EXCAVACIÓN MASIVA

se suma 0.25m a cada altura AREA (CAD) ALTURA VOLUMEN


exc. -19.25 131.48 19.25 2,530.99
exc. -19.225 54.68 19.225 1,051.22
exc. -19.20 148.61 19.20 2,853.31
exc. -18.6 187.41 18.60 3,485.83
exc. -21 (1) 242.65 21.00 5,095.65
exc. -21 (2) 260.80 21.00 5,476.80
exc. -20.4 294.29 20.40 6,003.52
1,319.92 27,822.19

EXCAVACIONES LOCALIZADAS
AREA (CAD) ALTURA VOLUMEN
CISTERNA
DE -21.00 242.65 3 764.35
DE -18.00 260.80 3 821.52
ZAPATAS
Z-6 15.51 1.375 23.46
Z-8 17.58 1.35 26.11
Z-17 3.94 0.85 11.05
Z-10 51.00 2.05 115.01
Z-11 31.47 1.95 67.50
Z-7 14.35 0.9 14.21
Z-12 35.68 2.15 92.05
Z-14 37.57 2.05 84.72
Z-4 12.51 1.4 21.02
Z-5 15.12 1.6 26.61
Z-1 14.43 1.15 18.25
Z-2 21.00 1.25 28.88
Z-1A 14.42 0.85 13.48
Z-15 36.92 0.9 36.55
Z-16 7.60 1.3 10.87
Z-9 16.32 0.5 8.98
CIMIENTOS
1,1A,2,2A,3C 22.35 2.24 55.07
3,3A,3B,5,6A,6 23.25 2.22 56.78
07 A 11 12.54 74 1,020.76
3,317.23

EXC. MASIVA 27,822.19


EXC LOCALIZADA (CISTERNA, ZAPATAS Y CIMIENTOS) 3,317.23
TOTAL EN BANCO 31,139.42