Está en la página 1de 7

SUM. E INST.

ADOQUIN - M2
CANT. CANT. REQUER
MATERIALES 10000
REQUER CORTAD. ADOQ.
CANT/
DESCRIPCION UND VALOR DESP VR. PARCIAL
REND
adoquin de 12 cms m2 1 50,000.00 2% 51,000.00
arena para sello m3 0.030 33,000.00 5% 1,039.50

SUBTOTAL 52,039.50
HERRAMIENTAS/EQUIPOS
CANT/ DIAS TOTAL
DESCRIPCION UND REND VALOR VR. PARCIAL REND DIAS CALC RECUR REQ
cortadora de adoquin Dia 0.010 35,000.00 350.00 100 1 10 2

SUBTOTAL 350.00
TRANSPORTE
CANT/ HORAS DIAS TOTAL
DESCRIPCION UND VALOR VR. PARCIAL REND
REND X DIA CALC RECUR REQ
montacargas Hora 0.010 35,000.00 350.00 100 8 12.5 2

SUBTOTAL 350.00
MANO DE OBRA
CANT/ HORAS DIAS TOTAL
DESCRIPCION UND VALOR PRESTAC VR. PARCIAL REND
REND X DIA CALC RECUR REQ
comision topografica (1 TOP + 2 CAD) HC 0.029 19,531.25 60% 892.86 70 8 17.9 2
cuadrilla (1 OFICIAL + 4 AYUDANTES ) HH 0.667 48,750.00 60% 52,000.00 15 8 83.3 10

SUBTOTAL 52,892.86

TOTAL COSTO DIRECTO 105,632.36 DIAS ADOQUIN 9


BASE ESTABILIZADA CON CEMENTO DE 1800 PSI - M3
CANT.
MATERIALES 5500 m3
REQUER
CANT/
DESCRIPCION UND VALOR DESP VR. PARCIAL
REND
Arena palmarito m3 1 32,500.00 35% 43,875.00
cemento gris kg 120 352.94 5% 44,470.59
agua lt 180 30.00 0% 5,400.00

SUBTOTAL 93,745.59
HERRAMIENTAS/EQUIPOS
CANT/ HORAS DIAS TOTAL
DESCRIPCION UND REND VALOR VR. PARCIAL REND X DIA CALC RECUR REQ
motoniveladora HR 0.033 120,000.00 4,000.00 60 8 11.5 2
Retrocargador HR 0.086 100,000.00 8,571.43 35 8 19.6 3
vibrocompactador HR 0.029 90,000.00 2,571.43 70 8 9.8 2
carrotanque HR 0.008 37,500.00 300.00 125 8 5.5 1

SUBTOTAL 15,442.86
TRANSPORTE
CANT/
DESCRIPCION UND VALOR VR. PARCIAL
REND

SUBTOTAL
MANO DE OBRA
DESCRIPCION UND CANT/ VALOR PRESTAC VR. PARCIAL REND HORAS DIAS TOTAL
REND X DIA CALC RECUR REQ
comision topografica (1 TOP + 2 CAD) HC 0.010 19,531.25 60% 312.50 100 8 6.9 1
ayudante HH 0.250 9,375.00 60% 3,750.00 20 8 34.4 5

SUBTOTAL 4,062.50

TOTAL COSTO DIRECTO 113,250.95 DIAS BASE 7


SUB BASE TIPO INVIAS (PAVIMENTO) - M3
CANT.
MATERIALES 3000
REQUER
CANT/
DESCRIPCION UND VALOR DESP VR. PARCIAL
REND
areana palmarito m3 0.500 32,500.00 35% 21,937.50
arena zahorra m3 0.500 17,500.00 35% 11,812.50
agua lt 50 30.00 0% 1,500.00

SUBTOTAL 35,250.00
HERRAMIENTAS/EQUIPOS
CANT/ HORAS DIAS TOTAL
DESCRIPCION UND REND VALOR VR. PARCIAL REND X DIA CALC RECUR REQ
motoniveladora HR 0.050 120,000.00 6,000.00 40 8 9.4 2
vibrocompactador HR 0.033 90,000.00 3,000.00 60 8 6.3 2
carrotanque HR 0.002 37,500.00 75.00 500 8 0.8 1

SUBTOTAL 9,075.00
TRANSPORTE
CANT/
DESCRIPCION UND REND VALOR VR. PARCIAL

SUBTOTAL
MANO DE OBRA
CANT/ HORAS DIAS TOTAL
DESCRIPCION UND VALOR PRESTAC VR. PARCIAL REND
REND X DIA CALC RECUR REQ
comision topografica (1 TOP + 2 CAD) HC 0.040 19,531.25 60% 1,250.00 50 8 7.5 2

SUBTOTAL 1,250.00

TOTAL COSTO DIRECTO 45,575.00 DIAS SUB-BASE

TOTAL DIAS 5
dias recalculados
5

dias recalculados
6.25

dias recalculados
8.9
8.3
dias recalculados
5.73
6.55
4.91

dias recalculados

6.88
dias recalculados
4.6875
3.125

dias recalculados
3.75
PRESUPUESTO
ITEM DESCRIPCIÓN UND
CANTIDAD VR. UNITARIO VR. PARCIAL
1 ESTRUCTURA DE PAVIMENTO
SUMINISTRO E INSTALACIÓN DE ADOQUIN DE 12 CMS SEGÚN
1.1 NORMA NTC 2017 M2 10,000.00 $ 105,632.36 $ 1,056,323,571

BASE ESTABILIZADA CON CEMENTO 1800 PSI 28 DÍAS TIPO


1.2 INVIAS M3 5,500.00 $ 113,250.95 $ 622,880,200

1.3 SUBBASE GRANULAR TIPO INVIAS M3 30,000.00 $ 45,575.00 $ 1,367,250,000

TOTAL COSTO DIRECTO $ 3,046,453,771


ADMINISTRACIÓN 1.5075 $ 4,592,680,657
UTILIDAD 10% $ 3,351,099,148
IMPREVISTOS 0.0075 $ 23,000,000
TOTAL COSTOS ANTES DE IVA
IVA 19%

COSTO TOTAL

Cálculo Administración
COSTOS
Ingeniero Residente $ 5,000,000.00 mensual
Inspector HSEQ $ 3,000,000.00 mensual
Director de Obra $ 8,000,000.00 mensual
Campamento de obra $ 2,000,000.00 mensual
Gastos oficina central $ 5,000,000.00 mensual
Pólizas $ 4,569,680,657 1.5 % del C.D.

TOTAL
EN PORCENTAJE