CRONOGRAMA VALORADO INICIO 20-Jun-18 25-Jun-18 Monday-Jul9-2018 Monday-Jul23-2018 Monday-Aug6-2018 Monday-Aug20-2018 Monday-Sep3-2018 Monday-Sep17-2018 Monday-Oct1-2018 Monday-Oct15-2018 Monday-Oct29-2018 Monday-Nov12-2018 Monday-Nov26-2018
PROYECTO PLAZA TIA FIN 24-Jun-18 Sunday-Jul8-2018 Sunday-Jul22-2018 Sunday-Aug5-2018 Sunday-Aug19-2018 Sunday-Sep2-2018 Sunday-Sep16-2018 Sunday-Sep30-2018 Sunday-Oct14-2018 Sunday-Oct28-2018 Sunday-Nov11-2018 Sunday-Nov25-2018 Sunday-Dec9-2018
ITEM DESCRIPCION UNIDAD CANTIDAD PRECIO PRECIO TOTAL PESO QUINCENA 1 QUINCENA 2 QUINCENA 3 QUINCENA 4 QUINCENA 5 QUINCENA 6 QUINCENA 7 QUINCENA 8 QUINCENA 9 QUINCENA 10 QUINCENA 11 QUINCENA 12
UNITARIO
100 PRELIMINARES DE OBRA
101 Cerramiento del solar con Plancha de Zinc. H= 2,00 ml 520.00 $23.36 $12,147.20 0.51% 12,147.20
102 oficina de obra(direccion arquitectonica; fiscalizacion) m² 30.00 $100.44 $3,013.20 0.13% 903.96 1,205.28 903.96
103 bodega materiales,caseta guardian m² 60.00 $30.80 $1,848.00 0.08% 554.40 739.20 554.40
104 Letrero de obra de plancha de metal de 2x2 M2 4.00 $101.70 $406.80 0.02% 122.04 162.72 122.04
105 Instalaciones provisionales y consumo de energía elé mes 6.00 $157.02 $942.12 0.04% 78.51 78.51 78.51 78.51 78.51 78.51 78.51 78.51 78.51 78.51 78.51 78.51
106 Instalaciones provisionales y consumo de agua potab mes 6.00 $92.69 $556.14 0.02% 46.35 46.35 46.35 46.35 46.35 46.35 46.35 46.35 46.35 46.35 46.35 46.35
107 Alquiler de batería sanitaria para residentes mes 6.00 $396.31 $2,377.86 0.10% 198.16 198.16 198.16 198.16 198.16 198.16 198.16 198.16 198.16 198.16 198.16 198.16
108 Alquiler de batería sanitaria para trabajadores mes 6.00 $573.31 $3,439.86 0.14% 286.66 286.66 286.66 286.66 286.66 286.66 286.66 286.66 286.66 286.66 286.66 286.66
109 Guardias seguridad dia y noche( 1 de dìa - 1 en la no mes 6.00 $3,540.00 $21,240.00 0.89% 1,770.00 1,770.00 1,770.00 1,770.00 1,770.00 1,770.00 1,770.00 1,770.00 1,770.00 1,770.00 1,770.00 1,770.00
110 Limpieza general de la obra m² 13,703.55 $1.05 $14,388.73 0.60% 1,199.06 1,199.06 1,199.06 1,199.06 1,199.06 1,199.06 1,199.06 1,199.06 1,199.06 1,199.06 1,199.06 1,199.06
111 Replanteo y trazado control con Topografo por el tie M2/MES 13,703.55 $0.87 $11,922.09 0.50% 993.51 993.51 993.51 993.51 993.51 993.51 993.51 993.51 993.51 993.51 993.51 993.51
112 Relleno con material de sitio(Incluye planta de tratami m3 1,106.59 $8.66 $9,583.07 0.40% 2,874.92 3,833.23 2,874.92
113 Excavación para cimentación (Incluye planta de trat m³ 3,624.78 $8.51 $30,846.88 1.29% 9,254.06 12,338.75 9,254.06
114 Relleno compactado sub-base clase 1 e=20cm (patio m² 500.00 $6.88 $3,440.00 0.14% 1,032.00 1,376.00 1,032.00
115 Relleno compactado subase clase 1 e=15cm area pa m² 4,610.00 $5.30 $24,433.00 1.02% 7,329.90 9,773.20 7,329.90
SUB-TOTAL $140,584.94 5.88% 38,790.72 34,000.61 26,643.52 4,572.23 4,572.23 4,572.23 4,572.23 4,572.23 4,572.23 4,572.23 4,572.23 4,572.23
500 PARQUEOS
501 Adoquinado de hormigòn para àrea de parqueo de ar m² 4,610.00 $21.90 $100,959.00 4.22% 20,191.80 20,191.80 20,191.80 20,191.80 20,191.80
502 Adoquinado de parqueo patio de maniobras de alto tr m2 500.00 $32.00 $16,000.00 0.67% 5,333.33 5,333.33 5,333.33
503 Topes de parqueo de hormigón L = 2,20 ml 300.00 $20.86 $6,258.00 0.26% 2,086.00 2,086.00 2,086.00
SUB-TOTAL $123,217.00 5.16% - - - - - - 20,191.80 27,611.13 27,611.13 27,611.13 20,191.80 -
700 SUPERESTRUCTURA
701 Hormigón de losa de Cubierta e=10ms, inc. Estructur m² 522.04 $50.39 $26,305.60 1.10% 13,152.80 13,152.80
702 Hormigón para relleno de columnas metálicas f'c=210 m³ 60.00 $214.41 $12,864.60 0.54% 3,859.38 3,859.38 3,859.38 1,286.46
SUB-TOTAL $39,170.20 1.64% - - 3,859.38 3,859.38 3,859.38 14,439.26 13,152.80 - - - - -
1000 CUBIERTA
1001 Canalón metálico galvanizado2000X,65 Con pintura b ml 361.89 $30.05 $10,874.79 0.46% 2,174.96 4,349.92 3,262.44 1,087.48
1002 Malla electroosoldada 7 c/ 15 pintada con anticorrosi m2 1,368.32 $12.39 $16,953.48 0.71% 3,390.70 6,781.39 5,086.05 1,695.35
1003 Chova al caliente ml 295.00 $10.62 $3,132.90 0.13% 1,566.45 1,566.45
SUB-TOTAL $30,961.18 1.30% - - - - - 5,565.66 11,131.31 9,914.93 4,349.28 - - -
1100 ALBAÑILERÍAS
MAMPOSTERIAS Y ESTRUCTURAS MENORES
1101 Contrapiso de h. simple en áreas comunes y locales c m² 2,611.77 $20.13 $52,574.93 2.20% 10,514.99 21,029.97 15,772.48 5,257.49
1102 Contrapiso con malla 5.5c/15 para instalar baldosa T m² 1,368.32 $24.52 $33,551.21 1.40% 6,710.24 13,420.48 10,065.36 3,355.12
1103 Mampostería de bloque de hormigón (9x19x39cm) ma m² 810.00 $21.25 $17,212.50 0.72% 2,065.50 3,442.50 3,786.75 3,098.25 2,581.88 2,237.63
1104 Mampostería de bloque de hormigón (14x19x39cm) m m² 5,195.54 $23.60 $122,614.74 5.13% 14,713.77 24,522.95 26,975.24 22,070.65 18,392.21 15,939.92
1105 Pilaretes y viguetas de H.A. (10x20cm) incluye filos ml 382.52 $14.84 $5,676.60 0.24% 681.19 1,135.32 1,248.85 1,021.79 851.49 737.96
1106 Pilaretes y viguetas de H.A. (15x20cm) incluye filos ml 812.40 $16.45 $13,363.98 0.56% 1,603.68 2,672.80 2,940.08 2,405.52 2,004.60 1,737.32
1107 Losetas de mesones de cocina y baños (a=60cm) inc ml 21.90 $21.96 $480.92 0.02% 240.46 240.46
1108 Pulida de pisos con chadur cuarto de máquinas y cua m2 142.88 $9.96 $1,423.08 0.06% 711.54 711.54
1109 Cerramiento exterior (linderos) mamposteria de hormi m2 660.30 $39.79 $26,273.34 1.10% 5,254.67 10,509.33 7,882.00 2,627.33
SUB-TOTAL $273,171.30 11.43% - - 3,669.18 21,510.26 32,385.09 50,953.09 67,384.04 60,517.82 34,124.49 2,627.33 - -
1300 ACABADOS
RECUBRIMIENTOS PISOS Y PAREDES
1301 Suministro de porcelanato antideslizante en piso de a m² 837.72 $34.18 $28,633.27 1.20% 5,726.65 11,453.31 8,589.98 2,863.33
1302 Suministro e instalación de porcelanato rugoso en pi m2 848.59 $34.18 $29,004.81 1.21% 5,800.96 11,601.92 8,701.44 2,900.48
1303 Suministro e instalación de porcelanato antideslizante m² 86.40 $39.85 $3,443.04 0.14% 1,721.52 1,721.52
1304 Suministro e instalación de porcelanato brillannte en m² 216.02 $38.01 $8,210.92 0.34% 1,642.18 3,284.37 2,463.28 821.09
1305 Suministro e instalación de rastreras (H=15cm) pared ml 207.40 $8.25 $1,711.05 0.07% 342.21 684.42 513.32 171.11
1306 Suministro e instalación de rastreras (H=30cm) pared ml 40.85 $15.14 $618.47 0.03% 309.23 309.23
1307 Espacato muro de cerramiento m2 181.64 $37.70 $6,847.83 0.29% 3,423.91 2,396.74 1,027.17
SUB-TOTAL $78,469.38 3.28% - - - - - - - 13,512.01 30,447.93 24,695.51 9,813.93 -
1900 TUMBADO
1901 Tumbado de Gypsum interior normal incluye pintura m² 831.23 $17.22 $14,313.78 0.60% 7,156.89 5,009.82 2,147.07
1902 Tumbado de Gypsum antihumedad incluye pintura m² 360.00 $19.10 $6,876.00 0.29% 3,438.00 2,406.60 1,031.40
1903 Flashing de Tool parte superior de fronton ml 87.07 $15.85 $1,380.06 0.06% 690.03 483.02 207.01
SUB-TOTAL $22,569.84 0.94% - - - - - - - 11,284.92 7,899.44 3,385.48 - -
2000 VARIOS
2001 Mesones de granito ml 20.80 $157.93 $3,284.94 0.14% 1,642.47 1,149.73 492.74
2002 Escalera tipo caracol terminada e instalada para la ad u 1.00 $1,711.00 $1,711.00 0.07% 855.50 598.85 256.65
2003 Bolardos U 71.00 $98.77 $7,012.67 0.29% 3,506.34 2,454.43 1,051.90
2005 Cubierta de steel panel-Estaciòn de bombeo m2 23.20 $35.26 $818.03 0.03% 409.02 286.31 122.70
2006 Resanes del Sistema Electrico y electronico Aire aco 1.00 $4,994.94 $4,994.94 0.21% 998.99 1,997.98 1,498.48 249.75 249.75
SUB-TOTAL $17,821.59 0.75% - - - - - - 7,412.31 6,487.30 3,422.48 249.75 249.75 -
3000 IMPERMEABILIZACIONES
3001 Impermeabilizacion losas de equipos de AACC-medi m2 876.70 $20.65 $18,103.86 0.76% 9,051.93 6,336.35 2,715.58
SUB-TOTAL $18,103.86 0.76% - - - - - - - 9,051.93 6,336.35 2,715.58 - -
TOTAL OBRA CIVIL $1,949,724.94 81.58% 73,700.89 111,769.83 130,940.78 136,449.99 172,174.71 197,144.89 232,528.35 266,543.87 256,725.62 209,816.78 135,885.70 26,043.44
2301 Planta de Tratamiento - Instalaccion de equipo y pue glb 1.00 $63,475.23 $63,475.23 2.66% 19,042.57 25,390.09 19,042.57
2302 CANASTILLA de acero inoxidable para retencion de s glb 1.00 $2,621.58 $2,621.58 0.11% 786.47 1,048.63 786.47
2303 Estaciòn de bombeo- 2 bombas sumergibles AAS S,i u 2.00 $4,507.01 $9,014.02 0.38% 1,081.68 1,802.80 1,712.66 1,622.52 1,261.96 1,081.68 450.70
SUB-TOTAL $75,110.83 3.14% - 1,081.68 1,802.80 1,712.66 1,622.52 1,261.96 1,081.68 450.70 19,829.04 26,438.72 19,829.04 -
-
2400 SISTEMA DE AGUAS GRASAS
2401 Tub. AASS Pvc D/N D = 110mm + Accesorios m 96.00 $10.64 $1,021.44 0.04% 204.29 255.36 306.43 255.36
2402 Tub. AASS Pvc D/N D = 75mm + Accesorios m 96.00 $9.09 $872.64 0.04% 174.53 218.16 261.79 218.16
2403 Puntos de aguas grasas D=75mm u 17.00 $22.69 $385.73 0.02% 77.15 96.43 115.72 96.43
2405 Trampas de grasa de H.A u 3.00 $4,188.49 $12,565.47 0.53% 2,513.09 3,141.37 3,769.64 3,141.37
2406 Soporte de tuberia U 20.00 $8.50 $170.00 0.01% 34.00 42.50 51.00 42.50
2407 Excavacion para tuberia m3 26.00 $5.25 $136.50 0.01% 27.30 34.13 40.95 34.13
2408 Arena para tuberia m3 12.56 $18.69 $234.75 0.01% 70.42 93.90 70.42
2409 relleno con material de sitio m3 19.86 $8.01 $159.08 0.01% 47.72 63.63 47.72
2410 Desalojo del material sobrante m3 17.45 $4.58 $79.92 0.00% 23.98 31.97 23.98
2411 Caja de registro de aguas grasas u 14.00 $235.99 $3,303.86 0.14% 991.16 1,321.54 991.16
SUB-TOTAL $18,929.39 0.79% - - - - 1,133.28 4,541.40 4,921.23 4,545.53 3,787.95 - - -
-
2500 SISTEMA DE AGUAS LLUVIAS
2501 Tub. Estructural doble pared Novafort D=640mm + A m 86.15 $153.56 $13,229.19 0.55% 1,587.50 2,645.84 2,513.55 2,381.25 1,852.09 1,587.50 661.46
2502 Tub. Estructural doble pared Novafort D=550mm + A m 80.00 $113.52 $9,081.60 0.38% 1,089.79 1,816.32 1,725.50 1,634.69 1,271.42 1,089.79 454.08
2503 Tub. Estructural doble pared Novafort D=440mm + A m 198.00 $73.70 $14,592.60 0.61% 1,751.11 2,918.52 2,772.59 2,626.67 2,042.96 1,751.11 729.63
2504 Tub. Estructural doble pared Novafort D=400mm + A m 12.00 $67.10 $805.20 0.03% 96.62 161.04 152.99 144.94 112.73 96.62 40.26
2505 Tub. Estructural doble pared Novafort D=335mm + A m 60.00 $44.94 $2,696.40 0.11% 323.57 539.28 512.32 485.35 377.50 323.57 134.82
2506 Tub. Estructural doble pared Novafort D=250mm + A m 84.00 $31.47 $2,643.48 0.11% 317.22 528.70 502.26 475.83 370.09 317.22 132.17
2507 Tub. Estructural doble pared Novafort D=200mm + A m 30.00 $25.84 $775.20 0.03% 93.02 155.04 147.29 139.54 108.53 93.02 38.76
2508 Tub.AALL Pvc D/N D = 160mm + Accesorios m 324.00 $22.08 $7,153.92 0.30% 858.47 1,430.78 1,359.24 1,287.71 1,001.55 858.47 357.70
2512 Puntos de AALL DE 160 mm m 26.00 $33.42 $868.92 0.04% 104.27 173.78 165.09 156.41 121.65 104.27 43.45
2513 Puntos de AALL DE 110 mm U 19.00 $27.01 $513.19 0.02% 61.58 102.64 97.51 92.37 71.85 61.58 25.66
2514 Tub.AALL Pvc D/N D = 160mm + Accesorios ml 124.00 $10.64 $1,319.36 0.06% 158.32 263.87 250.68 237.48 184.71 158.32 65.97
2515 Rejilla Tipo CC 200X150mm(aluminio) u 26.00 $71.12 $1,849.12 0.08% 221.89 369.82 351.33 332.84 258.88 221.89 92.46
2516 Rejilla Tipo CC 150X110mm(aluminio) u 119.00 $51.45 $6,122.55 0.26% 734.71 1,224.51 1,163.28 1,102.06 857.16 734.71 306.13
2517 Sumidero simple con rejilla u 5.00 $557.60 $2,788.00 0.12% 334.56 557.60 529.72 501.84 390.32 334.56 139.40
2518 Camara de agua lluvia tipo 1 u 8.00 $1,923.76 $15,390.08 0.64% 1,846.81 3,078.02 2,924.12 2,770.21 2,154.61 1,846.81 769.50
2519 Soporte de tuberia U 148.00 $8.50 $1,258.00 0.05% 150.96 251.60 239.02 226.44 176.12 150.96 62.90
2520 Excavacion de tuberias m3 465.00 $5.25 $2,441.25 0.10% 610.31 854.44 634.73 341.78
2521 Arena para tuberia m3 142.00 $18.69 $2,653.98 0.11% 663.50 928.89 690.03 371.56
2522 relleno con material de sitio m3 215.63 $8.01 $1,727.20 0.07% 431.80 604.52 449.07 241.81
2523 Desalojo de Material m3 375.26 $4.58 $1,718.69 0.07% 429.67 601.54 446.86 240.62
SUB-TOTAL $89,627.93 3.75% - - 11,865.70 19,206.75 17,627.19 15,791.38 11,352.15 9,730.42 4,054.34 - - -
TOTAL INSTALACIONES $440,275.06 18.42% - 22,181.29 44,672.69 40,502.88 32,268.09 33,591.64 32,931.63 39,373.75 68,359.37 68,738.21 55,455.94 2,199.57
GRAN TOTAL OBRA CIVIL MAS INSTALACIONES SIN IVA $2,390,000.00 100.00% 73,700.89 133,951.12 175,613.47 176,952.87 204,442.80 230,736.53 265,459.98 305,917.62 325,084.99 278,554.99 191,341.64 28,243.01
INVERSION QUINCENAL PROGRAMADA $73,700.89 $133,951.12 $175,613.47 $176,952.87 $204,442.80 $230,736.53 $265,459.98 $305,917.62 $325,084.99 $278,554.99 $191,341.64 $28,243.01
AVANCE QUINCENAL PROGRAMADO 3.08% 5.60% 7.35% 7.40% 8.55% 9.65% 11.11% 12.80% 13.60% 11.66% 8.01% 1.18%
INVERSION ACUMULADA PROGRAMADA $73,700.89 $207,652.01 $383,265.48 $560,218.35 $764,661.14 $995,397.67 $1,260,857.65 $1,566,775.27 $1,891,860.26 $2,170,415.25 $2,361,756.89 $2,390,000.00
AVANCE ACUMULADO PROGRAMADO 3.08% 8.69% 16.04% 23.44% 31.99% 41.65% 52.76% 65.56% 79.16% 90.81% 98.82% 100.00%
______________________________
______________________________ Representante Legal de
Representante Legal de TIA Furoiani Obras y Proyectos S.A.
CRONOGRAMA VALORADO INICIO Monday-Jun4-2018 Monday-Jun18-2018 Monday-Jul2-2018 Monday-Jul16-2018 Monday-Jul30-2018 Monday-Aug13-2018 Monday-Aug27-2018 Monday-Sep10-2018 Monday-Sep24-2018 Monday-Oct8-2018 Monday-Oct22-2018 Monday-Nov5-2018
PROYECTO PLAZA TIA FIN Sunday-Jun17-2018 Sunday-Jul1-2018 Sunday-Jul15-2018 Sunday-Jul29-2018 Sunday-Aug12-2018 Sunday-Aug26-2018 Sunday-Sep9-2018 Sunday-Sep23-2018 Sunday-Oct7-2018 Sunday-Oct21-2018 Sunday-Nov4-2018 Sunday-Nov18-2018
PRECIO
ITEM DESCRIPCION UNIDAD CANTIDAD UNITARIO PRECIO TOTAL PESO QUINCENA 1 QUINCENA 2 QUINCENA 3 QUINCENA 4 QUINCENA 5 QUINCENA 6 QUINCENA 7 QUINCENA 8 QUINCENA 9 QUINCENA 10 QUINCENA 11 QUINCENA 12
100 PRELIMINARES DE OBRA
101 Cerramiento del solar con Plancha de Zinc. H= 2,00 ml 520.00 $23.36 $12,147.20 0.51%
102 oficina de obra(direccion arquitectonica; fiscalizacion) m² 30.00 $100.44 $3,013.20 0.13%
103 bodega materiales,caseta guardian m² 60.00 $30.80 $1,848.00 0.08%
104 Letrero de obra de plancha de metal de 2x2 M2 4.00 $101.70 $406.80 0.02%
105 Instalaciones provisionales y consumo de energía eléctrica mes 6.00 $157.02 $942.12 0.04%
106 Instalaciones provisionales y consumo de agua potable mes 6.00 $92.69 $556.14 0.02%
107 Alquiler de batería sanitaria para residentes mes 6.00 $396.31 $2,377.86 0.10%
108 Alquiler de batería sanitaria para trabajadores mes 6.00 $573.31 $3,439.86 0.14%
109 Guardias seguridad dia y noche( 1 de dìa - 1 en la noche) mes 6.00 $3,540.00 $21,240.00 0.89%
110 Limpieza general de la obra m² 13,703.55 $1.05 $14,388.73 0.60%
111 Replanteo y trazado control con Topografo por el tiempo de la obra 13,703.55 $0.87 $11,922.09 0.50%
112 Relleno con material de sitio(Incluye planta de tratamiento y Est. De bombeo m3 1,106.59 $8.66 $9,583.07 0.40%
113 Excavación para cimentación (Incluye planta de tratamiento y Est. Bombeo) m³ 3,624.78 $8.51 $30,846.88 1.29%
115 Relleno compactado subase clase 1 e=15cm area parqueo donde van adoquines m² 4,610.00 $5.30 $24,433.00 1.02%
500 PARQUEOS
501 Adoquinado de hormigòn para àrea de parqueo de ar m² 4,610.00 $21.90 $100,959.00 4.22%
502 Adoquinado de parqueo patio de maniobras de alto tr m2 500.00 $32.00 $16,000.00 0.67%
503 Topes de parqueo de hormigón L = 2,20 ml 300.00 $20.86 $6,258.00 0.26%
SUB-TOTAL $123,217.00 5.16%
700 SUPERESTRUCTURA
701 Hormigón de losa de Cubierta e=10ms, inc. Estructur m² 522.04 $50.39 $26,305.60 1.10%
702 Hormigón para relleno de columnas metálicas f'c=210 m³ 60.00 $214.41 $12,864.60 0.54%
SUB-TOTAL $39,170.20 1.64%
1000 CUBIERTA
1001 Canalón metálico galvanizado2000X,65 Con pintura b ml 361.89 $30.05 $10,874.79 0.46%
1002 Malla electroosoldada 7 c/ 15 pintada con anticorrosi m2 1,368.32 $12.39 $16,953.48 0.71%
1003 Chova al caliente ml 295.00 $10.62 $3,132.90 0.13%
SUB-TOTAL $30,961.18 1.30%
1100 ALBAÑILERÍAS
MAMPOSTERIAS Y ESTRUCTURAS MENORES
1101 Contrapiso de h. simple en áreas comunes y locales c m² 2,611.77 $20.13 $52,574.93 2.20%
1102 Contrapiso con malla 5.5c/15 para instalar baldosa T m² 1,368.32 $24.52 $33,551.21 1.40%
1103 Mampostería de bloque de hormigón (9x19x39cm) ma m² 810.00 $21.25 $17,212.50 0.72%
1104 Mampostería de bloque de hormigón (14x19x39cm) m m² 5,195.54 $23.60 $122,614.74 5.13%
1105 Pilaretes y viguetas de H.A. (10x20cm) incluye filos ml 382.52 $14.84 $5,676.60 0.24%
1106 Pilaretes y viguetas de H.A. (15x20cm) incluye filos ml 812.40 $16.45 $13,363.98 0.56%
1107 Losetas de mesones de cocina y baños (a=60cm) inc ml 21.90 $21.96 $480.92 0.02%
1108 Pulida de pisos con chadur cuarto de máquinas y cua m2 142.88 $9.96 $1,423.08 0.06%
1109 Cerramiento exterior (linderos) mamposteria de hormi m2 660.30 $39.79 $26,273.34 1.10%
SUB-TOTAL $273,171.30 11.43%
1300 ACABADOS
RECUBRIMIENTOS PISOS Y PAREDES
1301 Suministro de porcelanato antideslizante en piso de a m² 837.72 $34.18 $28,633.27 1.20%
1302 Suministro e instalación de porcelanato rugoso en pi m2 848.59 $34.18 $29,004.81 1.21%
1303 Suministro e instalación de porcelanato antideslizante m² 86.40 $39.85 $3,443.04 0.14%
1304 Suministro e instalación de porcelanato brillannte en m² 216.02 $38.01 $8,210.92 0.34%
1305 Suministro e instalación de rastreras (H=15cm) pared ml 207.40 $8.25 $1,711.05 0.07%
1306 Suministro e instalación de rastreras (H=30cm) pared ml 40.85 $15.14 $618.47 0.03%
1307 Espacato muro de cerramiento m2 181.64 $37.70 $6,847.83 0.29%
SUB-TOTAL $78,469.38 3.28%
PRECIO
ITEM DESCRIPCION UNIDAD CANTIDAD UNITARIO PRECIO TOTAL PESO QUINCENA 1 QUINCENA 2 QUINCENA 3 QUINCENA 4 QUINCENA 5 QUINCENA 6 QUINCENA 7 QUINCENA 8 QUINCENA 9 QUINCENA 10 QUINCENA 11 QUINCENA 12
1400 CARPINTERIA DE MADERA
1401 Puerta P1 (1.00x2.10) u. 6.00 $526.20 $3,157.20 0.13%
1402 Puerta P3 (0.70x2.00) u. 41.00 $480.15 $19,686.15 0.82%
SUB-TOTAL $22,843.35 0.96%
1900 TUMBADO
1901 Tumbado de Gypsum interior normal incluye pintura m² 831.23 $17.22 $14,313.78 0.60%
1902 Tumbado de Gypsum antihumedad incluye pintura m² 360.00 $19.10 $6,876.00 0.29%
1903 Flashing de Tool parte superior de fronton ml 87.07 $15.85 $1,380.06 0.06%
SUB-TOTAL $22,569.84 0.94%
2000 VARIOS
2001 Mesones de granito ml 20.80 $157.93 $3,284.94 0.14%
2002 Escalera tipo caracol terminada e instalada para la ad u 1.00 $1,711.00 $1,711.00 0.07%
2003 Bolardos U 71.00 $98.77 $7,012.67 0.29%
2005 Cubierta de steel panel-Estaciòn de bombeo m2 23.20 $35.26 $818.03 0.03%
2006 Resanes del Sistema Electrico y electronico Aire aco 1.00 $4,994.94 $4,994.94 0.21%
SUB-TOTAL $17,821.59 0.75%
3000 IMPERMEABILIZACIONES
3001 Impermeabilizacion losas de equipos de AACC-medi m2 876.70 $20.65 $18,103.86 0.76%
SUB-TOTAL $18,103.86 0.76%
2301 Planta de Tratamiento - Instalaccion de equipo y pue glb 1.00 $63,475.23 $63,475.23 2.66%
2302 CANASTILLA de acero inoxidable para retencion de s glb 1.00 $2,621.58 $2,621.58 0.11%
2303 Estaciòn de bombeo- 2 bombas sumergibles AAS S,i u 2.00 $4,507.01 $9,014.02 0.38%
SUB-TOTAL $75,110.83 3.14%
-
2400 SISTEMA DE AGUAS GRASAS
2401 Tub. AASS Pvc D/N D = 110mm + Accesorios m 96.00 $10.64 $1,021.44 0.04%
2402 Tub. AASS Pvc D/N D = 75mm + Accesorios m 96.00 $9.09 $872.64 0.04%
2403 Puntos de aguas grasas D=75mm u 17.00 $22.69 $385.73 0.02%
2405 Trampas de grasa de H.A u 3.00 $4,188.49 $12,565.47 0.53%
2406 Soporte de tuberia U 20.00 $8.50 $170.00 0.01%
2407 Excavacion para tuberia m3 26.00 $5.25 $136.50 0.01%
2408 Arena para tuberia m3 12.56 $18.69 $234.75 0.01%
2409 relleno con material de sitio m3 19.86 $8.01 $159.08 0.01%
2410 Desalojo del material sobrante m3 17.45 $4.58 $79.92 0.00%
2411 Caja de registro de aguas grasas u 14.00 $235.99 $3,303.86 0.14%
SUB-TOTAL $18,929.39 0.79%
-
2500 SISTEMA DE AGUAS LLUVIAS
2501 Tub. Estructural doble pared Novafort D=640mm + A m 86.15 $153.56 $13,229.19 0.55%
2502 Tub. Estructural doble pared Novafort D=550mm + A m 80.00 $113.52 $9,081.60 0.38%
2503 Tub. Estructural doble pared Novafort D=440mm + A m 198.00 $73.70 $14,592.60 0.61%
2504 Tub. Estructural doble pared Novafort D=400mm + A m 12.00 $67.10 $805.20 0.03%
2505 Tub. Estructural doble pared Novafort D=335mm + A m 60.00 $44.94 $2,696.40 0.11%
2506 Tub. Estructural doble pared Novafort D=250mm + A m 84.00 $31.47 $2,643.48 0.11%
2507 Tub. Estructural doble pared Novafort D=200mm + A m 30.00 $25.84 $775.20 0.03%
2508 Tub.AALL Pvc D/N D = 160mm + Accesorios m 324.00 $22.08 $7,153.92 0.30%
2512 Puntos de AALL DE 160 mm m 26.00 $33.42 $868.92 0.04%
2513 Puntos de AALL DE 110 mm U 19.00 $27.01 $513.19 0.02%
2514 Tub.AALL Pvc D/N D = 160mm + Accesorios ml 124.00 $10.64 $1,319.36 0.06%
2515 Rejilla Tipo CC 200X150mm(aluminio) u 26.00 $71.12 $1,849.12 0.08%
2516 Rejilla Tipo CC 150X110mm(aluminio) u 119.00 $51.45 $6,122.55 0.26%
2517 Sumidero simple con rejilla u 5.00 $557.60 $2,788.00 0.12%
2518 Camara de agua lluvia tipo 1 u 8.00 $1,923.76 $15,390.08 0.64%
2519 Soporte de tuberia U 148.00 $8.50 $1,258.00 0.05%
2520 Excavacion de tuberias m3 465.00 $5.25 $2,441.25 0.10%
2521 Arena para tuberia m3 142.00 $18.69 $2,653.98 0.11%
2522 relleno con material de sitio m3 215.63 $8.01 $1,727.20 0.07%
2523 - Desalojo
- de Material m3 375.26 $4.58 $1,718.69 0.07%
SUB-TOTAL $89,627.93 3.75%
GRAN TOTAL OBRA CIVIL MAS INSTALACIONES SIN IVA $2,390,000.00 100.00%
______________________________
______________________________ Representante Legal de
Representante Legal de TIA Furoiani Obras y Proyectos S.A.
lunes lunes lunes lunes lunes lunes lunes lunes lunes lunes lunes lunes
CRONOGRAMA VALORADO INICIO 20-Jun-18 25-Jun-18 Monday-Jul9-2018 Monday-Jul23-2018 Monday-Aug6-2018 Monday-Aug20-2018 Monday-Sep3-2018 Monday-Sep17-2018 Monday-Oct1-2018 Monday-Oct15-2018 Monday-Oct29-2018 Monday-Nov12-2018 Monday-Nov26-2018
PROYECTO PLAZA TIA FIN 24-Jun-18 Sunday-Jul8-2018 Sunday-Jul22-2018 Sunday-Aug5-2018 Sunday-Aug19-2018 Sunday-Sep2-2018 Sunday-Sep16-2018 Sunday-Sep30-2018 Sunday-Oct14-2018 Sunday-Oct28-2018 Sunday-Nov11-2018 Sunday-Nov25-2018 Sunday-Dec9-2018
GRAN TOTAL OBRA CIVIL MAS INSTALACIONES SIN IVA $140,584.94 38,790.72 34,000.61 26,643.52 4,572.23 4,572.23 4,572.23 4,572.23 4,572.23 4,572.23 4,572.23 4,572.23 4,572.23
INVERSION QUINCENAL PROGRAMADA $38,790.72 $34,000.61 $26,643.52 $4,572.23 $4,572.23 $4,572.23 $4,572.23 $4,572.23 $4,572.23 $4,572.23 $4,572.23 $4,572.23
AVANCE QUINCENAL PROGRAMADO 27.59% 24.19% 18.95% 3.25% 3.25% 3.25% 3.25% 3.25% 3.25% 3.25% 3.25% 3.25%
INVERSION ACUMULADA PROGRAMADA $38,790.72 $72,791.33 $99,434.85 $104,007.08 $108,579.31 $113,151.55 $117,723.78 $122,296.01 $126,868.24 $131,440.48 $136,012.71 $140,585.05
AVANCE ACUMULADO PROGRAMADO 27.59% 51.78% 70.73% 73.98% 77.23% 80.49% 83.74% 86.99% 90.24% 93.50% 96.75% 100.00%