AVANCE DIARIO 45 M2
MO
Op 1 Hh 0.188889 22.02 4.159333
Pe 0.25 Hh 0.047222 15.91 0.751306 1 bolsa 22.5kg
MAT x 0.75Kg
Aditivo PENETRON BOL 0.033333 271.1864 9.039548
EQ y H
Herramienta Manual %MO 0.05 4.910639 0.245532 14.19572
IMPERMEABILIZACION HORIZONTAL
AVANCE DIARIO 45 M2
MO
Op 1 Hh 0.177778 22.02 3.914667 1 bolsa 22.5kg
Pe 0.333333 Hh 0.059259 15.91 0.942815 x 1.1Kg
MAT
Aditivo PENETRON BOL 0.048889 320 15.64444
EQ y H
Herramienta Manual %MO 0.05 4.857481 0.242874 20.7448
AVANCE DIARIO 12 M2
MO 1 BOL
Op 1 Hh 0.708333 22.02 15.5975 x bol
Pe 0.333333 Hh 0.236111 15.91 3.756528
MAT
Azulejo M2 1 21.10169 21.10169
Pegamento Bls 0.2675 32.49607 8.692698
EQ y H
Herramienta Manual %MO 0.05 19.35403 0.967701 50.11612
FRAGUADO
AVANCE DIARIO 12 M2
MO 1 bols 5Kg x
Of 2 Hh 1.333333 17.65 23.53333 x 3.55 kg 1 m2
Pe 1 Hh 0.666667 15.91 10.60667
MAT 0.71
Fragua Bls 0.7597 30.54255 23.20317
EQ y H
Herramienta Manual %MO 0.05 34.14 1.707 59.05017
Presupuesto
IMPERMEABILIZACION vertical 33 14.19572 468.46
IMPERMEABILIZACION horizontal 14 20.7448 290.43
RVESTIMIENTO CON PEPELMA 47 50.11612 2355.46
FRAGUADO 47 59.05017 2775.36
5889.71 58897.1
CANTIDAD REQUERIDAS