REAJUSTE DE
VALORIZACION

CURSO : PLANIFICACION Y CONTROL DE OBRAS

ESTUDIANTES
 FARFAN AYMA MICHELLE A.
 CODIGO : 013100639J

CUSCO – PERU
2020

PLANIFICACION Y CONTROL DE OBRAS


VALORIZACION DE OBRA

CONTRATADO ACUMULADO ANTERIOR PRESENTE VAL SALDO


DESCRIPCION
UND CANT P.U(s/.) TOTAL CANT % SUB TOTAL CANT % SUB TOTAL
CANT % SUB TOTALCANT % SUB TOTAL
ESTRUCTURAS 168526.8 84263.405 84263.4

OBRAS 10097 5048.5 5048.5


PRELIMINARES

CONTENEDOR día 90 20 1800 0 0.00% 0 0.00% 45 50.00% 900 45 50% 900


OFICINA
CONTENEDOR día 90 20 1800 0 0.00% 0 0.00% 45 50.00% 900 45 50% 900
ALMACEN
CONTENEDOR día 90 20 1800 0 0.00% 0 0.00% 45 50.00% 900 45 50% 900
INODORO,
LAVATORIOS
TRAZO INICIAL gbl 1 77 77 0 0.00% 0 0.00% 0.5 50.00% 38.5 0.5 50% 38.5
TRAZO día 60 77 4620 0 0.00% 0 0.00% 30 50.00% 2310 30 50% 2310
DURANTE LA
EJECUCION DE
LA OBRA
TRANSPORTE 22000 0 0 0.00% 0 50.00% 11000 0 50% 11000
VERTICAL Y
HORIZONTAL
DE
MATERIALES
TRANSPORTE vje 5000 4.4 22000 0 0.00% 0 0.00% 2500 50.00% 11000 2500 50% 11000
VERTICAL Y
HORIZONTAL
DE
MATERIALES
EN OBRA
DEMOLICIONES 3167.2 0 0 0.00% 0 50.00% 1583.6 0 50% 1583.6

DEMOLICION m3 5 296.6 1483 0 0.00% 0 0.00% 2.5 50.00% 741.5 2.5 50% 741.5
CONSTRUCCIO
N EXISTENTE
PICADO DE m2 30 56.14 1684.2 0 0.00% 0 0.00% 15 50.00% 842.1 15 50% 842.1
REBABAS EN
CIMIENTOS Y
SOBRECIMIENT
OS DE
CONSTRUCCIO
N ADYACENTE

MOVIMIENTO 5397.51 0 #¡DIV/0! 0 0.00% 0 50.00% 2698.755 0 50% 2698.76


DE TIERRAS
LIMPIEZA DE m2 355 2.61 926.55 0 0.00% 0 0.00% 177.5 50.00% 463.275 177.5 50% 463.275
TERRENO
MANUAL
EXCAVACION m3 66 23.11 1525.26 0 0.00% 0 0.00% 33 50.00% 762.63 33 50% 762.63
PARA
CIMIENTOS
HASTA 1.00
mTERRENO
NORMAL
NIVELACION m2 290 1.76 510.4 0 0.00% 0 0.00% 145 50.00% 255.2 145 50% 255.2
INTERIOR
APISONADO
MANUAL
ELIMINACION m3 70 34.79 2435.3 0 0.00% 0 0.00% 35 50.00% 1217.65 35 50% 1217.65
CON
TRANSPORTE
(CARGUIO A
MANO) R=25
m3/día
CONCRETO 21066.03 0 0 0.00% 0 50.00% 10533.015 0 50% 10533
SIMPLE
SOLADOS m2 33 9.36 308.88 0 0.00% 0 0.00% 16.5 50.00% 154.44 16.5 50% 154.44
CONCRETO
f'c=100 kg/cm2
h=2"
CIMIENTOS m3 66 128.71 8494.86 0 0.00% 0 0.00% 33 50.00% 4247.43 33 50% 4247.43
CORRIDOS
MEZCLA 1:10
CEMENTO-
HORMIGON
30% PIEDRA
ENCOFRADO Y m2 45 28.63 1288.35 0 0.00% 0 0.00% 22.5 50.00% 644.175 22.5 50% 644.175
DESENCOFRAD
O NORMAL
PARA
SOBRECIMIENT
O HASTA 0.30 m

CONCRETO m3 34.2 159.51 5455.24 0 0.00% 0 0.00% 17.1 50.00% 2727.62 17.1 50% 2727.62
1:8+25% PM
PARA
SOBRECIMIENT
OS
CONCRETO EN m2 290 19.03 5518.7 0 0.00% 0 0.00% 145 50.00% 2759.35 145 50% 2759.35
FALSOPISO
MEZCLA 1:8
CEMENTO-
HORMIGON
E=4"

CONCRETO 106799.1 0 #¡DIV/0! 0 0.00% 0 50.00% 53399.535 0 50% 53399.5


ARMADO
ZAPATAS Y 9680.08 0 #¡DIV/0! 0 0.00% 0 50.00% 4840.04 0 50% 4840.04
VIGAS DE
CIMENTACION
CONCRETO m3 20 245.37 4907.4 0 0.00% 0 0.00% 10 50.00% 2453.7 10 50% 2453.7
PARA ZAPATAS
f'c=210 kg/cm2

ENCOFRADO m2 17 26.86 456.62 0 0.00% 0 0.00% 8.5 50.00% 228.31 8.5 50% 228.31
DE ZAPATAS
ACERO fy=4200 kg 1120 2.27 2542.4 0 0.00% 0 0.00% 560 50.00% 1271.2 560 50% 1271.2
kg/cm2 GRADO
60 en ZAPATAS

ENCOFRADO m2 7 32.51 227.57 0 0.00% 0 0.00% 3.5 50.00% 113.785 3.5 50% 113.785
DE VIGAS DE
CIMENTACION
CONCRETO EN m3 3.5 251.06 878.71 0 0.00% 0 0.00% 1.75 50.00% 439.355 1.75 50% 439.355
VIGAS DE
CIMENTACION
f'c=210 kg/cm2
ACERO fy=4200 kg 294 2.27 667.38 0 0.00% 0 0.00% 147 50.00% 333.69 147 50% 333.69
kg/cm2 GRADO
60 en VIGAS DE
CIMENTACION

COLUMNAS 15956.96 0 #¡DIV/0! 0 0.00% 0 50.00% 7978.48 0 50% 7978.48


ACERO fy=4200 kg 2248 2.27 5102.96 0 0.00% 0 0.00% 1124 50.00% 2551.48 1124 50% 2551.48
kg/cm2 GRADO
60 en
COLUMNAS

ENCOFRADO Y m2 126 43.25 5449.5 0 0.00% 0 0.00% 63 50.00% 2724.75 63 50% 2724.75
DESENCOFRAD
O NORMAL EN
COLUMNAS

CONCRETO EN m3 18 300.25 5404.5 0 0.00% 0 0.00% 9 50.00% 2702.25 9 50% 2702.25


COLUMNAS
f'c=210 kg/cm2

VIGAS 32142.24 0 0 0.00% 0 50.00% 16071.12 0 50% 16071.1


ENCOFRADO Y m2 96 61.65 5918.4 0 0.00% 0 0.00% 48 50.00% 2959.2 48 50% 2959.2
DESENCOFRAD
O NORMAL EN
VIGAS

ACERO fy=4200 kg 9000 2.27 20430 0 0.00% 0 0.00% 4500 50.00% 10215 4500 50% 10215
kg/cm2 GRADO
60 en VIGAS

CONCRETO EN m3 24 241.41 5793.84 0 0.00% 0 0.00% 12 50.00% 2896.92 12 50% 2896.92


VIGAS f'c=210
kg/cm2
LOSAS 45107.18 0 0 0.00% 0 50.00% 22553.59 0 50% 22553.6
ALIGERADAS
ENCOFRADO Y m2 486 39.34 19119.24 0 0.00% 0 0.00% 243 50.00% 9559.62 243 50% 9559.62
DESENCOFRAD
O NORMAL EN
LOSAS
ALIGERADAS

LADRILLO pza 5830 1.01 5888.3 0 0.00% 0 0.00% 2915 50.00% 2944.15 2915 50% 2944.15
HUECO DE
ARCILLA h=15
cm PARA
TECHO
ALIGERADO
ACERO fy=4200 kg 3300 2.27 7491 0 0.00% 0 0.00% 1650 50.00% 3745.5 1650 50% 3745.5
kg/cm2 GRADO
60 en LOSAS
ALIGERADAS

CONCRETO EN m3 48 262.68 12608.64 0 0.00% 0 0.00% 24 50.00% 6304.32 24 50% 6304.32


LOSAS
ALIGERADAS
f'c=210 kg/cm2
ESCALERAS 3912.61 0 0 0.00% 0 50.00% 1956.305 0 50% 1956.31
ENCOFRADO Y m2 24 52.55 1261.2 0 0.00% 0 0.00% 12 50.00% 630.6 12 50% 630.6
DESENCOFRAD
O NORMAL EN
ESCALERAS

ACERO fy=4200 kg 520 2.27 1180.4 0 0.00% 0 0.00% 260 50.00% 590.2 260 50% 590.2
kg/cm2 GRADO
60 en
ESCALERAS

CONCRETO EN m3 5.6 262.68 1471.01 0 0.00% 0 0.00% 2.8 50.00% 735.505 2.8 50% 735.505
ESCALERAS
f'c=210 kg/cm2

TOTAL 168526.8 84263.405 84263.4


GASTOS 21114.05 10557
GENERALES
UTILIDAD 16852.68 8426.34
10%
------------

IMPUESTO (IGV 39233.77 19616.9


19%) ========

TOTAL 245727.3 122863.655


PRESUPUESTO
UNIVERSIDAD ANDINA DEL CUSCO
CARRERA PROFESIONAL DE INGENIERIA CIVIL

INDICES UNIFICADOS DE ENERO DEL 2020

PLANIFICACION Y CONTROL DE OBRAS


UNIVERSIDAD ANDINA DEL CUSCO
CARRERA PROFESIONAL DE INGENIERIA CIVIL

INDICES UNIFICADOS ENERO 2019:

SIMB. I.U. C.INC. % Ir (mes valorización) Io (mes presupuesto) Ir/Io K


(1) (2) (3) 4=(3)*(2) (5) 6=(5)*(2) 7=(4)/(6) 8=(1)*(7)
J 47 0.352 1.0000 619.99 619.99 600.4 600.40 1.0326 0.363
- -
L 17 0.079 1.0000 888.19 888.19 882.02 882.02 1.0070 0.080
- -
C 21 0.255 1.0000 419.52 419.52 418.38 418.38 1.0027 0.256
- -
P/M 5 0.113 0.7430 627.62 466.32 632.32 469.81
43 0.113 0.2570 938.17 241.11 892.6 229.40
0.113 707.43 699.21 1.0118 0.114
H 38 0.071 1.0000 635.68 635.68 657.48 657.48 0.9668 0.069
- -
GGU 39 0.13 1.0000 460.84 460.84 452.29 452.29 1.0189 0.132
1.000 K= 1.014

PLANIFICACION Y CONTROL DE OBRAS


UNIVERSIDAD ANDINA DEL CUSCO
CARRERA PROFESIONAL DE INGENIERIA CIVIL

CALCULO DEL REINTEGRO:

𝑹 = 𝟏𝟐𝟐𝟖𝟔𝟑. 𝟔𝟓𝟓(𝟏. 𝟎𝟏𝟒 − 𝟏)

𝐑 = 𝟏𝟕𝟐𝟎. 𝟎𝟗𝟏𝟏𝟕

CALCULO DEL REAJUSTE DE LAS VALORIZACIONES:

𝑹 = 𝟏𝟕𝟐𝟎. 𝟎𝟗𝟏𝟏𝟕 + 𝟏𝟐𝟐𝟖𝟔𝟑. 𝟔𝟓𝟓 = 𝟏𝟐𝟒𝟓𝟖𝟑. 𝟕𝟒𝟔𝟏𝟕 𝑺𝑶𝑳𝑬𝑺