2019

ITEM DESCRIPCION UND METRADO P.U. PARCIAL


Abril Mayo

90 Dias DEFENSA RIBEREÑA


01.00.00 OBRAS PROVISIONALES
01.01.00 CAMPAMENTO M2 50 20.09 1,004.50 1004.5 0
01.02.00 CARTEL DE UND 1 836.01 836.01 836.01 0
01.03.00 FLETE TERRGLB 1 1568 1,568.00 0 1568
01.04.00 MOVILIZACIGLB 1 10584 10,584.00 10584 0
02.00.00 TRABAJOS PRELIMINARES 12424.51 1568
02.01.00 LIMPIEZA MM2 850 1.08 918.00 306 612
02.02.00 TRAZO Y REM 850 0.59 501.50 0 501.5
02.03.00 CAMINOS DE M 200 5.95 1,190.00 0 1190
02.04.00 DESVIO PROM 300 2.34 702.00 0 702
03.00.00 MOVIMIENTO DE TIERRAS 306 3005.5
03.01.00 LIMPIEZA D M3 5400 2.2 11,880.00 0 11880
03.02.00 EXCAVACION M3 5121.75 3.22 16,492.04 0 16492.04
03.03.00 LIMPIEZA Y M3 11092.5 3.62 40,154.85 0 40154.85
03.04.00 CONFORMAC M3 2947.8 9.64 28,416.79 0 8525.04
03.05.00 CORTE Y ACM3 2947.8 3.51 10,346.78 0 6897.85
03.06.00 CARGUIO Y M3 2947.8 5.26 15,505.43 0 0
04.00.00 ENROCADOS DE PROTECCION 0 83949.78
04.01.00 VOLADURA M D3 8795.8 8.15 71,685.77 0 71685.77
04.02.00 CARGUIO Y M3 8795.8 8.61 75,731.84 0 75731.84
04.03.00 ENROCADO M3 6766 7.14 48,309.24 0 0
05.00.00 VARIOS 0 147417.61
05.01.00 ACARREO DM3 40 18.87 754.80 0 754.8
05.02.00 ENTABLADOM 10 29.53 295.30 0 295.3
05.03.00 LIMPIEZA G KM 0.85 37.74 32.08 0 10.69
05.04.00 MITIGACIONGLB 1 753.41 753.41 0 753.41
TOTAL VARIOS 0 1814.2
TOTAL PROYECTO 12730.51 237755.09
TOTAL GENERAL 12730.51 237755.09
Total 2019 Total general
Junio

0 1004.5 1004.5
0 836.01 836.01
0 1568 1568
0 10584 10584
0 13992.51 13992.51
0 918 918
0 501.5 501.5
0 1190 1190
0 702 702
0 3311.5 3311.5
0 11880 11880
0 16492.04 16492.04
0 40154.85 40154.85
19891.75 28416.79 28416.79
3448.93 10346.78 10346.78
15505.43 15505.43 15505.43
38846.11 122795.89 122795.89
0 71685.77 71685.77
0 75731.84 75731.84
48309.24 48309.24 48309.24
48309.24 195726.85 195726.85
0 754.8 754.8
0 295.3 295.3
21.39 32.08 32.08
0 753.41 753.41
21.39 1835.59 1835.59
87176.74 337662.34 337662.34
87176.74 337662.34 337662.34