Documentos de Académico
Documentos de Profesional
Documentos de Cultura
JUNIN
FECHA DE INICIO DE OBRA 05 DE SETIEMBRE DEL 2016
PLAZO DE EJECUCION 60 DIAS CALENDARIOS TARMA
MURO DE CONTENCION
TRABAJOS PRELIMINARES
CASETA PARA GUARDIANIA Y ALMACEN dia 60.00 1.00 60.00 60.00 50.00 3000.00 30.00 1500.00 50% 30.00 1500.00 50% 60.00 3000.00 100%
EXPLANACIONES
Escarif, Riego y Compactacion de Base de Fundacion m2 1557.27 1200.00 1.30 3.00 3.14 4889.83 1557.27 4889.83 100% 1557.27 4889.83 100%
Mejoramiento con Material Over 6" a 10" m2 1868.72 200.00 9.34 10.00 26.89 50249.88 1868.72 50249.88 100% 1868.72 50249.88 100%
CONCRETO SIMPLE
Solado de concreto 140 Kg/cm2 m3 155.73 15.00 10.38 11.00 275.76 42944.10 155.73 42944.10 100% 155.73 42944.10 100%
Mamposteria de Piedra m3 45.00 40.00 1.13 2.00 164.33 7394.85 45.00 7394.85 100% 45.00 7394.85 100%
CANAL DE IRRIGACION
TRABAJOS PRELIMINARES
Trazo de Niveles y Replanteo m 465.00 400.00 1.16 3.00 1.21 562.65 465.00 562.65 100% 465.00 562.65 100%
Reposicion Provic. de Canal Demolido con tubo PVC 8" m 465.00 66.67 6.97 7.00 38.17 17749.05 465.00 17749.05 100% 465.00 17749.05 100%
MOVIMIENTO DE TIERRAS
Demolicion de Canal Existente m3 153.45 10.00 15.35 15.00 14.04 2154.44 153.45 2154.44 100% 153.45 2154.44 100%
Eliminacion de desmonte Prov, Demolicion de Canal m3 153.45 200.00 0.77 2.00 8.52 1307.39 153.45 1307.39 100% 153.45 1307.39 100%
CONCRETO ARMADO
Concreto F'c=210 kg/cm2 m3 169.37 12.00 14.11 15.00 389.65 65995.02 169.37 65995.02 100% 169.37 65995.02 100%
Encofrado y desencofrado m2 1005.56 15.00 33.52 35.00 39.99 40212.34 402.22 16084.94 40% 603.34 24127.41 60% 1005.56 40212.34 100%
Acero de Refuerzo F'y=4200 kg/cm2 kg 21805.52 250.00 29.07 30.00 4.35 94854.01 13083.31 56912.41 60% 8722.21 37941.60 40% 21805.52 94854.01 100%
Acabado cara Exterior m2 1450.60 20.00 24.18 20.00 14.47 20990.18 1450.60 20990.18 100% 1450.60 20990.18 100%
JUNTAS
Junta de Dilatacion /Contraccion m 218.40 5.00 14.56 15.00 70.46 15388.46 218.40 15388.46 100% 218.40 15388.46 100%
LIMPIEZA
Limpieza General de Zona de Trabajo m 465.00 80.00 2.91 2.00 1.75 813.75 465.00 813.75 100% 465.00 813.75 100%
COSTO DIRECTO S/. 368,655.95 201,749.54 54.73% 166,906.43 45.27% 368,655.97 100.00%
GASTOS GENERALES 10.00% S/. 36,865.60 20,174.95 54.73% 16,690.64 45.27% 36,865.60 100.00%
SUB TOTAL S/. 405,521.55 221,924.49 54.73% 183,597.07 45.27% 405,521.57 100.00%
SUPERVICION 5 % S/. 20,276.08 11,096.22 54.73% 9,179.85 45.27% 20,276.08 100.00%
PRESUPUESTO TOTAL S/. 425,797.63 233,020.72 54.73% 192,776.92 45.27% 425,797.64 100.00%