PROYECTO "PARQUE SAN MARTÍN" - PRESUPUESTO CASCO

PORCENTAJE DE AVANCE SEMANAL


Item DESCRIPCIÓN 1ra 2da 3ra 4ta 5ta 6ta 7ma TOTAL
Semana Semana Semana Semana Semana Semana Semana
01 ACERO DE PLACAS 7% 16% 17% 19% 24% 17% 0% 100%
02 ENCOFRADO DE PLACAS 5% 15% 19% 22% 23% 16% 0% 100%
03 CONCRETO DE PLACAS 4% 16% 21% 20% 17% 22% 0% 100%
04 ENCOFRADO DE VIGAS 3% 11% 26% 18% 28% 14% 0% 100%
05 ACERO DE VIGAS 2% 19% 22% 25% 19% 13% 0% 100%
06 ENCOFRADO DE LOSA 1% 5% 19% 26% 23% 15% 11% 100%
07 LADRILLOS 0% 14% 16% 19% 23% 16% 12% 100%
08 ACERO DE LOSA 0% 17% 14% 18% 21% 18% 12% 100%
09 VACIADO DE LOSA 0% 12% 12% 16% 17% 19% 24% 100%
TOTAL Valorización Acumulada a la Valorización Actual 4ta Valorización Acumulada a la Saldo a la 4ta Semana
Item DESCRIPCIÓN UND CANT 3ra Semana Semana 4ta Semana
P.U. Costo % Cant Parcial % Cant. Parcial % Cant. Parcial % Cant. Parcial

1 ACERO DE PLACAS kg 7,000.00 5.00 35000.00 40% 2800.00 14000.00 19% 1330.00 6650.00 59% 4130.00 20650.00 41% 2870.00 14350.00
2 ENCOFRADO DE PLACAS m2 340.00 40.00 13600.00 39% 132.60 5304.00 22% 74.80 2992.00 61% 207.40 8296.00 39% 132.60 5304.00
3 CONCRETO DE PLACAS m3 260.00 340.00 88400.00 41% 106.60 36244.00 20% 52.00 17680.00 61% 158.60 53924.00 39% 101.40 34476.00
4 ENCOFRADO DE VIGAS m2 140.00 36.00 5040.00 40% 56.00 2016.00 18% 25.20 907.20 58% 81.20 2923.20 42% 58.80 2116.80
5 ACERO DE VIGAS kg 13,000.00 5.00 65000.00 43% 5590.00 27950.00 25% 3250.00 16250.00 68% 8840.00 44200.00 32% 4160.00 20800.00
6 ENCOFRADO DE LOSA m2 2,300.00 30.00 69000.00 25% 575.00 17250.00 26% 598.00 17940.00 51% 1173.00 35190.00 49% 1127.00 33810.00
7 LADRILLOS und 14,000.00 3.20 44800.00 30% 4200.00 13440.00 19% 2660.00 8512.00 49% 6860.00 21952.00 51% 7140.00 22848.00
8 ACERO DE LOSA kg 5,500.00 5.00 27500.00 31% 1705.00 8525.00 18% 990.00 4950.00 49% 2695.00 13475.00 51% 2805.00 14025.00
9 VACIADO DE LOSA m3 220.00 380.00 83600.00 24% 52.80 20064.00 16% 35.20 13376.00 40% 88.00 33440.00 60% 132.00 50160.00

COSTO DIRECTO 431940.00 144793.00 89257.20 234050.20 197889.80

GASTOS GENERALES 12% 51832.8 17375.16 10710.864 28086.024 23746.776


UTILIDADES 10% 43194 14479.3 8925.72 23405.02 19788.98

SUB-TOTAL 526966.80 176647.46 108893.78 285541.24 241425.56


IGV (N.S.) 18% 94854.02 31796.54 19600.88 51397.42 43456.60
TOTAL 621820.82 208444.00 128494.67 336938.67 284882.16

FONDO DE GARANTIA 5% 31091.04 10422.20 6424.73 16846.93 14244.11


PRÉSTAMO 8% 49745.67 16675.52 10279.57 26955.09 22790.57

NETO A COBRAR (N.S.) 181346.28 111790.36 293136.64 247847.48


TOTAL
Item DESCRIPCIÓN UND CANT
P.U. Costo

01 ACERO DE PLACAS kg 8,000.00 4.50 36000.00


02 ENCOFRADO DE PLACAS m2 350.00 35.00 12250.00
03 CONCRETO DE PLACAS m3 240.00 350.00 84000.00

COSTO DIRECTO 132250.00

GASTOS GENERALES 12% 15870


UTILIDADES 10% 13225

SUB-TOTAL 161345.00
IGV (N.S.) 18% 29042.10
TOTAL 190387.10

FONDO DE GARANTIA 5% 9519.36


PRÉSTAMO 8% 15230.97

NETO A COBRAR (N.S.)