PRESUPUESTO N° 01

ESPECIALDAD ESTRUCTURAS
Obra AGENCIA VENTANILLA
Lugar Ventanilla - Callao - Lima Costo al 30-May-05 Metrados Avance Valorizacion
Item Descripción Und Metrado Precio S/. Parcial S/. VAL 1 VAL 2 VAL 3
1.00 OBRAS PROVISIONALES
1.01 CASETA DE OBRA m2 18.00 80.76 1,453.68 18.00 0.00 0.00
1.02 CERCO DE OBRA h=2.20 m. m 24.00 21.68 520.32 24.00 0.00 0.00
1.03 TRAZO Y REPLANTEO m2 400.00 2.24 896.00 400.00 0.00 0.00
1.04 LIMPIEZA PERMANENTE DE OBRA mes 4.00 200.00 800.00 1.00 2.00 1.00
1.05 CARTEL DE OBRA m2 2.88 120.96 348.36 2.88 0.00 0.00
1.06 SERVICIOS HIGIENICOS PORTATILES (2 UNIDADES) mes 4.00 820.00 3,280.00 1.00 3.00 0.00
2.00 OBRAS PRELIMINARES
2.01 DEMOLICIONES
2.01.1DEMOLICIONES DE PISO INC/ FALSO PISO m2 62.00 9.74 603.88 58.90 3.10 0.00
2.01.2DEMOLICIONES DE PISOS Y CONTRAPISOS m2 265.41 7.22 1,916.26 252.14 13.27 0.00
2.01.3DEMOLICION DE MUROS DE LADRILLO K.K. CABEZA m2 6.07 19.64 119.21 5.77 0.30 0.00
2.01.4DEMOLICION DE MUROS DE LADRILLO K.K. SOGA m2 166.28 14.73 2,449.30 157.97 8.31 0.00
2.01.5DEMOLICIONES DE LOSA ALIGERADA h=20 MANUAL m2 147.37 10.10 1,488.44 140.00 7.37 0.00
2.01.6DEMOLICION DE CONCRETO ARMADO MANUAL m3 0.72 353.47 254.50 0.68 0.04 0.00
2.02 DESMONTAJES
2.02.1DESMONTAJE DE PUERTA DE MADERA m2 18.45 11.53 212.73 18.45 0.00 0.00
2.02.2DESMONTAJE VENTANA DE ALUMINIIO m2 2.97 13.98 41.52 2.97 0.00 0.00
2.02.3DESMONTAJE REJA DE FIERRO m2 3.66 7.49 27.41 3.66 0.00 0.00
2.02.4DESMONTAJE DE APARATOS SANITARIOS und 6.00 14.55 87.30 6.00 0.00 0.00
2.02.5DESMONTAJE DE AVISOS LUMINOSO m2 5.70 12.30 70.11 5.70 0.00 0.00
2.02.6DESMONTAJE DE MAMPARA DE VIDRIO m2 44.64 15.08 673.17 44.64 0.00 0.00
2.02.7DESMONTAJE DE MOBILIARIO TOT 1.00 279.47 279.47 1.00 0.00 0.00
2.02.8DESMONTAJE TABIQUES m2 3.78 9.04 34.17 3.78 0.00 0.00
2.02.9DESMONTAJE DE TECHOS DE FIBRABLOCK m2 7.32 12.61 92.31 6.95 0.37 0.00
DESMONTAJE DE INSTALACIONES ELECTRICAS, SANITARIAS, Y
2.02.1MECANICAS EXISTENTES
GLB 3.00 368.93 1,106.79 2.85 0.15 0.00
2.03 PICADOS
PICADO DE DE CONCRETO PARA EL ANCLAJE DE COLUMNAS,
2.03.1VIGAS Y REFUERZO TOT 1.00 433.42 433.42 0.95 0.05 0.00
PICADO DE ESTRUCTURA EXISTENTE PARA INSTALACIONES
2.03.2SANITARIAS TOT 1.00 263.34 263.34 0.95 0.05 0.00
PICADO DE ESTRUCTURA EXISTENTE PARA INSTALACIONES
2.03.3ELECTRICAS TOT 1.00 718.20 718.20 0.95 0.05 0.00
PICADO DE ESTRUCTURA EXISTENTE PARA INSTALACIONES
2.03.4MECANICAS TOT 1.00 399.00 399.00 0.95 0.05 0.00
2.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y HERRAMIENTAS
2.04.1MOVILIZACION Y DESMOVILIZACION DE EQUIPOS GLB 1.00 2,198.24 2,198.24 0.50 0.50 0.00
3.00 MOVIMIENTO DE TIERRAS
3.01 CORTES Y EXCAVACIONES
3.01.1EXCAVACIÓN MANUAL TERRENO NATURAL m3 162.99 28.89 4,708.78 154.84 8.15 0.00
3.02 RELLENOS
3.02.1RELLENO COMPACTADO CON MATERIAL PROPIO m3 4.34 10.52 45.66 4.12 0.22 0.00
3.03 ELIMINACION
3.03.1ELIMINACION DE MATERIAL, CARGUIO MANUAL/ VOLQUETE DE 6m m3 329.75 48.19 15,890.65 115.41 148.39 65.95
4.00 OBRAS DE CONCRETO SIMPLE
4.01 CIMIENTOS
4.01.1CONCRETO f´c= 100 Kg/cm2+30% P.G., PARA CIMIENTO CORRIDO m3 0.80 133.87 107.10 0.76 0.04 0.00
4.02 SOBRECIMIENTOS
4.02.1CONCRETO 1:6 + 25% P.M., PARA SOBRECIMIENTOS m3 0.29 185.71 53.86 0.22 0.07 0.00
PRESUPUESTO N° 01
ESPECIALDAD ESTRUCTURAS
Obra AGENCIA VENTANILLA
Lugar Ventanilla - Callao - Lima Costo al 30-May-05 Metrados Avance Valorizacion
Item Descripción Und Metrado Precio S/. Parcial S/. VAL 1 VAL 2 VAL 3
4.02.2ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTO m2 3.84 23.44 90.01 2.88 0.96 0.00
4.03 FALSOPISO
4.03.1CONCRETO C:H; 1:6, e=4", PARA FALSOPISO m2 36.60 21.99 804.83 27.45 9.15 0.00
4.04.1 FALSOS CIMIENTOS
4.04.1CONCRETO 1:12 + 30% P.G, PARA FALSOS CIMIENTOS m3 17.90 144.82 2,592.28 17.01 0.90 0.00
5.00 OBRAS DE CONCRETO ARMADO
5.01 CIMIENTOS REFORZADOS
5.01.1CONCRETO EN CIMIENTOS REFORZADOS f´c=210 Kg/cm2 m3 13.05 227.12 2,963.92 9.79 3.26 0.00
5.01.2ACERO Fy=4200 Kg/cm2 kg 49.07 3.60 176.65 36.80 12.27 0.00
5.02 LOSAS DE CIMENTACION
5.02.1CONCRETO EN LOSAS DE CIMENTACION f´c=210 Kg/cm2 m3 1.18 253.89 299.59 0.89 0.30 -0.01
5.02.2ACERO Fy=4200 Kg/cm2 kg 28.28 3.60 101.81 21.21 7.07 0.00
5.03 TABIQUES Y PLACAS
5.03.1CONCRETO EN MUROS Y PLACAS f´c=210 Kg/cm2 m3 33.11 316.08 10,465.41 21.52 9.93 1.66
5.03.2ENCOFRADO Y DESENCOFRADO EN MUROS Y PLACAS m2 273.06 27.79 7,588.34 177.49 81.92 13.65
5.03.3ACERO Fy=4200 Kg/cm2 kg ###### 3.60 6,080.65 1,097.90 506.72 84.45
5.04 COLUMNAS
5.04.1CONCRETO EN COLUMNAS f´c=210 Kg/cm2 m3 9.76 316.16 3,085.72 3.42 6.34 0.00
5.04.2ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 91.74 39.70 3,642.08 32.11 59.63 0.00
5.04.3ACERO Fy=4200 Kg/cm2 kg ###### 3.60 6,943.46 675.06 1,253.68 0.00
5.05 VIGAS Y DINTELES
5.05.1CONCRETO DE VIGAS f´c=210 Kg/cm2 m3 31.22 282.12 8,807.79 0.00 26.54 4.68
5.05.2ENCOFRADO Y DESENCOFRADO EN VIGAS m2 280.64 39.79 11,166.67 0.00 238.54 42.10
5.05.3ACERO Fy=4200 Kg/cm2 kg ###### 3.60 13,247.93 0.00 3,127.98 552.00
5.06 LOSAS MACIZAS
5.06.1CONCRETO EN LOSA MACIZA f´c=210 kg/cm2 m3 0.67 282.13 189.03 0.00 0.64 0.03
5.06.2ENCOFRADO Y DESENCOFRADO CONCRETO EN LOSA MACIZA m2 1.38 34.93 48.20 0.00 1.31 0.07
5.06.3ACERO Fy=4200 Kg/cm2 kg 28.25 3.60 101.70 0.00 26.84 1.41
5.07 LOSAS ALIGERADAS
5.07.1CONCRETO LOSA ALIGERADA f´c=210 Kg/cm2 m3 5.56 272.33 1,514.15 0.00 5.56 0.00
5.07.2ENCOFRADO Y DESNCOFRADO CONCRETO LOSA ALIGERADA m2 46.35 23.82 1,104.06 0.00 46.35 0.00
5.07.3LADRILLO HUECO DE ARCILLA 15x30x30 und 387.00 1.39 537.93 0.00 387.00 0.00
5.07.4ACERO Fy=4200 Kg/cm2 kg 180.83 3.60 650.99 0.00 180.83 0.00
5.08 ESCALERAS
5.08.1CONCRETO EN ESCALERAS f´c=210 Kg/cm2 m3 3.22 384.18 1,237.06 0.00 3.22 0.00
5.08.2ENCOFRADO Y DESENCOFRADO EN ESCALERAS m2 26.60 54.69 1,454.75 0.00 26.60 0.00
5.08.3ACERO Fy=4200 Kg/cm2 kg 84.67 3.60 304.81 0.00 84.67 0.00
5.09 VARIOS
5.09.1ANCLAJE DE ACERO CON PEGAMENTO EPOXICO TOT 1.00 783.93 783.93 0.00 1.00 0.00
5.09.2APLICACION DE PEGAMENTO EPOXICO SOBRE SUPERFICIE DE COTOT 1.00 815.57 815.57 0.00 1.00 0.00
5.09.3RELLENO DE POLIESTILENO EXPANDIDO TOT 1.00 310.74 310.74 0.00 1.00 0.00
6.00 ESTRUCTURAS METALICAS
6.01 VIGA METALICA 75 X 200 X 4.5 MM m 7.87 277.27 2,182.11 1.18 5.12 1.57
6.02 VIGUETA VC-1 m m 73.56 89.65 6,594.65 11.03 47.81 14.71
6.03 VIGUETA VC-2 m m 39.71 82.85 3,289.97 5.96 25.81 7.94
6.04 VIGUETA VC-3 m m 6.96 82.38 573.36 1.04 4.52 1.39
6.05 ARMADURA 1 und 1.00 1,551.02 1,551.02 0.15 0.65 0.20
6.06 ARMADURA 2 und 1.00 859.13 859.13 0.15 0.65 0.20
PRESUPUESTO N° 01
ESPECIALDAD ESTRUCTURAS
Obra AGENCIA VENTANILLA
Lugar Ventanilla - Callao - Lima Costo al 30-May-05 Metrados Avance Valorizacion
Item Descripción Und Metrado Precio S/. Parcial S/. VAL 1 VAL 2 VAL 3
6.07 ARMADURA 3 und 1.00 995.61 995.61 0.15 0.65 0.20
6.08 ARMADURA 4 und 1.00 693.55 693.55 0.15 0.65 0.20
6.09 ARMADURA 5 und 1.00 766.97 766.97 0.15 0.65 0.20
6.10 ARMADURA 6 und 1.00 695.11 695.11 0.15 0.65 0.20
6.11 ARMADURA 7 und 1.00 1,098.36 1,098.36 0.15 0.65 0.20
6.12 ARRIOSTRE TIPICO DE VIGUETAS m 48.00 36.40 1,747.20 7.20 31.20 9.60
6.13 ARRIOSTRE TIPICO DE ARMADURAS m 44.00 47.03 2,069.32 6.60 28.60 8.80
6.14 ESCALERA METALICA und 1.00 6,891.29 6,891.29 0.15 0.65 0.20
6.15 MONTAJE DE ESTRUCTURAS METALICAS TOT 1.00 7,569.85 7,569.85 0.15 0.65 0.20
COSTO DIRECTO 166,260.74
Gastos Generales 10% 16,626.07
Utilidades 10% 16,626.07
Sub Total 199,512.88
I.G.V. 19% 37,907.45
TOTAL 237,420.33