PROGRAMACION VIGADUCTO HGMAG COLON 22-11-18

ID ACTIVIDADES DIAS F. INICIO F. FIN


1 ETAPA 1 92 26-11-18 27-02-19
1.1 CAMARAS TRANSF TX-6, TX-7, TX-8, TX-9, TX-10, TX-11, TX-12 (7 u) 17 26-11-18 11-12-18
1.1.1 TERMINAR LOSA DE CAMARA TX-6 3 26-11-18 28-12-18
1.1.2 TERMINAR LOSA DE CAMARA TX-7 3 26-11-18 28-11-18
1.1.3 TERMINAR LOSA DE CAMARA TX-8 3 28-11-18 30-11-18
1.1.4 TERMINAR LOSA DE CAMARA TX-10 3 28-12-18 30-11-18
1.1.5 TERMINACION INTERIOR DE CAMARAS (7 u) 14 26-11-18 11-12-18
1.2 CAMARAS DE PASO REP-4, RES-1 13 03-12-18 15-12-18
1.2.1 TERMINAR LOSA DE CAMARA RES-1 3 03-12-18 05-12-18
1.2.2 TERMINAR LOSA DE CAMARA REP-4 3 03-12-18 05-12-18
1.2.3 TERMINACION INTERIOR DE CAMARAS (2 u) 4 12-12-18 15-12-18
1.3 VIGADUCTOS SECUNDARIOS 16 03-12-18 19-12-18
1.3.1 TX-6, 12 PVC 4" 3 03-12-18 05-12-18
1.3.2 TX-7, 6 PVC 4" 2 06-12-18 07-12-18
1.3.3 TX-8, 6 PVC 4" 2 08-10-02 11-12-18
1.3.4 TX-9, 2 PVC 4" 2 12-12-18 13-12-18
1.3.5 TX-10, 2 PVC 4" 2 14-12-18 15-12-18
1.3.6 TX-11, 8 PVC 4" 3 17-12-18 19-12-18
PROGRAMACION VIGADUCTO HGMAG COLON 22-11-18
ID ACTIVIDADES DIAS F. INICIO F. FIN
2 ETAPA 2 24 06-12-18 29-12-18
2.1 CAMARA TRANSF TX-13 3 17-12-18 19-12-18
2.1.1 TERMINACION INTERIOR DE CAMARA TX-13 (1 u) 3 17-12-18 19-12-18
2.2 CAMARAS DE PASO RES-2, REP-15, REP-16, REP-17, REP-18, REP-19, REP-20, REP-21, REP-22 (9 u 15 06-12-18 29-12-18
2.2.1 TERMINAR LOSA DE CAMARA REP-19 3 06-12-18 08-12-18
2.2.2 TERMINAR LOSA DE CAMARA REP-20 4 06-12-18 08-12-18
2.2.3 TERMINACION INTERIOR DE CAMARAS (9 u) 10 20-12-18 29-12-18
2.3 VIGADUCTOS SECUNDARIOS 2 23-12-18 24-12-18
2.3.1 TX-13, 1 PVC 3" 2 23-12-18 24-12-18
3 ETAPA 3 48 10-12-18 26-01-19
3.1 CAMARAS TRANSF TX-1, TX-2, TX-3, TX-4 (4 u) 32 10-12-18 10-01-19
3.1.1 TERMINAR LOSA DE CAMARA TX-1 3 10-12-18 12-12-18
3.1.2 TERMINAR LOSA DE CAMARA TX-2 3 10-12-18 12-12-18
3.1.3 TERMINAR LOSA DE CAMARA TX-3 3 13-12-18 15-12-18
3.1.4 TERMINAR LOSA DE CAMARA TX-4 3 13-12-18 15-12-18
3.1.5 TERMINACION INTERIOR DE CAMARAS (4 u) 8 02-01-19 10-01-19
3.2 CAMARAS DE PASO REP-5, REP-6, REP-6A, REP-7, REP-23, REP-24, REP-25, REP-26 (8 u) 41 17-12-18 26-01-19
3.2.1 TERMINAR LOSA DE CAMARA REP-5 3 17-12-18 19-12-18
3.2.2 TERMINAR LOSA DE CAMARA REP-6 3 17-12-18 19-12-18
3.2.3 TERMINAR LOSA DE CAMARA REP-6A 3 20-12-18 22-12-18
3.2.4 TERMINAR LOSA DE CAMARA REP-7 3 20-12-18 22-12-18
3.2.5 TERMINAR LOSA DE CAMARA REP-23 3 24-12-18 29-12-18
3.2.6 TERMINAR LOSA DE CAMARA REP-25 3 24-12-18 29-12-18
3.2.7 TERMINACION INTERIOR DE CAMARAS (8 u) 16 11-01-19 26-01-19
3.3 VIGADUCTOS SECUNDARIOS 11 26-12-18 05-01-19
3.3.1 TX-1, 1 PVC 3" 2 26-12-18 27-12-18
3.3.2 TX-2, 2 PVC 3" 2 28-12-18 29-12-18
3.3.3 TX-3, 1 PVC 3" 2 30-12-18 03-01-19
3.3.4 TX-4, 2 PVC 3" 2 04-01-19 05-01-19
3.4 OTROS 10 07-01-19 16-01-19
3.4.1 VIGADUCTO PRIMARIO REP-7 A P-SINC 4 PVC 6" + 8 PVC 4" 4 07-01-19 10-01-19
PROGRAMACION VIGADUCTO HGMAG COLON 22-11-18
ID ACTIVIDADES DIAS F. INICIO F. FIN
3.4.2 VIGADUCTO PRIMARIO REP-9 A TX-2 4 PVC 4" 3 14-01-19 16-01-19
PROGRAMACION VIGADUCTO HGMAG COLON 22-11-18
ID ACTIVIDADES DIAS F. INICIO F. FIN
4 ETAPA 4 48 02-01-19 18-02-19
4.1 CAMARAS TRANSF TX-5 Y CAMARA USS-1 (2 u) 30 02-01-19 31-01-19
4.1.1 TERMINAR LOSA DE CAMARA TX-5 3 02-01-19 05-01-19
4.1.2 TERMINAR LOSA DE CAMARA USS-1 3 02-01-19 05-01-19
4.1.5 TERMINACION INTERIOR DE CAMARAS (2 u) 4 28-01-19 31-01-19
4.2 CAMARAS DE PASO REP-1, REP-2, REP-3, REP-10, REP-11, REP-12, REP-12-1, REP-13, REP-14 (9 u 43 07-01-19 18-02-19
4.2.1 TERMINAR LOSA DE CAMARA REP-2 3 07-01-19 09-01-19
4.2.2 TERMINAR LOSA DE CAMARA REP-3 3 07-01-19 09-01-19
4.2.3 TERMINAR LOSA DE CAMARA REP-10 3 10-01-19 12-01-19
4.2.4 TERMINAR LOSA DE CAMARA REP-11 3 10-01-19 12-01-19
4.2.5 TERMINAR LOSA DE CAMARA REP-12 3 14-01-19 16-01-19
4.2.6 TERMINAR LOSA DE CAMARA REP-12-1 3 14-01-19 14-01-19
4.2.7 TERMINAR LOSA DE CAMARA REP-13 3 17-01-19 19-01-19
4.2.8 TERMINAR LOSA DE CAMARA REP-14 3 17-01-19 19-01-19
4.2.9 TERMINACION INTERIOR DE CAMARAS (9 u) 18 01-02-19 18-02-19
4.3 VIGADUCTOS SECUNDARIOS 2 17-01-19 18-01-19
4.3.1 TX-5, 1 PVC 3" 2 17-01-19 18-01-19
4.4 TELECOMUNICACIONES 38 21-01-19 27-02-19
4.4.1 CAMARAS TELECOMUNICACIONES 1.24 X 0.90 m (4 u) RCP-1, RCP-2, RCP-3, RCP-4 38 21-01-19 27-02-19
A TERMINAR LOSA DE CAMARA RCP-1 2 21-01-19 23-01-19
B TERMINAR LOSA DE CAMARA RCP-2 2 21-01-19 23-01-19
C TERMINAR LOSA DE CAMARA RCP-3 2 24-01-19 26-01-19
D TERMINAR LOSA DE CAMARA RCP-4 2 24-01-19 26-01-19
E TERMINACION INTERIOR DE CAMARAS (4 u) 8 19-02-19 27-02-19
4.4.2 VIGADUCTO TELECOMUNICACIONES 2 PVC 4" + 2 PVC 2" (90 m) 6 21-01-19 26-01-19
A TUBERIA DE RCP-1 a RCP-2 (2 PVC 4" + 2 PVC 2") 2 21-01-19 22-01-19
B TUBERIA DE RCP-2 a RCP-3 (2 PVC 4" + 2 PVC 2") 2 23-01-19 24-01-19
C TUBERIA DE RCP-3 a RCP-4 (2 PVC 4" + 2 PVC 2") 2 25-01-19 26-01-19
GRUPOS DE TRABAJO
ID DESCRIPCION PERS INICIO FIN
1 TERMINACION INTERIOR DE CAMARAS 2 26-11-18 27-02-19
2 LOSAS EN CAMARAS 1 4 26-11-18 26-01-19
3 LOSAS EN CAMARAS 2 4 26-11-18 26-01-19
4 VIGADUCTOS 4 26-11-18 25-01-19