DATOS:
h = ??
H = ??
W T SC = 1.80 TON/M²
q ad 10.20 TON/M²
c).- Cálculo del área de apoyo:
An = 3.04 m²
H = 1.74 m
B = 1.74 m
e = 0.01 m
H = 0.04 m No es posible
H = 2.00 m
B = 2.00 m
A = 4.00 m
= 7.90 TON/M²
min
= 7.60 TON/M²
Paso No. 2.- Cálculo de la reacción del terreno debida a las cargas factorizadas.
Pu = 43.40 TON
Mu = 0.31 TON-M
eu = 0.0071 m
min
= 11.08 TON/M²
= 10.62 TON/M²
= 10.62
TON/M²
y1 = 10.88 TON/M²
= 11.08
Mu = TON/M²
a= 4.6260719 c= 4.7100625
b= 0.2833333 d= 0.5666667 Mu = 7.96 TON-M
) rMAX = 0.0153
Ku = 46.8636 Kg/cm²
df = 9.2153 cm
b1 = 0.85 rb =
e= 170 d= 13.8230 cm
f= 0.592826
dv = dv = 37.59 cm
x= 0.3337168
y= 4.1739514 dprom = 38.00 cm
z= 2.0434879 d/H =
c= 0.0217 h= 48.00 cm
k= 0.1500
v c
1.06 f ´c = 14.99
q = 0.0217
c u
4 v c
k c 1 = 0.1500
H
¿ d < d prom? ¿ 13.82 < 38 SI!!! OK
c1 = 30 0.30
Paso 4.- Revisión por Cortante c2 = 30 0.30
0.53 d= 38 0.38
c1 + d
c2 + d = 68.00
B= 2.00
66 68.0 66
q min = 10.62
Ton/m²
y3 = 10.93 Ton/m²
b0 = 136.00 cm
b1 = 1
as = 40.00
sd
V n1 0.265(2
b0
) f ´c b0 d
V n1
255.20 Ton
B= 2.00
b).- Acción unidireccional: H= 2.00
dmin = 59.00 cm
c1 = 30.00
c2 = 30.00
(H-c1)/2-d
c1
B= 2.00 d min
c2
H= 2.00
174.00 26.00
q min = 10.62
Ton/m² q max = 11.08 Ton/m²
Y4 = 11.02 Ton/m²
WT sc = 1.80 Ton/m²
q ad = 10.20 Ton/m²
C).- Se verifica que qmax < qa :
P= 31
A= 4e= 0.0064516
M= 0.2 P/A = 7.75
Paso 6.- Diseño del Acero de Refuerzo de la Zapata
Mu = 795951.16 Kg-cm
b= 200.00 cm
w= 0.0155341
Mu
0.848 0.719
0.53bd 2 f ´c As = 5.62
f ´c A= 14.142135624
As bd B= 9.8994949366
fy C= 7600.00
0.7 f ´c
As . min bd
fy
No de Varillas = 9.00
3h 144.00
Sep. Máxima =
45 cms 45.00
¿Sep Pro < Sep min ? ¿ 11.00 < 45 SI !! COLOCAR Sep Prop
* Nota: En el Sentido Perpendicular se requiere menor cantidad de acero de refuerzo.- Para facili -
tar la colocación, se aplicará el mismo refuerzo en el otro sentido.
H=
2.00