OBRA "CONSTRUCCION DEL CENTRO DE INSTRUCCIÓN TECNICA COMUNIDAD CAMPESINA SEGUNDA ETAPA"

PROP. VOLCAN COMPAÑÍA MINERA S.A.A.


UBICACIÓN DISTRITO YAULI
PROVINCIA LA OROYA
DEPARTAMENTO JUNIN
SUPERVISION ING. RUBEN LARENAS
SUPERVISION ING. ROY CRUZ ARZAPALO S/.201,797.17+IGV
PRESUPUESTO CONTRATADO (INC. IGV)

INICIO
28-May 0.00%
4-Jun 3.00%
11-Jun 6.00%
18-Jun 9.00%
CURVA S
25-Jun 12.00%
2-Jul 16.00%
AVANCE PROGRAMADO

Avance P rogramado Avance Ej ecutado Avance Programado Avance Ej ecutado

% DE AVANCE ACUMULADO
9-Jul 22.00%
16-Jul 32.00%
120.00%
23-Jul 45.00%
30-Jul 57.00%
6-Aug 71.00%
13-Aug 85.00%
20-Aug 95.00% 100.00%
27-Aug 98.00% 100.00% 98.00%
4-Oct 100.00% 95.00%

85.00%

80.00%

71.00%

28-May 0.00%
4-Jun 3.42%
11-Jun 6.48% 60.00% 57.00%
18-Jun 12.28%
25-Jun 19.24%
2-Jul 19.30%
45.00%
9-Jul 19.30%
16-Jul 22.56%
AVANCE EJECUTADO

40.00%
23-Jul 26.63%
30-Jul 32.07% 32.00% 32.07%
6-Aug
26.63%
13-Aug
22.00% 22.56%
20-Aug
19.24% 19.30% 19.30%
27-Aug 20.00%
16.00%
4-Oct
12.00%
12.28%
6.00% 9.00%
6.48%
3.42%
3.00%
0.00%
96.94
0.00% 0.00%
5/28/2017

6/4/2017

6/18/2017

6/25/2017

7/2/2017

7/9/2017

7/30/2017

8/6/2017

8/13/2017

8/20/2017

8/27/2017

10/4/2017
6/11/2017

7/16/2017

7/23/2017
INICIO

PLAZO DE EJECUCION DE OBRA EN SEMANAS


FICHA TÉCNICA DE LA OBRA

1.00 OBRA "CONSTRUCCION DEL CENTRO DE INSTRUCCIÓN TECNICA COMUNIDAD CAMPESINA SEGUN

2.00 PROPIETARIO VOLCAN COMPAÑÍA MINERA S.A.A.

3.00 EJECUTA ECOSERMY

4.00 UBICACIÓN:

LUGAR CENTRO DE INSTRUCCIÓN TECNICA

DISTRITO YAULI

PROVINCIA LA OROYA

DEPARTAMENTO JUNIN

S/.201,797.17+IGV
5.00 PRESUPUESTO INC. IGV

6.00 PLAZO DE EJECUCION

7.00 INICIO OFICIAL DEL PLAZO

8.00 SUPERVISION VOLCAN ING. RUBEN LARENAS

9.00 SUPERVISION ECOSERMY ING. ROY CRUZ ARZAPALO


COMUNIDAD CAMPESINA SEGUNDA ETAPA"
#VALUE!
OBRA : "CONSTRUCCION DEL CENTRO DE INSTRUCCIÓN TECNICA COMUNIDAD CAMPESINA SEGUNDA ETAPA"
CLIENTE: VOLCAN COMPAÑÍA MINERA S.A.A.
UBICACIÓN: CENTRO DE INSTRUCCIÓN TECNICA
CONTRATISTA: ECOSERMY

CALENDARIO DE AVANCE DE OBRA VALORIZADO A LA FECHA DE INI


FEBRERO 2017 MARZO 2017
01/02 - 28/02 01/03 - 31/03
N° DESCRIPCION C. D. (S/.)
31 30
31 61

01 ESTRUCTURAS 117,280.98 16,240.13 22,112.73


02 ARQUITECTURA 283,116.79 14,561.52 20,258.79
03 INSTALACIONES SANITARIAS 23,329.37 0.00 0.00
04 INSTALACIONES ELECTRICAS 37,187.43 0.00 0.00

CD 460,914.57 30,801.65 42,371.52

TOTAL COSTO DIRECTO 460,914.57 30,801.65 42,371.52


GASTOS GENERALES 69,137.19 4,620.25 6,355.73
UTILIDAD 46,091.46 3,080.17 4,237.15
SUB TOTAL 576,143.21 38,502.06 52,964.40
IGV (18.00%) 103,705.78 6,930.37 9,533.59
TOTAL PRESUPUESTO 679,848.99 45,432.43 62,497.99

Feb-17 Mar-17
PORCENTAJE PARCIAL 6.68% 9.19%
PORCENTAJE ACUMULADO 6.68% 15.88%
ESINA SEGUNDA ETAPA"
PLAZO DE EJECUCION: 120
INICIO DE OBRA: 2/1/2017

LA FECHA DE INICIO DE OBRA


ABRIL 2017 MAYO 2017
01/04 - 30/04 01/05 - 31/05
TOTAL
31 30
92 122

27,985.28 50,942.84 117,280.98


248,296.48 0.00 283,116.79
3,161.80 20,167.57 23,329.37
25,794.19 11,393.24 37,187.43

305,237.75 82,503.65 460,914.57

305,237.75 82,503.65 460,914.57


45,785.66 12,375.55 69,137.19
30,523.78 8,250.37 46,091.46
381,547.19 103,129.56 576,143.21
68,678.49 18,563.32 103,705.77
450,225.68 121,692.88 679,848.98

Apr-17 May-17
66.22% 17.90%
82.10% 100.00%