CERTIFICADO DE AVANCE DE OBRA Nº 21

EMPRESA CONTRATISTA:
CASTELLANOS CONSTRUCCIONES S.R.L.
PROYECTO: CONSTRUCCION Y DOTACION DE MOBILIARIO NUEVO BLOQUE DE LA FACULTAD DE ODONTOLOGIA
- UAJMS

CONTRATO ACTUALIZADO SEG


ITEM CONTRATO ORIGINAL CONTRATO MODIFICATORIO N°1 ORDEN DE TRABAJO N°1 ORDEN DE TRABAJO N°2 ORDEN DE TRABAJO N°3
MODIFICATORIO N°2
DESCRIPCION DEL ITEM

Nº UNID. CANTIDAD P. U. (Bs) MONTO (Bs) CANTIDAD MONTO (Bs) CANTIDAD MONTO (Bs) CANTIDAD MONTO (Bs) CANTIDAD MONTO (Bs) CANTIDAD

M06 - INSTALACION ELECTRICA, AIRE ACOND. Y AIRE COMPRIMI 4,410,686.99 0.00 0.00
1 PROV INST TRANSF TRIFASICO 400KVA,24,9 KV 380/220V pza 1.00 218,254.12 218,254.12 1.00
2 PROV INST. ESTRUCTURA VGH-25 EN PLATAFORMA pza 1.00 17,645.55 17,645.55 1.00
3 PROV INST. TABLERO MEDICION TRIFASICO ELECTRONICO pza 1.00 14,174.00 14,174.00 0.00
4 PROV INSTALACION TABLERO GENERAL pza 1.00 34,791.01 34,791.01 0.00
5 PROV INSTALACION TABLERO DE DISTRIBUCION pza 4.00 13,679.23 54,716.92 4.00
6 PROV INSTALACION TABLERO SECUNDARIO pza 41.00 4,441.48 182,100.68 41.00
7 PROV Y COLOC POSTE HºAº 800KG DE 11M pza 1.00 3,410.03 3,410.03 0.00
8 TOMACORRIENTES DOBLES C/PUESTA A TIERRA pto 491.00 278.62 136,802.42 491.00
9 TOMACORRIENTES SIMPLE C/PUESTA A TIERRA SCHUKOT pto 195.00 357.35 69,683.25 195.00
10 TOMACORRIENTE SIMPLE C/PUESTA TIERRA ESPEC C/TAPA pto 415.00 395.30 164,049.50 415.00
11 PROV E INST. PANTALLA 2x20W LED pza 376.00 1,202.12 451,997.12 376.00
12 PROV INST. SPOT 25 WLED CUADRADO pza 313.00 1,066.95 333,955.35 313.00
13 PROV INST. SPOT 16 WLED CUADRADO pza 289.00 754.44 218,033.16 289.00
14 PROV INST. PROYECTOR DE PISO 36W pza 391.00 767.82 300,217.62 391.00
15 PROV INST. APLIQUET 5W LED pza 85.00 586.87 49,883.95 85.00
16 PROV INST. SPOT S/PONER 6 W LED pza 16.00 790.44 12,647.04 16.00
17 PROV INST. PROYECTOR EXTERIOR DE MURO 9 WLED pza 17.00 856.23 14,555.91 17.00
18 PROV INST. PROYECTOR EXTERIOR DE PISO 6 W LED pza 21.00 808.22 16,972.62 21.00
19 PROV INST. SPOT 5W LED PARA EMPOTRAR pza 30.00 598.91 17,967.30 30.00
20 PROV INST. CABLE UNIPOLAR 1x2 AWG 25KW m 87.00 1,036.75 90,197.25 87.00
21 PROV INST. CABLE UNIPOLAR 1x4/0 AWG AISL 1KV m 525.00 150.26 78,886.50 525.00
22 PROV INST. CABLE TETRAPOLAR 3x1/0 AWG AISL 1KV m 22.00 90.25 1,985.50 22.00
23 PROV INST. CABLE TETRAPOLAR 3x4 AWG m 84.00 65.78 5,525.52 84.00
24 PROV INST. CABLE TETRAPOLAR 3x8 AWG m 460.00 149.11 68,590.60 460.00
25 PROV INST. CABLE 2x10 AWG m 634.00 77.09 48,875.06 634.00
26 PROV INST. CABLE SINTENAX 2X14 AWG m 130.00 19.48 2,532.40 130.00
27 PROV INST. DUCTOS DE PVC D=1" m 426.00 36.02 15,344.52 426.00
28 PROV INST. DUCTOS DE PVC D=4" E-40 m 167.00 91.74 15,320.58 167.00
29 EXCAVACION DE ZANJAS P/CABLE SUBTERR. m³ 41.00 39.29 1,610.89 41.00
30 RELLENO Y COMPACTADO DE ZANJAS m³ 41.00 37.81 1,550.21 41.00
31 PROV INST. SISTEMA DE ATERRAMIENTO EN MALLA pza 36.00 380.60 13,701.60 5.00
32 PROV INST. PARARRAYOS TIPO FRANKLIN 3 PUNT+TORRE pza 4.00 3,437.54 13,750.16 0.00
33 PROV INST. EQUIPO SONIDO DE 2000W POTENCIA SALIDA pza 1.00 15,951.20 15,951.20 1.00
34 PROV Y COLOC SEÑALIZACION - LETREROS pza 134.00 305.97 40,999.98 134.00
35 PROV Y COLOC VENTILADORES DE TECHO pza 103.00 856.34 88,203.02 77.00
36 PROV Y COLOC AIRE ACOND CASSETTE 18000BTU SIST 1X1 pza 36.00 6,855.99 246,815.64 13.00
37 PROV Y COLOC AIRE ACOND CASSETTE 9000BTU SIST 1X1 pza 24.00 4,623.89 110,973.36 8.00
38 PROV E INST LINEA FRIGORIFICA m 984.00 179.32 176,450.88 200.00
39 PROV Y COLOC AIRE ACOND PARED 9000BTU SIST 1X1 pza 4.00 4,544.33 18,177.32 4.00
CERTIFICADO DE AVANCE DE OBRA Nº 21
EMPRESA CONTRATISTA:
CASTELLANOS CONSTRUCCIONES S.R.L.
PROYECTO: CONSTRUCCION Y DOTACION DE MOBILIARIO NUEVO BLOQUE DE LA FACULTAD DE ODONTOLOGIA
- UAJMS

CONTRATO ACTUALIZADO SEG


ITEM CONTRATO ORIGINAL CONTRATO MODIFICATORIO N°1 ORDEN DE TRABAJO N°1 ORDEN DE TRABAJO N°2 ORDEN DE TRABAJO N°3
MODIFICATORIO N°2
DESCRIPCION DEL ITEM

Nº UNID. CANTIDAD P. U. (Bs) MONTO (Bs) CANTIDAD MONTO (Bs) CANTIDAD MONTO (Bs) CANTIDAD MONTO (Bs) CANTIDAD MONTO (Bs) CANTIDAD

40 PROV E INST CAMARA DE INSP 0.40X0.40X0.6M pza 3.00 421.92 1,265.76 0.00
41 PROV. E INST. BANDEJA METALICA m 920.95 334.74 308,278.80 920.95
42 PROV INST. ASCENSOR P/CAMILLA (2.35x1.75m) 630KG glb 1.00 357,670.89 357,670.89 1.00
43 PROV INST. TUBO 15W ULTRA VIOLETA pza 9.00 802.45 7,222.05 9.00
44 PROV INST. COMPRESORA TRIFASICA 7.5 HP 400L pza 3.00 26,354.04 79,062.12 3.00
45 PROV INST. AIRE COMPRIMIDO P/SILLONES (d=3/4") pto 143.00 824.31 117,876.33 0.00
46 PROV. Y TENDIDO TUBERIA FG D=3" (AIRE COMP) m 156.00 225.40 35,162.40 0.00
47 PROV. Y TENDIDO TUBERIA FG D=21/2" (AIRE COMP) m 168.00 164.55 27,644.40 0.00
48 PROV. Y TENDIDO TUBERIA FG D=2" (AIRE COMP) m 136.00 129.86 17,660.96 0.00
49 PROV. Y TENDIDO TUBERIA FG D=1.5" (AIRE COMP) m 405.00 99.90 40,459.50 0.00
50 PROV Y COLOC TANQUE PULMON 56m3 pza 3.00 9,036.78 27,110.34 3.00
51 ACCESORIOS FG, LLAVES Y VALVULAS AIRE COMPRIMIDO gbl 1.00 23,973.70 23,973.70 0.00
DE AVANCE DE OBRA Nº 21
UNIVERSIDAD AUTONOMA "JUAN MISAEL SARACHO"

CONTRATO ACTUALIZADO SEGÚN


AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO
MODIFICATORIO N°2

VOLUMEN VOLUMEN VOLUMEN


MONTO (Bs) MONTO Bs. % AVANCE MONTO Bs. % AVANCE MONTO Bs. % AVANCE
(+ ó -) (+ ó -) (+ ó -)

3,674,198.41 415,839.20 0.00 415,839.20


218,254.12 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
17,645.55 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
54,716.92 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
182,100.68 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
136,802.42 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
69,683.25 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
164,049.50 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
451,997.12 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
333,955.35 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
218,033.16 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
300,217.62 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
49,883.95 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
12,647.04 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
14,555.91 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
16,972.62 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
17,967.30 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
90,197.25 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
78,886.50 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
1,985.50 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
5,525.52 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
68,590.60 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
48,875.06 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
2,532.40 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
15,344.52 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
15,320.58 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
1,610.89 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
1,550.21 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
1,903.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
15,951.20 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
40,999.98 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
65,938.18 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
89,127.87 10.00 68,559.90 27.78% 0.00 0.00% 10.00 68,559.90 76.92%
36,991.12 8.00 36,991.12 33.33% 0.00 0.00% 8.00 36,991.12 100.00%
35,864.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
18,177.32 4.00 18,177.32 100.00% 0.00 0.00% 4.00 18,177.32 100.00%
DE AVANCE DE OBRA Nº 21
UNIVERSIDAD AUTONOMA "JUAN MISAEL SARACHO"

CONTRATO ACTUALIZADO SEGÚN


AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO
MODIFICATORIO N°2

VOLUMEN VOLUMEN VOLUMEN


MONTO (Bs) MONTO Bs. % AVANCE MONTO Bs. % AVANCE MONTO Bs. % AVANCE
(+ ó -) (+ ó -) (+ ó -)

0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%


308,278.80 872.65 292,110.86 94.76% 0.00 0.00% 872.65 292,110.86 94.76%
357,670.89 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
7,222.05 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
79,062.12 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
27,110.34 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%