Está en la página 1de 5

FORMATO 1

Hoja N°…..……..de….………
PLANILLA DE METRADOS
OBRA : _____________________________________________________________________
PARTIDA : UNIDAD : __________
CODIGO : ____________________________________________________________________
PROPIETARIO : _________________________________ HECHO POR: _________________

FECHA : ____________________________

MEDIDAS
N° DESCRIPCION UNIDAD CANTIDAD LARGO ANCHO ALTURA PARCIAL TOTAL

EXCAVACION:

CIMIENTO CORRIDO CC-1 EJE A-A m3 2 1.7 0.6 1.3 2.652

ZAPATA Z-1 EJE A-2 m3 1 1.8 2.1 1.70 6.426

V.Total 9.078

CONCRETO CICLOPEO

CC-1 EJE A-A m3 2 1.7 0.6 0.5000 1.020

V.Total 1.02

CONCRETO
SOBRECIMIENTO EJE A-A m3 2 1.7 0.25 0.4 0.34

ZAPATA Z-1 EJE A-2 m3 1 2.1 1.8 0.5 1.89

PLACA P-2 EJE A-2 m3

1 1.2 0.2 4.7 1.128

1 0.25 0.25 4.7 0.29375

VIGA VC-1 EJE A-A m3 2 0.25 0.5 3.5 0.875

V.Total 4.52675

ENCOFRADO

SOBRECIMIENTO EJE A-A m2 4 1.7 0.4 2.720

ZAPATA Z-1 EJE A-2 m2

EJE VERTICAL 2 1.8 0.5 1.800

EJE HORIZONTAL 2 1.8 0.5 1.800

PLACA P-2 EJE A-2 m2

1 1.2 4.7 5.640

2 0.2 4.7 1.880

2 0.475 4.7 4.465

2 0.25 4.7 2.350

1 0.25 4.7 1.175

VIGA VC-1 EJE A-A m2

EJE VERTICAL 2 0.5 3.5 3.500

EJE HORIZONTAL 2 0.25 3.5 1.750

V.Total 27.08

RELLENO DE EXCAVACION

CC-1 EJE A-A m3 2 1.7 0.35 0.7 0.833

ZAPATA Z-1 EJE A-2 m3 1 2.1 1.8 0.7 2.646

V.Total 3.48

OBSERVACIONES: _____________________________________________________________
____________________________________________________________________________________
FORMATO 2
Hoja N°…..……..de….…
PLANILLA DE METRADOS
OBRA : _________________________________________________________________________________________________________________
PARTIDA : UNIDAD : KG CODIGO :________________________
PROPIETARIO : ___________________________________________________________________________________ HECHO POR: ________________
FECHA : ____________________________

N° LONGITUD ACERO DE REFUERZO


LONGITUD
LONGITUD PIEZAS N° DE DIAMETRO PARCIAL
DESCRIPCION DEL ELEMENTO UNITARIA POR ELEMENT 4.7 6 mm 8 mm 3/8" 12 mm 1/2" 5/8" 3/4" 1"
(m) ELEMEN IGUALES
N° TO Ø (m) 0.1362 0.22 0.395 0.56 0.888 0.994 1.552 2.235 3.973

ACERO ZAPATA Z-1


Eje A-2 Horizontal 1.66 12 1 1/2" 19.92 19.92
Eje A-2 Vertical 1.96 10 1 1/2" 19.6 19.6

ACERO PLACA P-1


ACERO DE 3/4" 4.9 10 1 3/4" 49 49
ACERO DE 5/8" 4.9 4 1 5/8" 19.6 19.6
ACERO DE 1/2" 4.9 2 1 1/2" 9.8 9.8
ESTRIBOS 4.867 21 1 3/8" 102.21 102.2

VIGA DE CIMENTACION VC-1

ACERO DE 1/2" 4 6 2 1/2" 48 48


ACERO DE 3/8" 4 2 2 3/8" 16 16
ESTRIBOS 1.21 17 2 3/8" 41.14 41.14
SUMA TOTAL (m) x Ø 0 0 159 0 77.4 19.60 49.00
(En Metros)
OBSERVACIONES: ___________________________________________________________________________________________________________________

___________________________________________________________________________________________________________________________________________________
Hoja N°…..……..de….………

____________________________
_________________

METRADO N° DE VARILLAS
PARCIAL

(Kg) (Unidad)

19.80 3
19.48 3

109.52 6
30.42 10
9.74 2
57.23 24

47.71 6
8.96 2
23.04 5
306.10 58.00
(En Kg) (En Unidad)
_________________________________________________________________________