S I G R A L S. A.

09/01/2018 Hoja 1
Departamento de Ingeniería

METRADO ESTRUCTURA METÁLICA

OBRA : ADMINISTRATION/MEDICAL BUILDING (AREA=468 m2) Rev. "A"


MATERIAL CANT LONG P.UNIT. PESO

PÓRTICOS (6 unidades)
Tubo-6"x6"x3.0 12 3,800 13.89 633
Tubo-6"x6"x3.0 12 4,150 13.89 692
Tubo-6"x6"x3.0 2 3,150 13.89 88
PL. 1/2"x300 26 300 29.9 233

Tubo-10"x6"x3.0 6 7000 18.68 785


Tubo-10"x6"x3.0 12 4000 18.68 897
Tubo-8"x6"x3.0 2 7000 16.28 228
PL-3/8"x250 72 300 18.64 403
PL-3/8"x200 8 300 14.92 36
3,995

VIGAS Y CORREAS
Tubo 10"x4"x3.0 20 6,000 16.28 1,954
PL-3/8"x200 40 300 14.92 179

Tubo C 8"x4"x2.0 25 5,850 10.35 1,514


PL-1/4"x200 50 200 10.05 101

Tubo 100x100x2.0 6 2,350 6.07 86


PL-1/4"x200 12 200 10.05 24
3,858

SISTEMA DE ARRIOSTRAMIENTO
Barra 1/2" 20 7,000 1.00 140
Barra 1/2" 20 7,200 1.00 144
L-2x2x1/8" 36 1,130 2.45 100
L-2x2x1/8" 30 1,415 2.45 104
488
TOTAL METRADO 8,341

PESO TOTAL = 8,341 KG


VARIACIÓN ESTIMADA (5%) = 417 KG
PESO PARA PRESUPUESTO = 8,758 KG
ÁREA TECHADA = 468 M2
DENSIDAD = 18.71 KG/M2
S I G R A L S. A.
09/01/2018 Hoja 2
Departamento de Ingeniería

METRADO ESTRUCTURA METÁLICA

OBRA : ADMINISTRATION/MEDICAL BUILDING (AREA=468 m2) Rev. "A"


MATERIAL CANT LONG P.UNIT. PESO

RIELES Y JAMBAS
U-52x25x2.0 32 3,000 2.38 228
U-42x25x2.0 70 3,000 1.44 302
0
U-52x25x1.5 29 3,000 1.79 156
U-42x25x1.5 43 3,000 1.08 139
825

ESTRUCTURA DE SOPORTE DE PANELES EN FALSO CIELO


Tubo-100x100x2.0 20 5,850 6.07 710
C-4"x2"x2.0 14 4,000 3.58 200
C-4"x2"x2.0 7 7,000 3.58 175
0
0

0
0
1,085

SISTEMA DE ARRIOSTRAMIENTO
Barra 1/2" 20 7,000 1.00 140
Barra 1/2" 20 7,200 1.00 144
L-2x2x1/8" 36 1,130 2.45 100
L-2x2x1/8" 30 1,415 2.45 104
488
TOTAL METRADO 2,398

PESO TOTAL = 2,398 KG


VARIACIÓN ESTIMADA (5%) = 120 KG
PESO PARA PRESUPUESTO = 2,518 KG
ÁREA TECHADA = 468 M2
DENSIDAD = 5.38 KG/M2
S I G R A L S. A.
09/01/2018 Hoja 3
Departamento de Ingeniería

METRADO ESTRUCTURA METÁLICA

OBRA : VEHICLE MAINTENANCE (AREA=157 m2) Rev. "A"


MATERIAL CANT LONG P.UNIT. PESO

PÓRTICOS (5 unidades)
Tubo-8"x6"x4.5 10 5,500 24.08 1,324
PL.1/2"x300 10 350 29.90 105

Tubo-10"x6"x3.0 10 4580 18.68 856


PL.3/8"x250 20 350 18.64 130
2,415

VIGAS Y CORREAS
Tubo -10"x4"x3.0 8 4,270 16.28 556
PL.3/8"x250 16 150 18.64 45
Tubo -6"x4"x3.0 16 4,270 11.50 786
PL.3/8"x200 32 300 14.92 143
1,530
TOTAL METRADO 3,945

PESO TOTAL = 3,945 KG


VARIACIÓN ESTIMADA (5%) = 197 KG
PESO PARA PRESUPUESTO = 4,142 KG
ÁREA TECHADA = 157 M2
DENSIDAD = 26.38 KG/M2
S I G R A L S. A.
09/01/2018 Hoja 4
Departamento de Ingeniería

METRADO ESTRUCTURA METÁLICA

OBRA : GUARD HOUSE BUILDING (AREA=14 m2) Rev. "A"


MATERIAL CANT LONG P.UNIT. PESO

PÓRTICOS (2 unidades)
Tubo-100x100x4.5 4 3,600 13.08 188
PL-3/8"x200 4 200 14.92 12

Tubo-6"x4"x3.0 4 1850 11.50 85


L-3"x3"x1/4" 8 130 7.29 8
293

VIGAS Y CORREAS
Tubo-6"x4"x3.0 2 3,700 11.50 85
0
C-4"x2"x2.0 4 3,700 3.58 53
Barra - 1/2" 4 1,000 1.00 4
142
TOTAL METRADO 435

PESO TOTAL = 435 KG


VARIACIÓN ESTIMADA (5%) = 22 KG
PESO PARA PRESUPUESTO = 457 KG
ÁREA TECHADA = 14 M2
DENSIDAD = 32.63 KG/M2
S I G R A L S. A.
09/01/2018 Hoja 5
Departamento de Ingeniería

METRADO ESTRUCTURA METÁLICA

OBRA : SECURITY BUILDING (AREA=287 m2) Rev. "A"


MATERIAL CANT LONG P.UNIT. PESO

PÓRTICOS (6 unidades)
Tubo- 6"x6"x3.0 12 3,600 13.89 600
Tubo- 6"x6"x3.0 6 4100 13.89 342
PL.1/2"x300 18 300 29.9 161

Tubo-10"x6"x3.0 12 6100 18.68 1,367


PL.3/8"x250 48 350 18.64 313
2,783

VIGAS Y CORREAS
Tubo-8"x6"x3.0 5 4,700 16.28 383
PL-3/8"x150 10 200 11.18 22
Tubo-8"x4"x2.0 10 4,700 9.36 440
PL-3/8"x150 20 200 11.18 45
Tubo-6"x4"x3.0 30 4,700 11.50 1,622
PL-3/8"x150 60 150 11.18 101
2,613
TOTAL METRADO 5,396

PESO TOTAL = 5,396 KG


VARIACIÓN ESTIMADA (5%) = 270 KG
PESO PARA PRESUPUESTO = 5,666 KG
ÁREA TECHADA = 287 M2
DENSIDAD = 19.74 KG/M2
S I G R A L S. A.
09/01/2018 Hoja 6
Departamento de Ingeniería

METRADO ESTRUCTURA METÁLICA

OBRA : FIRE WATER (AREA=138 m2) Rev. "A"


MATERIAL CANT LONG P.UNIT. PESO

PÓRTICOS (4 unidades)
Tubo-8"x6"x4.5 8 4,100 13.08 429
PL-1/2"x200 8 200 19.94 32

Tubo- 10"x6"x3.0 8 5000 18.68 747


PL-3/8"x250 24 350 18.64 157
L-3"x3"x1/4" 24 130 7.29 23
1,388

VIGAS Y CORREAS
Tubo -8"x4"3.0 6 5,000 13.89 417
PL-3/8"x150 12 200 11.18 27
0
C-6"x3"x3.0 18 5,000 7.61 685
1,129

VIGAS Y CORREAS
Barra - 5/8" 8 7,000 1.55 87
Barra - 1/2" 36 1,700 1.00 61
148
TOTAL METRADO 2,665

PESO TOTAL = 2,665 KG


VARIACIÓN ESTIMADA (5%) = 133 KG
PESO PARA PRESUPUESTO = 2,798 KG
ÁREA TECHADA = 138 M2
DENSIDAD = 20.28 KG/M2
S I G R A L S. A.
09/01/2018 Hoja 7
Departamento de Ingeniería

METRADO ESTRUCTURA METÁLICA

OBRA : TURBINE COMPRESSOR (AREA=80 m2) Rev. "A"


MATERIAL CANT LONG P.UNIT. PESO

PÓRTICOS (3 unidades)
Tubo-8"x6"x3.0 6 3,600 16.28 352
PL-1/2"X300 6 350 29.9 63

Tubo-10"x6"x3.0 6 3450 18.68 387


PL-3/8"x250 18 350 18.64 117
919

VIGAS Y CORREAS
Tubo-8"x4"x2.0 8 5,800 9.36 434
PL-3/8"x200 16 200 14.92 48
Tubo-8"x4"x2.0 4 5,800 9.36 217
PL-3/8"x200 8 200 14.92 24
723
TOTAL METRADO 1,642

PESO TOTAL = 1,642 KG


VARIACIÓN ESTIMADA (5%) = 82 KG
PESO PARA PRESUPUESTO = 1,724 KG
ÁREA TECHADA = 80 M2
DENSIDAD = 21.55 KG/M2