LYG DISEÑO Y CONSTRUCCIÓN

PRESUPUESTO
URBA TACNA MZ. E LOTE 03 FECHA 1/24/2019
TACNA - TACNA - TACNA PRESUPUESTO # 1
lyg.constructora@gmail.com CLIENTE ID 15
Teléfono: 052-241010 / 952715902 /952656591

CLIENTE DETALLES DEL PROYECTO


SR. HUMBERTO DAVID ROA FERNANDEZ AMPLIACION DEL 1ER NIVEL - CASCO GRIS

ITEM DESCRIPCIÓN UND METRDO P.U. TOTAL


01 OBRAS PROVICIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y S 2707.52
01.01 TRABAJOS PRELIMINARES
01.01.01 LIMPIEZA DE TERRENO MANUAL m2 79.15 1.89 149.58
01.01.02 TRAZO Y REPLANTEO DE OBRA glb 1.00 85.00 85.00
01.01.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y HERRAMIENTAS glb 1.00 100.00 150.00
01.03 DEMOLICIONES
01.03.01 DEMOLICION DE CIMIENTOS CORRIDOS m3 3.05 241.06 735.96
01.03.02 DEMOLICION DE SOBRECIMIENTOS m3 0.10 250.38 24.19
01.03.03 DEMOLICION PISO CERAMICO MANUAL m2 11.37 11.82 134.39
01.03.04 DEMOLICION DE FALSO PISO m2 11.37 27.03 307.33
01.03.05 DEMOLICION DE COLUMNAS DE CONCRETO ARMADO C/EQUIPO m3 0.38 358.48 135.51
01.03.06 DEMOLICION DE MURO P/C-1 Y TUBERIA DE DESAGUE m2 9.02 11.82 106.57
01.03.07 DEMOLICION DE LOSAS m3 2.45 358.48 878.99
02 ESTRUCTURAS Err:509
02.01 MOVIMIENTO DE TIERRAS
02.01.01 EXCAVACION DE ZAPATAS EN TERRENO NORMAL H=1.6 m m3 4.90 48.21 236.23
02.01.02 EXCAVACION PARA CIMIENTOS DE ESCALERAS m3 0.24 36.16 8.68
02.01.03 RELLENO COMPACTADO CON MATERIAL PROPIO m3 4.23 32.12 135.87
02.01.04 ACARREO DE MATERIAL EXCEDENTE HASTA 40 M m3 24.45 25.19 615.79
02.01.05 ELIMINACION DE MATERIAL EXCEDENTE C/VOLQUETE DE 15m3 m3 21.06 27.17 572.25
02.02 OBRAS DE CONCRETO SIMPLE
02.02.01 CIMIENTOS CORRIDOS: F'C=100 KG/CM2 + 30% P.G. m3 2.00 195.17 390.34
02.02.02 SOLADOS P/ZAPATA m2 5.50 24.88 136.84
02.02.03 SOBRECIMIENTOS: MEZCLA C:H 1:8 m3 0.38 261.19 97.95
02.02.04 SOBRECIMIENTOS: ENCOFRADO Y DESENCOFRADO m2 2.50 45 112.50
02.02.05 FALSO PISO DE 4" CON MEZCLA 1:8 CH m2 10.52 31.25 328.75
02.03 OBRAS DE CONCRETO ARMADO
02.03.01 ZAPATAS
02.03.01.01ZAPATAS: CONCRETO F'C=175 KG/CM2 m3 3.05 296.98 905.79
02.03.01.02ACERO EN ZAPATAS kg 73.66 4.5 331.45
02.03.03 COLUMNAS
02.03.03.01COLUMNAS: CONCRETO F'C=210 KG/CM2 m3 0.00 390 0.00
02.03.03.02COLUMNAS: ENCOFRADO Y DESENCOFRADO NORMAL m2 0.00 45 0.00
02.03.03.03ACERO COLUMNAS kg Err:509 4.5 Err:509
02.03.04 VIGAS
02.03.04.01VIGAS: CONCRETO F'C=210 KG/CM2 m3 5.53 390 2158.46
02.03.04.02VIGAS: ENCOFRADO Y DESENCOFRADO NORMAL m2 36.04 45 1621.59
02.03.04.03VIGAS: ACERO FY=4200 KG/CM2 kg 1111.76 4.5 5002.91
02.03.05 LOSAS
02.03.05.01LOSA ALIGERADA: CONCRETO F'C=210 KG/CM2 m3 0.00 390 0.00
02.03.05.02LOSA ALIGERADA: ENCOFRADO Y DESENCOFRADO NORMAL m2 0.00 45 0.00
02.03.05.03LOSA ALIGERADA: ACERO FY=4200 KG/CM2 kg Err:509 4.5 Err:509
02.03.05.04LOSA ALIGERADA: LADRILLO HUECO 30X30X15 CM und 0.00 2.44 0.00
02.03.05.05LOSA MACIZA: CONCRETO F'C=210 KG/CM2 m3 Err:509 390 Err:509
02.03.05.06LOSA MACIZA: ENCOFRADO Y DESENCOFRADO NORMAL m2 Err:509 45 Err:509
02.03.05.07LOSA MACIZA: ACERO FY=4200 KG/CM2 kg Err:509 4.5 Err:509
02.03.06 ESCALERA
02.03.06.01ESCALERA: CONCRETO F'C= KG/CM2 m3 2.67 390 1039.59
02.03.06.02ESCALERA: ENCOFRADO Y DESENCOFRADO NORMAL m2 12.58 45 566.25
02.03.06.02ESCALERA: ACERO FY=4200 KG/CM2 kg 279.30 4.5 1256.85
03 ARQUITECTURA 3633.98
03.01 MUROS Y TABIQUES
03.01.01 MURO DE LADRILLO DE SOGA C/MEZCLA 1:4 C/LADRILLO KK m2 0.00 54.63 0.00
03.02 REVOQUES Y REVESTIMIENTOS
03.02.01 TARRAJEO EN INTERIORES Y EXTERIORES m2 9.36 23.78 222.58
03.02.02 TARRAJEO EN COLUMNAS m2 17.58 25.35 445.65
03.02.03 TARRAJEO DE VIGAS m2 42.06 35.11 1476.74
03.02.04 CIELO RASO CON MEZCLA 1:5 CEMENTO-ARENA m2 37.64 28.53 1073.87
03.02.05 TARRAJEO EN FONDO DE ESCALERA m2 3.87 29.4 113.86
03.02.06 TARRAJEO DE GRADAS DE CONCRETO m2 6.72 28.53 191.72
03.02.07 TARRAJEO DE DESCANSO DE ESCALERAS DE CONCRETO m2 3.84 28.53 109.56
04 INSTALACIONES SANITARIAS 1427.97
04.01 EXCAVACION MANUAL PARA ZANJAS ml 15.04 6.06 91.14
04.02 CAMA DE APOYO E=0.10 M. ml 15.04 4.76 71.59
04.03 RELLENO COMPACTADO CON MATERIAL PROPIO C/EQUIPO LIVIANO ml 15.04 6.18 92.95
04.04 ACARREO DE MATERIAL EXCEDENTE HASTA 40M m3 0.98 25.19 24.63
04.05 ELIMINACION DE MATERIAL EXCEDENTE C/VOLQUETE DE 15m3 m3 0.98 27.17 26.56
04.01 SISTEMA DE DESAGUE
04.01.01 SALIDA DE PVC SAL PARA DESAGUE 4" pto 3.00 24.12 72.36
04.01.02 SUMINISTRO E INSTALACION TUBERIA PVC SAL 4" m 23.44 19.72 462.24
04.01.03 SUMINISTRO CODO PVC SAL 4"X90º und 3.00 5.2 15.60
04.02 SISTEMA DE AGUA FRIA
04.02.01 SALIDA DE AGUA FRIA C/TUB. DE PVC-RIGIDO 1" pto 1.00 28.76 28.76
04.02.02 SALIDA DE AGUA FRIA C/TUB. DE PVC-RIGIDO 1/2" pto 1.00 25.86 25.86
04.02.03 SALIDA DE AGUA FRIA C/TUB. DE PVC-RIGIDO 1 1/2" pto PTO 31.56 31.56
04.02.04 SUMINISTRO Y INSTALACION TUBERIA PVC RIDIGO-CLASE 10/AGUA POTABLE ml 1.50 13.53 20.30
04.02.05 SUMINISTRO Y INSTALACION TUBERIA PVC RIDIGO-CLASE 10/AGUA POTABLE D ml 13.28 18.86 250.46
04.02.06 SUMINISTRO Y INSTALACION TUBERIA PVC RIDIGO-CLASE 10/AGUA POTABLE ml 1.50 15.34 23.01
04.02.07 SUMINISTRO CODO PVC SAP 1/2"X90° und 2.00 1.59 3.18
04.02.08 SUMINISTRO TEE PVC SAP 1/2" und 1.00 3.48 3.48
04.02.09 SUMINISTRO CODO PVC SAP 1 1/2"X90° und 6.00 7.46 44.76
04.02.10 SUMINISTRO CODO PVC SAP 1"X90° und 2.00 5.77 11.54
04.02.11 SUMINISTRO E INSTALACION DE REDUCCION 1" a 1/2" und 1.00 28 28.00
04.02.12 PRUEBA HIDRAULICA glb 1.00 100 100.00
05 INSTALACIONES ELECTRICAS 793.10
05.01 SALIDA PARA LUMINARIA C/LAMP 22W ADOSABLE EN TECHO pto 3.00 28.02 84.06
05.02 SALIDA PARA LUMINARIA C/LAMP 22W ADOSABLE EN MURO pto 1.00 28.02 28.02
05.03 SALIDA PARA INTERRUPTOR UNIPOLAR pto 2.00 27.43 54.86
05.04 SALIDA PARA INTERRUPTOR UNIPOLAR DOBLE O TRIPLE pto 1.00 29.52 29.52
05.05 SALIDA PARA INTERRUPTOR DE TRES VIAS pto 2.00 32.45 64.90
05.06 SALIDA PARA LAMPARA INCANDESCENTE, TIPO SPOT LIGHT pto 1.00 29.45 29.45
05.07 SALIDA PARA CAJA DE PASO pto 1.00 26.23 26.23
05.08 RED DE DISTRIBUCION TUBERIA PVC-SEL DE 3/4" DE LUZ Y CABLEADO m 36.35 8.97 326.06
05.09 COLOCACION DE ACCESORIOS glb 1.00 150 150.00
6 OTROS
06.01 SUMINISTRO Y INSTALACION DE TANQUE CISTERNA glb 1.00 1900 1900.00
06.02 SUMINISTRO Y INSTALACION DE ELECTROBOMBA DE SERVICIO 1.5HP glb 1.00 1650 1650.00
06.03 LIMPIEZA FINAL DE OBRA glb 1.00 150 150.00

[42] SUBTOTAL Err:509


GASTOS G. (8%) Err:509
UTILIDADES (10%) Err:509
1.- PRESUPUESTO DE CASCO GRIS TOTAL Err:509
2.- INSTALACIONES ELECTRICAS INCLUYE EL ENTUBADO Y EL CABLEADO DE LA RED ELECTRICA
3.- TIEMPO ESTIMADO DE ENTREGA DE OBRA - 30 DIAS
Nº DE MEDIDAS
ITEM ESPECIFICACION PARCIAL
VECES LARGO ANCHO ALTURA
1 OBRAS PROVICIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD
01.01 OBRAS PROVICIONALES
01.01.01 OFICINA Y ALMACEN 1 1.00 1.00
01.01.02 CERCO PROVISIONAL DE OBRA CON TELA ARPILLERO Y PARANTES DE 3"
01.01.03 GUARDIANIA
01.02 TRABAJOS PRELIMINARES
01.02.01 LIMPIEZA DE TERRENO MANUAL 1 AREA= 79.15 79.15
01.02.02 TRAZO Y REPLANTEO DE OBRA 1 AREA= 79.15 79.15
01.02.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y HERRAMIENTAS 1 1.00 1.00
01.03 SEGURIDAD Y SALUD
01.03.01 EQUIPOS DE PROTECCION INDIVIDUAL
01.04 DEMOLICIONES
01.04.01 DEMOLICION PISO CERAMICO MANUAL 11.37
PARA ZAPATAS
Z-1 1 1.00 1.00 1.00
Z-2 3 1.50 1.00 4.50

PARA INSTALACION DE TUBERIA


1 AREA= 1.64 1.64
ITEM 1 AREA= 0.91 0.91
1 AREA= 2.83 2.83
PARA C-1
2 0.30 0.15 0.09

PARA CIMENTACION DE ESCALERA


1 0.80 0.50 0.40

01.04.02 DEMOLICION DE FALSO PISO 11.37


PARA ZAPATAS
Z-1 1 1.00 1.00 1.00
Z-2 3 1.50 1.00 4.50
PARA INSTALACION DE TUBERIA
1 AREA= 1.64 1.64
1 AREA= 0.91 0.91
1 AREA= 2.83 2.83
PARA C-1
2 0.30 0.15 0.09

PARA CIMENTACION DE ESCALERA


1 0.80 0.50 0.40

DEMOLICION DE COLUMNAS DE CONCRETO ARMADO C/EQUIPO


C-EXISTENTE 3 0.30 0.15 2.80 0.38

DEMOLICION DE MURO P/C-1 Y TUBERIA DE DESAGUE 9.02


PARA C-1 Y TUBERIA
1 0.80 2.80 2.24
1 0.15 2.80 0.42
1 0.48 2.80 1.34
1 0.29 2.80 0.81
1 0.90 2.80 2.52
PARA C-A
2 0.30 2.80 1.68

DEMOLICION DE SOBRECIMIENTOS 0.10


PARA C-1 Y TUBERIA
1 0.15 0.15 0.20 0.0045
1 0.80 0.15 0.20 0.02
1 0.48 0.15 0.20 0.01
1 0.29 0.15 0.20 0.01
1 0.90 0.15 0.20 0.03
PARA C-A
2 0.30 0.15 0.20 0.02

DEMOLICION DE LOSAS 2.45


1 AREA= 2.13 0.20 0.43
1 AREA= 2.67 0.20 0.53
1 AREA= 7.46 0.20 1.49

DEMOLICION DE CIMIENTOS CORRIDOS 3.05


4 1.50 AREA= 0.43 2.58
2 0.30 AREA= 0.43 0.26
1 0.50 AREA= 0.43 0.22

2 ESTRUCTURAS
02.01 MOVIMIENTO DE TIERRAS
02.01.01 EXCAVACIONES SIMPLES
02.01.01.01 EXCAVACION DE ZAPATAS EN TERRENO NORMAL H=1.6 m 4.90
ZAPATAS
Z-1 1 0.50 0.50 1.60 0.40
1 AREA= 0.75 0.60 0.45
Z-2 3 1.50 0.50 1.60 3.60
1 1.50 0.50 0.60 0.45

EXCAVACION PARA CIMIENTOS ESCALERAS


ESCALERA
EJE A 1 0.80 0.50 0.60 0.24

EXCAVACION PARA TANQUE CISTERNA


TANQUE 1 1.65 1.65 1.75 4.76

02.01.02 RELLENOS
02.01.02.01 RELLENO COMPACTADO MANUAL CON MATERIAL PROPIO 4.23
ZAPATAS
Z-1 1 AREA= 0.910 1.00 0.91
Z-2 3 AREA= 1.410 1.00 4.23

02.01.04 ACARREO DE MATERIAL EXCEDENTE HASTA 40 M 24.45


Viene de excavacion zapatas, esponjamiento F=1.30 1 VOL= 4.90 1.30 6.37
Viene de excavación de cimientos de escaleras, esponjamiento F=1.30 1 VOL= 0.24 1.30 0.31
Viene de excavación de cimientos de escaleras, esponjamiento F=1.30 1 VOL= 4.76 1.30 6.19
Viene de demolicion de piso ceramico manual, espojamiento F=1.30 1 VOL= 0.11 1.30 0.15
Viene de demolicion de falso piso, espojamiento F=1.30 1 VOL= 0.11 1.30 0.15
Viene de demolicion de columnas de concreto armado c/equipo, espojamiento F=1.30 1 VOL= 0.38 1.30 0.49
Viene de demolicion de muro p/c-1 y tuberia de desague F=1.30 1 VOL= 0.09 1.30 0.12
Viene de demolicion sobrecimiento F=1.30 1 VOL= 0.10 1.30 0.13
Viene de demolicion de losas F=1.30 1 VOL= 2.45 1.30 3.19
Viene de demolicion cimientos corridos F=1.30 1 VOL= 3.05 1.30 3.97
Viene de relleno, esponjamiento F=0.8 1 VOL= 4.23 0.80 3.38
02.01.05 ELIMINACION DE MATERIAL EXCEDENTE C/VOLQUETE DE 15m3 21.06
Viene de acarreo de material excedente incl. Esponjamiento F=1.30 1 VOL= 21.06

02.02 OBRAS DE CONRETO SIMPLE


0.00
02.02.04 SOLADO P/ZAPATA 5.50
ZAPATAS
Z-1 1 1.00 1.00 1.00
Z-2 3 1.50 1.00 4.50

CIMIENTOS CORRIDOS
CONCRETO 1:10+30% P.G. PARA CIMIENTOS F'C=100KG/CM2 2.00
EJE A 1 5.00 0.50 0.80 2.00

02.02.07 SOBRECIMIENTOS MEZCLA C:H 1:8 0.38


1:8 CEMENTO HORMIGON +25% - MAX 3"
EJE A 1 5.00 0.15 0.50 0.38

ENCOFRADO Y DESENCOFRADO 2.50


EJE A 1 5.00 0.50 2.50

02.02.06 FALSO PISO


02.02.06.01 CONCRETO F'C= 140 KG/CM2 10.52
ZAPATAS
Z-1 1 AREA= 0.91 0.91
Z-1 3 AREA= 1.41 4.23
TUBERIA
1 AREA= 5.38 5.38

02.02.06 CONTRAPISO
02.02.06.01 CONCRETO F'C= 140 KG/CM2
2DO NIVEL 1 AREA= 109.60 109.60
3ER NIVEL 1 AREA= 1.00
4TO NIVEL 1 AREA= 1.00

02.03 OBRAS DE CONCRETO ARMADO


02.03.01 ZAPATAS
02.03.01.01 ZAPATAS : CONCRETO F'C= 175 KG/CM2 3.05
ZAPATAS
Z-1 1 1.00 1.00 0.50 0.50
Z-2 3 1.50 1.00 0.50 2.25
Z-3 2 0.30 0.50 1.00 0.30

02.03.01.02 ZAPATAS : ACERO FY=4200 KG/CM2 GRADO 60 73.66


SEGÚN METRADO DE ACERO 1 Peso= 73.66

02.03.03 PLACAS
02.03.03.01 PLACAS: CONCRETO F'C= 210 KG/CM2
2DO NIVEL 3.14
P-1 2 1.42 0.25 2.80 1.99
P-2 1 1.65 0.25 2.80 1.16

PLACAS: ENCOFRADO Y DESENCOFRADO


2DO NIVEL 27.66
P-1 2 PER= 3.04 2.80 17.02
P-2 1 PER= 3.80 2.80 10.64

PLACAS: ACERO FY=4200 KG/CM2 GRADO 60


2DO NIVEL 1 Peso= 285.02 285.02

02.03.03 COLUMNAS
02.03.03.01 COLUMNAS: CONCRETO F'C= 210 KG/CM2

2DO NIVEL 5.44


C-1 15 0.30 0.25 2.80 3.15
C-2 3 PER 0.14 2.80 1.13
C-4 5 0.20 0.15 2.80 0.42
C-5 7 0.25 0.15 2.80 0.74

02.03.03.02 COLUMNAS: ENCOFRADO Y DESENCOFRADO

2DO NIVEL 59.32


Eje1
C-1 1 PER= 0.80 2.60 2.08
C-2 1 PER= 1.30 2.60 3.38
C-5 3 PER= 0.50 2.60 3.90
Eje 2
C-1 2 PER= 0.80 2.60 4.16
C-1 1 PER= 0.65 2.60 1.69
C-2 1 PER= 1.15 2.60 2.99
C-4 2 PER= 0.25 2.80 1.40
C-4 1 PER= 0.55 2.80 1.54
C-5 3 PER= 0.50 2.60 3.90
Eje 3
C-1 3 PER= 0.80 2.60 6.24
C-1 1 PER= 0.95 2.60 2.47
C-4 1 PER= 0.55 2.80 1.54
Eje 4
C-1 2 PER= 0.75 2.60 3.90
C-1 1 PER= 0.95 2.60 2.47
Eje 5
C-1 2 PER= 0.75 2.60 3.90
C-1 1 PER= 0.95 2.60 2.47
C-4 1 PER= 0.55 2.80 1.54
Eje 6
C-2 1 PER= 1.30 2.60 3.38
C-1 1 PER= 0.95 2.60 2.47
C-5 3 PER= 0.50 2.60 3.90

02.03.05.03 COLUMNAS: ACERO FY=4200 KG/CM2 GRADO 60


2DO NIVEL 1 Peso= 944.46 944.46

02.03.04 VIGAS
02.03.04.01 VIGAS: CONCRETO F'C= 210 KG/CM2

2DO NIVEL 5.53


Eje A
VP-1 (0.4X0.25) 1 12.85 0.25 0.40 1.29
VS-2(0.20X0.25) 1 1.00 0.25 0.20 0.05
Vb (0.15X0.20) 1 0.65 0.15 0.20 0.02
Eje B
VP-1 (0.4X0.25) 1 11.82 0.25 0.40 1.18
VS-2(0.20X0.25) 1 1.00 0.25 0.20 0.05
V-1 (0.15X0.20) 1 4.45 0.15 0.20 0.13
Eje C
VP-1 (0.4X0.25) 1 3.40 0.25 0.40 0.34
Eje D
VP-1 (0.4X0.25) 1 9.92 0.25 0.40 0.99
VS-2(0.20X0.25) 1 1.00 0.25 0.20 0.05
Eje 1
VS-1 (0.3X0.2) 1 2.50 0.30 0.20 0.15
Eje 2
VS-1 (0.3X0.2) 1 6.80 0.30 0.20 0.41
Eje 3
VS-1 (0.3X0.2) 1 6.80 0.30 0.20 0.41
Vb (0.15X0.20) 1 2.45 0.15 0.20 0.07
Eje 4
VS-1 (0.3X0.2) 1 7.25 0.30 0.20 0.44
Eje 5
VS-1 (0.3X0.2) 1 7.25 0.30 0.20 0.44
Eje 7
VP-2 (0.15X0.4) 1 2.50 0.15 0.40 0.15
VP-3 (0.4X0.25) 1 4.45 0.25 0.40 0.45
Vb (0.15X0.20) 1 7.10 0.15 0.20 0.21

02.03.04.02 VIGAS: ENCOFRADO Y DESENCOFRADO

2DO NIVEL 36.04


Eje A
VP-1 (0.4X0.25) 1 12.85 PER= 0.85 10.92
VS-2(0.20X0.25) 1 1.00 PER= 0.45 0.45
Vb (0.15X0.20) 1 0.65 PER= 0.35 0.23
Eje B
VP-1 (0.4X0.25) 1 11.82 PER= 0.65 7.68
VS-2(0.20X0.25) 1 1.00 PER= 0.25 0.25
V-1 (0.15X0.20) 1 4.45 PER= 0.15 0.67
Eje C
VP-1 (0.4X0.25) 1 3.40 PER= 0.65 2.21
Eje D
VP-1 (0.4X0.25) 1 9.92 PER= 0.85 8.43
VS-2(0.20X0.25) 1 1.00 PER= 0.45 0.45
Eje 1
VS-1 (0.3X0.2) 1 2.50 0.30 0.50 0.38
Eje 2
VS-1 (0.3X0.2) 1 6.80 0.30 0.50 1.02
Eje 3
VS-1 (0.3X0.2) 1 6.80 0.30 0.30 0.61
Vb (0.15X0.20) 1 2.45 0.15 0.35 0.13
Eje 4
VS-1 (0.3X0.2) 1 7.25 0.30 0.30 0.65
Eje 5
VS-1 (0.3X0.2) 1 7.25 0.30 0.30 0.65
Eje 7
VP-2 (0.15X0.4) 1 2.50 0.15 0.55 0.21
VP-3 (0.4X0.25) 1 4.45 0.25 0.65 0.72
Vb (0.15X0.20) 1 7.10 0.15 0.35 0.37

02.03.04.03 VIGAS: ACERO FY=4200 KG/CM2 GRADO 60


2DO NIVEL 1 Peso= 1,111.76 1,111.76

02.03.04 LOSAS
02.03.04.01 LOSA ALIGERADA: CONCRETO F'C= 210 KG/CM2

2DO NIVEL F=0.0875 7.85


LOSA 1 1 AREA= 5.30 0.0875 0.46
LOSA 2 1 AREA= 6.89 0.0875 0.60
LOSA 3 1 AREA= 0.91 0.0875 0.08
LOSA 4 1 AREA= 8.16 0.0875 0.71
LOSA 5 1 AREA= 6.63 0.0875 0.58
LOSA 6 1 AREA= 5.96 0.0875 0.52
LOSA 7 1 AREA= 10.35 0.0875 0.91
LOSA 8 1 AREA= 5.43 0.0875 0.48
LOSA 9 1 AREA= 9.43 0.0875 0.83
LOSA 10 1 AREA= 9.26 0.0875 0.81
LOSA 11 1 AREA= 3.40 0.0875 0.30
LOSA 12 1 AREA= 11.73 0.0875 1.03
LOSA 13 1 AREA= 2.25 0.0875 0.20
LOSA 14 1 AREA= 1.09 0.0875 0.10
LOSA 15 1 AREA= 2.93 0.0875 0.26

LOSA ALIGERADA: DESENCOFRADO Y ENCOFRADO

2DO NIVEL 84.42


LOSA 1 1 AREA= 5.30 5.30
LOSA 2 1 AREA= 6.89 6.89
LOSA 3 1 AREA= 0.91 0.91
LOSA 4 1 AREA= 8.16 8.16
LOSA 5 1 AREA= 6.63 6.63
LOSA 6 1 AREA= 5.96 5.96
LOSA 7 1 AREA= 10.35 10.35
LOSA 8 1 AREA= 5.43 5.43
LOSA 9 1 AREA= 9.43 9.43
LOSA 10 1 AREA= 9.26 9.26
LOSA 11 1 AREA= 3.40 3.40
LOSA 12 1 AREA= 11.73 11.73
LOSA 13 1 AREA= 2.25 2.25
LOSA 14 1 AREA= 1.09 1.09
LOSA 15 1 AREA= 2.93 2.93

02.03.04.03 LOSA: ACERO FY=4200 KG/CM2 GRADO 60


SEGÚN METRADO DE ACERO
2DO NIVEL 1 Peso= 573.40 573.40

02.03.04.03 LADRILLO P/LOSA ALIGERADA E=20CM


2DO NIVEL FACTOR 747.37
LOSA 1 1 AREA= 5.30 8.33 44.15
LOSA 2 1 AREA= 6.89 8.33 57.39
LOSA 3 1 AREA= 0.91 8.33 7.58
LOSA 4 1 AREA= 8.16 8.33 67.97
LOSA 5 1 AREA= 6.63 8.33 55.23
LOSA 6 1 AREA= 5.96 8.33 49.65
LOSA 7 1 AREA= 10.35 8.33 86.22
LOSA 8 1 AREA= 5.43 8.33 45.23
LOSA 9 1 AREA= 9.43 8.33 78.55
LOSA 10 1 AREA= 9.26 8.33 77.14
LOSA 11 1 AREA= 3.40 8.33 28.32
LOSA 12 1 AREA= 11.73 8.33 97.71
LOSA 13 1 AREA= 2.25 8.33 18.74
LOSA 14 1 AREA= 1.09 8.33 9.08
LOSA 15 1 AREA= 2.93 8.33 24.41

02.03.04 ESCALERA
02.03.04.01 ESCALERA: CONCRETO F'C= 210 KG/CM2
1ER NIVEL 2.67
TRAMO 1 1 1.03 VOL= 0.85 0.87
TRAMO 2 1 0.95 VOL= 0.82 0.78
TRAMO 2 1 1.02 VOL= 0.95 0.97
re RELLENO DE CONCRETO 1 AREA= 0.32 0.17 0.05

02.03.04.01 ESCALERA: ENCOFRADO Y DESENCOFRADO


1ER NIVEL 12.58
TRAMO 1
CUELLO 1 PER= 2.07 1.03 2.13
LATERALES 2 AREA= 0.58 1.15
CONTRAPASOS 1 PER= 0.88 1.03 0.90
TRAMO 2
CUELLO 1 PER= 2.02 0.95 1.92
LATERALES 2 AREA= 0.58 1.17
CONTRAPASOS 1 PER= 0.68 0.95 0.65
TRAMO 3
CUELLO 1 PER= 2.63 1.02 2.68
LATERALES 2 AREA= 0.51 1.01
CONTRAPASOS 1 PER= 1.02 0.95 0.97
02.03.04.03 ESCALERA: ACERO FY=4200 KG/CM2 GRADO 60
1ER NIVEL 1 Peso= 279.30 279.30

3 ARQUITECTURA
MUROS Y TABIQUES
MURO DE LADRILLO DE SOGA C/MEZCLA 1:4 C/LADRILLO KK 0.00
2DO NIVEL

REVOQUES Y REVESTIMIENTOS
TARRAJEO EN INTERIORES Y EXTERIORES
1ER NIVEL 9.36
EJE B 2 1.80 2.60 9.36

TARRAJEO EN COLUMNAS
1ER NIVEL 17.58
EJE A
C-1 3 PER= 0.90 3.90 10.53
C-2 1 PER= 0.90 3.90 3.51
C-A 2 PER= 0.60 2.95 3.54

TARRAJEO DE VIGAS 42.06


1ER NIVEL
Eje A
VCH-1 (0.3X0.2) 1 0.95 PER= 0.35 0.33
VP-2(0.15X0.4) 1 2.65 PER= 0.95 2.52
Eje B
VP-3 (0.3X0.6) 1 4.73 PER= 1.10 5.20
VP-3 (0.3X0.6) 1 1.50 PER= 1.30 1.95
VP-1 (0.3X0.3) 1 2.45 PER= 0.70 1.72
VCH-1 (0.3X0.2) 1 6.15 PER= 0.50 3.08
VCH-1 (0.3X0.2) 1 2.35 PER= 0.30 0.71
Vb (0.15X0.20) 1 3.80 PER= 0.35 1.33
Eje C
VCH-1 (0.3X0.2) 1 7.58 PER= 0.50 3.79
VCH-1 (0.3X0.2) 1 1.50 PER= 0.70 1.05
VP-2(0.15X0.4) 1 1.85 PER= 0.95 1.76
VP-2(0.15X0.4) 1 1.35 PER= 0.75 1.01
Eje 1
VCH-1 (0.3X0.2) 1 4.15 PER= 0.30 1.25
VP-2(0.15X0.4) 1 2.05 PER= 0.95 1.95
VP-2(0.15X0.4) 1 0.90 PER= 0.75 0.68
Vb (0.15X0.20) 1 5.55 PER= 0.35 1.94
Eje 2
VCH-1 (0.3X0.2) 1 5.31 PER= 0.30 1.59
VCH-1 (0.3X0.2) 1 3.15 PER= 0.50 1.58
Eje 5
VCH-1 (0.3X0.2) 1 6.10 PER= 0.50 3.05
VCH-1 (0.3X0.2) 1 1.15 PER= 0.30 0.35
Eje 6
VCH-1 (0.3X0.2) 1 3.00 PER= 0.70 2.10
VCH-1 (0.3X0.2) 1 1.65 PER= 0.50 0.83
Eje 7
VCH-1 (0.3X0.2) 1 4.65 PER= 0.50 2.33

CIELO RASO CON MEZCLA 1:5 CEMENTO-ARENA 37.64


1ER NIVEL
LOSA 1 1 AREA= 1.11 1.11
LOSA 2 1 AREA= 13.20 13.20
LOSA 3 1 AREA= 2.80 2.80
LOSA 4 1 AREA= 0.81 0.81
LOSA 5 1 AREA= 2.85 2.85
LOSA 6 1 AREA= 0.89 0.89
LOSA 7 1 AREA= 3.31 3.31
LOSA 8 1 AREA= 10.99 10.99
LOSA 9 1 AREA= 1.68 1.68

TARRAJEO EN FONDO DE ESCALERA 3.87


ESCALERA PRIMER NIVEL 1 3.76 1.03 3.87

TARRAJEO DE GRADAS DE CONCRETO 6.72


ESCALERA PRIMER NIVEL 16 1.00 PERIMETRO = 0.42 6.72
TARRAJEO DE DESCANSO DE ESCALERAS DE CONCRETO 3.84
ESCALERA PRIMER NIVEL 2 AREA= 1.92 3.84

4 INSTALACIONES SANITARIAS
EXCAVACION MANUAL PARA ZANJAS
Red de desague 4" 1 15.04 15.04

CAMA DE APOYO E=0.10 M.


desague p/tuberia 4" 1 15.04 15.04

RELLENO COMPACTADO CON MATERIAL PROPIO C/EQUIPO LIVIANO


desague p/tuberia 4" 1 15.04 15.04

ACARREO DE MATERIAL EXCEDENTE HASTA 30M F=1.3


1 0.75 0.98 0.98

ELIMINACION DE MATERIAL EXCEDENTE C/VOLQUETE DE 15m3


1 vol= 0.98 0.98

SISTEMA DE DESAGUE
SALIDA DE PVC SAL PARA DESAGUE 4"
1.00 3.00 3.00
SUMINISTRO E INSTALACION TUBERIA PVC SAL 4"
1.00 23.44 23.44
SUMINISTRO E INSTALACION CODO PVC SAL 4"X90º
1 3.00 3.00
04.01 SISTEMA DE AGUA FRIA
04.01.01 SALIDA DE AGUA FRIA C/TUB. DE PVC-RIGIDO 1"
PRIMER NIVEL 1 1.00 1.00

04.01.01 SALIDA DE AGUA FRIA C/TUB. DE PVC-RIGIDO 1 1/2"


PRIMER NIVEL 1 1.00 1.00

SALIDA DE AGUA FRIA C/TUB. DE PVC-RIGIDO 1/2"


PRIMER NIVEL 1 1.00 1.00

04.01.05 SUMINISTRO Y INSTALACION TUBERIA PVC RIDIGO-CLASE 10/AGUA POTABLE DE 1 1/2"


PRIMER NIVEL 1 13.28 13.28

04.01.05 SUMINISTRO Y INSTALACION TUBERIA PVC RIDIGO-CLASE 10/AGUA POTABLE DE 1"


PRIMER NIVEL 1 3.49 3.49

SUMINISTRO Y INSTALACION TUBERIA PVC RIDIGO-CLASE 10/AGUA POTABLE DE 1"


PRIMER NIVEL 1 1.50 1.50

04.01.06 SUMINISTRO E INSTALACION CODO PVC SAP 1/2"X90°


PRIMER NIVEL 1 2.00 2.00

04.01.09 SUMINISTRO E INSTALACION TEE PVC SAP 1/2" "X90°


PRIMER NIVEL 1 1.00 1.00

SUMINISTRO E INSTALACION CODO PVC SAP 1 1/2"X90°


PRIMER NIVEL 1 6.00 6.00

SUMINISTRO E INSTALACION CODO PVC SAP 1"X90°


PRIMER NIVEL 1 2.00 2.00

SUMINISTRO E INSTALACION DE REDUCCION 1" a 1/2"


PRIMER NIVEL 1 1.00 1.00

PRUEBA HIDRAULICA
PRIMER NIVEL 1 1.00 1.00

5 INSTALACIONES ELECTRICAS
PRIMER NIVEL
SALIDA PARA LUMINARIA C/LAMP 22W ADOSABLE EN TECHO 1 3.00
SALIDA PARA LUMINARIA C/LAMP 22W ADOSABLE EN MURO 1 1.00
SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE C/T PROTECC. A TIERRA
1 0.00
0.40M
SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE C/T PROTECC. A TIERRA
1 0.00
1.10M
SALIDA PARA INTERRUPTOR UNIPOLAR 1 2.00
SALIDA PARA INTERRUPTOR UNIPOLAR DOBLE O TRIPLE 1 1.00
SALIDA PARA INTERRUPTOR DE TRES VIAS 1 2.00
SALIDA PARA LAMPARA INCANDESCENTE, TIPO SPOT LIGHT 1 1.00
RED DE DISTRIBUCION TUBERIA HFT DE 3/4" DE LUZ 1 36.35
RED DE DISTRIBUCION TUBERIA HFT DE 3/4" DE TOMACORRIENTE 1 0.00
COLOCACION DE ACCESORIOS 1 1.00
UND

glb
m

m2
m2
glb

m2

m2
m2

m2
m2
m2

m2

m2

m2

m2
m2

m2
m2
m2
m2

m2

m3

m2

m3

m3

m3
m3

m3

m3

m3

m3
m3

m2

m3

m3

m2

m2

m2
m2
m2
m3

kg

m3

m2

kg

m3

m2
kg

m3
m2
kg

m3
m2

kg

und
m3

m2
kg

m2

m2

m2

m2
m2

m2

m2
m2

ml

ml

ml

m3

m3

pto

und

PTO

PTO

PTO
ML

ML

ML

UND

UND

UND

UND

UND

GLB

pto
pto
pto
pto
pto
pto
pto
pto
m
m
glb
N° de N° de
ITEM DESCRIPCION Ø elem. pzas x
iguals elem.

02.03.01.01 ZAPATAS : ACERO FY=4200 KG/CM2 GRADO 60


EJE A
Z-1
Acero horizontal 5/8" 1 4
Acero vertical 5/8" 1 4
Z-2
Acero horizontal 5/8" 3 4
Acero vertical 5/8" 3 6

02.03.05.03 PLACAS: ACERO FY=4200 KG/CM2 GRADO 60


2DO NIVEL
P-1
Acero longitudinal 1/2" 2 20
Estribos extremos 6mm 2 20
Estribos medios 6mm 2 1.2
Estribos extremos 6mm 2 20
Estribos medios 6mm 2 1.2
P-2
Acero longitudinal 1/2" 1 20
Estribos extremos 6mm 1 20
Estribos medios 6mm 1 1.2
Estribos extremos 6mm 1 20
Estribos medios 6mm 1 1.2

02.03.05.03 COLUMNAS: ACERO FY=4200 KG/CM2 GRADO 60


2DO NIVEL
C-1
Acero longitudinal 5/8" 15 6
Estribos extremos 3/8" 15 10
Estribos medios 3/8" 15 5.2
C-2
Acero longitudinal 5/8" 3 7
Acero longitudinal 1/2" 3 4
Estribos extremos 3/8" 3 10
Estribos medios 3/8" 3 5.2
Estribos extremos 3/8" 3 10
Estribos medios 3/8" 3 5.2
C-4
Acero longitudinal 3/8" 5 4
Estribos extremos 6mm 5 16
Estribos medios 6mm 5 4
C-5
Acero longitudinal 1/2" 7 4
Estribos extremos 6mm 7 16
Estribos medios 6mm 7 4

02.03.06.03 VIGAS: ACERO FY=4200 KG/CM2 GRADO 60

2DO NIVEL
Eje A
VP-1 (0.25X0.4)
Longitudinal 5/8" 1 4
Longitudinal 1/2" 1 2
Estribos extremos 3/8" 1 60
Estribos medios 3/8" 1 32
VS-2(0.20X0.25)
Longitudinal 1/2" 1 6
Estribos extremos 6mm 1 8
Vb (0.15X0.20)
Longitudinal 3/8" 1 4
Estribos extremos 6mm 1 6
Eje B
VP-1 (0.25X0.4)
Longitudinal 5/8" 1 4
Longitudinal 1/2" 1 2
Estribos extremos 3/8" 1 60
Estribos medios 3/8" 1 27
VS-2(0.20X0.25)
Longitudinal 1/2" 1 6
Estribos extremos 6mm 1 8
V-1(0.15X0.2)
Longitudinal 1/2" 1 4
Estribos extremos 6mm 1 24
Estribos medios 6mm 1 2
Eje C
VP-1 (0.25X0.4)
Longitudinal 5/8" 1 4
Longitudinal 1/2" 1 2
Estribos extremos 3/8" 1 12
Estribos medios 3/8" 1 16
Eje D
VP-1 (0.25X0.4)
Longitudinal 5/8" 1 4
Longitudinal 1/2" 1 2
Estribos extremos 3/8" 1 48
Estribos medios 3/8" 1 24
VS-2(0.20X0.25)
Longitudinal 1/2" 1 6
Estribos extremos 6mm 1 8
Eje 1
VS-1 (0.3X0.2)
Longitudinal 1/2" 1 6
Estribos extremos 6mm 1 12
Estribos medios 6mm 1 6
Eje 2
VS-1 (0.3X0.2)
Longitudinal 1/2" 1 6
Estribos extremos 6mm 1 36
Estribos medios 6mm 1 15
Eje 3
VS-1 (0.3X0.2)
Longitudinal 1/2" 1 6
Estribos extremos 6mm 1 36
Estribos medios 6mm 1 15
Vb (0.15X0.20)
Longitudinal 3/8" 1 4
Estribos extremos 6mm 1 24
Eje 4
VS-1 (0.3X0.2)
Longitudinal 1/2" 1 6
Estribos extremos 6mm 1 24
Estribos medios 6mm 1 23
Eje 5
VS-1 (0.3X0.2)
Longitudinal 1/2" 1 6
Estribos extremos 6mm 1 24
Estribos medios 6mm 1 23
Eje 7
VP-2 (0.3X0.2)
Longitudinal 1/2" 1 4
Estribos extremos 6mm 1 12
Estribos medios 6mm 1 6
VP-3 (0.4X0.25)
Longitudinal 1/2" 1 6
Estribos extremos 6mm 1 22
Estribos medios 6mm 1 11
Vb (0.15X0.20)
Longitudinal 3/8" 1 4
Estribos extremos 6mm 1 36
Estribos medios 6mm 1 16

LOSA ALIGERADA: FY=4200 KG/CM2 GRADO 60


1ER NIVEL
PAÑO 1
Acero positivo 1/2" 1 5.00
Acero negativo 1/2" 1 5.00
Acero temperatura 6mm 1 10.6
PAÑO 2
Acero positivo 1/2" 1 6.5
Acero positivo 1/2" 1 6.5
Acero negativo 1/2" 1 6.5
Acero temperatura 6mm 1 28
PAÑO 3
Acero positivo 1/2" 1 2
Acero positivo 1/2" 1 2
Acero negativo 1/2" 1 2
Acero temperatura 6mm 1 23
PAÑO 4
Acero positivo 1/2" 1 5.6
Acero negativo 1/2" 1 5.6
Acero negativo 1/2" 1 5.6
Acero temperatura 6mm 1 29
PAÑO 5
Acero positivo 1/2" 1 5.1
Acero negativo 1/2" 1 5.1
Acero negativo 1/2" 1 5.1
Acero temperatura 6mm 1 29
PAÑO 6
Acero positivo 1/2" 1 8.8
Acero negativo 1/2" 1 8.8
Acero negativo 1/2" 1 8.8
Acero temperatura 6mm 1 29
PAÑO 7
Acero positivo 1/2" 1 2.1
Acero negativo 1/2" 1 2.1
Acero negativo 1/2" 1 2.1
Acero temperatura 6mm 1 29
PESO DEL ACERO TOTA
02.03.01.01 ZAPATAS : ACERO FY=4200 KG/CM2 GRADO 60
02.03.05.03 COLUMNAS: ACERO FY=4200 KG/CM2 GRADO 60
02.03.06.03 VIGAS: ACERO FY=4200 KG/CM2 GRADO 60
#REF! #REF!
Long.
Por
pieza

1
1

1.5
1

2.80
3.34
3.34
2.9
2.9

2.80
3.8
3.8
2.9
2.9

2.80
1.1
1.1

2.80
2.80
1.3
1.3
1.3
1.3

2.80
0.7
0.7
2.80
0.8
0.8

15.85
15.85
1.30
1.30

1.70
0.90

1.40
0.70

15.85
15.85
1.30
1.30

1.70
0.90

3.85
1.10
1.10

5.25
4.30
1.30
1.30

13.55
13.55
1.30
1.30

1.70
0.90

3.45
1.00
1.00

8.30
1.00
1.00

8.30
1.00
1.00

3.45
0.70

8.30
1.00
1.00

8.30
1.00
1.00

3.45
1.00
1.00

3.45
1.00
1.00

8.30
0.70
0.70

3.15
2
2.3

8
3.7
2
2.9
6.65
4.2
1
0.8

8
2.3
3
2.55

8
2.3
3
2.35

8
3.3
3
3.95

8
3.3
3
1
PESO DEL ACERO TOTAL
Longitud (m) por Ø
Peso
6mm 8mm 3/8" 1/2" 5/8" 3/4" 1"
0.24 0.40 0.56 0.99 1.55 2.24 3.97 kg

73.66

- - - - 4.0 - - 6.70
- - - - 4.0 - - 6.70

- - - - 18.0 - - 30.13
- - - - 18.0 - - 30.13

-
285.02
- -
- - - 112.0 - - - 119.75
133.6 - - - - - - 34.63
8.0 - - - - - - 2.08
116.0 - - - - - - 30.07
7.0 - - - - - - 1.80
- -
- - - 56.0 - - - 59.88
76.0 - - - - - - 19.70
4.6 - - - - - - 1.18
58.0 - - - - - - 15.03
3.5 - - - - - - 0.90

-
944.46
- -
- - - - 252.0 - - 421.85
- - 165.0 - - - - 99.79
- - 85.8 - - - - 51.89
- -
- - - - 58.8 - - 98.43
- - - 33.6 - - - 35.93
- - 39.0 - - - - 23.59
- - 20.3 - - - - 12.27
- - 39.0 - - - - 23.59
- - 20.3 - - - - 12.27
- -
- - 56.0 - - - - 33.87
56.0 - - - - - - 14.52
14.0 - - - - - - 3.63
- -
- - - 78.4 - - - 83.83
89.6 - - - - - - 23.22
22.4 - - - - - - 5.81

1,111.76

- - - - 63.4 - - 106.13
- - - 31.7 - - - 33.89
- - 78.0 - - - - 47.17
- - 41.3 - - - - 24.96
- -
- - - 10.2 - - - 10.91
7.2 - - - - - - 1.87
- -
- - 5.6 - - - - 3.39
4.2 - - - - - - 1.09

- - - - 63.4 - - 106.13
- - - 31.7 - - - 33.89
- - 78.0 - - - - 47.17
- - 34.6 - - - - 20.91
- -
- - - 10.2 - - - 10.91
7.2 - - - - - - 1.87
- -
- - - 15.4 - - - 16.47
26.4 - - - - - - 6.84
1.9 - - - - - - 0.50

- - - - 21.0 - - 35.15
- - - 8.6 - - - 9.20
- - 15.6 - - - - 9.43
- - 20.5 - - - - 12.38

- - - - 54.2 - - 90.73
- - - 27.1 - - - 28.98
- - 62.4 - - - - 37.74
- - 30.7 - - - - 18.56
- -
- - - 10.2 - - - 10.91
7.2 - - - - - - 1.87

- -
- - - 20.7 - - - 22.13
12.0 - - - - - - 3.11
6.0 - - - - - - 1.56

- -
- - - 49.8 - - - 53.25
36.0 - - - - - - 9.33
14.5 - - - - - - 3.76

- -
- - - 49.8 - - - 53.25
36.0 - - - - - - 9.33
14.5 - - - - - - 3.76
- -
- - 13.8 - - - - 8.35
16.8 - - - - - - 4.35

- -
- - - 49.8 - - - 53.25
24.0 - - - - - - 6.22
23.3 - - - - - - 6.03

- -
- - - 49.8 - - - 53.25
24.0 - - - - - - 6.22
23.3 - - - - - - 6.03

- -
- - - 13.8 - - - 14.75
12.0 - - - - - - 3.11
6.0 - - - - - - 1.56
- -
- - - 20.7 - - - 22.13
22.0 - - - - - - 5.70
10.8 - - - - - - 2.79
- -
- - 33.2 - - - - 20.08
25.2 - - - - - - 6.53
11.2 - - - - - - 2.90

-
- 573.40
-
- - - 15.8 - - - 16.84
- - - 10.0 - - - 10.69
24.4 - - - - - - 6.32

- - - 52.0 - - - 55.60
- - - 24.1 - - - 25.71
- - - 13.0 - - - 13.90
81.2 - - - - - - 21.05
- - - 13.3 - - - 14.22
- - - 8.4 - - - 8.98
- - - 2.0 - - - 2.14
18.4 - - - - - - 4.77
- -
- - - 45.0 - - - 48.11
- - - 12.9 - - - 13.83
- - - 16.9 - - - 18.04
74.0 - - - - - - 19.17
- -
- - - 41.0 - - - 43.84
- - - 11.8 - - - 12.60
- - - 15.4 - - - 16.44
68.2 - - - - - - 17.66
- -
- - - 70.0 - - - 74.84
- - - 28.9 - - - 30.87
- - - 26.3 - - - 28.07
114.6 - - - - - - 29.69
- -
- - - 17.0 - - - 18.18
- - - 7.0 - - - 7.50
- - - 6.4 - - - 6.82
29.0 - - - - - - 7.52
EL ACERO TOTAL
73.66
#REF!
-
#REF!
#REF!
4.15 20.75

5.28
EX IN
1 12 3
2 12 10.5
3 12 4.75
4 12 3.75
5 12 9.75
60 31.75
91.75