Está en la página 1de 11

PRESUPUESTO

S10

Presupuesto 0403005 LOSAS DEPORTIVAS


Subpresupuesto 002 CONSTRUCCION LOSA DEPORTIVA HUANCAMACHAY
Cliente MUNICIPALIDAD DISTRITAL DE SAN FRANCISCO DE ASIS-YARUSYACAN
Lugar PASCO - PASCO - SAN FCO.DE ASIS DE YARUSYACAN

Item Descripción Und.


01 OBRAS PROVISIONALES
01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40 m u

02 TRABAJOS PRELIMINARES
02.01 LIMPIEZA DE TERRENO MANUAL m2
02.02 TRAZO NIVELES Y REPLANTEO PRELIMINAR m2
02.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPO glb

03 MOVIMIENTO DE TIERRAS
03.01 MOVIMIENTO DE TIERRAS EN LOSA DEPORTIVA
03.01.01 CORTE SUPERFICIAL MANUAL, H=0.20M, EN LOSA m3
03.01.02 RELLENO Y COMPACTACION CON MATERIAL SELECCIONADO, CON EQUIPO, E=10cm m2
03.01.03 RELLENO Y COMPACTACION CON MATERIAL PROPIO CON EQUIPO, E=10cm m2
03.01.04 ELIMINACION DE MATERIAL EXCEDENTE FORMA MANUAL m3

03.02 MOVIMIENTO DE TIERRAS EN CARRETERA


03.02.01 CORTE DE MATERIAL SUELTO R=460 m3/día m3
03.02.02 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIAS DIST. = 1 KM. m3

04 OBRAS DE CONCRETO SIMPLE


04.01 CONCRETO EN LOSAS, e=10cm, f'c=175 kg/cm2 m2
04.02 ENCOFRADO Y DESENCOFRADO ENTRE PAÑOS m2
04.03 JUNTA DE DILATACION C/MORTERO ASFALTICO m

05 PINTURA
05.01 PINTURA EN MARCAS PARA LAS TRES DISCIPLINAS m

06 CARPINTERIA METALICA
06.01 ARCOS(INC. MALLA), TABLERO DE BASQUET(INC.MALLA), PARANTES DE VOLEY(INC. MALLA) glb

06.02 MALLA METALICA ENCIMA MURO DE CONCRETO CICLOPEO


06.02.01 TUBERIA DE FºGº, 2"X2.5mm m
06.02.02 MALLA METALICA COCADA 1 1/2" DE FºGº, #12 m2
06.02.03 ANGULOS DE 1 1/2"X1/8" m
06.02.04 ANCLAJES DE TUBERIA EN CONCRETO u
06.03 MALLA METALICA EN TRIBUNAS
06.03.01 TUBERIA DE FºGº, 2"X2.5mm m
06.03.02 MALLA METALICA COCADA 1 1/2" DE FºGº, #12 m2
06.03.03 ANGULOS DE 1 1/2"X1/8" m
06.03.04 ANCLAJES DE TUBERIA EN CONCRETO u

07 MURO DE CONTENCION DE CONCRETO CICLOPEO


07.01 EXCAVACION PARA ESTRUCTURA m3
07.02 REFINE, NIVELACION Y COMPACTACION EN T.N MANUAL m2
07.03 SOLADO DE CONCRETO 1:8 e=0.10 m. m2
07.04 ENCOFRADO Y DESENCOFRADO m2
07.05 CONCRETO CICLOPEO F'C = 175 KG/CM2 + 30% P.G m3
07.06 JUNTA DE DILATACION C/MORTERO ASFALTICO m2
07.07 TUBERIA DE DRENAJE (PVC, SP-CLASE 7.5, D=3") m

08 TRIBUNAS DE CONCRETO ARMADO


08.01 MOVIMIENTO DE TIERRAS
08.01.01 EXCAVACION ZAPATAS COLUMNAS Y VIGAS m3

08.02 OBRAS DE CONCRETO SIMPLE


08.02.01 SOLADO DE CONCRETO 1:8 e=0.10 m. m2

08.03 OBRAS DE CONCRETO ARMADO


08.03.01 ZAPATAS
08.03.01.01 ENCOFRADO DE ZAPATAS m2
08.03.01.02 CONCRETO f'c = 210 kg/cm2 m3
08.03.01.03 ACERO fy=4200 kg/cm2 kg

08.03.02 COLUMNAS
08.03.02.01 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2
08.03.02.02 CONCRETO f'c = 210 kg/cm2 m3
08.03.02.03 ACERO fy=4200 kg/cm2 kg

08.03.03 VIGAS
08.03.03.01 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2
08.03.03.02 CONCRETO f'c = 210 kg/cm2 m3
08.03.03.03 ACERO fy=4200 kg/cm2 kg

08.03.04 LOSA DE TRIBUNAS


08.03.04.01 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS MACIZAS m2
08.03.04.02 CONCRETO f'c = 210 kg/cm2 m3
08.03.04.03 ACERO fy=4200 kg/cm2 kg

08.03.05 ESCALERA CENTRAL


08.03.05.01 ENCOFRADO Y DESENCOFRADO NORMAL EN ESCALERAS m2
08.03.05.02 CONCRETO f'c = 210 kg/cm2 m3
08.03.05.03 ACERO fy=4200 kg/cm2 kg
08.03.05.04 JUNTA DE DILATACION C/MORTERO ASFALTICO m2

09 VARIOS
09.01 FLETE
09.01.01 FLETE TERRESTRE kg

10 OBRAS VARIAS
10.01 LIMPIEZA DE OBRA m2
10.02 ELIMINACION DE MATERIAL EXCEDENTE FORMA MANUAL m3

COSTO DIRECTO
GASTOS GENERALES ( 6.341040 % )

SUB-TOTAL 01
IGV( 19 %)

SUB-TOTAL 02
EXPEDIENTE TECNICO
SUPERVISION

PRESUPUESTO TOTAL

SON : TRESCIENTOS QUINCE MIL CIENTO SETENTICUATRO Y 73/100 NUEVOS SOLES


Página 1

Costo al 29/08/2008

Metrado Precio S/. Parcial S/. Sub-Total Total


655.200 655.200
1.00 655.20 655.20

14,127.460 14,127.460
1,470.00 1.38 2,028.60
1,470.00 5.63 8,276.10
1.00 3,822.76 3,822.76

26,409.065
15,728.832
144.00 13.66 1,967.04
720.00 12.97 9,338.40
720.00 3.87 2,786.40
201.60 8.12 1,636.99

10,680.233
851.83 4.60 3,918.42
1,192.56 5.67 6,761.82

9,220.439 9,220.439
76.45 33.58 2,567.19
54.40 92.67 5,041.25
208.00 7.75 1,612.00

728.323 728.323
492.11 1.48 728.32

5,000.000 50,200.679
1.00 5,000.00 5,000.00

30,838.469
408.50 37.86 15,465.81
241.50 17.59 4,247.99
481.80 19.73 9,505.91
22.00 73.58 1,618.76
14,362.210
168.60 37.86 6,383.20
96.05 17.59 1,689.52
251.65 19.73 4,965.05
18.00 73.58 1,324.44

35,607.570 35,607.570
323.99 13.66 4,425.70
85.26 14.01 1,194.49
85.26 25.22 2,150.26
332.92 34.96 11,638.88
51.16 302.09 15,454.92
13.88 27.36 379.76
22.40 16.23 363.55

91,857.311
1,494.312
107.35 13.92 1,494.31

6,298.695
249.75 25.22 6,298.70

84,064.304
12,223.917
72.00 29.50 2,124.00
22.50 339.24 7,632.90
445.31 5.54 2,467.02

5,937.606
39.75 33.83 1,344.74
3.31 339.24 1,122.88
626.35 5.54 3,469.98

8,114.753
71.05 33.00 2,344.65
5.39 339.24 1,828.50
711.48 5.54 3,941.60

55,083.016
483.79 33.69 16,298.89
55.68 339.24 18,888.88
3,591.20 5.54 19,895.25

2,705.012
21.90 30.99 678.68
3.80 339.24 1,289.11
110.70 5.54 613.28
4.53 27.36 123.94

3,457.302
3,457.302
34,573.02 0.10 3,457.30

2,572.304 2,572.304
1,470.00 0.47 690.90
231.70 8.12 1,881.40

234,835.64
14,891.02
-------------------------
249,726.66
47,448.07
=================
297,174.73
10,500.00
7,500.00
=================
315,174.73
CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA

PROYECTO: "CONSTRUCCION LOSA DEPORTIVA HUANCAMACHAY"


DEPARTAMENTO :PASCO PROVINCIA :PASCO
DISTRITO :SAN FCO.DE ASIS DE YARUSYACAN HECHO POR :ARQ. K.Q.C.
FECHA SEPTIEMNRE 2008

PRESUPUESTO
1er. MES
PARTIDA DESCRIPCION
1° SEM 2° SEM 3° SEM 4° SEM
655.20
01.00.00 OBRAS PROVISIONALES 655.20
14,127.46
02.00.00 TRABAJOS PRELIMINARES 14,127.46
26,409.07
03.00.00 MOVIMIENTO DE TIERRAS 13,204.53 13,204.53
9,220.44
04.00.00 OBRAS DE CONCRETO SIMPL 3,073.48 3,073.48 3,073.48
728.32
05.00.00 PINTURA 728.32
50,200.68
06.00.00 CARPINTERIA METALICA 12,550.17
35,607.57
07.00.00 MURO DE CONTENCION DE C 7,121.51 7,121.51 7,121.51
91,857.31
08.00.00 TRIBUNAS DE CONCRETO AR
3,457.30
09.00.00 VARIOS
2,572.30
10.00.00 OBRAS VARIAS
COSTO DIRECTO TOTAL 234,835.65 27,987.19 23,399.53 10,194.99 23,473.49
CION DE OBRA

2do. MES
1° SEM 2° SEM 3° SEM 4° SEM

12,550.17 12,550.17 12,550.17

7,121.51 7,121.51

30,619.10 30,619.10 30,619.10

3,457.30

2,572.30
19,671.68 50,290.79 43,169.27 36,648.71
ANALISIS POR EL METODO DE VA

ACTIVIDAD BAC

OBRAS PROVISIONALES 655.20

TRABAJOS PRELIMINARES 14,127.46

MOVIMIENTO DE TIERRAS 26,409.07

OBRAS DE CONCRETO SIMPLE 9,220.44

PINTURA 728.32

CARPINTERIA METALICA 50,200.68

MURO DE CONTENCION DE CONCRETO CICLOPEO 35,607.57

TRIBUNAS DE CONCRETO ARMADO 91,857.31

VARIOS 3,457.30

OBRAS VARIAS 2,572.30


COSTO DIRECTO TOTAL 234,835.65
ANALISIS POR EL METODO DE VALOR GANADO AL TERMINO DE LA TERCERA SEMANA

VALOR VARIACION DEL VARIACION DE


PROGRESO FISICO VALOR GANADO COSTO REAL PROGRAMA COSTOS
(%) PLANIFICADO (PV) (EV) (AC) (EV-PV) (EV-AC)

100% 655.20 655.20 655.20 0.00 0.00

100% 14,127.46 14,127.46 14,127.46 0.00 0.00

95% 26,409.07 25,088.61 25,100.00 -1,320.45 -11.39

40% 6,146.96 3,688.18 3,200.00 -2,458.78 488.18

40% 364.16 291.33 250.00 -72.83 41.33

12% 8,366.78 6,024.08 5,800.00 -2,342.70 224.08

30% 21,364.54 10,682.27 9,800.00 -10,682.27 882.27

0%

0%

0%
77,434.17 60,557.13 58,932.66 -16,877.04 1,624.47
RENDIMIENTO DE RENDIMIENTO DE
PROGRAMA (EV/PV) COSTOS (EV/AC)

1.00 1.00 EL PROYECTO PRESENTA


RETRASO Y SE HA
1.00 1.00 GASTADO MAS DEL
PRESUPUESTO
0.95 1.00 PLANIFICADO.
0.60 1.15

0.80 1.17

0.72 1.04

0.50 1.09

5.57 7.45

También podría gustarte