CALCULO DE METRAJE DE ZAPATAS

RESOLVIENDO
DATOS CALCULO DE METRADO
H-ZAP 0.6 V. EXCAVACION
NPT -1.3 H A-ZAP
NFZ -2.3 1.1 1
H-SOLADO 0.1
NFS -2.4 V. ACARREO
REVEST 0.075 V.EXC FW
H-EXCAV 1.1 1.79 0.89
A-ZAP 1
B-ZAP 1.55 V. ELIMINACION
FW 0.89 V.ACA REUT%
# ZAP 1 2.012 100%
REUTIL % 0%
DESPE 1.05 CON. SOLADO
A-5/8 5 H-SOL A-ZAP
B-5/8 8 0.1 1
Pn-5/8 1.552
CON. ZAPATA
H-ZAP A-ZAP
0.6 1

ACERO ZAPATA
L-HOR #VAR-B
0.85 8
L-VER #VAR-A
1.4 5
CULO DE METRADO RESULTADO

B-ZAP DESP #ZAP V. EXCAVACION


1.55 1.05 1 1.790 m3

V. ACARREO
2.012 m3

IMINACION
V. ELIMINACION
2.012 m3

B-ZAP DESP #ZAP CON. SOLADO


1.55 1.05 1 0.163 M3

B-ZAP DESP #ZAP CON. ZAPATA


1.55 1.05 1 0.977 M3

Pn DESP #ZAP ACERO ZAPATA


1.552 1.05 1 11.08
Pn DESP #ZAP 22.49 KG
1.552 1.05 1 11.41
CALCULO DE METRAJE DE ZAPATAS
RESOLVIENDO
DATOS CALCULO DE METRADO
H-ZAP 0.9 V. EXCAVACION
NPT -1.3 H
NFZ -2.6 1.4
H-SOLADO 0.1
NFS -2.7 V. ACARREO
REVEST 0.075 V.EXC
H-EXCAV 1.4 23.667
A-ZAP 1.75
B-ZAP 2.3 V. ELIMINACION
FW 0.89 V.ACA
# ZAP 4 26.592
REUTIL % 0%
DESPE 1.05 CON. SOLADO
A-5/8 9 H-SOL
B-5/8 12 0.1
Pn-5/8 1.552
CON. ZAPATA
H-ZAP
0.9

ACERO ZAPATA
L-HOR
1.6
L-VER
2.15
RESOLVIENDO
CALCULO DE METRADO RESULTADO
V. EXCAVACION
A-ZAP B-ZAP DESP #ZAP V. EXCAVACION
1.75 2.3 1.05 4 23.667 m3

V. ACARREO
FW V. ACARREO
0.89 26.592 m3

V. ELIMINACION
REUT% V. ELIMINACION
100% 26.592 m3

CON. SOLADO
A-ZAP B-ZAP DESP #ZAP CON. SOLADO
1.75 2.3 1.05 4 1.691 M3

CON. ZAPATA
A-ZAP B-ZAP DESP #ZAP CON. ZAPATA
1.75 2.3 1.05 4 15.215 M3

ACERO ZAPATA
#VAR-B Pn DESP #ZAP ACERO ZAPATA
12 1.552 1.05 4 125.15
#VAR-A Pn DESP #ZAP 251.28 KG
9 1.552 1.05 4 126.13
SOLADO
H-SOL PERIM DESP #ZAP
0.1 5.1 1.05 1
SOLADO
0.54 m2