19065 EDP - FABRICA Y MONTAJE DE PLUMAS Y OTROS

N° DETALLE DE PARTIDAS NOVIEMBRE DICIEMBRE TOTAL COSTO


1.0 GERENCIA DE PROYECTO 0
1.1 PLANIFICACION Y CONTROL DE PROYECTO 5349.08 0 5,349.08
MANO DE OBRA 5349.08 5,349.08
2.0 INGENIERÍA 1400 1400
2.1 ING. MECANICA - DISEÑO DE ING. BASICA Y DETALLE 1400 0 1,400.00
3.0 SUMINISTRO Y FABRICACIONES 6801.23 0 6,801.23
3.1 PLATAFORMAS COLGANTES 0 0 0.00
3.2 PANELES DE ENCOFRADO 0 0 0.00
3.3 TOLVAS 0 0 0.00
3.4 PLUMA DE 7M 6801.23 0 6,801.23
3.5 PLUMA DE 3M 0 0 0.00
3.6 ESTRUCTURA PARA IZAJE 0 0 0.00
4.0 OBRAS MECANICAS
4.1 INSTALACION DE ESTRUCTURA METALICA GENERAL 0 0 0.00
5.0 GASTOS GENERALES 197.32 0 197.32
TOTAL 13747.63 0 13,747.63

DETALLE MONTO S/. Objetivo


TOTAL INGRESOS 136,444.00 Venta 136,444.00 100% 68.222
FACTURA E001-40 10,619.00 Costo Proyec 86,500.00 63% 43.25
FACTURA E001-41 1,288.14 Margen proye 49,944.00 37% 12.9104477612

RESULTADO ESTIMADO
Precio Vta 136,444.00 100%
Costo Real 13,747.63 10%
Costo proyec 72,752.37 53%
POR COBRAR S/. 124,536.86 Margen proye 49,944.00 37%
20.36477612
RECURSOS POR EJECUTAR
19065 EDP - FABRICA Y MONTAJE DE PLUMAS Y OTROS

N° DETALLE DE PARTIDAS SUBTOTALES TOTALES


1.0 GERENCIA DE PROYECTOS 9650.92
1 PLANIFICACION Y CONTROL DE PROYECTO 9650.92
MANO DE OBRA 9,650.92
2.0 INGENIERÍA Y SUPERVISIÓN 4600
2 DIEÑO DE ING BASICA Y DETALLE 4600
MANO DE OBRA 4,600.00
COSTOS INDIRECTOS
SERVICIO TERCERO
3.0 OBRAS MECÁNICAS 30128.77
3 PLATAFORMAS COLGANTES 4730
MATERIALES 2,680.00
MANO DE OBRA 2,050.00
COSTOS INDIRECTOS
SERVICIO TERCERO
3 PANELES DE ENCOFRADO 11500
MATERIALES 9,000.00
MANO DE OBRA 2,500.00
COSTOS INDIRECTOS
SERVICIO TERCERO
3 TOLVAS 3000
MATERIALES 2,200.00
MANO DE OBRA 800.00
COSTOS INDIRECTOS
SERVICIO TERCERO
3 PLUMA DE 7M 2098.77
MATERIALES 1,468.77
MANO DE OBRA 630.00
COSTOS INDIRECTOS
SERVICIO TERCERO
4 PLUMA DE 3M 5900
MATERIALES 3,900.00
MANO DE OBRA 2,000.00
COSTOS INDIRECTOS
SERVICIO TERCERO
4 ESTRUCTURA PARA IZAJE 2900
MATERIALES 2,100.00
MANO DE OBRA 800.00
COSTOS INDIRECTOS
SERVICIO TERCERO
4.0 OBRAS MECANICAS 15970
4 INSTALACION DE ESTRUCTURA METALICA GENERAL 15970
MATERIALES 6,850.00
MANO DE OBRA 9,120.00
COSTOS INDIRECTOS
SERVICIO TERCERO
5.0 GASTOS GENERALES 12402.68
SEGURIDAD 1,402.68
ALIMENTACION 3,600.00
MOVILIDAD 800.00
SEGUROS Y FIANZAS 3,600.00
OFICINA CENTRAL 3,000.00
TOTAL 72,752.37
RESUMEN DE EJECUCION DE PRESUPUESTO EN PROYECTO AÑO 2019
19065 EDP - FABRICA Y MONTAJE DE PLUMAS Y OTROS
FABRICACION DE SEGUNDA PARTE DE DUCTOS
VARIACION DE
N° DETALLE DE PARTIDAS PRESUPUESTO EJECUTADO POR EJECUTAR PRESUPUESTO SALDO % % DE AVANCE

1.00 GERENCIA DE PROYECTO 15,000.00 5,349.08 9,650.92 0.00


1 PLANIFICACION Y CONTROL DE PROYECTO 15000 5,349.08 9,650.92 0.00
2.00 INGENIERÍA 6,000.00 1,400.00 4,600.00 0.00 9%
2 ING. MECANICA - DISEÑO DE ING. BASICA Y DETAL 6000 1,400.00 4,600.00 0.00 90%
3.00 SUMINISTRO Y FABRICACIONES MECANICAS 36,930.00 6,801.23 30,128.77 0.00 9%
3 PLATAFORMAS COLGANTES 4730 0.00 4,730.00 0.00
3 PANELES DE ENCOFRADO 11500 0.00 11,500.00 0.00
3 TOLVAS 3000 0.00 3,000.00 0.00
3 PLUMA DE 7M 8900 6,801.23 2,098.77 0.00 85%
4 PLUMA DE 3M 5900 0.00 5,900.00 0.00
4 ESTRUCTURA PARA IZAJE 2900 0.00 2,900.00 0.00
4.00 OBRAS MECANICAS 15,970.00 0.00 15,970.00 0.00 0%
4 INSTALACION DE ESTRUCTURA METALICA GENERAL 15970 0.00 15,970.00 0.00
5.00 GASTOS GENERALES 12,600.00 197.32 12,402.68 0.00
TOTAL 86,500.00 13,747.63 72,752.37 0.00 18%
* PARA LA MEDICION DE AVANCE DE PROYECTO SOLO SE ESTA CONSIDERANDO PARTIDAS QUE SON DIRECTAMENTE ACTIVIDADES DEL PROYECTO

INGRESOS DEL PROYECTO


DETALLE MONTO S/. %
VENTA 136,444.00 100%
COBRADO 11,907.14 9%
POR COBRAR S/. 124,536.86 91%

EJECUCION DE PRESUPUESTO
PRESUPUESTO 86,500.00 100%
EJECUTADO -13,747.63 -16%
PROYECTADO -72,752.37 -84%
PRESUPUESTO POR EJECUTAR 0.00 0%
P.U. CONSUMIBLES MATERIALES PERSONAL PERSONAL / D
2927.78 KG 9.57 S/ 28,018.85 S/ 6,500.00 S/ 15,000.00 S/ 6,518.85

motoreductor EPLI incluido IGV S/ 8,250.01 TIEMPO DE FABRICACION 15


movilizacion y GG S/ 1,000.00

TOTAL S/ 37,268.86 $11,158.34

compras ###

Sin IGV 26059.3305


Mano de Obr S/ 6,518.85
32578.1851

Depositos
12-Aug 50
13-Aug 100
13-Aug 200
14-Aug 250
TOTAL 600.00
Gastos
Uniforme soldador -70.00
Materiales aire -192.00
Viaticos L-V -450.00
Total Gastos -712.00

diferencia -112.00
PERSONAL / DIA PERSONAL FABRICACION ATACOCHA
S/ 434.59 x DIA TOTAL x DIA
AYUDANTES 2 S/ 50.00 S/ 100.00
SOLDADOR 1 S/ 90.00 S/ 90.00
ARMADOR 1 S/ 80.00 S/ 80.00
SUPER GATO 1 S/ 100.00 S/ 100.00
S/ 370.00 PERSONAL X DIA 4810
15 DIAS TRABAJO
TOTAL S/ 5,550.00

INICIO FABRICACIONES 01/03/2019


PERSONAL CARGO
SEGUNDO 100
CABRERA ARMADOR 90
JONATHAN AYUDANTE 45