/06/19 8 0% 0 8 P
9.5 ENCOFRADO Y DESENCOFRADO CARAVISTA 07/06/19 15/06/19 9 0% 0 9 P
9.6 ENCOFRADO Y DESENCOFRADO NORMAL 15/06/19 24/06/19 10 0% 0 10 P
9.7 MAMPOSTERÍA DE PIEDRA (e=0.15) 15/06/19 24/06/19 10 0% 0 10 P
9.8 JUNTA DE DILATACIÓN 15/06/19 15/06/19 1 0% 0 1 P
9.9 JUNTA DE CONSTRUCCION 15/06/19 15/06/19 1 0% 0 1 P
9.10 SELLADO DE JUNTAS 21/06/19 24/06/19 4 0% 0 4 P
10 SEÑALIZACIÓN Y SEGURIDAD VIAL 27/05/19 03/07/19 38 0% 0 38 P
10.1 SEÑAL PREVENTIVA TRIANGULAR 27/05/19 28/05/19 2 0% 0 2 P
10.2 SEÑAL REGLAMENTARIA (0.80 x 0.80 m) 28/05/19 29/05/19 2 0% 0 2 P
10.3 SEÑAL INFORMATIVA 29/05/19 30/05/19 2 0% 0 2 P
10.4 ESTRUCTURAS DE SOPORTE DE SEÑALES TIPO E-1 30/05/19 02/06/19 4 0% 0 4 P
10.5 TACHAS REFLECTIVAS BIDIRECCIONALES 01/07/19 02/07/19 2 0% 0 2 P
10.6 MARCAS EN EL PAVIMENTO 02/07/19 03/07/19 2 0% 0 2 P
12 SEÑALIZACIÓN AMBIENTAL 03/06/19 09/06/19 7 0% 0 7 P
12.1 SEÑAL INFORMATIVA 03/06/19 09/06/19 7 0% 0 7 P
12.2 ESTRUCTURAS DE SOPORTE DE SEÑALES TIPO E-1 03/06/19 09/06/19 7 0% 0 7 P

20/06/18 11/07/19
5/14/2019

5/15/2019

5/16/2019

SEMANA 72
5/17/2019

5/18/2019

5/19/2019

5/20/2019

5/21/2019

5/22/2019

5/23/2019

SEMANA 73
5/24/2019

5/25/2019

5/26/2019

5/27/2019

5/28/2019

5/29/2019

SEMANA 74 5/30/2019

5/31/2019

6/1/2019

6/2/2019

6/3/2019

6/4/2019

6/5/2019

6/6/2019
SEMANA 75

6/7/2019

6/8/2019

6/9/2019

6/10/2019

6/11/2019

6/12/2019

6/13/2019
SEMANA 76

6/14/2019

6/15/2019

6/16/2019

6/17/2019

6/18/2019

6/19/2019

6/20/2019
SEMANA 77

6/21/2019

6/22/2019

6/23/2019

6/24/2019

6/25/2019

6/26/2019

6/27/2019
SEMANA 78

6/28/2019

6/29/2019

6/30/2019

7/1/2019

7/2/2019

7/3/2019

7/4/2019
SEMANA 79

7/5/2019

7/6/2019

7/7/2019

7/8/2019

7/9/2019

7/10/2019

7/11/2019
SEMANA 80

7/12/2019

7/13/2019

7/14/2019

7/15/2019

7/16/2019

7/17/2019

7/18/2019
SEMANA 81

7/19/2019

7/20/2019

7/21/2019

7/22/2019

7/23/2019

7/24/2019

7/25/2019
SEMANA 82

7/26/2019

7/27/2019

7/28/2019

7/29/2019

7/30/2019

7/31/2019

8/1/2019
SEMANA 83

8/2/2019

8/3/2019

8/4/2019

8/5/2019

8/6/2019

8/7/2019

8/8/2019
SEMANA 84

8/9/2019

8/10/2019

8/11/2019

8/12/2019

8/13/2019

8/14/2019

8/15/2019
SEMANA 85

8/16/2019

8/17/2019

8/18/2019

8/19/2019

8/20/2019

8/21/2019

8/22/2019
SEMANA 86

8/23/2019

8/24/2019

8/25/2019

8/26/2019

8/27/2019

8/28/2019

8/29/2019
SEMANA 87

8/30/2019

8/31/2019

9/1/2019

9/2/2019

9/3/2019

9/4/2019

9/5/2019
SEMANA 88
SEMANA 88
9/6/2019

9/7/2019

9/8/2019

9/9/2019

9/10/2019

9/11/2019

9/12/2019

SEMANA 89
9/13/2019

9/14/2019

9/15/2019

9/16/2019

9/17/2019

9/18/2019

9/19/2019
SEMANA 90

9/20/2019

9/21/2019

9/22/2019

9/23/2019

9/24/2019

9/25/2019

9/26/2019
SEMANA 91

9/27/2019

9/28/2019

9/29/2019

9/30/2019

10/1/2019

10/2/2019

10/3/2019
SEMANA 92

10/4/2019

10/5/2019

10/6/2019

10/7/2019

10/8/2019

10/9/2019

10/10/2019
SEMANA 93

10/11/2019

10/12/2019

10/13/2019

10/14/2019

10/15/2019

10/16/2019

10/17/2019
SEMANA 94

10/18/2019

10/19/2019

10/20/2019

10/21/2019

10/22/2019

10/23/2019

10/24/2019
SEMANA 95

10/25/2019

10/26/2019

10/27/2019

10/28/2019

10/29/2019

10/30/2019

10/31/2019
SEMANA 96

11/1/2019

11/2/2019

11/3/2019
DESCRIPCION
RESTRICCIONES
ESTATUS
PRIORIDAD

RESPONSABLE
BAJA
ALTA

PRIORIDAD
MEDIA

Atrasado
Ejecutado
B
A

En Progreso

Fecha de
Cumplimiento
P

D
O

Días Restantes
Estatus