ID Task Nombre de tarea Duration Start Finish Predecessors

Mode 29 Apr '19 6 May '19 13 May '19


T W T F S S M T W T F S S M T W T
1 PROYECTO 49.5 days Thu 2/05/19 Wed
CONSTRUCCION MI 3/07/19
CASA
2 REUNION 44.5 days Mon 6/05/19Mon 1/07/19
3 REUNION 1 1 hour Mon 6/05/19Mon 6/05/19
4 REUNION 2 1 hour Mon 13/05/19Mon 13/05/19
5 REUNION 3 1 hour Mon 20/05/19Mon 20/05/19
6 REUNION 4 1 hour Mon 27/05/19Mon 27/05/19
7 REUNION 5 1 hour Mon 3/06/19Mon 3/06/19
8 REUNION 6 1 hour Mon 10/06/19Mon 10/06/19
9 REUNION 7 1 hour Mon 17/06/19Mon 17/06/19
10 REUNION 8 1 hour Mon 24/06/19Mon 24/06/19
11 REUNION 9 1 hour Mon 1/07/19Mon 1/07/19
12 FASE CIMIENTOS 4 days Thu 2/05/19 Tue 7/05/19
15 FIN DE FASE 0 days Tue 7/05/19 Tue 7/05/19 14 7/05
16 FASE 23 days Tue 7/05/19 Tue 4/06/19
ESTRUCCTURAL
17 COLUMNAS Y 1 wk Tue 7/05/19 Mon 15 ARENA[90 BOLS
VIGAS 13/05/19
18 PAREDES 2 wks Mon 13/05/19Sat 25/05/19 17
19 PISO 2 days Mon 13/05/19Wed 15/05/1917 ARENA[9
20 ENCOFRADO 7 days Sat 25/05/19 Mon 18;19 JULI
TECHO 3/06/19
21 LLENADO TECHO 1 day Mon 3/06/19Tue 4/06/19 20
Tarea Resumen inactivo Tareas externas

División Tarea manual Hito externo

Hito solo duración Fecha límite


Proyecto: MI CASA1
Resumen Informe de resumen manual Tareas críticas
Fecha: Sat 18/05/19
Resumen del proyecto Resumen manual División crítica

Tarea inactiva solo el comienzo Progreso

Hito inactivo solo fin Progreso manual

Página 1
ID Task Nombre de tarea Duration Start Finish Predecessors
Mode 29 Apr '19 6 May '19 13 May '19
T W T F S S M T W T F S S M T W T
22 FIN DE FASE 0 days Tue 4/06/19 Tue 4/06/19 21
23 FASE MECANICA 10.5 days Tue 11/06/19Mon 24/06/19
24 PLOMERIA 1.3 wks Tue 11/06/19Wed 19/06/1921FS+5 days;22
25 ELECTRICIDAD 3.5 days Wed 19/06/19Mon 24/06/1924
26 FIN DE FASE 0 days Mon 24/06/19Mon 24/06/1925
27 FASE ACABADO 7 days Mon Wed
INTERIOR EXTERIOR 24/06/19 3/07/19
28 COLOCAR 3.5 days Mon Wed 26
PUERTAS 24/06/19 3/07/19
29 COLOCAR 4 days Mon Fri 28/06/19 26
VENTANAS 24/06/19
30 DECORACION 3 days Wed 26/06/19Mon 1/07/1929FS-50%
31 HG 0 days Mon 1/07/19Mon 1/07/1930

Tarea Resumen inactivo Tareas externas

División Tarea manual Hito externo

Hito solo duración Fecha límite


Proyecto: MI CASA1
Resumen Informe de resumen manual Tareas críticas
Fecha: Sat 18/05/19
Resumen del proyecto Resumen manual División crítica

Tarea inactiva solo el comienzo Progreso

Hito inactivo solo fin Progreso manual

Página 2
May '19 20 May '19 27 May '19 3 Jun '19 10 Jun '19 17 Jun '19 24 Jun '19
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

ARENA[90 BOLSA X 50 KG];CEMENTO[30 BOLSA X 50 KG];MARIO HINOJOSA;NICOLAS MENDOZA;OSCAR PEREZ;RICARDO MERINO

ARENA[30 BOLSA X 50 KG];CEMENTO[10 BOLSA X 50 KG];LADRILLOS[5 X MILLAR];NICOLAS MENDOZA;OSCAR PEREZ


ARENA[90 BOLSA X 50 KG];CEMENTO[30 BOLSA X 50 KG];LOZETA[100 X METRO 2];MARIO HINOJOSA;OSCAR PEREZ;RICARDO MERINO
JULIO ROSAS[50%];MARIO HINOJOSA;PABLO SAMANIEGO

ARENA[120 BOLSA X 50 KG];CEMENTO[40 BOLSA X 50 KG];JULIO ROSAS[50%];LADRILLOS

Tarea Resumen inactivo Tareas externas

División Tarea manual Hito externo

Hito solo duración Fecha límite


Proyecto: MI CASA1
Resumen Informe de resumen manual Tareas críticas
Fecha: Sat 18/05/19
Resumen del proyecto Resumen manual División crítica

Tarea inactiva solo el comienzo Progreso

Hito inactivo solo fin Progreso manual

Página 3
May '19 20 May '19 27 May '19 3 Jun '19 10 Jun '19 17 Jun '19 24 Jun '19
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
4/06

ARENA[4.5 BOLSA X 50 KG];CEMENTO


CABLE ELECTRICO[5
24/06

LUIS S

Tarea Resumen inactivo Tareas externas

División Tarea manual Hito externo

Hito solo duración Fecha límite


Proyecto: MI CASA1
Resumen Informe de resumen manual Tareas críticas
Fecha: Sat 18/05/19
Resumen del proyecto Resumen manual División crítica

Tarea inactiva solo el comienzo Progreso

Hito inactivo solo fin Progreso manual

Página 4
19 1 Jul '19 8 Jul '19 15 Jul '19 22 Jul '19 29 Jul '19 5 Aug '19
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

AR PEREZ

[50%];LADRILLOS[1 X MILLAR];MARIO HINOJOSA;MEZCLADORA;NICOLAS MENDOZA;OSCAR PEREZ;PABLO SAMANIEGO;RICARDO MERINO

Tarea Resumen inactivo Tareas externas

División Tarea manual Hito externo

Hito solo duración Fecha límite


Proyecto: MI CASA1
Resumen Informe de resumen manual Tareas críticas
Fecha: Sat 18/05/19
Resumen del proyecto Resumen manual División crítica

Tarea inactiva solo el comienzo Progreso

Hito inactivo solo fin Progreso manual

Página 5
19 1 Jul '19 8 Jul '19 15 Jul '19 22 Jul '19 29 Jul '19 5 Aug '19
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

50 KG];CEMENTO[1.5 BOLSA X 50 KG];LEONCIO HARO;PEDRO MARTINEZ;TUBERIA DE AGUA[30 X METRO]


ABLE ELECTRICO[50 X METRO];JUAN SALAS
4/06

LUIS SORIA;MADERA[40 X PIE 2];MANUEL PEÑA

LUIS SORIA;MADERA[20 X PIE 2];MANUEL PEÑA

COMPUTADORA;ROSA PEREZ
1/07

Tarea Resumen inactivo Tareas externas

División Tarea manual Hito externo

Hito solo duración Fecha límite


Proyecto: MI CASA1
Resumen Informe de resumen manual Tareas críticas
Fecha: Sat 18/05/19
Resumen del proyecto Resumen manual División crítica

Tarea inactiva solo el comienzo Progreso

Hito inactivo solo fin Progreso manual

Página 6