Está en la página 1de 1

CRONOGRAMA VALORIZADO DE OBRA

Obra : MEJORAMIENTO DE PISTAS Y VEREDAS DE LAS PRINCIPALES VIAS DEL DISTRITO DE CHONGOS BAJO-CHUPACA-JUNIN
Propietario
Distrito CHONGOS BAJO Departamento: JUNIN
Lugar CHONGOS BAJO Provincia CHUPACA

ITEM PARTIDA MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 SUB TOTAL
PAVIMENTO
01 OBRAS PROVISIONALES S/. 36,264.26
01.01 GUARDIANIA Y ALMACEN S/. 360.00 S/. 360.00 S/. 360.00 S/. 360.00 S/. 360.00 S/. 360.00 S/. 360.00 S/. 360.00 S/. 2,880.00
01.02 CARTEL DE IDENTIFICACION DE OBRA Y PROMOCION DE OBRA 8.50 * 3.60m S/. 2,829.34 S/. 2,829.34
01.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPO S/. 18,332.95 S/. 12,221.97 S/. 30,554.92
02 TRABAJOS PRELIMINARES S/. 83,528.03
02.01 TRAZO DE NIVELES Y REPLANTEO OBRA EN GENERAL S/. 20,312.94 S/. 20,312.94 S/. 20,312.94 S/. 60,938.83
02.02 MANTENIMIENTO DE VIA ALTERNA PARA DESVIO S/. 4,176.90 S/. 5,105.10 S/. 9,282.00
02.03 CARTEL DE SEÑALIZACION PARA DESVIACION DE TRANSITO S/. 13,307.20 S/. 13,307.20
03 MOVIMIENTO DE TIERRAS S/. 359,218.38
03.01 DEMOLICION DE OBRAS DE CONCRETO S/. 18,654.64 S/. 18,654.64
03.02 CORTE DE MATERIAL SUELTO NIVEL SUBRASANTE S/. 147,648.96 S/. 147,648.96
03.04 RELLENO Y COMPACTACION A NIVEL DE SUBRASANTE S/. 8,516.39 S/. 9,226.09 S/. 17,742.48
03.05 ELIMINACION DE MATERIAL EXCEDENTE-CORTE S/. 175,172.30 S/. 175,172.30
04 AFIRMADO SUB BASE GRANULAR S/. 324,345.61
04.01 EXTENDIDO RIEGO Y COMPACTACION SUB-BASE GRANULAR E=0.15m. C/EQUIPO S/. 324,345.61 S/. 324,345.61
05 AFIRMADO BASE GRANULAR S/. 307,355.06
05.01 EXTENDIDO RIEGO Y COMPACTACION BASE GRANULAR E=0.15m. C/EQUIPO S/. 307,355.06 S/. 307,355.06
06 PAVIMENTOS FLEXIBLES S/. 1,160,409.11
06.01 IMPRIMACION ASFALTICA S/. 225,244.61 S/. 225,244.61
06.02 CARPETA ASFALTICA EN CALIENTE E = 2" S/. 935,164.50 S/. 935,164.50
08 PAVIMENTO RIGIDO EN BADEN S/. 87,674.47
08.01 ENCOFRADO Y DESENCOFRADO EN BADEN S/. 19,363.77 S/. 19,363.77
08.02 LOSA CONCRETO FC=210 KG/CM2 EN BADEN S/. 61,479.63 S/. 6,831.07 S/. 68,310.70
09 SARDINEL SUMERGIDO DE CONCRETO S/. 2,776.65
09.01 ENCOFRADO Y DESENCOFRADO EN SARDINEL SUMERGIDO S/. 1,002.62 S/. 1,002.62
09.02 CONCRETO FC=210 KG/CM2 EN SARDINEL SUMERGIDO S/. 1,774.03 S/. 1,774.03
10 DRENAJE-CUNETAS DE CONCRETO S/. 598,657.25
10.01 ENCOFRADO Y DESENCOFRADO EN CUNETA S/. 174,690.82 S/. 174,690.82
10.02 CONCRETO FC=175 KG/CM2 EN CUNETA S/. 423,966.43 S/. 423,966.43
11 JUNTAS S/. 10,346.79
11.01 RELLENO DE JUNTAS CON ASFALTO S/. 10,346.79 S/. 10,346.79
12 MUROS DE CONTENCION S/. 46,296.22
12.01 TRABAJOS PRELIMINARES S/. 285.83
12.01.01 TRAZO DE NIVELES Y REPLANTEO EN MUROS DE CONTENCION S/. 285.83 S/. 285.83
12.02 MOVIMIENTO DE TIERRAS S/. 6,955.20
12.02.01 PERFILADO NIVELADO Y COMPACTADO BASE MUROS DE CONTENCION S/. 327.60 S/. 327.60
12.02.02 EXCAVACION MANUAL DE ZANJAS PARA MUROS DE CONTENCION S/. 4,329.61 S/. 4,329.61
12.02.03 RELLENO CON MATERIAL PROPIO EN MURO DE CONTENCION S/. 2,030.65 S/. 2,030.65
12.02.04 ELIMINACION DE MATERIAL EXCEDENTE-CORTE S/. 267.34 S/. 267.34
12.03 CONCRETO SIMPLE S/. 1,918.10
12.03.01 SOLADO DE CONCRETO F'c=100 Kg/cm2 h=0.10m S/. 1,918.10 S/. 1,918.10
12.04 CONCRETO ARMADO S/. 40,500.70
12.04.01 ENCOFRADO Y DESENCOFRADO DE MUROS DE CONTENCION S/. 8,726.16 S/. 8,726.16
12.04.02 CONCRETO FC=175 KG/CM2 P/MURO DE CONTENCION S/. 14,339.87 S/. 14,339.87
12.04.03 ACERO DE REFUERZO FY=4200 S/. 17,434.67 S/. 17,434.67
13 SEÑALIZACION HORIZONTAL S/. 95,693.03
13.01 PINTURA LINEAL EN SARDINEL S/. 23,929.86 S/. 23,929.86
13.02 PINTURA ZONAL CRUCE PEATONAL S/. 19,875.10 S/. 19,875.10
13.03 PINTURA INTERM. DISCONT. - CENTRO DE VIA S/. 40,501.54 S/. 40,501.54
13.04 PINTURA DE SIMBOLOS - FLECHAS S/. 11,386.53 S/. 11,386.53
14 SEÑALIZACION VERTICAL S/. 38,777.89
14.01 SEÑALES INFORMATIVAS S/. 19,887.87 S/. 19,887.87
14.02 SEÑALES REGLAMENTARIAS S/. 18,890.02 S/. 18,890.02
15 TRABAJOS COMPLEMENTARIOS-VARIOS S/. 86,247.75
15.01 RECONEXION DE PUNTOS DE DESAGUE S/. 19,110.23 S/. 19,110.23
15.02 RECONEXION DE PUNTOS DE AGUA S/. 19,137.38 S/. 3,377.18 S/. 22,514.56
15.03 ENCIMADO DE BUZON DE CONCRETO S/. 10,296.66 S/. 10,296.66
15.04 LIMPIEZA FINAL DE OBRA S/. 34,326.30 S/. 34,326.30
16 PLAN DE MANEJO AMBIENTAL S/. 22,354.20
16.01 READECUACION AMBIENTAL DE CANTERAS Y AREAS DE ELIMINACION DE S/. 22,354.20 S/. 22,354.20
EXCEDENTES
ACERA PEATONAL
01 TRABAJOS PRELIMINARES S/. 53,207.59
01.01 TRAZO Y REPLANTEO EN OBRA S/. 19,001.26 S/. 4,750.31 S/. 23,751.57
01.02 DEMOLICION DE VEREDAS DE CONCRETO S/. 29,456.02 S/. 29,456.02
02 MOVIMIENTO DE TIERRAS S/. 67,353.76
02.01 PERFILADO Y COMPACTADO SUB RASANTE VEREDAS S/. 35,627.36 S/. 35,627.36
02.02 EXCAVACION MANUAL DE SARDINEL S/. 24,529.61 S/. 24,529.61
02.03 ELIMINACION DE MATERIAL EXCEDENTE S/. 7,196.79 S/. 7,196.79
03 AFIRMADO DE BASE GRANULAR EN VEREDAS S/. 154,234.89
03.01 EXT. RIEGO Y COMPAC. DE BASE C/MATERIAL SELECCIONADO E=0.10m. S/. 115,676.17 S/. 38,558.72 S/. 154,234.89
04 SARDINEL DE CONCRETO S/. 390,014.75
04.01 ENCOFRADO Y DESENCOFRADO DE SARDINELES S/. 153,999.56 S/. 27,176.39 S/. 181,175.95
04.02 SARDINEL EXPUESTO CONCRETO F'c=175 KG/CM2 S/. 208,838.80 S/. 208,838.80
05 VEREDAS DE CONCRETO S/. 567,120.79
05.01 CONCRETO EN VEREDAS F'c=175 KG/CM2 S/. 527,795.99 S/. 527,795.99
05.02 ENCOFRADO DE SEPARACION EN ACERA PEATONAL S/. 9,143.32 S/. 9,143.32
05.03 CURADO DE CONCRETO EN VEREDAS S/. 17,588.19 S/. 17,588.19
05.04 RELLENO DE JUNTAS S/. 12,593.29 S/. 12,593.29
06 NIVELACION DE CAJAS DE AGUA Y DESAGUE S/. 79,119.00
06.01 NIVELACION DE CAJAS DE DESAGUE S/. 42,350.20 S/. 42,350.20
06.02 NIVELACION DE CAJAS DE AGUA S/. 36,768.80 S/. 36,768.80
07 TACHOS DE BASURA S/. 44,671.60
07.01 COLOCACION DE TACHOS DE BASURA SEGUN DISEÑO S/. 44,671.60 S/. 44,671.60
08 PROTECCION AMBIENTAL S/. 4,645,788.79
08.01 LIMPIEZA FINAL DE OBRA S/. 13,379.05 S/. 13,379.05
COSTO DIRECTO S/. 716,037.57 S/. 82,756.28 S/. 28,665.57 S/. 67,024.55 S/. 233,940.19 S/. 36,989.98 S/. 402,800.68 S/. 3,064,194.92 S/. 4,632,409.74
MONTO ACUMULADO S/. 716,037.57 S/. 798,793.85 S/. 827,459.42 S/. 894,483.97 S/. 1,128,424.16 S/. 1,165,414.14 S/. 1,568,214.82 S/. 4,632,409.74

PORCENTAJE DE AVANCE 15.46% 1.79% 0.62% 1.45% 5.05% 0.80% 8.70% 66.15%
PORCENTAJE ACUMULADO 15.46% 17.24% 17.86% 19.31% 24.36% 25.16% 33.85% 100.00%