PLANILLA DE METRADOS

02.00 MOVIMIENTO DE TIERRAS

02.02 Excavacion en material suelto (bajo agua)

DESCRIPCIO
CANT. AREA1 AREA 2 ALTO TOTAL
N

MARGEN IZQUIERDA 10.50 M3


SOLADO 1.00 140.07 0.08 10.50
ESTRIBO
C.F. 1656.528 166.84
N.F. 1661.83 166.84 - -

MARGEN DERECHA 11.54 M3


SOLADO 1.00 153.92 0.08 11.54
ESTRIBO
C.F. 1656.339 182.58
N.F. 1661.83 182.58 - -

TOTAL EJECUTADO 22.04 M3

02.03 Relleno compactado con material seleccionado

DESCRIPCIO
CANTIDAD AREA1 AREA 2 ALTO TOTAL
N

MARGEN IZQUIERDA
CORTE A-A 26.77 1.50 40.15 m3
CORTE B-B 140.90
CORTE C-C 148.06 3.80 549.01 m3
CORTE D-D 97.45
CORTE E-E 98.68 0.70 68.64 m3
CORTE E-E 98.68 5.08 501.27 m3
AREA F 27.00 0.42 11.34 m3

MARGEN DERECHA
CORTE A-A 28.66 1.50 42.99 m3
CORTE B-B 154.81
CORTE C-C 162.87 3.99 633.76 m3
CORTE D-D 110.37
CORTE E-E 111.43 0.51 56.56 m3
CORTE E-E 111.43 5.08 566.06 m3
AREA F 31.78 0.42 13.35 m3

TOTAL EJECUTADO 2,483.13 m3


02.00 MOVIMIENTO DE TIERRAS

02.04 Relleno compactado con material propio

DESCRIPCIO
CANTIDAD AREA1 AREA2 ALTO TOTAL
N

TOTAL EJECUTADO - m3

02.05 Demolición de estructuras de concreto

DESCRIPCIO
CANTIDAD AREA1 AREA2 ALTO TOTAL
N

TOTAL EJECUTADO - m3

02.06 Eliminación de material excedente

DESCRIPCIO VOLUMEN
CANTIDAD PORCENTAJE PARCIAL TOTAL
N (M3)

02.01 Excavacion en material suelto 1.00


(en seco) #REF! #REF! m3
02.02 Excavacion en material suelto (bajo
1.00 agua) 22.04 22.04 m3

TOTAL EJECUTADO #REF! m3


PLANILLA DE METRADOS
V12
V45
ENCOFRADOS Y DESENCOFRADOS

Encofrado no visto en Estribos ( en agua)

DESCRIPCIO ALTURA/
CANTIDAD AREA LONGITUD TOTAL
N DISTANCIA

ESTRIBO IZQUIERDO 274.97 m2


ZAPATA
Perimetro 1.00 - 50.49 1.50 75.74
PATALLA
AREA ANTERIOR Af1 1.00 46.05 46.05
AREA POSTERIOR 1.00 3.84 12.65 48.58
ALA 1
AREA ANTERIOR "AVL3 y AVL4" 1.00 25.10 25.10
AREA POSTERIOR "AVL3" 1.00 19.49 19.49
AREA COSTADO 1.00 3.80 0.30 1.14
ALA 2
REA ANTERIOR "AVL4' y AVL5" 1.00 32.23 32.23
AREA POSTERIOR "AVL5" 1.00 25.50 25.50
AREA COSTADO 1.00 3.81 0.30 1.14

ESTRIBO DERECHO 293.22 m2


ZAPATA
Perimetro 1.00 - 55.32 1.50 82.98
PATALLA
AREA ANTERIOR Af1 1.00 48.62 48.62
AREA POSTERIOR 1.00 3.84 13.86 53.22
ALA 1
AREA ANTERIOR "AVL3 y AVL4" 1.00 25.10 25.10
AREA POSTERIOR "AVL3" 1.00 19.49 19.49
AREA COSTADO 1.00 3.80 0.30 1.14
ALA 2
REA ANTERIOR "AVL5 y AVL4' " 1.00 34.76 34.76
AREA POSTERIOR "AVL5" 1.00 26.77 26.77
AREA COSTADO 1.00 3.80 0.30 1.14
TOTAL EJECUTADO 568.19 m2

Encofrado no visto en Estribos( en seco)

DESCRIPCIO ALTURA/
CANTIDAD AREA LONGITUD TOTAL
N DISTANCIA

ESTRIBO IZQUIERDO 184.20 m2


PANTALLA
A FRONTAL Af3 (Uña parapeto) 1.00 18.98 18.98
OSTERIOR Af3 (Uña parapeto) 1.00 1.62 12.23 19.81
AREA POSTERIOR Af2 1.00 55.89 55.89
ALA1
AREA POSTERIOR AVL1 1.00 38.89 38.89
AREA COSTADO 1.00 7.08 0.30 2.12
ALA2
AREA POSTERIOR AVL7 1.00 0.50 7.15 3.58
REA POSTERIOR AVL7 Oblicua 1.00 5.46 7.15 39.04
OSTERIOR AVL7 Sobresaliente 1.00 3.82 3.82
AREA COSTADO 1.00 6.93 0.30 2.08

ESTRIBO DERECHO 195.76 m2


PANTALLA
AREA FRONTAL Af3 (Cajuela) 1.00 20.39 20.39
REA POSTERIOR Af3 (Cajuela) 1.00 1.62 13.21 21.40
AREA POSTERIOR Af2 1.00 58.64 58.64
ALA1
AREA POSTERIOR AVL1 1.00 0.50 5.50 2.75
REA POSTERIOR AVL1 Oblicua 1.00 6.60 5.50 36.30
AREA COSTADO 1.00 7.08 0.30 2.12
ALA2
AREA POSTERIOR AVL7 1.00 0.50 7.60 3.80
REA POSTERIOR AVL7 Oblicua 1.00 5.50 7.60 41.80
OSTERIOR AVL7 Sobresaliente 1.00 6.30 6.30
AREA COSTADO 1.00 7.54 0.30 2.26
TOTAL EJECUTADO 379.96 m2

Encofrado caravista en Estribos ( en seco)

DESCRIPCIO ALTURA/
CANTIDAD AREA LONGITUD TOTAL
N DISTANCIA

ESTRIBO IZQUIERDO 154.43 m2


PANTALLA
AREA FRONTAL Af2 1.00 55.71 55.71
AREA FRONTAL Af4 1.00 0.18 0.18
AREA FRONTAL Af5 1.00 0.15 0.15
ALA1
AREA FRONTAL "AVL1 y AVL2" 1.00 44.96 44.96
ALA2
AREA FRONTAL "AVL7 y AVL8" 1.00 53.43 53.43

ESTRIBO DERECHO 162.11 m2


PANTALLA
AREA FRONTAL Af2 1.00 58.49 58.49
AREA FRONTAL Af4 1.00 0.15 0.15
AREA FRONTAL Af5 1.00 0.22 0.22
ALA1
AREA FRONTAL "AVL1 y AVL2" 1.00 44.96 44.96
ALA2
AREA FRONTAL "AVL7 y AVL2' " 1.00 58.29 58.29
TOTAL EJECUTADO 316.54 m2

Encofrado Losa de Aproximacion ( en seco)

DESCRIPCIO
CANTIDAD LONGITUD ALTO PARCIAL TOTAL
N
LOSA DE APROXIMACIÓN 17.28 m2
ESTRIBO IZQUIERD
LATERAL 1 1.00 4.00 0.25 1.00
LATERAL 2 1.00 4.83 0.25 1.21
LONGITUDINALES 1 1.00 13.21 0.25 3.30
LONGITUDINALES 2 1.00 10.51 0.25 2.63
ESTRIBO DERECHO
LATERAL 1 1.00 4.00 0.25 1.00
LATERAL 2 1.00 5.69 0.25 1.42
LONGITUDINALES 1 1.00 15.45 0.25 3.86
LONGITUDINALES 2 1.00 11.41 0.25 2.85
TOTAL EJECUTADO 17.28 m2

Encofrados de losa, vigas, veredas y diafragmas

DESCRIPCIO ALTO/
CANTIDAD LONGITUD PARCIAL TOTAL
N ANCHO

LOSA 137.41 m2
MURO LONGITUDINALES
LATERAL 1.00 12.09 0.20 2.42
LATERAL 1.00 13.19 0.20 2.64
MURO CURVOS
LATERAL 1.00 19.21 0.20 3.84
LATERAL 1.00 18.49 0.20 3.70
SUPERFICIE INFERIOR 1.00 124.814 m2 124.81
VIGAS 243.21 m2
LATERAL 1 5.00 18.15 1.12 101.64
LATERAL 2 5.00 18.15 1.06 96.20
BASES 5.00 18.15 0.50 45.38
VEREDAS 67.51 m2
EN CURVA ABIERTA 1.00 19.21 1.83 35.15
EN CURVA CERRADA 1.00 18.49 1.75 32.36
DIAFRAGMAS 52.80 m2
DIAFRAGMA DERE
LATERAL 8.00 1.767 m2 14.14
BASE 4.00 1.85 0.30 2.22
EXTREMO 1 1.00 2.32 0.30 0.70
EXTREMO 2 2.00 1.499 m2 3.00
DIAFRAGMA IZQUI
LATERAL 8.00 1.767 m2 14.14
BASE 4.00 1.85 0.30 2.22
EXTREMO 1 1.00 2.04 0.30 0.61
EXTREMO 2 2.00 1.223 m2 2.45
DIAFRAGMA CENT
LATERAL 8.00 1.482 m2 11.86
BASE 4.00 1.85 0.20 1.48
* METRADO PARA ADICIONAL Nº4 500.93 m2
PLANILLA DE METRADOS

OBRAS DE CONCRETO

Concreto f´c=100 kg/cm2 (solado)

DESCRIPCIO
ANCHO LARGO AREA ALTO TOTAL
N

ESTRIBO DERECHO
SOLADO PARA ZAPATA AREA BASE= 153.916 0.100 15.39 M3
OLADO PARA LOSA APROX AREA BASE= 53.640 0.100 5.36 M3
ESTRIBO IZQUIERDO
SOLADO PARA ZAPATA AREA BASE= 140.066 0.100 14.01 M3
OLADO PARA LOSA APROX AREA BASE= 47.440 0.100 4.74 M3

TOTAL EJECUTADO 34.76 m3

Concreto f´c=210 kg/cm2 (en agua)

DESCRIPCIO
ANCHO LARGO AREA ALTO TOTAL
N

ESTRIBO DERECHO
ZAPATA 140.066 - 1.50 210.10
ESTRIBO IZQUIERDO
ZAPATA 153.916 - 1.50 230.87

TOTAL EJECUTADO 440.97 m3

Concreto f´c=280 kg/cm2 (en agua)

DESCRIPCIO
AREA 1 AREA 2 ALTO PARCIAL TOTAL
N
ESTRIBO IZQUIERDO 105.92 m3
PANTALLA N.F.(+3.80m sobre Zapata) 19.43 Vol.3 - 0.30 5.83
Vol.4 20.125 12.583 3.80 62.15
Vol.5 25.385 - 0.30 7.62
Vol.6 0.03 - 3.80 0.11
Vol 3' 2.58 - 5.50 14.19
Vol 5' 2.242 - 7.15 16.03
ESTRIBO DERECHO 112.17 m3
PANTALLA N.F.(+3.80m sobre Zapata) 19.43 Vol.3 - 0.30 5.83
Vol.4 21.713 13.496 3.80 66.90
Vol.5 26.71 - 0.30 8.01
Vol.6 0.05 - 3.80 0.17
Vol.3` 2.58 - 5.50 14.19
Vol.5` 2.246 - 7.60 17.07
TOTAL EJECUTADO 218.09 m3

Concreto f´c=280 kg/cm2 (en seco)

DESCRIPCIO
AREA 1 AREA 2 ALTO PARCIAL TOTAL
N
ESTRIBO IZQUIERDO 106.64 m3
PANTALLA N.F.(Mayor a 3.80m) 38.888 Vol.1 - 0.30 11.67
Vol.7 47.407 0.30 14.22
Vol.8-A 12.583 11.295 0.70 8.36
Vol.8-B 4.062 3.19 12.11 43.94
Vol.9 18.977 - 0.30 5.69
Vol 9' 0.135 - 12.69 1.71
Vol 10 0.409 - 3.42 1.40
Vol 1' 1.730 - 5.50 9.52
Vol 7` 1.187 - 7.15 8.49
Uña parapeto 0.135 - 12.23 1.65
ESTRIBO DERECHO 112.48 m3
PANTALLA N.F.(Mayor a 3.80m) 38.888 Vol.1 - 0.30 11.67
Vol.7 51.303 0.30 15.39
Vol.8-A 13.496 12.101 0.70 8.96
Vol.8-B 3.153 4.06 12.79 46.14
Vol.9 20.395 - 0.30 6.12
Vol 9' 0.135 - 12.69 1.71
Vol 10 0.611 - 3.37 2.06
Vol 1' 1.730 - 5.50 9.52
Vol 7` 1.202 - 7.60 9.14
Uña parapeto 0.135 - 13.21 1.78
TOTAL EJECUTADO 219.12 m3

Concreto f´c=450 kg/cm2

DESCRIPCIO ALTURA/
CANTIDAD AREA PARCIAL TOTAL
N LONGITUD

VIGAS PRINC 5.00 0.535 18.15 48.55 48.55

Concreto f´c=280 kg/cm2

DESCRIPCIO ALTURA/
CANTIDAD AREA PARCIAL TOTAL
N LONGITUD
LOSA 1.00 215.57 0.20 43.11
DIAFRAGMA
ESTRIBO DERECHO 4.00 1.767 0.30 2.12
Extremo 1.00 1.499 0.30 0.45
ESTRIBO IZQUIERDO 4.00 1.767 0.30 2.12
Extremo 1.00 1.223 0.30 0.37
EJE CENTRAL 4.00 1.482 0.20 1.19
TOTAL 49.36 m3

04.05 Concreto f´c=210 kg/cm2 (vereda y losa de aproximación)

DESCRIPCIO ALTURA/
CANTIDAD AREA PARCIAL TOTAL
N LONGITUD
LOSA DE APROXIMACIÓN 25.29 m3
ESTRIBO IZQUIERDO 1.00 47.44 0.25 11.86
ESTRIBO DERECHO 1.00 53.73 0.25 13.43
VEREDA 10.79 m3
CCIÓN EN CURVA ABIERTA 1.00 0.274 18.49 5.07
CIÓN EN CURVA CERRADA 1.00 0.298 19.21 5.725
TOTAL EJECUTADO 36.08 m3
07.00 ACERO

07.01 Acero de refuerzo G-60 / fy=4200 kg/cm2

Nº LONGITUD PESO
DIAMETRO PESO/ML
VARILLAS TOTAL (m) PARCIAL
Ø1" 1,330.00 11,970.00 3.97 47,520.90
Ø1/2" 1,160.00 10,440.00 0.99 10,335.60
Ø5/8" 1,534.00 13,806.00 1.55 21,399.30
Ø3/4" 1,134.00 10,206.00 2.24 22,861.44
Ø3/8" 90.00 810.00 0.56 453.60

PESO TOTAL ACERO PUENTE ALFAMAYO 102,570.84


PLANILLA DE METRADOS

08.00 VARIOS

08.01 JUNTA DE DILATACIÓN METALICA (inc. Neopreno)

DESCRIPCIO
CANTIDAD LARGO ANCHO AREA TOTAL
N

SOBRE ESTRIBO IZQUIERDO


1.00 9.4 9.40

SOBRE ESTRIBO DERECHO


1.00 9.4 9.40

CANTIDAD TOTAL 18.80

08.02 Acabado de veredas

DESCRIPCIO
CANTIDAD LARGO ANCHO AREA TOTAL
N

VEREDA AGUAS ABAJO1.00 19.21 19.21

VEREDA AGUAS ARRIBA1.00 18.49 18.49

CANTIDAD TOTAL 37.70

08.03 Bruñas Rompe Aguas

DESCRIPCIO
CANTIDAD LARGO ANCHO AREA TOTAL
N

VEREDA AGUAS ARRIBA1.00 18.49 18.49

CANTIDAD TOTAL 18.49

08.04 Tubos de drenaje PVC D = 4" x 0.60 m

DESCRIPCIO
CANTIDAD LARGO ANCHO AREA TOTAL
N

AGUAS DEBAJO DE LOSA


4.00 4.00

CANTIDAD TOTAL 4.00

08.05 APOYO DE NEOPRENOS


DESCRIPCIO
CANTIDAD LARGO ANCHO AREA TOTAL
N

SOBRE ESTRIBO IZQUIERDO


5.00 5.00

SOBRE ESTRIBO DERECHO


5.00 5.00

CANTIDAD TOTAL 10.00

08.06 Topes Sismicos

DESCRIPCIO
CANTIDAD LARGO ANCHO AREA TOTAL
N

SOBRE ESTRIBO IZQUIERDO


4.00 4.00

SOBRE ESTRIBO DERECHO


4.00 4.00

CANTIDAD TOTAL 8.00

08.07 Colocacion de baranda metalica (Incluye Pintura)

DESCRIPCIO
CANTIDAD LARGO ANCHO AREA TOTAL
N

VEREDA AGUAS ABAJO1.00 19.21 19.21

VEREDA AGUAS ARRIBA1.00 18.49 18.49

CANTIDAD TOTAL 37.70

08.08 Tubos PVC D = 6" x L

DESCRIPCIO
CANTIDAD LARGO ANCHO AREA TOTAL
N

VEREDA AGUAS ABAJO3.00 19.21 57.63

VEREDA AGUAS ARRIBA3.00 18.49 55.47

CANTIDAD TOTAL 113.10

08.09 RIEGO DE LIGA

DESCRIPCIO
CANTIDAD LARGO ANCHO AREA TOTAL
N
SOBRE LOSA 1.00 #REF! #REF!

CANTIDAD TOTAL #REF!

08.10 CARPETA ASFALTICA (e= 5cm)

DESCRIPCIO
CANTIDAD LARGO ANCHO AREA TOTAL
N

LOSA 1.00 215.57 215.57

CANTIDAD TOTAL 215.57

08.11 PINTURA EN ELEMENTOS DE CONCRETO

DESCRIPCIO
CANTIDAD LARGO ANCHO AREA TOTAL
N
EN CURVA ABIERTA 1.00 19.21 #REF! #REF! #REF!
EN CURVA CERRADA 1.00 18.49 #REF! #REF!
CANTIDAD TOTAL #REF!
ITEM DESCRIPCION UND. Metrado
01.00.00 OBRAS PRELIMINARES
01.01.00 Desbroce y limpieza en la zona m2 1,501.95
01.02.00 Pase provisional (vado) ml 81.64
Volume 166 m3
Volume 396 m3
Alcanta 29.16 ml
01.03.00 Mantenimiento de pase provisi mes 6.00
01.04.00 Trazo, replanteo y control topo m2 1,501.95
02.00.00 MOVIMIENTO DE TIERRAS
02.01.00 Demolición de estructuras exis m3 -
02.02.00 Excavacion en material suelto m3 156.73
02.03.00 Excavacion en material suelto m3 -
02.04.00 Relleno compactado con materi m3 -
02.05.00 Relleno compactado con materi m3 566.06
02.06.00 Eliminación de material provin m3 -
02.07.00 Eliminación de material provin m3 -
03.00.00 ESTRIBOS (cimentacion)
03.01.00 Concreto f'c=100kg/cm2 bajo a m3 -
03.02.00 Concreto f'c=210kg/cm2 bajo a m3 210.10
03.03.00 Encofrado cara no vista bajo a m2 #VALUE!
04.00.00 ESTRIBOS (elevacion)
04.01.00 Concreto f'c=280kg/cm2 bajo a m3 -
04.02.00 Concreto f'c=280kg/cm2 en sec m3 -
04.03.00 Encofrado cara no vista bajo a m2 1,014.84
04.04.00 Encofrado caravista bajo agua m2 -
04.05.00 Encofrado caravista en seco m2 -
04.06.00 Encofrado cara no vista en se m2 3.80
05.00.00 SUPERESTRUCTURA
05.01.00 Concreto f'c=280kg/cm2 en los m3 -
05.02.00 Concreto f'c=450kg/cm2 en vig m3 -
05.03.00 Concreto f'c=280kg/cm2 en ve m3 TOTAL
05.04.00 Concreto f'c=280kg/cm2 en di m3 45.23
05.05.00 Encofrado caravista en seco m2 248.27
05.06.00 Encofrado cara no vista en se m2 - 248.27
06.00.00 LOSA DE TRANSICION
06.01.00 Concreto f'c=100kg/cm2 (solad m3 #VALUE!
06.02.00 Concreto f'c=280kg/cm2 en los m3 -
06.03.00 Encofrado cara no vista en se m2 -
07.00.00 ACERO DE REFUERZO Fy=4,200 kg/cm2
07.01.00 Acero de refuerzo fy=4,200 kg kg 21,399.30
06.00.00 VARIOS
06.01.00 Juntas de dilatacion metalica ( m 9.40
06.02.00 Acabado de veredas m 19.21
06.03.00 Bruñas rompe aguas en losa m TOTAL
06.04.00 Tubos de drenaje PVC D = 4" und TOTAL
06.05.00 Apoyo de neopreno (45x45x14 und 5.00
06.06.00 Topes Sismicos und 4.00
06.07.00 Colocacion de baranda metalica m 19.21
06.08.00 Tubos PVC D = 6" x L (aligera m 57.63
06.09.00 Riego de liga m2 TOTAL
06.10.00 Carpeta asfaltica (e=5cm) m2 TOTAL
06.11.00 Pintura en elementos de concr m2 -