Está en la página 1de 68

Página 1 de 68

PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

CATALOGO DE CONCEPTOS Y CANTIDADES DE OBRA PARA EXPRESION DE PRECIOS UNITARIOS Y MONTO TOTAL DE LA PROPUESTA

Código Concepto Unidad Cantidad P. Unitario Precio con letra Importe


A PRELIMINARES
Total PRELIMINARES 2,536.75
B CIMENTACION
Total CIMENTACION 22,423.62
C MUROS
Total MUROS 20,137.07
D LOSAS
Total LOSAS 19,427.82
E ALBAÑILERIA
Total ALBAÑILERIA 11,473.35
F IMPERMEABILIZACION Y PINTURA
Total IMPERMEABILIZACION Y PINTURA 11,322.61
G PISOS Y RECUBRIMIENTOS
Total PISOS Y RECUBRIMIENTOS 12,877.91
H HERRERIA, ALUMINIO Y VIDRIO
Total HERRERIA, ALUMINIO Y VIDRIO 10,915.93
I CARPINTERIA Y CERRAJERIA
Total CARPINTERIA Y CERRAJERIA 6,509.80
J INSTALACION HIDROSANITARIA Y GAS
Total INSTALACION HIDROSANITARIA Y GAS 6,401.91
K MUEBLES DE BAÑO Y COCINA
Total MUEBLES DE BAÑO Y COCINA 11,908.71
L INSTALACIN ELECTRICA
Total INSTALACIN ELECTRICA 9,728.22
M LIMPIEZA
Total LIMPIEZA 460.48
N OBRA EXTERIOR
Total OBRA EXTERIOR 9,816.52

SUBTOTAL 155,940.69
I.V.A. 16.00% Página 2 de 68
24,950.51
Total del presupuesto 180,891.20
Página 3 de 68
Página 4 de 68
Página: 5+0
F&R CONSTRUCCIONES

Obra: CLOSET CUARTO No. 1

Lugar: Acayucan, Veracruz.

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

FABRICACION CLOSET DE MATERIAL TABLAROCA EN CUARTO No.1 TRASERO

MATERIALES
CUNETA DE AMARRE (TRAMOS DE 3 MTS.) M $46.00 9.000000 $414.00
POSTES (TRAMOS DE 3 MTS.) M $51.00 3.000000 $153.00
MENSULA PZA $119.00 1.000000 $119.00
TABLAROCA 1.22 X 2.44 MTS. PZA $195.00 4.000000 $780.00
CINTA 77 MTS. ROLLO $33.00 1.000000 $33.00
REDIMIX CUBETA 25 LTS. PZA $199.00 1.000000 $199.00
PIJA 1" (100 PZAS.) PZA $49.90 1.000000 $49.90
TIJERAS PARA ALUMINIO PZA $325.00 1.000000 $325.00
PRECIO UNITARIO $2,072.90

NOTA
Todos los precios fueron cotizados en la tienda Home Depot.

:
Página: 6+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: PRE00002 Unidad: M3


EXCAVACION MANUAL EN PLATAFORMA, PARA ALOJAR CIMENTACION, INCLUYE: HERRAMIENTA, MANO DE
OBRA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION.P.U.O.T

MANO DE OBRA
CUADRILLA 2 ( 2 PEONES) JOR $400.02 / 7.560000 $52.91 10.29%
CUADRILLA 4 ( 4PEONES PARA CONTRATRABES) JOR $1,743.55 / 3.780000 $461.26 89.71%

Subtotal: MANO DE OBRA $514.17 100.00%


Costo directo $514.17
INDIRECTOS 5.75% $29.56
SUBTOTAL $543.73
FINANCIAMIENTO 0.791% $4.30
SUBTOTAL $548.03
UTILIDAD 8% $43.84
PRECIO UNITARIO $591.87
(* QUINIENTOS NOVENTA Y UN PESOS 87/100 M.N. *)

:
Página: 7+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: CIM00001 Unidad: LOTE


MALLA ELECTROSOLDADA LECHO SUPERIOR DE 6X6-4/4, INCLUYE: TRASLAPES . AMARRES, INCLUYE:
HERRAMIENTA, MANO DE OBRA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION. P.U.O.T.

MATERIALES
ROLLO DE 2.5 X 40 M DE MALLA ROLLO $1,729.39 0.538669 $931.57 68.07%
ELECTROSOLDADA 6 X 6-4/4
ALAMBRE RECOCIDO KG $18.97 1.592218 $30.20 2.21%
Subtotal: MATERIALES $961.77 70.28%
MANO DE OBRA
CUADRILLA 1 (1 Of. Herrero + 1 Ayudante) JOR $1,700.04 / 4.180000 $406.71 29.72%
Subtotal: MANO DE OBRA $406.71 29.72%
Costo directo $1,368.48
INDIRECTOS 5.75% $78.69
SUBTOTAL $1,447.17
FINANCIAMIENTO 0.791% $11.45
SUBTOTAL $1,458.62
UTILIDAD 8% $116.69
PRECIO UNITARIO $1,575.31
(* UN MIL QUINIENTOS SETENTA Y CINCO PESOS 31/100 M.N. *)

:
Página: 8+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: CIM00002 Unidad: LOTE


MALLA ELECTROSOLDADA LECHO INFERIOR DE 6X6-4/4, INCLUYE: TRASLAPES . AMARRES, INCLUYE:
HERRAMIENTA, MANO DE OBRA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION. P.U.O.T.

MATERIALES
ROLLO DE 2.5 X 40 M DE MALLA ROLLO $1,729.39 0.398440 $689.06 67.37%
ELECTROSOLDADA 6 X 6-4/4
ALAMBRE RECOCIDO KG $18.97 1.592218 $30.20 2.95%
Subtotal: MATERIALES $719.26 70.32%
MANO DE OBRA
CUADRILLA 1 (1 Of. Herrero + 1 Ayudante) JOR $1,700.04 / 5.600000 $303.58 29.68%
Subtotal: MANO DE OBRA $303.58 29.68%
Costo directo $1,022.84
INDIRECTOS 5.75% $58.81
SUBTOTAL $1,081.65
FINANCIAMIENTO 0.791% $8.56
SUBTOTAL $1,090.21
UTILIDAD 8% $87.22
PRECIO UNITARIO $1,177.43
(* UN MIL CIENTO SETENTA Y SIETE PESOS 43/100 M.N. *)

:
Página: 9+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: CIM00003 Unidad: LOTE


LOSA MACIZA DE CIMENTACION DE 0.12 CM DE ESPESOR. CON UN F"C=200 KG/CM2. INCLUYE:
CIMBRA, TRASLAPES, AMARRES, REFUERZOS,ANDAMIOS,HERRAMIE MANO DE OBRA Y TODO LO NECESARIO
PARA SU CORRECTA EJECUCION. P.U.O.T.

MATERIALES
CONCRETO PREMEZCLADO F C= 200KG/CM2 M3 $1,164.63 3.380000 $3,936.45 68.95%
CIMBRA PARA CIMENTACION LOTE $172.41 1.000000 $172.41 3.02%
Subtotal: MATERIALES $4,108.86 71.97%
MANO DE OBRA
CUADRILLA 2 (1 CARPINTERO DE CIMENTACION JOR $400.00 1.000000 $400.00 7.01%
CUADRILLLA 3 (2 ALB. CIMENTACION + 1 AY) JOR $1,200.00 / 1.000000 $1,200.00 21.02%
Subtotal: MANO DE OBRA $1,600.00 28.03%
Costo directo $5,708.86
INDIRECTOS 5.75% $328.26
SUBTOTAL $6,037.12
FINANCIAMIENTO 0.791% $47.75
SUBTOTAL $6,084.87
UTILIDAD 8% $486.79
PRECIO UNITARIO $6,571.66
(* SEIS MIL QUINIENTOS SETENTA Y UN PESOS 66/100 M.N. *)

:
Página: 10+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: CIM00004 Unidad: ML


CONTRATRABE CT-1, DE 15 CM DE ANCHO POR 45 CM DE PERALTE ARMADA CON 8 VARILLAS DE
3/8", CON ESTRIBOS DE 1/4" A CADA 15 CM. INCLUYE:MATERIALES,ACARREOS, HABILITADO,
CIMBRADO, DECIMBRADO, HERRAMIENTA, MANO DE OBRA Y TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.P.U.O.T

MATERIALES
CONCRETO PREMEZCLADO F C= 200KG/CM2 M3 $1,164.63 0.135080 $157.32 59.89%
VARILLA FY= 4200 KG/CM2 DE 3/8" KG $11.64 4.704000 $54.75 20.84%
ROLLO DE ALAMBRON 1/4" KG $13.80 1.207960 $16.67 6.35%
ALAMBRE RECOCIDO KG $18.97 0.077043 $1.46 0.56%
Subtotal: MATERIALES $230.20 87.64%
MANO DE OBRA
CUADRILLA 1 (1 Of. Herrero + 1 Ayudante) JOR $1,700.04 / 91.000000 $18.68 7.11%
CUADRILLLA 3 (2 ALB. CIMENTACION + 1 AY) JOR $1,200.00 / 87.000000 $13.79 5.25%
Subtotal: MANO DE OBRA $32.47 12.36%
Costo directo $262.67
INDIRECTOS 5.75% $15.10
SUBTOTAL $277.77
FINANCIAMIENTO 0.791% $2.20
SUBTOTAL $279.97
UTILIDAD 8% $22.40
PRECIO UNITARIO $302.37
(* TRESCIENTOS DOS PESOS 37/100 M.N. *)

:
Página: 11+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: CIM00005 Unidad: ML


CONTRATRABE CT-2, DE 15 CM DE ANCHO POR 30 CM DE PERALTE ARMADA CON 4 VARILLAS DE
3/8", CON ESTRIBOS DE 1/4" A CADA 15 CM. INCLUYE:MATERIALES,ACARREOS, HABILITADO,
CIMBRADO, DECIMBRADO, HERRAMIENTA, MANO DE OBRA Y TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.P.U.O.T

MATERIALES
CONCRETO PREMEZCLADO F C= 200KG/CM2 M3 $1,164.63 0.050250 $58.52 39.59%
VARILLA FY= 4200 KG/CM2 DE 3/8" KG $11.64 2.240000 $26.07 17.64%
ROLLO DE ALAMBRON 1/4" KG $13.80 1.596922 $22.04 14.91%
ALAMBRE RECOCIDO KG $18.97 0.077043 $1.46 0.99%
Subtotal: MATERIALES $108.09 73.12%
MANO DE OBRA
CUADRILLA 1 (1 Of. Herrero + 1 Ayudante) JOR $1,700.04 / 81.000000 $20.99 14.20%
CUADRILLLA 3 (2 ALB. CIMENTACION + 1 AY) JOR $1,200.00 / 64.000000 $18.75 12.68%
Subtotal: MANO DE OBRA $39.74 26.88%
Costo directo $147.83
INDIRECTOS 5.75% $8.50
SUBTOTAL $156.33
FINANCIAMIENTO 0.791% $1.24
SUBTOTAL $157.57
UTILIDAD 8% $12.61
PRECIO UNITARIO $170.18
(* CIENTO SETENTA PESOS 18/100 M.N. *)

:
Página: 12+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: CIM00006 Unidad: M2


SUMINISTRO Y COLOCACION DE POLIETILENO NEGRO 600 MC, COMO IMPERMEABILIZANTE.INCLUYE:
HERRAMIENTA MANO DE OBRA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION. P.U.O.T.

MATERIALES
POLIETILENO NEGRO 93 M2 ROLLO $981.90 0.011828 $11.61 100.00%
Subtotal: MATERIALES $11.61 100.00%
Costo directo $11.61
INDIRECTOS 5.75% $0.67
SUBTOTAL $12.28
FINANCIAMIENTO 0.791% $0.10
SUBTOTAL $12.38
UTILIDAD 8% $0.99
PRECIO UNITARIO $13.37
(* TRECE PESOS 37/100 M.N. *)

:
Página: 13+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: MUR00001 Unidad: ML


CASTILLOS K-1 DE 0.12 X 0.12, ARMEX 10 X 10 -4

MATERIALES
ALAMBRE RECOCIDO KG $18.97 0.077043 $1.46 2.05%
CASTILLO ELECTROSOLDADO 10 X 10 CM ML $20.11 1.000000 $20.11 28.23%
Subtotal: MATERIALES $21.57 30.28%
MANO DE OBRA
CUADRILLA 4 ( 1 ALBAÑIL P/CASTILLOS + 1 JOR $750.01 / 20.000000 $37.50 52.64%
Subtotal: MANO DE OBRA $37.50 52.64%
BASICOS
CONCRETO F C=150 KG/CM2 M3 $804.57 0.015120 $12.17 17.08%
Subtotal: BASICOS $12.17 17.08%
Costo directo $71.24
INDIRECTOS 5.75% $4.10
SUBTOTAL $75.34
FINANCIAMIENTO 0.791% $0.60
SUBTOTAL $75.94
UTILIDAD 8% $6.08
PRECIO UNITARIO $82.02
(* OCHENTA Y DOS PESOS 02/100 M.N. *)

:
Página: 14+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: MUR00002 Unidad: ML


CASTILLOS K DE 0.12 X 0.12,CON UNA VARILLA DE 3/8", CONCRETO F c=150 Kg/cm2. INCLUYE:
HERRAMIENTA MANO DE OBRA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION.P.U.O.T.

MATERIALES
VARILLA FY= 4200 KG/CM2 DE 3/8" KG $11.64 0.560000 $6.52 31.80%
Subtotal: MATERIALES $6.52 31.80%
MANO DE OBRA
CUADRILLA 5 (1 OF. BLOQUERO +1 AY BLOCK) JOR $875.02 / 176.000000 $4.97 24.24%
Subtotal: MANO DE OBRA $4.97 24.24%
BASICOS
CONCRETO F C=150 KG/CM2 M3 $804.57 0.011200 $9.01 43.95%
Subtotal: BASICOS $9.01 43.95%
Costo directo $20.50
INDIRECTOS 5.75% $1.18
SUBTOTAL $21.68
FINANCIAMIENTO 0.791% $0.17
SUBTOTAL $21.85
UTILIDAD 8% $1.75
PRECIO UNITARIO $23.60
(* VEINTITRES PESOS 60/100 M.N. *)

:
Página: 15+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: MUR00006 Unidad: M2


MURO DE BLOCK 12X20X40 CMS DE ESPESOR ASENTADO CON MORTERO CEMENTO- CAL- ARENA
PROPORCIÓN 1:3:12 A NIVEL Y PLOMO, INCLUYE: ANDAMIOS, MATERIALES, MANO DE OBRA, EQUIPO
Y HERRAMIENTA, P.U.O.T.

MATERIALES
BLOCK DE CONCRETO DE 12 X 20 X 40 CMS PZA $6.03 12.000000 $72.36 55.67%
ESCALERILLA DE 5M PZA $11.50 0.366667 $4.22 3.25%
Subtotal: MATERIALES $76.58 58.91%
MANO DE OBRA
CUADRILLA 5 (1 OF. BLOQUERO +1 AY BLOCK) JOR $875.02 / 27.000000 $32.41 24.93%
Subtotal: MANO DE OBRA $32.41 24.93%
BASICOS
MORTERO CEMENTO CAL ARENA PROP: 1:.25:3 M3 $389.80 0.053880 $21.00 16.16%
Subtotal: BASICOS $21.00 16.16%
Costo directo $129.99
INDIRECTOS 5.75% $7.47
SUBTOTAL $137.46
FINANCIAMIENTO 0.791% $1.09
SUBTOTAL $138.55
UTILIDAD 8% $11.08
PRECIO UNITARIO $149.63
(* CIENTO CUARENTA Y NUEVE PESOS 63/100 M.N. *)

:
Página: 16+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: LOS00001 Unidad: ML


CR-1 , DE 0.12 X 0.25, ARMADO CON 4 VARILLAS DE 3/8" CON ESTRIBOS DE 1/4" A CADA 15 CM
INCLUYE: MATERIALES,ACARREOS, HABILITADO, CIMBRADO, DECIMBRADO, HERRAMIENTA, MANO DE OBRA
Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION.P.U.O.T

MATERIALES
VARILLA FY= 4200 KG/CM2 DE 3/8" KG $11.64 2.240000 $26.07 25.74%
ALAMBRE RECOCIDO KG $18.97 0.077043 $1.46 1.44%
ROLLO DE ALAMBRON 1/4" KG $13.80 1.745700 $24.09 23.79%
CONCRETO PREMEZCLADO F C= 200KG/CM2 M3 $1,172.41 0.033000 $38.69 38.20%
BOMB
Subtotal: MATERIALES $90.31 89.17%
MANO DE OBRA
CUADRILLA 1 (1 Of. Herrero + 1 Ayudante) JOR $1,700.04 / 155.000000 $10.97 10.83%
Subtotal: MANO DE OBRA $10.97 10.83%
Costo directo $101.28
INDIRECTOS 5.75% $5.82
SUBTOTAL $107.10
FINANCIAMIENTO 0.791% $0.85
SUBTOTAL $107.95
UTILIDAD 8% $8.64
PRECIO UNITARIO $116.59
(* CIENTO DIECISEIS PESOS 59/100 M.N. *)

:
Página: 17+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: LOS00002 Unidad: ML


T-1 , DE 0.24 X 0.12, ARMADO CON 6 VARILLAS DE 3/8" CON ESTRIBOS DE 1/4" A CADA 15 CM
INCLUYE: MATERIALES,ACARREOS, HABILITADO, CIMBRADO, DECIMBRADO, HERRAMIENTA, MANO DE OBRA
Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION.P.U.O.T

MATERIALES
VARILLA FY= 4200 KG/CM2 DE 3/8" KG $11.64 2.240000 $26.07 25.17%
ALAMBRE RECOCIDO KG $18.97 0.077043 $1.46 1.41%
ROLLO DE ALAMBRON 1/4" KG $13.80 1.745700 $24.09 23.26%
CONCRETO PREMEZCLADO F C= 200KG/CM2 M3 $1,172.41 0.033000 $38.69 37.35%
BOMB
Subtotal: MATERIALES $90.31 87.18%
MANO DE OBRA
CUADRILLA 1 (1 Of. Herrero + 1 Ayudante) JOR $1,700.04 / 128.000000 $13.28 12.82%
Subtotal: MANO DE OBRA $13.28 12.82%
Costo directo $103.59
INDIRECTOS 5.75% $5.96
SUBTOTAL $109.55
FINANCIAMIENTO 0.791% $0.87
SUBTOTAL $110.42
UTILIDAD 8% $8.83
PRECIO UNITARIO $119.25
(* CIENTO DIECINUEVE PESOS 25/100 M.N. *)

:
Página: 18+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: LOS00006 Unidad: M2


LOSA DE PLANA EN ESTRUCTURA, PERALTE DE 12 CMS, CIMBRA COMUN REFORZADA MALLA
ELECTROSOLDADA 6x6 -4/4 EN LECHO INFERIOR Y SUPERIOR COMO SE INDICA EN PLANO , CONCRETO
F'C = 200 KG/CM2- 3/4" . INCLUYE: APUNTALAMINETO, MANO DE OBRA (INCLUYE AISLANTE TERMICO
POR ESPECIFICACIÓN Y NORMA INFONAVIT SEPTIEMBRE DE 2010), HERRAMIENTA Y TODO LO NECESARIO
PARA SU CORRECTA EJECUCIÓN. P.U.O.T.

MATERIALES
ALAMBRE RECOCIDO KG $18.97 0.063906 $1.21 0.49%
CONCRETO PREMEZCLADO F C= 200KG/CM2 M3 $1,172.41 0.105000 $123.10 49.91%
BOMB
Subtotal: MATERIALES $124.31 50.41%
MANO DE OBRA
CUADRILLA 1 (1 Of. Herrero + 1 Ayudante) JOR $1,700.04 / 70.000000 $24.29 9.85%
CUADRILLLA 3 (2 ALB. CIMENTACION + 1 AY) JOR $1,200.00 / 49.830000 $24.08 9.76%
Subtotal: MANO DE OBRA $48.37 19.61%
BASICOS
MALLA ELECTROSOLDADA LECHO INFERIOR DE LOTE $1,022.84 / 49.830000 $20.53 8.32%
6X6-4/4, INCLUYE: TRASLAPES . AMARRES,
INCLUYE: HERRAMIENTA, MANO DE OBRA Y
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION. P.U.O.T.

MALLA ELECTROSOLDADA LECHO SUPERIOR DE LOTE $1,368.48 / 49.830000 $27.46 11.13%


6X6-4/4, INCLUYE: TRASLAPES . AMARRES,
INCLUYE: HERRAMIENTA, MANO DE OBRA Y
TODO LO NECESARIO PARA SU CORRECTA
EJECUCION. P.U.O.T.

Subtotal: BASICOS $47.99 19.46%


MATERIALES
CIMBRA PARA LOSA DE AZOTEA M2 $1,293.10 / 49.830000 $25.95 10.52%
Subtotal: MATERIALES $150.26 60.93%
Costo directo $246.62
INDIRECTOS 5.75% $14.18
SUBTOTAL $260.80
FINANCIAMIENTO 0.791% $2.06
SUBTOTAL $262.86
UTILIDAD 8% $21.03
PRECIO UNITARIO $283.89
(* DOSCIENTOS OCHENTA Y TRES PESOS 89/100 M.N. *)

:
Página: 19+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: ALB00001 Unidad: M2


APLANADO CON MORTERO FINO CEMENTO:ARENA SOBRE CARA DE TABIQUE. A UN PROMEDIO DE 2 CMS.
DE ESPESOR A REGLA Y PLOMO. INCLUYE: HERRAMIENTA ,MANO DE OBRA, Y TODO LO NECESARIO PARA
SU CORRECTA EJECUCION. P.U.O.T.

MANO DE OBRA
CUADRILLA 7 (1 ALBAÑIL APLANADO + A1 AY JOR $833.31 / 8.000000 $104.16 80.62%
Subtotal: MANO DE OBRA $104.16 80.62%
BASICOS
MORTERO CEMENTO ARENA PROP:1:4 M3 $1,138.33 0.022000 $25.04 19.38%
Subtotal: BASICOS $25.04 19.38%
Costo directo $129.20
INDIRECTOS 5.75% $7.43
SUBTOTAL $136.63
FINANCIAMIENTO 0.791% $1.08
SUBTOTAL $137.71
UTILIDAD 8% $11.02
PRECIO UNITARIO $148.73
(* CIENTO CUARENTA Y OCHO PESOS 73/100 M.N. *)

:
Página: 20+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: ALB00002 Unidad: M2


APLANADO DE YESERIA EN MUROS A TALOCHA DE 1.5 CM DE ESPESOR PROMEDIO CON MORTERO
YESO-AGUA.INCLUYE: ANDAMIOS,HERRAMIENTA,MANO DE OBRA Y TODO LO NECESARIO PARA SU CORRECTA
EJECUCION. P.U.O.T.

MATERIALES
YESO SUPREMO TON $1,293.00 0.014660 $18.96 41.09%
AGUA DE PIPA M3 $40.00 0.014660 $0.59 1.28%
SELLADOR DEL TORO KG $26.94 0.010000 $0.27 0.59%
Subtotal: MATERIALES $19.82 42.96%
MANO DE OBRA
CUADRILLA 6 (1 OF. YESERO + 1 AY YESERO) JOR $1,000.03 / 38.000000 $26.32 57.04%
Subtotal: MANO DE OBRA $26.32 57.04%
Costo directo $46.14
INDIRECTOS 5.75% $2.65
SUBTOTAL $48.79
FINANCIAMIENTO 0.791% $0.39
SUBTOTAL $49.18
UTILIDAD 8% $3.93
PRECIO UNITARIO $53.11
(* CINCUENTA Y TRES PESOS 11/100 M.N. *)

:
Página: 21+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: ALB00003 Unidad: M2


APLANADO DE YESERIA EN PLAFONES A TALOCHA DE 2 CM DE ESPESOR PROMEDIO CON MORTERO
YESO-AGUAINCLUYE: ANDAMIOS,HERRAMIENTA,MANO DE OBRA Y TODO LO NECESARIO P.U.O.T.

MATERIALES
YESO SUPREMO TON $1,293.00 0.009350 $12.09 30.94%
AGUA DE PIPA M3 $40.00 0.009775 $0.39 1.00%
SELLADOR DEL TORO KG $26.94 0.010000 $0.27 0.69%
Subtotal: MATERIALES $12.75 32.63%
MANO DE OBRA
CUADRILLA 6 (1 OF. YESERO + 1 AY YESERO) JOR $1,000.03 / 38.000000 $26.32 67.37%
Subtotal: MANO DE OBRA $26.32 67.37%
Costo directo $39.07
INDIRECTOS 5.75% $2.25
SUBTOTAL $41.32
FINANCIAMIENTO 0.791% $0.33
SUBTOTAL $41.65
UTILIDAD 8% $3.33
PRECIO UNITARIO $44.98
(* CUARENTA Y CUATRO PESOS 98/100 M.N. *)

:
Página: 22+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: IYP00003 Unidad: M2


SUMINISTRO Y APLICACIÓN DE PINTURA VINÍLICA A 2 MANOS INCLUYE SELLADO Y PREPARACIÓN DE
LA SUPERFICIE, HERRAMIENTA, MANO DE OBRA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN.
P.U.O.T.

MATERIALES
PINTURA VINILICA LINEA MULTI TONO ACABADO CUBETA $840.95 0.008947 $7.52 29.83%
MATE (BLANCO) CUBETA (19 LTS)
SELLADOR DEL TORO KG $26.94 0.100000 $2.69 10.67%
Subtotal: MATERIALES $10.21 40.50%
MANO DE OBRA
CUADRILLA 8 (1 PINTOR + 1 AY PINTOR) JOR $1,065.00 / 71.000000 $15.00 59.50%
Subtotal: MANO DE OBRA $15.00 59.50%
Costo directo $25.21
INDIRECTOS 5.75% $1.45
SUBTOTAL $26.66
FINANCIAMIENTO 0.791% $0.21
SUBTOTAL $26.87
UTILIDAD 8% $2.15
PRECIO UNITARIO $29.02
(* VEINTINUEVE PESOS 02/100 M.N. *)

:
Página: 23+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: IYP00002 Unidad: M2


IMPERMEABILIZACION DE LOSA HORIZONTAL O INCLINADA A BASE DE SISTEMA PREFABRICADO MARCA
IMPERQUIMIA, CON MODIPLY DE 3. M M DE ESPESOR GRANULADO EN COLOR ROJO Y GARANTIA DE 3
AÑOS ; INCLUYE : FLETES, ACARREOS, ELEVACIONES, DESPERDICIOS, PREPARACION DE LA
SUPERFICIE, SELLADO DE FISURAS Y PARTES CRITICAS CON CEMENTO PLASTICO ( BITUPLASTIC A.T.)
UNA APLICACION DE PRIMARIO TAPAPORO ( IMPERPRIM S-L ), COLOCACION DEL IMPERMEABILIZANTE
PREFABRICADO CON TERMOFUSION, CON TRASLAPES DE 10 CM EN LOS DOS SENTIDOS, SELLADO DE
TRASLAPES Y PUNTAS TERMINALES CON CEMENTO PLASTICO, APLICACION DE PINTURA AHULADA COLOR
ROJO TERRACOTA COMO ACABADO EN ZONAS DE SELLADO, LIMPIEZA Y RETIRO DE SOBRANTES FUERA
DE OBRA, INSTALACIONES ESPECIFICAS, MATERIALES, MANO DE OBRA EN CUALQUIER NIVEL, EQUIPO
DE SEGURIDAD, DE PRECIACION Y DEMAS CARGOS DERIVADOS DEL USO DE EQUIPO Y HERRAMIENTA;
P.U.O.T.

SUBCONTRATOS
IMPERMEABILIZACION M2 $90.00 1.000000 $90.00 100.00%
Subtotal: SUBCONTRATOS $90.00 100.00%
Costo directo $90.00
INDIRECTOS 5.75% $5.18
SUBTOTAL $95.18
FINANCIAMIENTO 0.791% $0.75
SUBTOTAL $95.93
UTILIDAD 8% $7.67
PRECIO UNITARIO $103.60
(* CIENTO TRES PESOS 60/100 M.N. *)

:
Página: 24+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: PYR00001 Unidad: M2


LOSETA CERAMICA 55 X 55 MODELO MAYACOBA DE 1RA CALIDAD, MARCA PORCELANITE, ASENTADO CON
PEGAZULEJO INLCUYE: MATERIAL, HERRAMIENTA, MANO DE OBRA Y TODO LO NECESARIO PARA SU
CORRECTA EJECUCIÓN. P.U.O.T.

MATERIALES
LOSETA CERAMICA 55 X 55 MODELO MAYACOBA CAJA $142.24 1.000000 $142.24 58.18%

PEGAZULEJO TON $2,370.69 0.005000 $11.85 4.85%


BOQUI CREST BULTO $83.19 0.055556 $4.62 1.89%
AGUA DE PIPA M3 $40.00 0.010000 $0.40 0.16%
Subtotal: MATERIALES $159.11 65.08%
MANO DE OBRA
CUADRILLA 9 (1 ALBAÑIL P/CANTERA + 1 AY JOR $700.00 / 8.200000 $85.37 34.92%
CANTERA)
Subtotal: MANO DE OBRA $85.37 34.92%
Costo directo $244.48
INDIRECTOS 5.75% $14.06
SUBTOTAL $258.54
FINANCIAMIENTO 0.791% $2.05
SUBTOTAL $260.59
UTILIDAD 8% $20.85
PRECIO UNITARIO $281.44
(* DOSCIENTOS OCHENTA Y UN PESOS 44/100 M.N. *)

:
Página: 25+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: PYR00002 Unidad: M2


PISO MOD. FALCON BEIGE-NVO DE 33x33 CMS, DE 1RA CALIDAD, MARCA PORCELANITE, ASENTADO CON
PEGAZULEJO INLCUYE: MATERIAL, HERRAMIENTA, MANO DE OBRA Y TODO LO NECESARIO PARA SU
CORRECTA EJECUCIÓN. P.U.O.T.

MATERIALES
PISO MOD. FALCON BEIGE DE 33 X 33 CMS 1.53 CAJA $110.74 0.718954 $79.62 51.42%
M2 POR CAJA
PEGAZULEJO TON $2,370.69 0.005000 $11.85 7.65%
AGUA DE PIPA M3 $40.00 0.010000 $0.40 0.26%
BOQUI CREST BULTO $83.19 / 6.000000 $13.87 8.96%
Subtotal: MATERIALES $105.74 68.29%
MANO DE OBRA
CUADRILLA 10 (1 AZULEJERO +1 AY AZULEJER JOR $932.99 / 19.000000 $49.10 31.71%
Subtotal: MANO DE OBRA $49.10 31.71%
Costo directo $154.84
INDIRECTOS 5.75% $8.90
SUBTOTAL $163.74
FINANCIAMIENTO 0.791% $1.30
SUBTOTAL $165.04
UTILIDAD 8% $13.20
PRECIO UNITARIO $178.24
(* CIENTO SETENTA Y OCHO PESOS 24/100 M.N. *)

:
Página: 26+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: PYR00003 Unidad: M2


AZULEJO MOD. FALCON HUESO DE 20x30 CMS DE 1RA CALIDAD, MARCA PORCELANITE, A UNA ALTURA
DE 2.10 M CON UN DESARROLLO DE 3.00 DE LONGITUD EN ÁREA HÚMEDA DE REGADERA Y COCINA
INCLUYE: PREVIO REPELLADO MORT 1:4 PARA RECIBIR LAMBRIN, MATERIAL, HERRAMIENTA, MANO DE
OBRA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN. P.U.O.T.

MATERIALES
AZULEJO MOD FAL HUESO DE 20 X 30 CMS 1.50 M2 $92.24 0.723680 $66.75 46.41%
MT2 POR CAJA
PEGAZULEJO TON $2,370.69 0.005000 $11.85 8.24%
AGUA DE PIPA M3 $40.00 0.010000 $0.40 0.28%
Subtotal: MATERIALES $79.00 54.93%
MANO DE OBRA
CUADRILLA 10 (1 AZULEJERO +1 AY AZULEJER JOR $932.99 / 21.000000 $44.43 30.89%
Subtotal: MANO DE OBRA $44.43 30.89%
MATERIALES
BOQUI CREST BCO BULTO $122.41 0.166667 $20.40 14.18%
Subtotal: MATERIALES $99.40 69.11%
Costo directo $143.83
INDIRECTOS 5.75% $8.27
SUBTOTAL $152.10
FINANCIAMIENTO 0.791% $1.20
SUBTOTAL $153.30
UTILIDAD 8% $12.26
PRECIO UNITARIO $165.56
(* CIENTO SESENTA Y CINCO PESOS 56/100 M.N. *)

:
Página: 27+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: PYR00004 Unidad: ML


ZOCLO CERÁMICO DE 5 CM DE ALTO DE LA MISMA LOSETA ASENTADO CON PEGAZULEJO INCLUYE:
MATERIAL, HERRAMIENTA, MANO DE OBRA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN.
P.U.O.T.

MATERIALES
PISO MOD. FALCON BEIGE DE 33 X 33 CMS 1.53 CAJA $110.74 0.072150 $7.99 25.85%
M2 POR CAJA
PEGAZULEJO TON $2,370.69 0.005000 $11.85 38.34%
AGUA DE PIPA M3 $40.00 0.004000 $0.16 0.52%
BOQUI CREST BULTO $83.19 0.016667 $1.39 4.50%
Subtotal: MATERIALES $21.39 69.20%
MANO DE OBRA
CUADRILLA 10 (1 AZULEJERO +1 AY AZULEJER JOR $932.99 / 98.000000 $9.52 30.80%
Subtotal: MANO DE OBRA $9.52 30.80%
Costo directo $30.91
INDIRECTOS 5.75% $1.78
SUBTOTAL $32.69
FINANCIAMIENTO 0.791% $0.26
SUBTOTAL $32.95
UTILIDAD 8% $2.64
PRECIO UNITARIO $35.59
(* TREINTA Y CINCO PESOS 59/100 M.N. *)

:
Página: 28+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: HAV00001 Unidad: LOTE


LOTE DE CANCELERIA

SUBCONTRATOS
LOTE DE CANCELERIA LOTE $9,482.76 1.000000 $9,482.76 100.00%
Subtotal: SUBCONTRATOS $9,482.76 100.00%
Costo directo $9,482.76
INDIRECTOS 5.75% $545.26 $545.26
SUBTOTAL $10,028.02 $10,028.02
FINANCIAMIENTO 0.791% $79.32
SUBTOTAL $10,107.34
UTILIDAD 8% $808.59
PRECIO UNITARIO $10,915.93
(* DIEZ MIL NOVECIENTOS QUINCE PESOS 93/100 M.N. *)

:
Página: 29+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: CYC00001 Unidad: PZA


PUERTA MULTIPANEL MIXTA IZQ VE/AD, COLOR BLANCA, MARCA MONTEALBAN, MOD EUCAPANE DE
90X210 CMS, EN ACCESO PRINCIPAL. INCLUYE: CHAPA DE PLOMO BOLA PARA ENTRADA, HERRAMIENTA,
MANO DE OBRA, COLOCACIÓN EN SITIO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN.
P.U.O.T.

MATERIALES
PERILLA PZA $81.89 1.000000 $81.89 3.60%
BISAGRA PZA $8.19 3.000000 $24.57 1.08%
PUERTA MULTIPANEL INTERIOR DE 85 X 210 CMS PZA $1,461.21 1.000000 $1,461.21 64.27%
MARCO P/PUERTA EXTERIOR PZA $456.00 1.000000 $456.00 20.06%
Subtotal: MATERIALES $2,023.67 89.00%
MANO DE OBRA
CUADRILLA 11 ( 1 CARPINTERO + 1 AY CARPI JOR $1,000.01 / 4.000000 $250.00 11.00%
Subtotal: MANO DE OBRA $250.00 11.00%
Costo directo $2,273.67
INDIRECTOS 5.75% $130.74
SUBTOTAL $2,404.41
FINANCIAMIENTO 0.791% $19.02
SUBTOTAL $2,423.43
UTILIDAD 8% $193.87
PRECIO UNITARIO $2,617.30
(* DOS MIL SEISCIENTOS DIECISIETE PESOS 30/100 M.N. *)

:
Página: 30+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: CYC00002 Unidad: PZA


PUERTA MULTIPANEL DE 85X210 CMS, EN RECAMARAS. INCLUYE: CHAPA DE PLOMO, HERRAMIENTA,
MANO DE OBRA, COLOCACIÓN EN SITIO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN.
P.U.O.T.

MATERIALES
PERILLA PZA $81.89 1.000000 $81.89 7.27%
BISAGRA PZA $8.19 3.000000 $24.57 2.18%
PUERTA MULTIPANEL DE 70 X 210 CMS PZA $576.72 1.000000 $576.72 51.17%
MARCO P/PUERTA INTERIOR PZA $193.97 1.000000 $193.97 17.21%
Subtotal: MATERIALES $877.15 77.82%
MANO DE OBRA
CUADRILLA 11 ( 1 CARPINTERO + 1 AY CARPI JOR $1,000.01 / 4.000000 $250.00 22.18%
Subtotal: MANO DE OBRA $250.00 22.18%
Costo directo $1,127.15
INDIRECTOS 5.75% $64.81
SUBTOTAL $1,191.96
FINANCIAMIENTO 0.791% $9.43
SUBTOTAL $1,201.39
UTILIDAD 8% $96.11
PRECIO UNITARIO $1,297.50
(* UN MIL DOSCIENTOS NOVENTA Y SIETE PESOS 50/100 M.N. *)

:
Página: 31+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: CYC00003 Unidad: PZA


PUERTA MULTIPANEL DE 70X210 CMS, EN BAÑO. INCLUYE: CHAPA, HERRAMIENTA, MANO DE OBRA,
COLOCACIÓN EN SITIO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN. P.U.O.T.

MATERIALES
PUERTA MULTIPANEL DE 70 X 210 CMS PZA $576.72 1.000000 $576.72 51.17%
PERILLA PZA $81.89 1.000000 $81.89 7.27%
BISAGRA PZA $8.19 3.000000 $24.57 2.18%
MARCO P/PUERTA INTERIOR PZA $193.97 1.000000 $193.97 17.21%
Subtotal: MATERIALES $877.15 77.82%
MANO DE OBRA
CUADRILLA 11 ( 1 CARPINTERO + 1 AY CARPI JOR $1,000.01 / 4.000000 $250.00 22.18%
Subtotal: MANO DE OBRA $250.00 22.18%
Costo directo $1,127.15
INDIRECTOS 5.75% $64.81
SUBTOTAL $1,191.96
FINANCIAMIENTO 0.791% $9.43
SUBTOTAL $1,201.39
UTILIDAD 8% $96.11
PRECIO UNITARIO $1,297.50
(* UN MIL DOSCIENTOS NOVENTA Y SIETE PESOS 50/100 M.N. *)

:
Página: 32+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: IHG00001 Unidad: LOTE


SALIDA DE CUADRO PARA MEDIDOR INCLUYE TUBERIAS DE CPVC 1/2" Y CONEXIONES NECESARIAS

MATERIALES
TUBO CPVC 1/2" MTO $8.52 15.000000 $127.80 48.08%
ADAPTADOR CPVC MACHO 1/2" PZA $1.12 1.000000 $1.12 0.42%
ADAPTADOR CPVC HEMBRA 1/2 PZA $1.90 1.000000 $1.90 0.71%
VALVULA FLOTADORA 1/2" DE COBRE PZA $58.62 1.000000 $58.62 22.05%
FLOTADOR PZA $34.78 1.000000 $34.78 13.08%
Subtotal: MATERIALES $224.22 84.35%
MANO DE OBRA
CUADRILLA 12 ( 1OF, PLOMERO + 1 AY PLOME JOR $1,167.01 / 28.050000 $41.60 15.65%
Subtotal: MANO DE OBRA $41.60 15.65%
Costo directo $265.82
INDIRECTOS 5.75% $15.28
SUBTOTAL $281.10
FINANCIAMIENTO 0.791% $2.22
SUBTOTAL $283.32
UTILIDAD 8% $22.67
PRECIO UNITARIO $305.99
(* TRESCIENTOS CINCO PESOS 99/100 M.N. *)

:
Página: 33+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: IHG00002 Unidad: LOTE


SALIDA HIDRAULICA PARA TARJA CON TUBERIA CPVC Y CONEXIONES NECESARIAS

MATERIALES
ADAPTADOR CPVC MACHO 1/2" PZA $1.12 2.000000 $2.24 0.83%
CODO CPVC 1/2" X 90 PZA $1.12 2.000000 $2.24 0.83%
TUBO CPVC 1/2" MTO $8.52 1.160000 $9.88 3.66%
TUBO CPVC 3/4" MTO $14.57 11.160000 $162.60 60.20%
TEE CPVC 3/4" PZA $2.50 3.000000 $7.50 2.78%
REDUCCION 3/4" A 1/2" PZA $1.03 2.000000 $2.06 0.76%
CODO CPVC 3/4" X 90 PZA $1.72 4.000000 $6.88 2.55%
Subtotal: MATERIALES $193.40 71.61%
MANO DE OBRA
CUADRILLA 12 ( 1OF, PLOMERO + 1 AY PLOME JOR $1,167.01 / 15.220000 $76.68 28.39%
Subtotal: MANO DE OBRA $76.68 28.39%
Costo directo $270.08
INDIRECTOS 5.75% $15.53
SUBTOTAL $285.61
FINANCIAMIENTO 0.791% $2.26
SUBTOTAL $287.87
UTILIDAD 8% $23.03
PRECIO UNITARIO $310.90
(* TRESCIENTOS DIEZ PESOS 90/100 M.N. *)

:
Página: 34+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: IHG00003 Unidad: LOTE


SALIDA HIDRAULICA PARA LAVADERO CON TUBERIA CPVC Y CONEXIONES NECESARIAS

MATERIALES
TUBO CPVC 1/2" MTO $8.52 1.650000 $14.06 10.38%
TUBO CPVC 3/4" MTO $14.57 1.100000 $16.03 11.84%
CODO CPVC 3/4" X 90 PZA $1.72 1.000000 $1.72 1.27%
REDUCCION 3/4" A 1/2" PZA $1.03 1.000000 $1.03 0.76%
CODO CPVC 1/2" X 90 PZA $1.12 1.000000 $1.12 0.83%
ADAPTADOR CPVC HEMBRA 1/2 PZA $1.90 1.000000 $1.90 1.40%
LLAVE NARIZ PZA $58.62 1.000000 $58.62 43.28%
TEE CPVC 3/4" PZA $2.50 1.000000 $2.50 1.85%
Subtotal: MATERIALES $96.98 71.61%
MANO DE OBRA
CUADRILLA 12 ( 1OF, PLOMERO + 1 AY PLOME JOR $1,167.01 / 30.350000 $38.45 28.39%
Subtotal: MANO DE OBRA $38.45 28.39%
Costo directo $135.43
INDIRECTOS 5.75% $7.79
SUBTOTAL $143.22
FINANCIAMIENTO 0.791% $1.13
SUBTOTAL $144.35
UTILIDAD 8% $11.55
PRECIO UNITARIO $155.90
(* CIENTO CINCUENTA Y CINCO PESOS 90/100 M.N. *)

:
Página: 35+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: IHG00004 Unidad: LOTE


SALIDA HIDRAULICA PARA REGADERA CON TUBERIA CPVC Y CONEXIONES NECESARIAS

MATERIALES
TEE CPVC 3/4" PZA $2.50 3.000000 $7.50 0.81%
TUBO CPVC 1/2" MTO $8.52 5.368000 $45.74 4.94%
ADAPTADOR CPVC MACHO 1/2" PZA $1.12 4.000000 $4.48 0.48%
CODO CPVC 1/2" X 90 PZA $1.12 2.000000 $2.24 0.24%
TEE CPVC 1/2" PZA $1.29 1.000000 $1.29 0.14%
REDUCCION 3/4" A 1/2" PZA $1.03 2.000000 $2.06 0.22%
CODO ADAPTADOR HEMBRA CPVC 1/2" X 90 PZA $10.26 1.000000 $10.26 1.11%
ADAPTADOR CPVC HEMBRA 1/2 PZA $1.90 4.000000 $7.60 0.82%
CODO CPVC 3/4" X 90 PZA $1.72 9.000000 $15.48 1.67%
NIPLE DE ACERO GALVANIZADO DE 3/4" X 4" PZA $10.09 1.000000 $10.09 1.09%
TUBO CPVC 1/2" MTO $8.52 5.000000 $42.60 4.60%
TUBO CPVC 3/4" MTO $14.57 23.050000 $335.84 36.30%
TEE CPVC 3/4" PZA $2.50 3.000000 $7.50 0.81%
TEE CPVC 1/2" PZA $1.29 1.000000 $1.29 0.14%
LLAVES EMPOTRABLES P/REGADERA JGO $235.34 1.000000 $235.34 25.44%
Subtotal: MATERIALES $729.31 78.83%
MANO DE OBRA
CUADRILLA 12 ( 1OF, PLOMERO + 1 AY PLOME JOR $1,167.01 / 5.960000 $195.81 21.17%
Subtotal: MANO DE OBRA $195.81 21.17%
Costo directo $925.12
INDIRECTOS 5.75% $53.19
SUBTOTAL $978.31
FINANCIAMIENTO 0.791% $7.74
SUBTOTAL $986.05
UTILIDAD 8% $78.88
PRECIO UNITARIO $1,064.93
(* UN MIL SESENTA Y CUATRO PESOS 93/100 M.N. *)

:
Página: 36+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: IHG00005 Unidad: LOTE


SALIDA HIDRAULICA PARA WC CON TUBERIA CPVC Y CONEXIONES NECESARIAS

MATERIALES
TUBO CPVC 3/4" MTO $14.57 2.040000 $29.72 54.67%
CODO CPVC 3/4" X 90 PZA $1.72 1.000000 $1.72 3.16%
REDUCCION 3/4" A 1/2" PZA $1.03 1.000000 $1.03 1.89%
TUBO CPVC 1/2" MTO $8.52 0.495000 $4.22 7.76%
CODO CPVC 1/2" X 90 PZA $1.12 1.000000 $1.12 2.06%
ADAPTADOR CPVC MACHO 1/2" PZA $1.12 1.000000 $1.12 2.06%
Subtotal: MATERIALES $38.93 71.62%
MANO DE OBRA
CUADRILLA 12 ( 1OF, PLOMERO + 1 AY PLOME JOR $1,167.01 / 75.610000 $15.43 28.38%
Subtotal: MANO DE OBRA $15.43 28.38%
Costo directo $54.36
INDIRECTOS 5.75% $3.13
SUBTOTAL $57.49
FINANCIAMIENTO 0.791% $0.45
SUBTOTAL $57.94
UTILIDAD 8% $4.64
PRECIO UNITARIO $62.58
(* SESENTA Y DOS PESOS 58/100 M.N. *)

:
Página: 37+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: IHG00006 Unidad: LOTE


SALIDA HIDRAULICA PARA LAVABO CON TUBERIA CPVC Y CONEXIONES NECESARIAS

MATERIALES
CODO CPVC 1/2" X 90 PZA $1.12 2.000000 $2.24 2.10%
CODO CPVC 3/4" X 90 PZA $1.72 2.000000 $3.44 3.22%
REDUCCION 3/4" A 1/2" PZA $1.03 2.000000 $2.06 1.93%
TUBO CPVC 1/2" MTO $8.52 2.816000 $23.99 22.44%
ADAPTADOR CPVC MACHO 1/2" PZA $1.12 1.000000 $1.12 1.05%
TUBO CPVC 3/4" MTO $14.57 3.000000 $43.71 40.88%
Subtotal: MATERIALES $76.56 71.61%
MANO DE OBRA
CUADRILLA 12 ( 1OF, PLOMERO + 1 AY PLOME JOR $1,167.01 / 38.450000 $30.35 28.39%
Subtotal: MANO DE OBRA $30.35 28.39%
Costo directo $106.91
INDIRECTOS 5.75% $6.15
SUBTOTAL $113.06
FINANCIAMIENTO 0.791% $0.89
SUBTOTAL $113.95
UTILIDAD 8% $9.12
PRECIO UNITARIO $123.07
(* CIENTO VEINTITRES PESOS 07/100 M.N. *)

:
Página: 38+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: IHG00007 Unidad: LOTE


SALIDA HIDRAULICA PARA ALIMENTACION A TINACO CON TUBERIA CPVC Y CONEXIONES NECESARIAS
DIAMETROS 19 Y 13 MM

MATERIALES
ADAPTADOR CPVC MACHO 1/2" PZA $1.12 1.000000 $1.12 0.34%
TUBO CPVC 1/2" MTO $8.52 15.000000 $127.80 39.06%
ADAPTADOR CPVC HEMBRA 1/2 PZA $1.90 1.000000 $1.90 0.58%
FLOTADOR PZA $34.78 1.000000 $34.78 10.63%
VALVULA FLOTADORA 1/2" DE COBRE PZA $58.62 1.000000 $58.62 17.92%
CODO CPVC 1/2" X 90 PZA $1.12 9.000000 $10.08 3.08%
Subtotal: MATERIALES $234.30 71.61%
MANO DE OBRA
CUADRILLA 12 ( 1OF, PLOMERO + 1 AY PLOME JOR $1,167.01 / 12.560000 $92.91 28.39%
Subtotal: MANO DE OBRA $92.91 28.39%
Costo directo $327.21
INDIRECTOS 5.75% $18.81
SUBTOTAL $346.02
FINANCIAMIENTO 0.791% $2.74
SUBTOTAL $348.76
UTILIDAD 8% $27.90
PRECIO UNITARIO $376.66
(* TRESCIENTOS SETENTA Y SEIS PESOS 66/100 M.N. *)

:
Página: 39+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: IHG00008 Unidad: LOTE


SALIDA DE ACERO GALVANIZADO PARA ALIMENTACION DE GAS AL BOILER, CILINDRO DE GAS Y
ESTUFA.

MATERIALES
CODO DE ACERO GALVANIZADO DE 1/2" X 90 PZA $5.00 3.000000 $15.00 6.01%
TEE DE ACERO GALVANIZADO DE 1/2" PZA $7.76 1.000000 $7.76 3.11%
TUBO ACERO GALVANIZADO 1/2" MTO $56.32 2.770000 $156.01 62.50%
Subtotal: MATERIALES $178.77 71.61%
MANO DE OBRA
CUADRILLA 12 ( 1OF, PLOMERO + 1 AY PLOME JOR $1,167.01 / 16.470000 $70.86 28.39%
Subtotal: MANO DE OBRA $70.86 28.39%
Costo directo $249.63
INDIRECTOS 5.75% $14.35
SUBTOTAL $263.98
FINANCIAMIENTO 0.791% $2.09
SUBTOTAL $266.07
UTILIDAD 8% $21.29
PRECIO UNITARIO $287.36
(* DOSCIENTOS OCHENTA Y SIETE PESOS 36/100 M.N. *)

:
Página: 40+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: IHG00009 Unidad: PZA


REGISTRO SANITARIO A BASE DE TABIQUE ROJO RECOCIDO COMUN, ASENTADO CON MORTERO
CEMENTO:ARENA 1:4, INCLUYE MARCO Y CONTRAMARCO DE ANGULO, TERMINADO AFINADO INTERIOR

MATERIALES
TABIQUE ROJO RECOCIDO DE 7 X 14 X 28 CMS MILLAR $2,327.59 0.120000 $279.31 29.70%
MARCO Y CONTRAMARCO DE ANGULO PZA $215.00 1.000000 $215.00 22.86%
Subtotal: MATERIALES $494.31 52.56%
MANO DE OBRA
CUADRILLA 1 ( 1OF. ALBAÑIL + 1 PEON) JOR $500.01 / 2.000000 $250.01 26.58%
Subtotal: MANO DE OBRA $250.01 26.58%
BASICOS
MORTERO CEMENTO ARENA PROP:1:4 M3 $1,138.33 0.062370 $71.00 7.55%
CONCRETO F C=150 KG/CM2 M3 $804.57 0.124700 $100.33 10.67%
MORTERO CEMENTO ARENA PROP:1:3 M3 $1,571.90 0.015840 $24.90 2.65%
Subtotal: BASICOS $196.23 20.86%
Costo directo $940.55
INDIRECTOS 5.75% $54.08
SUBTOTAL $994.63
FINANCIAMIENTO 0.791% $7.87
SUBTOTAL $1,002.50
UTILIDAD 8% $80.20
PRECIO UNITARIO $1,082.70
(* UN MIL OCHENTA Y DOS PESOS 70/100 M.N. *)

:
Página: 41+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: IHG00010 Unidad: LOTE


SALIDA SANITARIA PARA TARJA CON TUBERIA PVC 2" Y CONEXIONES NECESARIAS

MATERIALES
ADAPTADOR HULE DE 2" PZA $2.41 1.000000 $2.41 7.02%
CODO DE PVC SANITARIO DE 2" X 90 PZA $1.98 2.000000 $3.96 11.54%
TUBO DE PVC SANITARIO DE 2" MTO $9.62 1.892000 $18.20 53.05%
Subtotal: MATERIALES $24.57 71.61%
MANO DE OBRA
CUADRILLA 12 ( 1OF, PLOMERO + 1 AY PLOME JOR $1,167.01 / 119.800000 $9.74 28.39%
Subtotal: MANO DE OBRA $9.74 28.39%
Costo directo $34.31
INDIRECTOS 5.75% $1.97
SUBTOTAL $36.28
FINANCIAMIENTO 0.791% $0.29
SUBTOTAL $36.57
UTILIDAD 8% $2.93
PRECIO UNITARIO $39.50
(* TREINTA Y NUEVE PESOS 50/100 M.N. *)

:
Página: 42+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: IHG00011 Unidad: LOTE


SALIDA SANITARIA PARA LAVADERO CON TUBERIA PVC 2" Y CONEXIONES NECESARIAS

MATERIALES
TUBO PVC SANITARIO 2" MTO $9.62 1.100000 $10.58 14.32%
COLADERA PARA REGADERA PZA $40.34 1.000000 $40.34 54.61%
CODO DE PVC SANITARIO DE 2" X 90 PZA $1.98 1.000000 $1.98 2.68%
Subtotal: MATERIALES $52.90 71.61%
MANO DE OBRA
CUADRILLA 12 ( 1OF, PLOMERO + 1 AY PLOME JOR $1,167.01 / 55.640000 $20.97 28.39%
Subtotal: MANO DE OBRA $20.97 28.39%
Costo directo $73.87
INDIRECTOS 5.75% $4.25
SUBTOTAL $78.12
FINANCIAMIENTO 0.791% $0.62
SUBTOTAL $78.74
UTILIDAD 8% $6.30
PRECIO UNITARIO $85.04
(* OCHENTA Y CINCO PESOS 04/100 M.N. *)

:
Página: 43+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: IHG00012 Unidad: LOTE


SALIDA SANITARIA PARA COLADERA DE REGADERA CON TUBERIA PVC 2" Y CONEXIONES NECESARIAS

MATERIALES
COLADERA PARA REGADERA PZA $40.34 1.000000 $40.34 38.65%
CODO DE PVC SANITARIO DE 2" X 90 PZA $1.98 1.000000 $1.98 1.90%
TUBO PVC SANITARIO 2" MTO $9.62 1.122000 $10.79 10.34%
TEE EN YEE DE PVC SANITARIO DE 2" X 2" PZA $20.00 1.000000 $20.00 19.16%
CODO DE PVC SANITARIO DE 2" X 45 PZA $1.64 1.000000 $1.64 1.57%
Subtotal: MATERIALES $74.75 71.61%
MANO DE OBRA
CUADRILLA 12 ( 1OF, PLOMERO + 1 AY PLOME JOR $1,167.01 / 39.380000 $29.63 28.39%
Subtotal: MANO DE OBRA $29.63 28.39%
Costo directo $104.38
INDIRECTOS 5.75% $6.00
SUBTOTAL $110.38
FINANCIAMIENTO 0.791% $0.87
SUBTOTAL $111.25
UTILIDAD 8% $8.90
PRECIO UNITARIO $120.15
(* CIENTO VEINTE PESOS 15/100 M.N. *)

:
Página: 44+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: IHG00013 Unidad: LOTE


SALIDA SANITARIA PARA WC CON TUBERIA PVC 4" Y CONEXIONES NECESARIAS

MATERIALES
CODO PVC SANITARIO 90 4" X 2" PZA $13.79 1.000000 $13.79 9.03%
TUBO PVC SANITARIO 4" MTO $22.57 4.158000 $93.85 61.43%
Subtotal: MATERIALES $107.64 70.46%
MANO DE OBRA
CUADRILLA 12 ( 1OF, PLOMERO + 1 AY PLOME JOR $1,167.01 / 25.860000 $45.13 29.54%
Subtotal: MANO DE OBRA $45.13 29.54%
Costo directo $152.77
INDIRECTOS 5.75% $8.78
SUBTOTAL $161.55
FINANCIAMIENTO 0.791% $1.28
SUBTOTAL $162.83
UTILIDAD 8% $13.03
PRECIO UNITARIO $175.86
(* CIENTO SETENTA Y CINCO PESOS 86/100 M.N. *)

:
Página: 45+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: IHG00014 Unidad: LOTE


SALIDA SANITARIA PARA LAVABO CON TUBERIA PVC 2" Y CONEXIONES NECESARIAS

MATERIALES
TUBO PVC SANITARIO 2" MTO $9.62 1.000000 $9.62 43.08%
CODO DE PVC SANITARIO DE 2" X 90 PZA $1.98 2.000000 $3.96 17.73%
ADAPTADOR HULE DE 2" PZA $2.41 1.000000 $2.41 10.79%
Subtotal: MATERIALES $15.99 71.61%
MANO DE OBRA
CUADRILLA 12 ( 1OF, PLOMERO + 1 AY PLOME JOR $1,167.01 / 184.090000 $6.34 28.39%
Subtotal: MANO DE OBRA $6.34 28.39%
Costo directo $22.33
INDIRECTOS 5.75% $1.28
SUBTOTAL $23.61
FINANCIAMIENTO 0.791% $0.19
SUBTOTAL $23.80
UTILIDAD 8% $1.90
PRECIO UNITARIO $25.70
(* VEINTICINCO PESOS 70/100 M.N. *)

:
Página: 46+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: IHG00015 Unidad: LOTE


RAMALEO SANITARIO GENERAL CON TUBERIA PVC 4" Y CONEXIONES NECESARIAS

MATERIALES
TUBO PVC SANITARIO 4" MTO $22.57 14.000000 $315.98 68.42%
COPLE PVC SANITARIO 4" PZA $4.91 3.000000 $14.73 3.19%
Subtotal: MATERIALES $330.71 71.61%
MANO DE OBRA
CUADRILLA 12 ( 1OF, PLOMERO + 1 AY PLOME JOR $1,167.01 / 8.900000 $131.12 28.39%
Subtotal: MANO DE OBRA $131.12 28.39%
Costo directo $461.83
INDIRECTOS 5.75% $26.56
SUBTOTAL $488.39
FINANCIAMIENTO 0.791% $3.86
SUBTOTAL $492.25
UTILIDAD 8% $39.38
PRECIO UNITARIO $531.63
(* QUINIENTOS TREINTA Y UN PESOS 63/100 M.N. *)

:
Página: 47+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: IHG00016 Unidad: LOTE


SALIDA SANITARIA PARA LAVADORA CON TUBERIA PVC 2" Y CONEXIONES NECESARIAS

MATERIALES
CODO DE PVC SANITARIO DE 2" X 45 PZA $1.64 1.000000 $1.64 2.79%
CODO DE PVC SANITARIO DE 2" X 90 PZA $1.98 1.000000 $1.98 3.37%
TUBO DE PVC SANITARIO DE 2" MTO $9.62 4.000000 $38.48 65.45%
Subtotal: MATERIALES $42.10 71.61%
MANO DE OBRA
CUADRILLA 12 ( 1OF, PLOMERO + 1 AY PLOME JOR $1,167.01 / 69.920000 $16.69 28.39%
Subtotal: MANO DE OBRA $16.69 28.39%
Costo directo $58.79
INDIRECTOS 5.75% $3.38
SUBTOTAL $62.17
FINANCIAMIENTO 0.791% $0.49
SUBTOTAL $62.66
UTILIDAD 8% $5.01
PRECIO UNITARIO $67.67
(* SESENTA Y SIETE PESOS 67/100 M.N. *)

:
Página: 48+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: IHG00018 Unidad: LOTE


SALIDA HIDRAULICA PARA LAVADORA CON TUBERIA CPVC Y CONEXIONES NECESARIAS

MATERIALES
TEE CPVC 3/4" PZA $2.50 1.000000 $2.50 0.57%
LLAVE NARIZ PZA $58.62 2.000000 $117.24 26.80%
CODO CPVC 1/2" X 90 PZA $1.12 2.000000 $2.24 0.51%
REDUCCION 3/4" A 1/2" PZA $1.03 2.000000 $2.06 0.47%
CODO CPVC 3/4" X 90 PZA $1.72 2.000000 $3.44 0.79%
TUBO CPVC 1/2" MTO $8.52 3.000000 $25.56 5.84%
TUBO CPVC 3/4" MTO $14.57 11.000000 $160.27 36.64%
Subtotal: MATERIALES $313.31 71.62%
MANO DE OBRA
CUADRILLA 12 ( 1OF, PLOMERO + 1 AY PLOME JOR $1,167.01 / 9.400000 $124.15 28.38%
Subtotal: MANO DE OBRA $124.15 28.38%
Costo directo $437.46
INDIRECTOS 5.75% $25.15
SUBTOTAL $462.61
FINANCIAMIENTO 0.791% $3.66
SUBTOTAL $466.27
UTILIDAD 8% $37.30
PRECIO UNITARIO $503.57
(* QUINIENTOS TRES PESOS 57/100 M.N. *)

:
Página: 49+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: MBC00001 Unidad: PZAS


SUMINISTRO Y COLOCACION DE TINACO DE 600 LTS MCA ROTOPLAS O SIMILAR

MATERIALES
TINACO EUREKA TRICAPA NEGRO 600 LTS PZA $936.47 1.000000 $936.47 54.43%
C/ACCS
FLOTADOR PZA $34.78 1.000000 $34.78 2.02%
TEE CPVC 1/2" PZA $1.29 1.000000 $1.29 0.07%
ADAPTADOR CPVC HEMBRA 3/4" PZA $2.59 1.000000 $2.59 0.15%
ADAPTADOR CPVC HEMBRA 1/2 PZA $1.90 1.000000 $1.90 0.11%
Subtotal: MATERIALES $977.03 56.79%
MANO DE OBRA
CUADRILLA 12 ( 1OF, PLOMERO + 1 AY PLOME JOR $1,167.01 / 3.140000 $371.66 21.60%
CUADRILLA 12 ( 1OF, PLOMERO + 1 AY PLOME JOR $1,167.01 / 3.140000 $371.66 21.60%
Subtotal: MANO DE OBRA $743.32 43.21%
Costo directo $1,720.35
INDIRECTOS 5.75% $98.92
SUBTOTAL $1,819.27
FINANCIAMIENTO 0.791% $14.39
SUBTOTAL $1,833.66
UTILIDAD 8% $146.69
PRECIO UNITARIO $1,980.35
(* UN MIL NOVECIENTOS OCHENTA PESOS 35/100 M.N. *)

:
Página: 50+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: MBC00002 Unidad: PZAS


SUMINISTRO Y COLOCACION DE CALENTADOR DE 6 LT DE PASO MARCA CINSA O SIMILAR

MATERIALES
CALENTADOR DE PASO MCA CINSA DE 6 LTS PZA $2,508.78 1.000000 $2,508.78 71.55%
Subtotal: MATERIALES $2,508.78 71.55%
MANO DE OBRA
CUADRILLA 12 ( 1OF, PLOMERO + 1 AY PLOME JOR $1,167.01 / 1.170000 $997.44 28.45%
Subtotal: MANO DE OBRA $997.44 28.45%
Costo directo $3,506.22
INDIRECTOS 5.75% $201.61
SUBTOTAL $3,707.83
FINANCIAMIENTO 0.791% $29.33
SUBTOTAL $3,737.16
UTILIDAD 8% $298.97
PRECIO UNITARIO $4,036.13
(* CUATRO MIL TREINTA Y SEIS PESOS 13/100 M.N. *)

:
Página: 51+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: MBC00003 Unidad: PZA


SUMINISTRO Y COLOCACION DE LAVADERO DE GRANITO CON PILETA

MATERIALES
LAVADERO DE GRANITO CON PILETA PZA $523.28 1.000000 $523.28 80.72%
Subtotal: MATERIALES $523.28 80.72%
MANO DE OBRA
CUADRILLA 1 ( 1OF. ALBAÑIL + 1 PEON) JOR $500.01 / 4.000000 $125.00 19.28%
Subtotal: MANO DE OBRA $125.00 19.28%
Costo directo $648.28
INDIRECTOS 5.75% $37.28
SUBTOTAL $685.56
FINANCIAMIENTO 0.791% $5.42
SUBTOTAL $690.98
UTILIDAD 8% $55.28
PRECIO UNITARIO $746.26
(* SETECIENTOS CUARENTA Y SEIS PESOS 26/100 M.N. *)

:
Página: 52+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: MBC00004 Unidad: PZA


SUMINISTRO E INSTALACION DE TARJA CON ESCURRIDOR 96 X 40 INCLUYE MEZCLADORA LINEA
ECONOMICA

MATERIALES
TARJA CON ESCURRIDOR 96 X 40 CMS PZA $1,102.58 1.000000 $1,102.58 59.01%
MEZCLADORA PARA FREGADERO LINEA PZA $47.50 1.000000 $47.50 2.54%
ECONOMICA
CESPOL PARA FREGADERO LINEA ECONOMICA PZA $40.86 1.000000 $40.86 2.19%
VALVULA ANGULAR NACOBRE 1/2" PZA $37.32 2.000000 $74.64 3.99%
FLEXICOS PARA FREGADERO PZA $12.50 2.000000 $25.00 1.34%
CONTRACANASTA P/FREGADERO PZA $47.50 1.000000 $47.50 2.54%
Subtotal: MATERIALES $1,338.08 71.61%
MANO DE OBRA
CUADRILLA 12 ( 1OF, PLOMERO + 1 AY PLOME JOR $1,167.01 / 2.200000 $530.46 28.39%
Subtotal: MANO DE OBRA $530.46 28.39%
Costo directo $1,868.54
INDIRECTOS 5.75% $107.44
SUBTOTAL $1,975.98
FINANCIAMIENTO 0.791% $15.63
SUBTOTAL $1,991.61
UTILIDAD 8% $159.33
PRECIO UNITARIO $2,150.94
(* DOS MIL CIENTO CINCUENTA PESOS 94/100 M.N. *)

:
Página: 53+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: MBC00005 Unidad: JGO


SUMINISTRO E INSTALACION DE PAQUETE DE BAÑO COLOR BLANCO LINEA ECONOMICA CON MEZCLADORA
DE 4", INCLUYE TAZA, TANQUE, LAVAMANOS Y PEDESTAL.

MATERIALES
TANQUE CATO JAZMIN BLANCO PZA $362.93 1.000000 $362.93 18.81%
TAZA CATO JAZMIN REDONDO BLANCO PZA $363.09 1.000000 $363.09 18.82%
FLEXICO NAC ALUMINIO COBRECEL W.C. PZA $12.50 1.000000 $12.50 0.65%
LAVAVO CATO JAZMIN PZA $200.43 1.000000 $200.43 10.39%
PEDESTAL CATO JAZMIN BLANCO PZA $221.47 1.000000 $221.47 11.48%
MEZCLADORA P/LAVAVO LINEA ECONOMICA PZA $196.03 1.000000 $196.03 10.16%
FLEXICOS P/LAVAVO LINEA ECONOMICA PZA $12.66 2.000000 $25.32 1.31%
Subtotal: MATERIALES $1,381.77 71.61%
MANO DE OBRA
CUADRILLA 12 ( 1OF, PLOMERO + 1 AY PLOME JOR $1,167.01 / 2.130000 $547.89 28.39%
Subtotal: MANO DE OBRA $547.89 28.39%
Costo directo $1,929.66
INDIRECTOS 5.75% $110.96
SUBTOTAL $2,040.62
FINANCIAMIENTO 0.791% $16.14
SUBTOTAL $2,056.76
UTILIDAD 8% $164.54
PRECIO UNITARIO $2,221.30
(* DOS MIL DOSCIENTOS VEINTIUN PESOS 30/100 M.N. *)

:
Página: 54+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: MBC00006 Unidad: JGO


SUMINISTRO E INSTALACION DE REGADERA CON BRAZO Y CHAPETON LINEA ECONOMICA, INCLUYE
MANERALES

MATERIALES
ENSAMBLE DICA ROSCABLES PARA REGADERA JGO $196.03 1.000000 $196.03 50.51%
REGADERA INCLUYE BRAZO Y CHAPETON JGO $81.90 1.000000 $81.90 21.10%
Subtotal: MATERIALES $277.93 71.61%
MANO DE OBRA
CUADRILLA 12 ( 1OF, PLOMERO + 1 AY PLOME JOR $1,167.01 / 10.590000 $110.20 28.39%
Subtotal: MANO DE OBRA $110.20 28.39%
Costo directo $388.13
INDIRECTOS 5.75% $22.32
SUBTOTAL $410.45
FINANCIAMIENTO 0.791% $3.25
SUBTOTAL $413.70
UTILIDAD 8% $33.10
PRECIO UNITARIO $446.80
(* CUATROCIENTOS CUARENTA Y SEIS PESOS 80/100 M.N. *)

:
Página: 55+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: MBC00007 Unidad: JGO


SUMINISTRO Y COLOCACIÓN DE ACCESORIOS CERAMICOS PARA BAÑO: INCLUYE: JABONERA, CEPILLERO,
GANCHO Y PORTAPAPEL.

MATERIALES
ACCESORIOS CERAMICOS PARA BAÑO LINEA JGO $117.33 1.000000 $117.33 41.31%
ECONOMICA
Subtotal: MATERIALES $117.33 41.31%
MANO DE OBRA
CUADRILLA 1 ( 1OF. ALBAÑIL + 1 PEON) JOR $500.01 / 3.000000 $166.67 58.69%
Subtotal: MANO DE OBRA $166.67 58.69%
Costo directo $284.00
INDIRECTOS 5.75% $16.33
SUBTOTAL $300.33
FINANCIAMIENTO 0.791% $2.38
SUBTOTAL $302.71
UTILIDAD 8% $24.22
PRECIO UNITARIO $326.93
(* TRESCIENTOS VEINTISEIS PESOS 93/100 M.N. *)

:
Página: 56+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: IEL00001 Unidad: LOTE


SALIDA ELECTRICA PARA CONTACTO CON POLIDUCTO DE 13 MM, CABLE THW CAL. 12 Y 14, CAJA
CHALUPA GALVANIZADA, INCLUYE ACCESORIOS LINEA ECONOMICA

MATERIALES
CABLE THW CAL. 12 MTO $4.96 120.000000 $595.20 14.33%
CABLE THW CAL. 14 MTO $3.53 60.000000 $211.80 5.10%
CONTACTO DUPLEX MCA. MONTANA PZA $40.09 7.000000 $280.63 6.76%
CONTACTO A INTERPERIE PZA $150.00 2.000000 $300.00 7.22%
CONTACTO TIERRA A FALLA PZA $223.83 4.000000 $895.32 21.55%
CHALUPA GALVANIZADA PZA $7.75 13.000000 $100.75 2.43%
CINTA AISLANTE ELECTRICA PVC PZA $6.90 3.000000 $20.70 0.50%
Subtotal: MATERIALES $2,404.40 57.88%
MANO DE OBRA
CUADRILLA 30 ( 1 ELECTRICISTA + 1 AY EL) JOR $875.00 / 0.500000 $1,750.00 42.12%
Subtotal: MANO DE OBRA $1,750.00 42.12%
Costo directo $4,154.40
INDIRECTOS 5.75% $238.88
SUBTOTAL $4,393.28
FINANCIAMIENTO 0.791% $34.75
SUBTOTAL $4,428.03
UTILIDAD 8% $354.24
PRECIO UNITARIO $4,782.27
(* CUATRO MIL SETECIENTOS OCHENTA Y DOS PESOS 27/100 M.N. *)

:
Página: 57+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: IEL00002 Unidad: LOTE


SALIDA ELECTRICA PARA APAGADOR CON POLIDUCTO DE 13 MM, CABLE THW CAL. 12 Y 14, CAJA
CHALUPA GALVANIZADA, INCLUYE ACCESORIOS LINEA ECONOMICA

MATERIALES
CABLE THW CAL. 14 MTO $3.53 114.000000 $402.42 17.45%
POLIDUCTO NARANJA DE 13 MM MTO $1.55 114.000000 $176.70 7.66%
APAGADOR PZA $21.11 8.000000 $168.88 7.32%
TAPA CIEGA 4" PZA $5.43 11.000000 $59.73 2.59%
INTERRUPTOR TRES VIAS PZA $27.56 2.000000 $55.12 2.39%
SOQUET SENCILLO PZA $11.21 11.000000 $123.31 5.35%
CHALUPA GALVANIZADA PZA $7.75 7.000000 $54.25 2.35%
PLACA + CHASIS 1 MOD PZA $20.05 3.000000 $60.15 2.61%
PLACA + CHASIS 2 MOD PZA $20.05 4.000000 $80.20 3.48%
CINTA AISLANTE ELECTRICA PVC PZA $6.90 3.000000 $20.70 0.90%
CHALUPA GALVANIZADA 4" PZA $12.07 11.000000 $132.77 5.76%
Subtotal: MATERIALES $1,334.23 57.85%
MANO DE OBRA
CUADRILLA 30 ( 1 ELECTRICISTA + 1 AY EL) JOR $875.00 / 0.900000 $972.22 42.15%
Subtotal: MANO DE OBRA $972.22 42.15%
Costo directo $2,306.45
INDIRECTOS 5.75% $132.62
SUBTOTAL $2,439.07
FINANCIAMIENTO 0.791% $19.29
SUBTOTAL $2,458.36
UTILIDAD 8% $196.67
PRECIO UNITARIO $2,655.03
(* DOS MIL SEISCIENTOS CINCUENTA Y CINCO PESOS 03/100 M.N. *)

:
Página: 58+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: IEL00004 Unidad: PZA


CENTRO DE CARGA QO2 1 FASE 4 HILOS MCA IUSA, INCLUYE INTERRUPTOR TERMOMAGNETICO 20 AMP

MATERIALES
CENTRO DE CARGA 4 VIAS PZA $102.93 1.000000 $102.93 7.70%
INTERRUPTOR VOLTECH 20 A PZA $38.79 3.000000 $116.37 8.70%
CINTA AISLANTE ELECTRICA PVC PZA $6.90 1.000000 $6.90 0.52%
Subtotal: MATERIALES $226.20 16.92%
MANO DE OBRA
CUADRILLA 30 ( 1 ELECTRICISTA + 1 AY EL) JOR $875.00 / 1.500000 $583.33 43.63%
Subtotal: MANO DE OBRA $583.33 43.63%
MATERIALES
CABLE THW MTO $15.51 34.000000 $527.34 39.45%
Subtotal: MATERIALES $753.54 56.37%
Costo directo $1,336.87
INDIRECTOS 5.75% $76.87
SUBTOTAL $1,413.74
FINANCIAMIENTO 0.791% $11.18
SUBTOTAL $1,424.92
UTILIDAD 8% $113.99
PRECIO UNITARIO $1,538.91
(* UN MIL QUINIENTOS TREINTA Y OCHO PESOS 91/100 M.N. *)

:
Página: 59+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: IEL00005 Unidad: PZA


SALIDA PARA TV, TELEFONO Y EXTRACTOR A BASE DE POLIDUCTO DE 1/2" Y CAJA CHALUPA GUIADA
CON ALAMBRE GALV. INCLUYE: MATERIAL, MANO DE OBRA Y HERRAMIENTA.

MATERIALES
TOMA TV. 1 MOD PZA $85.32 1.000000 $85.32 36.53%
POLIDUCTO NARANJA DE 13 MM MTO $1.55 15.000000 $23.25 9.95%
PLACA + CHASIS 1 MOD PZA $20.05 1.000000 $20.05 8.58%
CHALUPA GALVANIZADA PZA $7.75 1.000000 $7.75 3.32%
Subtotal: MATERIALES $136.37 58.38%
MANO DE OBRA
CUADRILLA 30 ( 1 ELECTRICISTA + 1 AY EL) JOR $875.00 / 9.000000 $97.22 41.62%
Subtotal: MANO DE OBRA $97.22 41.62%
Costo directo $233.59
INDIRECTOS 5.75% $13.43
SUBTOTAL $247.02
FINANCIAMIENTO 0.791% $1.95
SUBTOTAL $248.97
UTILIDAD 8% $19.92
PRECIO UNITARIO $268.89
(* DOSCIENTOS SESENTA Y OCHO PESOS 89/100 M.N. *)

:
Página: 60+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: IEL00006 Unidad: PZA


SALIDA PARA TIMBRE INCLUYE: PLACA, ZUMBADOR Y BOTON TIMBRE.

MATERIALES
CABLE THW CAL. 14 MTO $3.53 16.000000 $56.48 30.35%
TIMBRE PZA $10.72 1.000000 $10.72 5.76%
ZUMBADOR PZA $19.30 1.000000 $19.30 10.37%
PLACA + CHASIS 1 MOD PZA $20.05 1.000000 $20.05 10.77%
Subtotal: MATERIALES $106.55 57.25%
MANO DE OBRA
CUADRILLA 30 ( 1 ELECTRICISTA + 1 AY EL) JOR $875.00 / 11.000000 $79.55 42.75%
Subtotal: MANO DE OBRA $79.55 42.75%
Costo directo $186.10
INDIRECTOS 5.75% $10.70
SUBTOTAL $196.80
FINANCIAMIENTO 0.791% $1.56
SUBTOTAL $198.36
UTILIDAD 8% $15.87
PRECIO UNITARIO $214.23
(* DOSCIENTOS CATORCE PESOS 23/100 M.N. *)

:
Página: 61+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: LIM00001 Unidad: LOTE


LIMPIEZA FINAL DE OBRA, INCLUYE PISOS, ZOCLOS, CRSITALES, MUEBLES DE BAÑO, AZULEJOS

MANO DE OBRA
CUADRILLA 12 ( 2 OF. LIMPIEZA) JOR $400.02 1.000000 $400.02 100.00%
Subtotal: MANO DE OBRA $400.02 100.00%
Costo directo $400.02
INDIRECTOS 5.75% $23.00
SUBTOTAL $423.02
FINANCIAMIENTO 0.791% $3.35
SUBTOTAL $426.37
UTILIDAD 8% $34.11
PRECIO UNITARIO $460.48
(* CUATROCIENTOS SESENTA PESOS 48/100 M.N. *)

:
Página: 62+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: OEX00002 Unidad: PZA


HUELLAS DE CONCRETO 0.50 X 0.90 CONCRETO

MANO DE OBRA
CUADRILLA 1 ( 1OF. ALBAÑIL + 1 PEON) JOR $500.01 / 24.000000 $20.83 36.76%
Subtotal: MANO DE OBRA $20.83 36.76%
BASICOS
CONCRETO F C=150 KG/CM2 M3 $804.57 0.044550 $35.84 63.24%
Subtotal: BASICOS $35.84 63.24%
Costo directo $56.67
INDIRECTOS 5.75% $3.26
SUBTOTAL $59.93
FINANCIAMIENTO 0.791% $0.47
SUBTOTAL $60.40
UTILIDAD 8% $4.83
PRECIO UNITARIO $65.23
(* SESENTA Y CINCO PESOS 23/100 M.N. *)

:
Página: 63+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: OEX00003 Unidad: M2


BANQUETA DE CONCRETO SIMPLE DE 10 CM DE ESPESOR CONCRETO HECHO EN OBRA F'C=150 KG/CM2,
AGREGADO MAXIMO 1 1/2" ACABADO ESCOBILLADO(BANQUETA DE ACCESO Y BANQUETA POSTERIOR)

MANO DE OBRA
CUADRILLA 13 (1 COLADOR + 1 AY DE COL) JOR $850.00 / 7.000000 $121.43 58.97%
Subtotal: MANO DE OBRA $121.43 58.97%
BASICOS
CONCRETO F C=150 KG/CM2 M3 $804.57 0.105000 $84.48 41.03%
Subtotal: BASICOS $84.48 41.03%
Costo directo $205.91
INDIRECTOS 5.75% $11.84
SUBTOTAL $217.75
FINANCIAMIENTO 0.791% $1.72
SUBTOTAL $219.47
UTILIDAD 8% $17.56
PRECIO UNITARIO $237.03
(* DOSCIENTOS TREINTA Y SIETE PESOS 03/100 M.N. *)

:
Página: 64+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: OEX00004 Unidad: ML


ZAPATA CORRIDA DE CONCRETO DE F'C=200 KG/CM2 EN LINDERO, DE 25 CMS DE ESPESOR INCLUYE:
VARILLA DE 3/8 A CADA 20 CMS AMBOS SENTIDOS, CADENA CD-1 A BASE DE ARMEX 12X12-4, MURO DE
BLOCK 12x20x40 CMS, ASENTADO CON MORTERO, CEMENTO, ARENA PROPORCIO 1:4, HERRAMIENTA, MANO
DE OBRA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN. P.U.O.T.

MATERIALES
CONCRETO PREMEZCLADO F C= 200KG/CM2 M3 $1,164.63 0.047000 $54.74 40.06%
CASTILLO ELECTROSOLDADO 10 X 10 CM ML $20.11 1.000000 $20.11 14.72%
ROLLO DE 2.5 X 40 M DE MALLA ROLLO $1,729.39 0.003150 $5.45 3.99%
ELECTROSOLDADA 6 X 6-4/4
POLIETILENO NEGRO 93 M2 ROLLO $981.90 0.006452 $6.34 4.64%
Subtotal: MATERIALES $86.64 63.41%
MANO DE OBRA
CUADRILLA 4 ( 1 ALBAÑIL P/CASTILLOS + 1 JOR $750.01 / 15.000000 $50.00 36.59%
Subtotal: MANO DE OBRA $50.00 36.59%
Costo directo $136.64
INDIRECTOS 5.75% $7.86
SUBTOTAL $144.50
FINANCIAMIENTO 0.791% $1.14
SUBTOTAL $145.64
UTILIDAD 8% $11.65
PRECIO UNITARIO $157.29
(* CIENTO CINCUENTA Y SIETE PESOS 29/100 M.N. *)

:
Página: 65+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: OEX00005 Unidad: M2


BARDA PERIMETRAL A BASE DE MURO DE BLOCK 12X20X40 CMS DE ESPESOR ASENTADO CON MORTERO
CEMENTO- CAL- ARENA PROPORCIÓN 1:3:12 A NIVEL Y PLOMO, CADENA CD-1 A BASE DE ARMEX
12X12-4, APLANADO CON MORTERO FINO CEMENTO:ARENA SOBRE CARA DE BLOCK A UN PROMEDIO DE 2
CMS. DE ESPESOR A REGLA Y PLOMO. INCLUYE: ANDAMIOS, MATERIALES, MANO DE OBRA, EQUIPO Y
HERRAMIENTA, P.U.O.T.

MATERIALES
BLOCK DE CONCRETO DE 12 X 20 X 40 CMS PZA $6.03 12.000000 $72.36 55.67%
ESCALERILLA DE 5M PZA $11.50 0.366670 $4.22 3.25%
Subtotal: MATERIALES $76.58 58.91%
MANO DE OBRA
CUADRILLA 5 (1 OF. BLOQUERO +1 AY BLOCK) JOR $875.02 / 27.000000 $32.41 24.93%
Subtotal: MANO DE OBRA $32.41 24.93%
BASICOS
MORTERO CEMENTO CAL ARENA PROP: 1:.25:3 M3 $389.80 0.053880 $21.00 16.16%
Subtotal: BASICOS $21.00 16.16%
Costo directo $129.99
INDIRECTOS 5.75% $7.47
SUBTOTAL $137.46
FINANCIAMIENTO 0.791% $1.09
SUBTOTAL $138.55
UTILIDAD 8% $11.08
PRECIO UNITARIO $149.63
(* CIENTO CUARENTA Y NUEVE PESOS 63/100 M.N. *)

:
Página: 66+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: OEX00001 Unidad: PZA


HUELLAS DE CONCRETO 0.45 X 0.45

MANO DE OBRA
CUADRILLA 1 ( 1OF. ALBAÑIL + 1 PEON) JOR $500.01 / 48.000000 $10.42 36.77%
Subtotal: MANO DE OBRA $10.42 36.77%
BASICOS
CONCRETO F C=150 KG/CM2 M3 $804.57 0.022275 $17.92 63.23%
Subtotal: BASICOS $17.92 63.23%
Costo directo $28.34
INDIRECTOS 5.75% $1.63
SUBTOTAL $29.97
FINANCIAMIENTO 0.791% $0.24
SUBTOTAL $30.21
UTILIDAD 8% $2.42
PRECIO UNITARIO $32.63
(* TREINTA Y DOS PESOS 63/100 M.N. *)

:
Página: 67+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: OEX00007 Unidad: ML


CASTILLOS K-1 DE 0.12 X 0.12, ARMEX 10 X 10 -4

MATERIALES
ALAMBRE RECOCIDO KG $18.97 0.077043 $1.46 2.05%
CASTILLO ELECTROSOLDADO 10 X 10 CM ML $20.11 1.000000 $20.11 28.23%
Subtotal: MATERIALES $21.57 30.28%
MANO DE OBRA
CUADRILLA 4 ( 1 ALBAÑIL P/CASTILLOS + 1 JOR $750.01 / 20.000000 $37.50 52.64%
Subtotal: MANO DE OBRA $37.50 52.64%
BASICOS
CONCRETO F C=150 KG/CM2 M3 $804.57 0.015120 $12.17 17.08%
Subtotal: BASICOS $12.17 17.08%
Costo directo $71.24
INDIRECTOS 5.75% $4.10
SUBTOTAL $75.34
FINANCIAMIENTO 0.791% $0.60
SUBTOTAL $75.94
UTILIDAD 8% $6.08
PRECIO UNITARIO $82.02
(* OCHENTA Y DOS PESOS 02/100 M.N. *)

:
Página: 68+0
PHOENIX INSTITUTO DE VALUACION

Obra: VIVIENDA UNIFAMILIAR 1 NIVEL 50 M2

Lugar: Irapuato,Guanajuato

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad Costo cantidad Importe %

Análisis: OEX00009 Unidad: PZA


SUMINISTRO Y COLOCACION DE CISTERNA

MANO DE OBRA
CUADRILLA 1 ( 1OF. ALBAÑIL + 1 PEON) JOR $500.01 / 1.000000 $500.01 20.50%
Subtotal: MANO DE OBRA $500.01 20.50%
MATERIALES
TINACO TRICAPA 1100 L MCA ROTOPLAS PZA $1,680.17 1.000000 $1,680.17 68.89%
TAPA P/CISTERNA PZA $258.62 1.000000 $258.62 10.60%
Subtotal: MATERIALES $1,938.79 79.50%
Costo directo $2,438.80
INDIRECTOS 5.75% $140.23
SUBTOTAL $2,579.03
FINANCIAMIENTO 0.791% $20.40
SUBTOTAL $2,599.43
UTILIDAD 8% $207.95
PRECIO UNITARIO $2,807.38
(* DOS MIL OCHOCIENTOS SIETE PESOS 38/100 M.N. *)