Está en la página 1de 3

D.U.

POR CAPACIDAD DE LA SUBESTACION


HORAS DE HORAS DE
SUBESTACION TOTAL DE HORAS COSTO TOTAL D.U. C.C, ARC FLASH
OFICINA CAMPO

30 2 4 6 $7,000.00 $4,900.00 $2,100.00


37.5 2 5 7 $7,375.00 $5,162.50 $2,212.50
45 3 6 9 $9,250.00 $6,475.00 $2,775.00
50 3 8 11 $10,625.00 $7,437.50 $3,187.50
75 4 9 13 $12,500.00 $8,750.00 $3,750.00
112.5 6 12 18 $17,250.00 $12,075.00 $5,175.00
150 9 12 21 $20,250.00 $14,175.00 $6,075.00
225 10 12 22 $22,125.00 $15,487.50 $6,637.50
300 10 15 25 $24,000.00 $16,800.00 $7,200.00
500 16 15 31 $29,750.00 $20,825.00 $8,925.00
750 18 18 36 $34,125.00 $23,887.50 $10,237.50
1000 18 21 39 $37,750.00 $26,425.00 $11,325.00
1250 20 21 41 $40,000.00 $28,000.00 $12,000.00
1500 24 21 45 $43,375.00 $30,362.50 $13,012.50
2000 33 24 57 $54,875.00 $38,412.50 $16,462.50
2500 40 30 70 $67,375.00 $47,162.50 $20,212.50
3000 42 36 78 $77,000.00 $53,900.00 $23,100.00
4000 45 48 93 $86,625.00 $60,637.50 $25,987.50
5000 55 48 103 $96,250.00 $67,375.00 $28,875.00

D.U. X TABLERO
PRECIO M.O. X
#FOTOS D.U. C.C, ARC FLASH
UNITARIO LEVANTAMIENTO
1A5 $1,400.00 980.00 $420.00 $245.00
6 A 10 $1,330.00 931.00 $399.00 $232.75
11 A 20 $1,270.00 889.00 $381.00 $222.25
MAS DE 21 $1,200.00 840.00 $360.00 $210.00

TERMOGRAFIAS
PRECIO
#FOTOS UNITARIO
1 A 25 $600.00
26 A 45 $510.00
46 A 65 $430.00
66 A 86 $360.00
M.O. X
LEVANTAMIENTO

$1,225.00 $3,675.00 $5,775.00 $9,450.00 $5,600.00


$1,290.63 $3,871.88 $6,084.38 $9,956.25 $5,900.00
$1,618.75 $4,856.25 $7,631.25 $12,487.50 $7,400.00
$1,859.38 $5,578.13 $8,765.63 $14,343.75 $8,500.00
$2,187.50 $6,562.50 $10,312.50 $16,875.00 $10,000.00
$3,018.75 $9,056.25 $14,231.25 $23,287.50 $13,800.00
$3,543.75 $10,631.25 $16,706.25 $27,337.50 $16,200.00
$3,871.88 $11,615.63 $18,253.13 $29,868.75 $17,700.00
$4,200.00 $12,600.00 $19,800.00 $32,400.00 $19,200.00
$5,206.25 $15,618.75 $24,543.75 $40,162.50 $23,800.00
$5,971.88 $17,915.63 $28,153.13 $46,068.75 $27,300.00
$6,606.25 $19,818.75 $31,143.75 $50,962.50 $30,200.00
$7,000.00 $21,000.00 $33,000.00 $54,000.00 $32,000.00
$7,590.63 $22,771.88 $35,784.38 $58,556.25 $34,700.00
$9,603.13 $28,809.38 $45,271.88 $74,081.25 $43,900.00
$11,790.63 $35,371.88 $55,584.38 $90,956.25 $53,900.00
$13,475.00 $40,425.00 $63,525.00 $103,950.00 $61,600.00
$15,159.38 $45,478.13 $71,465.63 $116,943.75 $69,300.00
$16,843.75 $50,531.25 $79,406.25 $129,937.50 $77,000.00
D.U. POR CAPACIDAD DE LA SUBESTACION
HORAS DE HORAS DE
SUBESTACION TOTAL DE HORAS COSTO TOTAL D.U. C.C, ARC FLASH
OFICINA CAMPO

30 2 4 6 $7,000.00 $4,900.00 $2,100.00


37.5 2 5 7 $7,375.00 $5,162.50 $2,212.50
45 3 6 9 $9,250.00 $6,475.00 $2,775.00
50 3 8 11 $10,625.00 $7,437.50 $3,187.50
75 4 9 13 $12,500.00 $8,750.00 $3,750.00
112.5 6 12 18 $17,250.00 $12,075.00 $5,175.00
150 9 12 21 $20,250.00 $14,175.00 $6,075.00
225 10 12 22 $22,125.00 $15,487.50 $6,637.50
300 10 15 25 $24,000.00 $16,800.00 $7,200.00
500 16 15 31 $29,750.00 $20,825.00 $8,925.00
750 18 18 36 $34,125.00 $23,887.50 $10,237.50
1000 18 21 39 $37,750.00 $26,425.00 $11,325.00
1250 20 21 41 $40,000.00 $28,000.00 $12,000.00
1500 24 21 45 $43,375.00 $30,362.50 $13,012.50
2000 33 24 57 $54,875.00 $38,412.50 $16,462.50
2500 40 30 70 $67,375.00 $47,162.50 $20,212.50
3000 42 36 78 $77,000.00 $53,900.00 $23,100.00
4000 45 48 93 $86,625.00 $60,637.50 $25,987.50
5000 55 48 103 $96,250.00 $67,375.00 $28,875.00

D.U. X TABLERO
PRECIO
#FOTOS D.U. C.C, ARC FLASH
UNITARIO
1A5 $1,400.00 980.00 $420.00
6 A 10 $1,330.00 931.00 $399.00
11 A 20 $1,270.00 889.00 $381.00
MAS DE 21 $1,200.00 840.00 $360.00

TERMOGRAFIAS
PRECIO
#FOTOS UNITARIO
1 A 25 $600.00
26 A 45 $510.00
46 A 65 $430.00
66 A 86 $360.00