CRONOGRAMA DE EJECUCION DE OBRA

PROYECTO: EJECUCION I.E. CESAR VALLEJO - CCATCA

DISTRITO: CCATCA
PROVINCIA:QUISPICANCHI Y DPTO : CUSCO.
PLAZO: 03 MES

DESCRIPCION UNIDAD PRIMER MES SEGÚN.MES TERCER MES


TRABAJOS PRELIMINARES
xxxxxxxxxxxxxxx
S/. 324.41 - -
LIMPIEZA DE TERRENO MANUAL % 100% 0% 0%
xxxxxxxxxxxxxxx
S/. 139.26 - -
TRAZO Y REPLANTEO CON BALIZAS % 100% 0% 0%
MOVIMIENTO DE TIERRAS
xxxxxxxxxxxxxxx
S/. 1,522.56 - -
EXCAVACION PARA ZAPATAS DE 1.40 MT A 2.10 MT DE PROFUNDIDAD % 100% 0% 0%
xxxxxxxxxxxxxxx
S/. 203.14 - -
EXCAVACION PARA CIMIENTOS HASTA 1.40 MT TERRENO NORMAL % 100% 0% 0%
xxxxxxxxxxxxxxx
S/. 13.71 - -
RECTIFICACION Y PERFILADO DE ZANJAS PARA CIMIENTOS % 100% 0% 0%
xxxxxxxxxxxxxxx
S/. 1,119.11 - -
ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 M ) % 100% 0% 0%
OBRAS DE CONCRETO SIMPLE
xxxxxxxxxxxxxxx
S/. 902.36 - -
SOLADO PARA ZAPATAS DE 4" MEZCLA 1:12 CEMENTO-HORMIGON % 100% 0% 0%
xxxxxxxxxxxxxxx
S/. 75.03 - -
EXCAVACION PARA CIMIENTOS HASTA 1.40 MT TERRENO NORMAL % 100% 0% 0%
xxxxxxxxxxxxxxx
S/. 1,433.28 - -
RECTIFICACION Y PERFILADO DE ZANJA PARA CIMIENTOS % 100% 0% 0%
xxxxxxxxxxxxxxx
S/. 1,693.32 - -
ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 M ) % 100% 0% 0%
OBRAS DE CONCRETO ARMADO
ZAPATAS
xxxxxxxxxxxxxxx
S/. 8,321.94 - -
CONCRETO PARA ZAPATAS F'C=210 KG/CM2 % 100% 0% 0%
xxxxxxxxxxxxxxx
S/. 2,102.41 - -
ACERO PARA ZAPATAS GRADO 60 % 100% 0% 0%
VIGAS DE CONEXION
xxxxxxxxxxxxxxx
S/. 3,086.05 - -
CONCRETO EN VIGAS DE CIMENTACION F'C= 210 KG/CM2 % 100% 0% 0%
xxxxxxxxxxxxxxx
S/. 2,960.62 - -
ACERO ESTRUCTURAL TRABAJADO PARA VIGAS DE CIMENTACION % 100% 0% 0%
xxxxxxxxxxxxxxx
S/. 273.80 - -
ENCOFRADO Y DESENCOFRADO NORMAL % 100% 0% 0%
COLUMNAS
xxxxxxxx xxxxxxxx
S/. 1,935.86 1,935.86 -
CONCRETO EN COLUMNAS F'C=210 KG/CM2 % 50% 50% 0%
xxxxxxxx xxxxxxxx
S/. 7,360.46 7,360.46 -
ACERO GRADO 60 EN VIGAS % 50% 50% 0%
xxxxxxxx xxxxxxxx
S/. 1,093.46 1,093.46 -
ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS % 50% 50% 0%
VIGAS
xxxxxxxx xxxxxxxx
S/. 4,465.02 4,465.02 -
CONCRETO EN VIGAS F'C=210 KG/CM2 % 50% 50% 0%
xxxxxxxx xxxxxxxx
S/. 3,464.38 3,464.38 -
ACERO GRADO 60 EN VIGAS % 50% 50% 0%
xxxxxxxx xxxxxxxx
S/. 3,173.83 3,173.83 -
ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS % 50% 50% 0%
LOSAS ALIGERADAS
xxxxxxxxxxx xxxx

CONCRETO EN LOSAS ALIGERADAS F'C=210 KG/CM2


S/. 4,954.12 2,123.20 -
CONCRETO EN LOSAS ALIGERADAS F'C=210 KG/CM2 % 70% 30% 0%
xxxxxxxxxxx xxxx
S/. 8,067.63 3,457.55 -
ACERO GRADO 60 EN LOSAS ALIGERADAS % 70% 30% 0%
xxxxxxxxxxxxxxx
S/. 2,574.37 - -
ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS % 100% 0% 0%
xxxxxxxx xxxxxxx
S/. 1,037.48 1,037.48 -
BLOQUE HUECO/CONCRETO 15X30X20 CM PARA LOSA ALIGERADA % 50% 50% 0%
MUROS TABIQUES DE ALBAÑILERIA
xxxxxxxx xxxxxxxx
S/. 2,870.95 2,870.95 -
MURO DE BLOQUE HUECO DE CONCRETO E=20 CM. MEZCLA 1:5 % 50% 50% 0%
CUBIERTAS
xxxxxxxxxxxxxx
S/. - 644.41 -
TIJERAL DE MADERA ACERRADA 2" X 7" % 0% 100% 0%
xxxxxxxxxxxxxx
S/. - 911.45 -
CORREAS DE MADERA 2 X 3 X 10' % 0% 100% 0%
xxxxxxxxxxxxxx
S/. - 5,040.90 -
COBERTURA DE TEJA COLONIAL % 0% 100% 0%
REVOQUES ENLUCIDOS Y MOLDURAS
xxxx xxxxxxxxxxx
S/. - 1,318.88 3,077.38
TARRAJEO EN INTERIORES ACABADO CON CEMENTO-ARENA % 0% 30% 70%
xxxxxxx xxxxxxxxx
S/. - 3,462.51 5,193.77
TARRAJEO EN EXTER CON CEMENTO-ARENA % 0% 40% 60%
xxxxxxxx xxxxxx
S/. - 1,064.78 709.85
ENLUCIDO CON YESO CIELORASO Y ALEROS % 0% 60% 40%
xxxx xxxxxxxxxxxx
S/. - 492.48 1,969.91
ENLUCIDO CIELO RASO SOBRE ENCHACLADO DE CARRIZO % 0% 20% 80%
ZOCALOS Y CONTRAZOCALOS
xxxxxxxxxxxxxxx
S/. - - 166.86
CONTRAZOCALO DE CEDRO 3/4" X 2" RODON DE 3/4" 0% 0% 100%
PISOS Y PAVIMENTOS
xxxx xxxxxxxxxx
S/. 962.12 3,848.48 -
FALSO PISO DE 4" DE CONCRETO 1:10 % 20% 80% 0%
xxxxxxxxxxxxxx
S/. - 5,415.75 -
CONTRAPISO DE 48 MM. % 0% 100% 0%
xxxx xxxxxxxxxxx
S/. - 1,502.47 6,009.90
PISO MADERA MACHIEMBRADA % 0% 20% 80%
xxxxxx xxxxxx
S/. - 989.28 989.28
PISOS DE CONCRETO COLOREADO FROTACHADO E=2.5 CMS. ESPESOR % 0% 50% 50%
xxxx xxxxxxxxxxx
S/. - 39.68 158.70
ENCOFRADO Y DESENCOFRADO EN VEREDAS % 0% 20% 80%
xxxxxxxx xxxxxxx
S/. - 269.22 269.22
EMPEDRADO VEREDA PERIMETRAL % 0% 50% 50%
xxxxxxxxxxxxxxx
S/. - - 1,038.08
VEREDA RIGIDA DE CONCRETO F'C=140 KG/CM2 E=10CM.,PASTA 1:2 % 0% 0% 100%
CARPINTERIA DE MADERA
xxxxxxxxx xxxx
S/. - 1,808.40 775.03
PUERTA MADERA AGUANO TABLERO REBAJADO % 0% 70% 30%
xxxxxxxxx xxxx
S/. - 2,588.44 1,109.33
VENTANA DE MADERA REFUERZO ACERO % 0% 70% 30%
CERRADURAS
xxx xxxxxxxxxxxx
S/. - 46.94 187.74
CHAPA DE 3 GOLPES PUERTA PRINCIPAL % 0% 20% 80%
xxxxxxxxxxxxxxx
S/. - - 123.84
CHAPA DE 3 GOLPES PUERTA PRINCIPAL % 0% 0% 100%
xxxxxxxxxxxxxxx
S/. - - 26.92
JALADOR PARA INTERIORES MAS COLOCADO % 0% 0% 100%
VIDRIOS, CRISTALES Y SIMILARES
xxxxxxxxxxxxxxx
S/. - - 1,996.32
VIDRIOS SEMIDOBLES NACIONALES % 0% 0% 100%
PINTURA
xxxxxxxxxxxxxxx
S/. - - 1,459.07
PINTURA LATEX EN MUROS INTERIORES - 2 MANOS % 0% 0% 100%
xxxxxxxxxxxxxxx
S/. - - 2,071.36
PINTURA LATEX EN MUROS EXTERIORES - 2 MANOS % 0% 0% 100%
xxxxxxxxxxxxxxx
S/. - - 1,113.42
PINTADO DE CIELO RASO C/LATEX VINILICO (VINILATEX O SIMILAR) % 0% 0% 100%
xxxxxxxxxxxxxxx
S/. - - 181.31
PINTURA EN PUERTAS C/BARNIZ 2 MANOS % 0% 0% 100%
xxxxxxxxxxxxxxx
S/. - - 528.74
PINTURA EN VENTANAS C/BARNIZ 2 MANOS % 0% 0% 100%
INSTALACIONES ELECTRICAS
xxxxxxx xxxxxxx
S/. - 253.56 253.56
SALIDA PARA CENTROS DE LUZ % 0% 50% 50%
xxxxxxx xxxxxxx
S/. - 512.16 512.16
SALIDA PARA TOMACORRIENTES BIPOLARES SIMPLES CON PVC % 0% 50% 50%
xxxxxxxxxxxxxxx
S/. - - 841.28
FLUORESCENTE RECTO ISPE 1 X 40 W INCLUYENDO EQUIPO Y PANTALL % 0% 0% 100%
xxxxxxxxxxxxxxx
S/. - - 71.76
FOCO 1OOWN SIMPLE. % 0% 0% 100%
TRANSPORTE
xxxx xxxxx xxxx
S/. 3,366.00 3,570.00 3,264.00
TRANSPORTE DE VARIOS % 33% 35% 32%
PRUEBA DE RESISTENCIA
xxxx xxxxx xxxx
S/. 40.99 42.23 40.99
PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) % 33% 34% 33%
COSTO MENSUAL S/. 69,537.64 64,804.17 34,139.77
PORCENTAJE MENSUAL % 41% 38% 20%
COSTO ACUMULADO S/. 69537.64 134341.81 168481.58
PORCENTAJE ACUMULADO % 41% 80% 100%
S/. 5,559.89 5,559.89 5,728.37
GASTOS GENERALES S/. % 33% 33% 34%
MONTO TOTAL S/. 185329.74