ITEM DESCRIPCION UND METRADO PU PARCIAL

01 OBRAS PROVISIONALES 13,045.14

01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 m X 2.40 m und 1.00 826.14 826.14
01.02 CONSTRUCCION DE CAMPAMENTO PROVISIONAL DE OBRA m2 100.00 64.19 6,419.00
01.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 5800.00 5,800.00
TRABAJOS PRELIMINARES 8,573.95
02.01 TRAZO Y REPLANTEO DURANTE LA EJECUCION km 6.37 944.39 6,015.76
02.02 RAYADO DE TALUDES km 6.37 401.60 2,558.19
MOVIMIENTO DE TIERRAS 281,318.46
03.01 CORTE DE MATERIAL COMPACTO A NIVEL DE SUB RASANTE m3 45945.59 3.74 171,836.51
03.02 CORTE ROCA SUELTA (PERFORACION Y DISPARO) m3 1431.95 18.87 27,020.90
03.03 CORTE DE ROCA FIJA (PERFORACION Y DISPARO) m3 1741.90 22.41 39,035.98
03.04 RELLENO CON MATERIAL PROPIO m3 2545.15 7.81 19,877.62
03.05 DESQUINCHE Y PEINADO DE TALUDES EM ZONAS ROCOSAS m2 750.00 3.43 2,572.50
03.06 PEINADO DE TALUDES m2 19421.25 1.08 20,974.95
AFRIMADO E=0.15 m. 201,624.68
4.01 EXTRACCION Y PREPARADO DE MATERIAL SELECCIONADO m3 4776.86 3.75 17,913.23
4.02 PERFILADO Y COMPACTADO A NIVEL SUBRASANTE m2 25476.56 1.62 41,272.03
4.03 CARGUIO Y TRANSPORTE DE MATERIAL SELECCIONADO m3 3821.48 6.54 24,992.48
4.04 EXTENDIDO, RIEGO Y COMPACTADO DEL MATERIAL AFIRMADO e=15 cm m2 25476.56 4.61 117,446.94
OBRAS DE ARTE Y DRENAJE
02 CUNETAS 36,889.73
05.01.01 EXCAVACION DE ZANJAS EN TERRENO COMPACTO m3 1289.75 18.38 23,705.61
05.01.02 PERFILADO Y COMPACTADO DE CUNETAS m 6369.14 2.07 13,184.12
03 ALCANTARILLA DE TMC ø 36" 05 UND 30,768.89
05.02.01 TRAZO NIVEL Y REPLANTEO m2 119.40 2.20 262.68
05.02.02 EXCAVACION DE ZANJAS EN TERRENO COMPACTO m3 62.05 18.38 1,140.48
05.02.03 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 92.23 68.02 6,273.48
05.02.04 CONCRETO SIMPLE f'c=140 kg/cm2 + 70% P.G. m3 17.46 166.11 2,900.28
05.02.05 CONCRETO SIMPLE f'c=175 kg/cm2 + 30% P.M. m3 24.22 194.53 4,711.52
05.02.06 CONCRETO SIMPLE f'c=175 kg/cm2 m3 10.50 322.90 3,390.45
05.02.07 ALCANTARILLA DE TMC ø 36" m 24.00 503.75 12,090.00
04 BADENES (03 UNDS) 27,205.35
05.03.01 TRAZO Y REPLANTEO m2 176.28 2.20 387.82
05.03.02 EXCAVACION EN TERRENO COMPACTO m3 97.70 18.38 1,795.73
05.03.03 ENCOFRADO Y DESENCOFRADO m2 87.95 33.75 2,968.31
05.03.04 CONCRETO SIMPLE f'c=210 kg/cm2 m3 34.60 352.43 12,194.08
05.03.05 CONCRETO SIMPLE f'c=175 kg/cm2 + 30% P.M. m3 27.47 194.53 5,343.74
05.03.06 MAMPOSTERIA DE CONCRETO f'c=140 kg/cm2 + 60% P.M. m2 9.09 194.33 1,766.46
05.03.07 ENROCADO DE PIEDRAS m3 25.10 91.19 2,288.87
05.03.08 JUNTA ASFALTICA e=1" m 108.06 4.26 460.34
05 CONTROL DE CALIDAD 3,370.00
6.01 ENSAYO DE VALOR RELATIVO DE SOPORTE (C.B.R) und 2.00 590.00 1,180.00
6.02 PRUEBA DE COMPACTACION (DENSIDAD DE CAMPO) und 8.00 35.00 280.00
6.03 DEISEÑO DE MESCLAS und 3.00 450.00 1,350.00
6.04 ROTURA DE BRIQUETAS und 16.00 35.00 560.00
05 SEÑALIZACION 4,471.22
7.01 HITOS KILOMETRICOS und 8.00 161.33 1,290.64
7.02 SEÑAL INFORMATIVA und 2.00 916.65 1,833.30
7.03 SEÑAL PREVENTIVA und 2.00 673.64 1,347.28
05 EQUIPOS DE PROTECCION PERSONAL (E.P.P.) 3,000.00
8.01 EQUIPOS DE PROTECCION PERSONAL glb 1.00 3000.00 3,000.00
05 PLACA RECORDATORIA 450.00
9.01 PLACA RECORDATORIA und 1.00 450.00 450.00
05 FLETE TERRESTRE 6,986.30
10.01 TRANSPORTE DE MATERIALES A LA OBRA glb 1.00 6986.30 6,986.30
11 CAPACITACION VIAL Y GESTION 5,000.00
11.01 CAPACITACION EN EDUCACION VIAL und 1.00 5000.00 5,000.00
05 MITIGACION AMBIENTAL 6,244.94
12.01 REFORESTACION m2 11782.91 0.53 6,244.94
05 PLAN DE MONITOREO 10,500.00
13.01 PLAN DE MONITOREO ARQUEOLOGICO mes 3.00 3500.00 10,500.00
COSTO DIRECTO S/. 639,448.66
GASTOS GENERALES 11.28% S/. 72,102.13
GASTOS DE LIQUIDACION 1.58% S/. 10,084.09
GASTOS DE EXPEDIENTE TECNICO 2.35% S/. 15,000.00
GASTOS DE SUPERVICION 3.98% S/. 25,475.01

TOTAL PRESUPUESTO S/. 762,109.89


FORMATO F-4A

VALORIZACION DE OBRA CORRESPONDIENTE AL MES D


PERIODO: AÑO FISCAL 2019
PERIODO REPROGRAMADO:
ENTIDAD : MUNICIPALIDAD DISTRITAL DE MARANGANI
MEJORAMIENTO DEL SERVICIO DEPORTIVO Y RECREATIVO EN LA COMUNIDAD DE MAM
PROVINCIA DE CANCHIS - DEPARTAMENTO DE CUSC
RESIDENTE : ARQ. JULIO CESAR CHURATA CRUZ
INSPECTOR :ING. CESAR JULIAN COILA VILCA

PRESUPUESTO ANTERIOR ACUMULADO


Item DESCRIPCION
Und Precio Metrado Parcial Metrado Parcial %

01 OBRAS PROVISIONALES 56,772.33 0.00 0.00%


01.01 ALQUILER DE ALMACEN, OFICINA Y GUARDIANÍA mes 150.00 4.00 600.00 0.00 0.00%
01.02 CARTEL DE IDENTIFICACION DE LA OBRA und 679.37 1.00 679.37 0.00 0.00%
01.03 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 587.50 1.00 587.50 0.00 0.00%
01.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQU glb 350.00 1.00 350.00 0.00 0.00%
01 OBRAS PRELIMINARES 0.00 #DIV/0!
02.01 TRAZO, NIVELES Y REPLANTEO DURANTE LA OBRA m2 1.27 867.12 1,101.24 0.00 0.00%
02.02 LIMPIEZA DEL TERRENO MANUAL m2 1.00 116.80 116.80 0.00 0.00%
01 SEGURIDAD Y SALUD 0.00 #DIV/0!
03.01 EQUIPOS DE PROTECCION INDIVIDUAL glb 3,839.40 1.00 3,839.40 0.00 0.00%
03.02 EQUIPO DE PROTECCION COLECTIVA glb 887.50 1.00 887.50 0.00 0.00%
01 MOVIMIENTO DE TIERRAS 0.00 #DIV/0!
04.01 CONFORMACIÓN DE SUPERFICIE PARA GRASS SINTÉTICO m2 6.51 116.80 760.37 0.00 0.00%
04.02 EXCAVACION EN TERRENO NORMAL PARA SARDINELES m3 14.78 8.97 132.58 0.00 0.00%
04.03 EXCAVACION DE ZANJAS PARA ZAPATAS DE LA COBERTUR m3 14.78 69.08 1,021.00 0.00 0.00%
04.04 RELLENO CON MATERIAL PROPIO m3 20.86 32.94 687.13 0.00 0.00%
04.05 REFINE, NIVELACION Y COMPACTACION m2 4.69 36.60 171.65 0.00 0.00%
04.06 ACARREO MANUAL DE MATERIAL EXCEDENTE m3 4.92 48.82 240.19 0.00 0.00%
04.07 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m m3 3.70 48.82 180.63 0.00 0.00%
FORMATO F-4A

VALORIZACION DE OBRA CORRESPONDIENTE AL MES D


PERIODO: AÑO FISCAL 2019
PERIODO REPROGRAMADO:
ENTIDAD : MUNICIPALIDAD DISTRITAL DE MARANGANI
MEJORAMIENTO DEL SERVICIO DEPORTIVO Y RECREATIVO EN LA COMUNIDAD DE MAM
PROVINCIA DE CANCHIS - DEPARTAMENTO DE CUSC
RESIDENTE : ARQ. JULIO CESAR CHURATA CRUZ
INSPECTOR :ING. CESAR JULIAN COILA VILCA

PRESUPUESTO ANTERIOR ACUMULADO


Item DESCRIPCION
Und Precio Metrado Parcial Metrado Parcial %
01 CONCRETO SIMPLE 0.00 #DIV/0!
05.01 SOLADOS 0.00 #DIV/0!
05.01.01 CONCRETO SOLADO f'c=140 kg/cm2 E=5cm m2 23.95 51.98 1,244.92 0.00 0.00%
05.02 SARDINELES 0.00 #DIV/0!
05.02.01 ENCOFRADO Y DESENCOFRADO DE SARDINEL m2 18.83 22.44 422.55 0.00 0.00%
05.02.02 CONCRETO EN SARDINELf'c=175 kg/cm2 m3 395.25 8.97 3,545.39 0.00 0.00%
05.02.03 TARRAJEO EN SARDINELES CON CEMENTO-ARENA e=1. m2 15.09 33.66 507.93 0.00 0.00%
05.02.04 JUNTAS ASFALTICAS m 9.83 50.05 491.99 0.00 0.00%
01 CONCRETO ARMADO 0.00 #DIV/0!
06.01 GRADERIAS DE CONCRETO EN LOSA MULTIDEPORTIVA 0.00 #DIV/0!
06.01.01 CORTE DE CONCRETO EN GRADERIAS m 1.48 10.45 15.47 0.00 0.00%
06.01.02 ENCOFRADO Y DESENCOFRADO DE GRADERIAS m2 18.18 0.33 6.00 0.00 0.00%
06.01.03 CONCRETO PARA BASE DE BARANDAS f'c=175 kg/cm2 m3 357.76 0.05 17.89 0.00 0.00%
06.01.04 TARRAJEO Y ACABADO, GRADERIAS 1:5 e=1.5cm m2 16.60 0.58 9.63 0.00 0.00%
06.01.05 PINTURA LATEX-ACRILICA EN GRADERIAS 2 MANOS (Inclu m2 5.11 180.79 923.84 0.00 0.00%
06.02 ZAPATAS 0.00 #DIV/0!
06.02.01 CONCRETO F'C=210 Kg/cm², EN ZAPATAS m3 385.69 22.50 8,678.03 0.00 0.00%
06.02.02 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 4.32 1,078.33 4,658.39 0.00 0.00%
06.02.03 CORTE DE LOSA DE CONCRETO CON DISCO e=0.20 m. m 1.48 43.84 64.88 0.00 0.00%
06.03 PEDESTALES 0.00 #DIV/0!
FORMATO F-4A

VALORIZACION DE OBRA CORRESPONDIENTE AL MES D


PERIODO: AÑO FISCAL 2019
PERIODO REPROGRAMADO:
ENTIDAD : MUNICIPALIDAD DISTRITAL DE MARANGANI
MEJORAMIENTO DEL SERVICIO DEPORTIVO Y RECREATIVO EN LA COMUNIDAD DE MAM
PROVINCIA DE CANCHIS - DEPARTAMENTO DE CUSC
RESIDENTE : ARQ. JULIO CESAR CHURATA CRUZ
INSPECTOR :ING. CESAR JULIAN COILA VILCA

PRESUPUESTO ANTERIOR ACUMULADO


Item DESCRIPCION
Und Precio Metrado Parcial Metrado Parcial %
06.03.01 CONCRETO F'C=210 Kg/cm², EN PEDESTALES m3 430.56 6.08 2,617.80 0.00 0.00%
06.04 COLUMNAS 0.00 #DIV/0!
06.04.01 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 31.86 46.80 1,491.05 0.00 0.00%
06.04.02 CONCRETO F'C=210 Kg/cm², EN COLUMNA m3 422.56 7.56 3,194.55 0.00 0.00%
06.04.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 4.32 1,208.10 5,218.99 0.00 0.00%
06.05 REPOSICION DE VEREDA 0.00 #DIV/0!
06.05.01 CONCRETO PARA VEREDA f'c=175 kg/cm2 m3 357.76 0.86 307.67 0.00 0.00%
06.06 ANCLAJE A PEDESTAL 0.00 #DIV/0!
06.06.01 ANCLAJE PARA PEDESTAL A COLUMNAS METALICAS und 600.00 20.00 12,000.00 0.00 0.00%
02 ESTRUCTURAS METALICAS Y COBERTURA 190,522.24 0.00 0.00%
07.01 COLUMNAS METALICAS
07.01.01 COLUMNA METÁLICA 150x250x6mm m 199.48 120.00 23,937.60 0.00 0.00%
07.01.02 COLUMNA METÁLICA 150x150x4mm m 100.61 67.08 6,748.92 0.00 0.00%
07.01.03 COLUMNA METÁLICA 100x100x3mm m 42.49 6.40 271.94 0.00 0.00%
07.02 VIGAS METALICAS 0.00 #DIV/0!
07.02.01 VIGA METÁLICA DE 100x150x3mm m 47.54 237.24 11,278.39 0.00 0.00%
07.02.02 VIGA METÁLICA DE 100x100x3mm m 42.49 115.00 4,886.35 0.00 0.00%
07.02.03 VIGA METÁLICA DE 75x75x3mm m 41.10 152.28 6,258.71 0.00 0.00%
07.03 ARCO TIPO I 0.00 0.00 #DIV/0!
07.03.01 ARCO TIPO I und 2,928.85 2.00 5,857.70 0.00 0.00%
FORMATO F-4A

VALORIZACION DE OBRA CORRESPONDIENTE AL MES D


PERIODO: AÑO FISCAL 2019
PERIODO REPROGRAMADO:
ENTIDAD : MUNICIPALIDAD DISTRITAL DE MARANGANI
MEJORAMIENTO DEL SERVICIO DEPORTIVO Y RECREATIVO EN LA COMUNIDAD DE MAM
PROVINCIA DE CANCHIS - DEPARTAMENTO DE CUSC
RESIDENTE : ARQ. JULIO CESAR CHURATA CRUZ
INSPECTOR :ING. CESAR JULIAN COILA VILCA

PRESUPUESTO ANTERIOR ACUMULADO


Item DESCRIPCION
Und Precio Metrado Parcial Metrado Parcial %
07.04 ARCO TIPO II 0.00 #DIV/0!
07.04.01 ARCO TIPO II und 4,035.57 8.00 32,284.56 0.00 0.00%
07.05 TENSORES 0.00 #DIV/0!
07.05.01 TENSORES BARRA LISA DE 1/2" m 9.90 653.95 6,474.11 0.00 0.00%
07.06 CORREAS METALICAS 0.00 #DIV/0!
07.06.01 CORREAS METALICAS m 23.19 1,121.00 25,995.99 0.00 0.00%
07.07 COBERTURAS 0.00 #DIV/0!
07.07.01 COBERTURA CON ALUZINC e=0.4mm Y POLICARBONATO m2 36.59 962.74 35,226.66 0.00 0.00%
07.07.02 COBERTURA LATERAL CON ALUZINC e=0.4mm m2 33.76 153.84 5,193.64 0.00 0.00%
07.07.03 MALLA GALVANIZADA LATERAL m2 28.26 522.38 14,762.46 0.00 0.00%
07.08 SEGURIDAD EN GRADERIAS 0.00 #DIV/0!
07.08.01 BARANDA METÁLICA DE PROTECCIÓN EN LAS GRADERI m 2,545.22 1.00 2,545.22 0.00 0.00%
07.09 CARPINTERIA METALICA 0.00 #DIV/0!
07.09.01 PUERTA METALICA DE ACCESO PESADA 1.77X2.30M und 2,500.00 2.00 5,000.00 0.00 0.00%
07.10 APOYO PARA ESTRUCTURA METALICA 0.00 #DIV/0!
07.10.01 APOYO FIJO und 190.00 10.00 1,900.00 0.00 0.00%
07.10.02 APOYO MOVIL und 190.00 10.00 1,900.00 0.00 0.00%
03 CANCHA SINTETICA 68,470.82 0.00 0.00%
08.01 INSTALACION DE GRASS SINTETICODEPORTIVO Y ARCOS
08.01.01 ADQUISICION E INSTALACION DE GRASS SINTETICO m2 80.00 689.87 55,189.60 0.00 0.00%
FORMATO F-4A

VALORIZACION DE OBRA CORRESPONDIENTE AL MES D


PERIODO: AÑO FISCAL 2019
PERIODO REPROGRAMADO:
ENTIDAD : MUNICIPALIDAD DISTRITAL DE MARANGANI
MEJORAMIENTO DEL SERVICIO DEPORTIVO Y RECREATIVO EN LA COMUNIDAD DE MAM
PROVINCIA DE CANCHIS - DEPARTAMENTO DE CUSC
RESIDENTE : ARQ. JULIO CESAR CHURATA CRUZ
INSPECTOR :ING. CESAR JULIAN COILA VILCA

PRESUPUESTO ANTERIOR ACUMULADO


Item DESCRIPCION
Und Precio Metrado Parcial Metrado Parcial %
08.01.02 HABILITACIÓN DE ARCOS DE FÚTBOL EXISTENTES und 544.56 2.00 1,089.12 0.00 0.00%
08.01.03 RELLENO DE CANALETA EXISTENTE m3 13.61 6.30 85.74 0.00 0.00%
08.01.04 SOPORTE PARA TUBERIA - MALLA DE VOLEY 0.00 #DIV/0!
08.01.04.01 CORTE DE LOSA DE CONCRETO CON DISCO e=0.20 m. m 1.48 1.20 1.78 0.00 0.00%
08.01.04.02 EXCAVACION MANUAL DE ZANJAS m3 14.78 0.07 1.03 0.00 0.00%
08.01.04.03 CONCRETO f'c=175 kg/cm2 m3 367.10 0.07 25.70 0.00 0.00%
08.01.04.04 SOPORTE PARA TUBERIA- MALLA DE VOLEY und 30.25 2.00 60.50 0.00 0.00%
08.02 INSTALACIONES SANITARIAS 0.00 0.00 #DIV/0!
08.02.01 TUBERIA PVC SAP 3" EN MONTANTE m 40.59 48.00 1,948.32 0.00 0.00%
08.03 INSTALACIONES ELECTRICAS 0.00 #DIV/0!
08.03.01 CABLE ELECTRICO TW AWG-MCM 10 mm2 m 5.88 70.96 417.24 0.00 0.00%
08.03.02 CABLE ELECTRICO TW AWG-MCM 4 mm2 m 3.20 225.55 721.76 0.00 0.00%
08.03.03 CABLE ELECTRICO TW AWG-MCM 2.5 mm2 m 2.22 110.30 244.87 0.00 0.00%
08.03.04 TABLERO GENERAL TDG und 417.06 1.00 417.06 0.00 0.00%
08.03.05 TABLERO DE DISTRIBUCION TD-1 und 433.06 1.00 433.06 0.00 0.00%
REFLECTOR CON LAMPARA HALOGENURO DE 400 3,119.04 0.00 0.00%
08.03.06
WATTS
und 389.88 8.00
TUBERIA ELECTRICA COLGANTE PVC-SAP 20mm INC. 1,159.74 0.00 0.00%
08.03.07
ACCESORIOS
m 11.37 102.00
TUBERIA ELECTRICA EMPOTRADA PVC-SAP 20mm INC. 22.30 0.00 0.00%
08.03.08
ACCESORIOS
m 8.92 2.50
FORMATO F-4A

VALORIZACION DE OBRA CORRESPONDIENTE AL MES D


PERIODO: AÑO FISCAL 2019
PERIODO REPROGRAMADO:
ENTIDAD : MUNICIPALIDAD DISTRITAL DE MARANGANI
MEJORAMIENTO DEL SERVICIO DEPORTIVO Y RECREATIVO EN LA COMUNIDAD DE MAM
PROVINCIA DE CANCHIS - DEPARTAMENTO DE CUSC
RESIDENTE : ARQ. JULIO CESAR CHURATA CRUZ
INSPECTOR :ING. CESAR JULIAN COILA VILCA

PRESUPUESTO ANTERIOR ACUMULADO


Item DESCRIPCION
Und Precio Metrado Parcial Metrado Parcial %
TUBERIA ELECTRICA EMPOTRADA PVC-SAP 25mm INC. 566.61 0.00 0.00%
08.03.09
ACCESORIOS
m 11.22 50.50
08.03.10 CAJA DE PASO METALICA CON TAPA und 62.26 2.00 124.52 0.00 0.00%
08.03.11 CAJA DE PASO CON TAPA CIEGA und 64.66 1.00 64.66 0.00 0.00%
08.03.12 POZO A TIERRA und 1,596.12 1.00 1,596.12 0.00 0.00%
08.04 EXCAVACIONES RED ELECTRICA 0.00 #DIV/0!
08.04.01 TRAZO Y REPLANTEO m2 0.71 25.32 17.98 0.00 0.00%
08.04.02 EXCAVACION MANUAL DE ZANJAS m3 14.78 10.13 149.72 0.00 0.00%
08.04.03 REFINE Y NIVELACION DE ZANJAS m 2.21 63.30 139.89 0.00 0.00%
08.04.04 CAMA DE APOYO TUBERIA e=0.10m m 8.88 63.30 562.10 0.00 0.00%
08.04.05 CINTA DE DEMARCACIÓN m 2.43 63.30 153.82 0.00 0.00%
08.04.06 RELLENO CON MATERIAL PROPIO m3 20.86 7.60 158.54 0.00 0.00%
04 ESCENARIO 2,811.07 0.00 0.00%
09.01 TRAZO Y REPLANTEO m2 0.71 18.40 13.06 0.00 0.00%
09.02 EXCAVACION MANUAL DE ZANJAS m3 14.78 1.80 26.60 0.00 0.00%
09.03 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 17.51 10.38 181.75 0.00 0.00%
09.04 ENCOFRADO Y DESENCOFRADO DE ESCENARIO m2 20.11 3.92 78.83 0.00 0.00%
CONCRETO CICLOPEO f'c=140 kg/cm2 + 70% P.G. EN 414.49 0.00 0.00%
09.05
CIMIENTO CORRIDO
m3 230.27 1.80
FORMATO F-4A

VALORIZACION DE OBRA CORRESPONDIENTE AL MES D


PERIODO: AÑO FISCAL 2019
PERIODO REPROGRAMADO:
ENTIDAD : MUNICIPALIDAD DISTRITAL DE MARANGANI
MEJORAMIENTO DEL SERVICIO DEPORTIVO Y RECREATIVO EN LA COMUNIDAD DE MAM
PROVINCIA DE CANCHIS - DEPARTAMENTO DE CUSC
RESIDENTE : ARQ. JULIO CESAR CHURATA CRUZ
INSPECTOR :ING. CESAR JULIAN COILA VILCA

PRESUPUESTO ANTERIOR ACUMULADO


Item DESCRIPCION
Und Precio Metrado Parcial Metrado Parcial %
CONCRETO CICLOPEO f'c=140 kg/cm2 + 70% P.G. EN 1,381.62 0.00 0.00%
09.06
MURO
m3 230.27 6.00
09.07 BASE DE PIEDRA E=0.125M m2 19.55 12.21 238.71 0.00 0.00%
09.08 CONCRETO f'c=175 kg/cm2 m3 260.11 1.83 476.00 0.00 0.00%
05 ESTACIONAMIENTO 13,968.86 0.00 0.00%
10.01 TRAZO Y REPLANTEO m2 0.71 148.20 105.22 0.00 0.00%
10.02 REFINE, NIVELACION Y COMPACTACION m2 4.69 148.20 695.06 0.00 0.00%
10.03 MURO SECO CON PIEDRA GRANDE m3 141.75 92.90 13,168.58 0.00 0.00%
06 MITIGACION E IMPACTO AMBIENTAL 8,516.37 0.00 0.00%
11.01 LIMPIEZA PERMANENTE DE LA OBRA, MITIGACION DE IMP m2 0.81 867.12 702.37 0.00 0.00%
06 ENSAYOS DE CONTROL DE CALIDAD 0.00 #DIV/0!
12.01 DISEÑO DE MEZCLAS und 250.00 1.00 250.00 0.00 0.00%
12.02 PRUEBA DE RESISTENCIA A LA COMPRESIÓN DEL CONCR und 22.00 12.00 264.00 0.00 0.00%
12.03 ENSAYO PROCTOR MODIFICADO und 350.00 1.00 350.00 0.00 0.00%
06 OTROS 0.00 #DIV/0!
13.01 FLETE RURAL glb 6,500.00 1.00 6,500.00 0.00 0.00%
13.02 PLACA RECORDATORIA und 450.00 1.00 450.00 0.00 0.00%
ANTERIOR
RESUMEN Valorización S/. Porcent %
TOTAL COSTO DIRECTO 341,061.69 0.00 0.00%
FORMATO F-4A

VALORIZACION DE OBRA CORRESPONDIENTE AL MES D


PERIODO: AÑO FISCAL 2019
PERIODO REPROGRAMADO:
ENTIDAD : MUNICIPALIDAD DISTRITAL DE MARANGANI
MEJORAMIENTO DEL SERVICIO DEPORTIVO Y RECREATIVO EN LA COMUNIDAD DE MAM
PROVINCIA DE CANCHIS - DEPARTAMENTO DE CUSC
RESIDENTE : ARQ. JULIO CESAR CHURATA CRUZ
INSPECTOR :ING. CESAR JULIAN COILA VILCA

PRESUPUESTO ANTERIOR ACUMULADO


Item DESCRIPCION
Und Precio Metrado Parcial Metrado Parcial %
341,061.69 0.00 0.00%
MATO F-4A

ONDIENTE AL MES DE AGOSTO DEL 2019

LA COMUNIDAD DE MAMUERA DEL DISTRITO DE MARANGANI -


DEPARTAMENTO DE CUSCO

ACTUAL ACUMULADO SALDO X VALORIZAR


Metrado Parcial % Metrado Parcial % Metrado Parcial %

16,830.23 29.65% 16,830.23 29.65% 39,942.11 70.35%


1.00 150.00 25.00% 1.00 150.00 25.00% 3.00 450.00 75.00%
1.00 679.37 100.00% 1.00 679.37 100.00% 0.00 0.00 0.00%
1.00 587.50 100.00% 1.00 587.50 100.00% 0.00 0.00 0.00%
1.00 350.00 100.00% 1.00 350.00 100.00% 0.00 0.00 0.00%
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
867.12 1,101.24 100.00% 867.12 1,101.24 100.00% 0.00 0.00 0.00%
116.80 116.80 100.00% 116.80 116.80 100.00% 0.00 0.00 0.00%
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
1.00 3,839.40 100.00% 1.00 3,839.40 100.00% 0.00 0.00 0.00%
1.00 887.50 100.00% 1.00 887.50 100.00% 0.00 0.00 0.00%
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
0.00 0.00 0.00% 0.00 0.00 0.00% 116.80 760.37 100.00%
0.00 0.00 0.00% 0.00 0.00 0.00% 8.97 132.58 100.00%
65.24 964.25 94.44% 65.24 964.25 94.44% 3.84 56.76 5.56%
0.00 0.00 0.00% 0.00 0.00 0.00% 32.94 687.13 100.00%
34.77 163.07 95.00% 34.77 163.07 95.00% 1.83 8.58 5.00%
0.00 0.00% 0.00 0.00 0.00% 48.82 240.19 100.00%
0.00 0.00% 0.00 0.00 0.00% 48.82 180.63 100.00%
MATO F-4A

ONDIENTE AL MES DE AGOSTO DEL 2019

LA COMUNIDAD DE MAMUERA DEL DISTRITO DE MARANGANI -


DEPARTAMENTO DE CUSCO

ACTUAL ACUMULADO SALDO X VALORIZAR


Metrado Parcial % Metrado Parcial % Metrado Parcial %
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
0.00 0.00% 0.00 0.00 0.00% 51.98 1,244.92 100.00%
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
0.00 0.00% 0.00 0.00 0.00% 22.44 422.55 100.00%
0.00 0.00% 0.00 0.00 0.00% 8.97 3,545.39 100.00%
0.00 0.00% 0.00 0.00 0.00% 33.66 507.93 100.00%
0.00 0.00% 0.00 0.00 0.00% 50.05 491.99 100.00%
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
0.00 0.00% 0.00 0.00 0.00% 10.45 15.47 100.03%
0.00 0.00% 0.00 0.00 0.00% 0.33 6.00 100.01%
0.00 0.00% 0.00 0.00 0.00% 0.05 17.89 100.01%
0.00 0.00% 0.00 0.00 0.00% 0.58 9.63 100.02%
0.00 0.00% 0.00 0.00 0.00% 180.79 923.84 100.00%
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
0.00 0.00% 0.00 0.00 0.00% 22.50 8,678.03 100.00%
1,078.33 4,658.39 100.00% 1,078.33 4,658.39 100.00% 0.00 0.00 0.00%
0.00 0.00% 0.00 0.00 0.00% 43.84 64.88 100.00%
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
MATO F-4A

ONDIENTE AL MES DE AGOSTO DEL 2019

LA COMUNIDAD DE MAMUERA DEL DISTRITO DE MARANGANI -


DEPARTAMENTO DE CUSCO

ACTUAL ACUMULADO SALDO X VALORIZAR


Metrado Parcial % Metrado Parcial % Metrado Parcial %
0.00 0.00% 0.00 0.00 0.00% 6.08 2,617.80 100.00%
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
0.00 0.00% 0.00 0.00 0.00% 46.80 1,491.05 100.00%
0.00 0.00% 0.00 0.00 0.00% 7.56 3,194.55 100.00%
771.46 3,332.71 63.86% 771.46 3,332.71 63.86% 436.64 1,886.28 36.14%
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
0.00 0.00% 0.00 0.00 0.00% 0.86 307.67 100.00%
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
0.00 0.00% 0.00 0.00 0.00% 20.00 12,000.00 100.00%
0.00 0.00% 0.00 0.00 0.00% 0.00 190,522.26 100.00%

0.00 0.00% 0.00 0.00 0.00% 120.00 23,937.60 100.00%


0.00 0.00% 0.00 0.00 0.00% 67.08 6,748.92 100.00%
0.00 0.00% 0.00 0.00 0.00% 6.40 271.94 100.00%
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
0.00 0.00% 0.00 0.00 0.00% 237.24 11,278.39 100.00%
0.00 0.00% 0.00 0.00 0.00% 115.00 4,886.35 100.00%
0.00 0.00% 0.00 0.00 0.00% 152.28 6,258.71 100.00%
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
0.00 0.00% 0.00 0.00 0.00% 2.00 5,857.70 100.00%
MATO F-4A

ONDIENTE AL MES DE AGOSTO DEL 2019

LA COMUNIDAD DE MAMUERA DEL DISTRITO DE MARANGANI -


DEPARTAMENTO DE CUSCO

ACTUAL ACUMULADO SALDO X VALORIZAR


Metrado Parcial % Metrado Parcial % Metrado Parcial %
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
0.00 0.00% 0.00 0.00 0.00% 8.00 32,284.56 100.00%
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
0.00 0.00% 0.00 0.00 0.00% 653.95 6,474.11 100.00%
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
0.00 0.00% 0.00 0.00 0.00% 1,121.00 25,995.99 100.00%
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
0.00 0.00% 0.00 0.00 0.00% 962.74 35,226.66 100.00%
0.00 0.00% 0.00 0.00 0.00% 153.84 5,193.64 100.00%
0.00 0.00% 0.00 0.00 0.00% 522.38 14,762.46 100.00%
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
0.00 0.00% 0.00 0.00 0.00% 1.00 2,545.22 100.00%
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
0.00 0.00% 0.00 0.00 0.00% 2.00 5,000.00 100.00%
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
0.00 0.00% 0.00 0.00 0.00% 10.00 1,900.00 100.00%
0.00 0.00% 0.00 0.00 0.00% 10.00 1,900.00 100.00%
0.00 0.00% 0.00 0.00% 68,470.82 100.00%

0.00 0.00% 0.00 0.00 0.00% 689.87 55,189.60 100.00%


MATO F-4A

ONDIENTE AL MES DE AGOSTO DEL 2019

LA COMUNIDAD DE MAMUERA DEL DISTRITO DE MARANGANI -


DEPARTAMENTO DE CUSCO

ACTUAL ACUMULADO SALDO X VALORIZAR


Metrado Parcial % Metrado Parcial % Metrado Parcial %
0.00 0.00% 0.00 0.00 0.00% 2.00 1,089.12 100.00%
0.00 0.00% 0.00 0.00 0.00% 6.30 85.74 100.00%
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
0.00 0.00% 0.00 0.00 0.00% 1.20 1.78 100.23%
0.00 0.00% 0.00 0.00 0.00% 0.07 1.03 99.56%
0.00 0.00% 0.00 0.00 0.00% 0.07 25.70 100.01%
0.00 0.00% 0.00 0.00 0.00% 2.00 60.50 100.00%
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
0.00 0.00% 0.00 0.00 0.00% 48.00 1,948.32 100.00%
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
0.00 0.00% 0.00 0.00 0.00% 70.96 417.24 100.00%
0.00 0.00% 0.00 0.00 0.00% 225.55 721.76 100.00%
0.00 0.00% 0.00 0.00 0.00% 110.30 244.87 100.00%
0.00 0.00% 0.00 0.00 0.00% 1.00 417.06 100.00%
0.00 0.00% 0.00 0.00 0.00% 1.00 433.06 100.00%

0.00 0.00% 0.00 0.00 0.00% 8.00 3,119.04 100.00%

0.00 0.00% 0.00 0.00 0.00% 102.00 1,159.74 100.00%

0.00 0.00% 0.00 0.00 0.00% 2.50 22.30 100.00%


MATO F-4A

ONDIENTE AL MES DE AGOSTO DEL 2019

LA COMUNIDAD DE MAMUERA DEL DISTRITO DE MARANGANI -


DEPARTAMENTO DE CUSCO

ACTUAL ACUMULADO SALDO X VALORIZAR


Metrado Parcial % Metrado Parcial % Metrado Parcial %
0.00 0.00% 0.00 0.00 0.00% 50.50 566.61 100.00%

0.00 0.00% 0.00 0.00 0.00% 2.00 124.52 100.00%


0.00 0.00% 0.00 0.00 0.00% 1.00 64.66 100.00%
0.00 0.00% 0.00 0.00 0.00% 1.00 1,596.12 100.00%
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
0.00 0.00% 0.00 0.00 0.00% 25.32 17.98 100.02%
0.00 0.00% 0.00 0.00 0.00% 10.13 149.72 100.00%
0.00 0.00% 0.00 0.00 0.00% 63.30 139.89 100.00%
0.00 0.00% 0.00 0.00 0.00% 63.30 562.10 100.00%
0.00 0.00% 0.00 0.00 0.00% 63.30 153.82 100.00%
0.00 0.00% 0.00 0.00 0.00% 7.60 158.54 100.00%
0.00 0.00% 0.00 0.00% 2,811.06 100.00%
0.00 0.00% 0.00 0.00 0.00% 18.40 13.06 99.97%
0.00 0.00% 0.00 0.00 0.00% 1.80 26.60 99.98%
0.00 0.00% 0.00 0.00 0.00% 10.38 181.75 100.00%
0.00 0.00% 0.00 0.00 0.00% 3.92 78.83 100.00%

0.00 0.00% 0.00 0.00 0.00% 1.80 414.49 100.00%


MATO F-4A

ONDIENTE AL MES DE AGOSTO DEL 2019

LA COMUNIDAD DE MAMUERA DEL DISTRITO DE MARANGANI -


DEPARTAMENTO DE CUSCO

ACTUAL ACUMULADO SALDO X VALORIZAR


Metrado Parcial % Metrado Parcial % Metrado Parcial %
0.00 0.00% 0.00 0.00 0.00% 6.00 1,381.62 100.00%

0.00 0.00% 0.00 0.00 0.00% 12.21 238.71 100.00%


0.00 0.00% 0.00 0.00 0.00% 1.83 476.00 100.00%
0.00 0.00% 0.00 0.00% 13,968.86 100.00%
0.00 0.00% 0.00 0.00 0.00% 148.20 105.22 100.00%
0.00 0.00% 0.00 0.00 0.00% 148.20 695.06 100.00%
0.00 0.00% 0.00 0.00 0.00% 92.90 13,168.58 100.00%
3,250.00 38.16% 3,250.00 38.16% 5,266.37 61.84%
0.00 0.00% 0.00 0.00 0.00% 867.12 702.37 100.00%
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
0.00 0.00% 0.00 0.00 0.00% 1.00 250.00 100.00%
0.00 0.00% 0.00 0.00 0.00% 12.00 264.00 100.00%
0.00 0.00% 0.00 0.00 0.00% 1.00 350.00 100.00%
0.00 #DIV/0! 0.00 0.00 #DIV/0! 0.00 0.00 #DIV/0!
0.50 3,250.00 50.00% 0.50 3,250.00 50.00% 0.50 3,250.00 50.00%
0.00 0.00% 0.00 0.00 0.00% 1.00 450.00 100.00%
ACTUAL ACUMULADO SALDO
Valorización S/. Porcent % Valorización S/. Porcent % Valorización S/. Porcent %
20,080.23 5.89% 20,080.23 5.89% 320,981.46 94.11%
MATO F-4A

ONDIENTE AL MES DE AGOSTO DEL 2019

LA COMUNIDAD DE MAMUERA DEL DISTRITO DE MARANGANI -


DEPARTAMENTO DE CUSCO

ACTUAL ACUMULADO SALDO X VALORIZAR


Metrado Parcial % Metrado Parcial % Metrado Parcial %
20,080.23 5.89% 20,080.23 5.89% 320,981.46 94.11%
FORMATO F-12B

VALORIZACION DE OBRA CORRESPONDIENTE AL MES DE AGOSTO DEL


PERIODO: AÑO FISCAL 2019
PERIODO REPROGRAMADO: MEJORAMIENTO DEL SERVICIO DEPORTIVO Y RECREATIVO EN
ENTIDAD : MUNICIPALIDAD DISTRITAL DE MARANGANI MAMUERA DEL DISTRITO DE MARANGANI - PROVINCIA DE CANC
RESIDENTE : ARQ. JULIO CESAR CHURATA CRUZ CUSCO
INSPECTOR :ING. CESAR JULIAN COILA VILCA

PRESUPUESTO ANTERIOR
Item DESCRIPCION
Und Precio Metrado Parcial Parcial %

TRABAJOS PRELIMNARES Y MOVIMIENTO DE TIERRAS M2 867.12 56,772.33 0.00 0.00%


ADECUADA INFRAESTRUCTURA
DEPORTIVA ESTRUCTURAS METALICAS Y COBERTURA M2 962.74 190,522.24 0.00 0.00%

CANCHA SINTETICA M2 689.87 68,470.82 0.00 0.00%


ESCENARIO M2 18.40 2,811.07 0.00 0.00%
ESTACIONAMIENTO M2 95.48 13,968.86 0.00 0.00%
ADECUADOS ESPACIOS
COMPLEMENTARIOS PARA LAS
ACTIVIDADES DEPORTIVAS
MITIGACION E IMPACTO AMBIENTAL M2 1.00 8,516.37 0.00 0.00%

RESUMEN Porcent %
TOTAL COSTO DIRECTO 341,061.69 0.00 0.00%
341,061.69 0.00 0.00%
ATO F-12B

NDIENTE AL MES DE AGOSTO DEL 2019

DEL SERVICIO DEPORTIVO Y RECREATIVO EN LA COMUNIDAD DE


RITO DE MARANGANI - PROVINCIA DE CANCHIS - DEPARTAMENTO DE
CUSCO

ACTUAL ACUMULADO SALDO


Parcial % Parcial % Parcial %

16,830.23 29.65% 16,830.23 29.65% 39,942.10 70.35%

0.00 0.00% 0.00 0.00% 190,522.24 100.00%

0.00 0.00% 0.00 0.00% 68,470.82 100.00%


0.00 0.00% 0.00 0.00% 2,811.07 100.00%
0.00 0.00% 0.00 0.00% 13,968.86 100.00%

3,250.00 38.16% 3,250.00 38.16% 5,266.37 61.84%

Porcent % Porcent % Porcent %


20,080.23 5.89% 20,080.23 5.89% 320,981.46 94.11%
20,080.23 5.89% 20,080.23 5.89% 320,981.46 94.11%