RELACION DE MATERIALES HASTA MUROS PRIMER PISO

Obra : VIVIENDA UNIFAMILIAR


Propietario : SRA. ROSA PUMA
Ejecuta
Formula : ARQUITECTURA, ESTRUCTURAS, INST. ELÉCTRICAS,
SANITARIAS Y ACABADOS

Ubicación : Mz "V"- Lte. "15" - HUARANGAL - ALTO SELVA ALEGRE


Fecha : NOVIEMBRE 2019
PARTIDAS METRADO UNIDAD PRECIO UNITARIO PRECIO PARCIAL TOTAL
1. CIMIENTOS 1/ 10 25.68
Cemento 65.00 Bls 21.50 1397.5
Piedra 8.00 m3 40.00 320.00
Hormigón 18.00 m3 45.00 810.00 2527.50

2.SOBRECIMIENTO 1/ 4 / 4 4m3
Cemento 19.00 Bls 21.50 408.50
Piedra 0.00 m3 40.00 0.00
Arena Gruesa 2.00 m3 40.00 80.00
Cascajo 2.00 m3 45.00 90.00 578.50

3. ZAPATAS 1/ 3 / 3 17 zap. 4 m3
Cemento 24.00 Bls 21.50 516.00
Ø 3/8” 15.00 vrlls 15.00 225.00
Arena gruesa 2.00 m3 40.00 80.00
Cascajo 2.00 m3 45.00 90.00
alambre 16 y clavos Glob Glob 20.00 20.00 931.00

4. COLUMNAS 1 / 2.5 / 2.5 17 col. 3.85 m3


Cemento 28.00 Bls 21.50 602.00
Ø 1/2” 72.00 vrlls 27.00 1944.00
Ø 5/8” 30.00 vrlls 45.00 1350.00
Ø 3/8 “ 12.00 vrlls 15.00 180.00
Ø 1/4" 51.00 vrlls 6.00 306.00
Alambre # 8 20.00 Kg 4.50 90.00
Alambre # 16 20.00 Kg 4.50 90.00
Clavos 2” 2 ½” 3” 15.00 Kg 4.00 60.00
Arena gruesa 2.00 m3 40.00 80.00
Cascajo 2.00 m3 45.00 90.00 4792.00

5. MUROS 1/5 91.215m2


Cemento 25.00 Bls 21.50 537.50
Alambre # 8 20.00 Kg 4.50 90.00
Ladrillo K-K / h=9 Cm. 5.50 Millar 900.00 4950.00
Arena gruesa 3.50 m3 40.00 140.00 5717.50

6. TECHO 1/ 2.5 / 2.5 45 m2


Cemento 77.00 Bls 21.50 1655.50
Ø 1/2” 84.00 vrlls 27.00 2268.00
Ø 3/8“ 5.00 vrlls 15.00 75.00
Ø 1/4" 79.00 vrlls 6.00 474.00
Alambre # 16 30.00 Kg 4.50 135.00
Clavos 2” 2 ½” 3” 25.00 Kg 4.00 100.00
Arena gruesa 8.50 m3 40.00 340.00
Cascajo 8.50 m3 45.00 382.50
Ladrillo Hueco 30 x 30 x 15 775.00 Unid. 3.50 2712.50 8142.50

7. ESCALERAS 1/ 2.5 / 2.5 45 m2


Cemento 10.00 Bls 21.50 215.00
Ø 3/8” 5.00 vrlls 25.00 125.00
Arena gruesa 0.70 m3 40.00 28.00
Cascajo 0.70 m3 45.00 31.50
alambre 16 y clavos Glob Glob 20.00 20.00 419.50

10. FALSO PISO 1/ 3.5 / 3.5 85.20 m2


Cemento 45.00 Bls 21.50 967.50
Arena gruesa 4.50 m3 40.00 180.00
Cascajo 4.50 m3 45.00 202.50 1350.00

11. INSTALACION ELECTRICA


Glb.
Y SANITARIA
Instalacion Sanitaria y Electrica 1.00 Glb 2000.00 2000.00 2000.00

TOTAL MATERIALES S/. 26458.50


GASTOS POR TRASPORTE Y EQUIPOS S/. 1000.00
COSTO MANO DE OBRA S/. 19000.00
TOTAL COSTO DIRECTO S/. 46458.50

RESUMEN MATERIALES PARA TODA LA OBRA


Obra : VIVIENDA UNIFAMILIAR
Propietario : SRA. ROSA PUMA
Ejecuta
Formula : ARQUITECTURA, ESTRUCTURAS, INST. ELÉCTRICAS,
SANITARIAS Y ACABADOS
Ubicación : Mz "V"- Lte. "15" - HUARANGAL - ALTO SELVA ALEGRE
Fecha : NOVIEMBRE 2019

MATERIALES CANT. UNI. PRECIO PR. PARCIAL TOTAL


Ø 1/2” 166.00 vrlls 27.00 4482.00
Ø 5/8” 30.00 vrlls 45.00 1350.00
Ø 3/8“ 40.00 vrlls 15.00 600.00
Ø 1/4" 130.00 vrlls 6.00 780.00
Alambre # 8 40.00 Kg 4.50 180.00
Alambre # 16 50.00 Kg 4.50 225.00
Clavos 2” 2 ½” 3” 40.00 Kg 4.00 160.00
alambre 16 y clavos GLOB. 40.00 40.00
Cemento 293.00 Bls 21.50 6299.50
Arena gruesa 23.20 m3 40.00 928.00
Cascajo 19.70 m3 45.00 886.50
Hormigon 18.00 m4 45.00 810.00
Ladrillo K-K / h=9 Cm. 5.50 Millar 900.00 4950.00
Ladrillo Hueco 30 x 30 x 15 775.00 Unid. 3.00 2325.00
Piedra 8.00 m3 40.00 320.00
Instalacion Sanitaria y Electrica 1.00 Glb 750.00 750.00
25086.00

COMPRA DE MATERIALES PARA CERCO PERIMETRICO


Obra : VIVIENDA UNIFAMILIAR
Propietario : SRA. ROSA PUMA
Ejecuta :
Formula : ARQUITECTURA, ESTRUCTURAS, INST. ELÉCTRICAS,
SANITARIAS Y ACABADOS
Ubicación : Mz "V"- Lte. "15" - HUARANGAL - ALTO SELVA ALEGRE
Fecha : NOVIEMBRE 2019
PARTIDAS METRADO UNIDAD PRECIO UNITARIO PRECIO PARCIAL TOTAL
1. CIMIENTOS 1/ 10 25.68
Cemento 10.00 Bls 21.50 215
Piedra 2.00 m3 40.00 80.00
Hormigón 3.00 m3 45.00 135.00 430.00

2.SOBRECIMIENTO 1/ 4 / 4 1m3
Cemento 5.00 Bls 21.50 107.50
Piedra 0.00 m3 40.00 0.00
Arena Gruesa 0.50 m3 40.00 20.00
Cascajo 0.50 m3 45.00 22.50 150.00

4. COLUMNAS CERCO 1 / 3 / 3 4 col. 0.5 m3


Cemento 2.00 Bls 21.50 43.00
Ø 3/8 “ 8.00 vrlls 15.00 120.00
Ø 1/4" 7.00 vrlls 6.00 42.00
Arena gruesa 0.25 m3 40.00 10.00
Cascajo 0.25 m3 45.00 11.25 226.25

5. MUROS 1/5 91.215m2


Cemento 7.00 Bls 21.50 150.50
Alambre # 8 20.00 Kg 4.50 90.00
Ladrillo K-K / h=8 Cm. 2.00 Millar 550.00 1100.00
Arena gruesa 1.00 m3 40.00 40.00 1380.50

TOTAL MATERIALES S/. 2186.75


GASTOS POR TRASPORTE Y EQUIPOS S/. 300.00
COSTO MANO DE OBRA S/. 1800.00
TOTAL COSTO DIRECTO S/. 4286.75
`
`