Libro #PLANTILLA
Libro #PLANTILLA
# DE # DE DIMENCIONES
ITEM DISCRIPCION REPT. ELEM. LARGO ANCHO ALTO PARCIAL TOTAL UND
TRABAJOS PRELIMINARES
LIMPIEZA DEL TERRENO 18.00 6.00 108.00 108.00 M2
TRAZO Y REPLANTEO 18.00 6.00 108.00 108.00 M2
1 ESTRUCTURAS
1.1 MOVIMIENTO DE TIERRAS
1.1.1 CORTE DEL TERRENO A MAQUINA 108.00 M3
18.00 6.00 1.00 108.00 108.00
1.1.2 ESCAVACIONES DE ZAPATAS MANUALES 18.19 M3
1.1.2.1 ESCAVACION DE Z-1 DE 1.20X1.20
5.00 1.20 1.20 1.10 7.92
1.1.2.2 ESCAVACION DE Z-2 DE 0.80X0.80
10.00 0.80 0.80 1.10 7.04
1.1.2.3 ESCAVACION DE Z-3 DE 0.70X0.70
6.00 0.70 0.70 1.10 3.23
1.1.3 ESCAVACIONES DE CIMIENTOS MANUALES 37.49 M3
1.1.3.1 ESCAVACION DE CIMIENTO DE A=1.00
EJE A;G TRAMO 1-4 2.00 3.90 0.50 1.00 3.90
EJE B;C;D;E:F TRAMO 1-4 5.00 3.20 0.50 1.00 8.00
EJE 1;4 TRAMO A-G 2.00 12.60 0.60 1.00 15.12
EJE 2 TRAMO A-D 1.00 5.05 0.60 1.00 3.03
EJE 3 TRAMO D-G 1.00 5.62 0.60 1.00 3.37
1.1.3.1 ESCAVACION DE CIMIENTO DE A=0.70
EJE B' TRAMO 1-2 1.00 1.15 0.40 0.70 0.32
EJE D' TRAMO 1-2 1.00 1.27 0.38 0.70 0.34
EJE D' TRAMO 1-2 1.00 0.26 0.23 0.70 0.04
EJE D' TRAMO 1-2 1.00 1.53 0.40 0.70 0.43
EJE E' TRAMO 1-2 1.00 1.33 0.40 0.70 0.37
EJE E' TRAMO 1-2 1.00 0.28 0.20 0.70 0.04
EJE E' TRAMO 3-4 1.00 0.75 0.42 0.70 0.22
EJE E' TRAMO 3-4 1.00 0.28 0.20 0.70 0.04
EJE F' TRAMO 1-2 1.00 1.53 0.40 0.70 0.43
EJE 1' TRAMO D-E 1.00 0.93 0.40 0.70 0.26
EJE 1' TRAMO E-F 1.00 1.87 0.40 0.70 0.52
EJE 1' TRAMO F-G 1.00 2.23 0.40 0.70 0.62
EJE 3' TRAMO D-E 1.00 1.55 0.40 0.70 0.43
1.1.3.2 ESCAVACION PARA CISTERNA DE 2.70 X 1.80 X 1.75 8.70 M3
2.70 1.80 1.75 8.51
TRAPECIO 2.00 0.65 0.15 0.20
1.1.4 RELLENO CON MATERIAL PROPIO 15.39 M3
2.06
SOBRECIMIENTO ALTURA= 0.40 0.20
EJE A TRAMO 2-4 1.00 1.96 0.15 0.10 0.03
EJE G TRAMO 1-4 1.00 5.25 0.15 0.10 0.08
EJE 2 TRAMO A-D 1.00 3.50 0.15 0.10 0.05
EJE 3 TRAMO A-D 1.00 2.35 0.15 0.10 0.04
EJE 1' TRAMO D-G 1.00 0.25 0.15 0.10 0.00
SOBRECIMIENTO ALTURA= 0.45 0.56
EJE 1 TRAMO A-G 1.00 15.70 0.15 0.10 0.24
EJE B TRAMO 2-4 1.00 1.96 0.15 0.10 0.03
EJE E TRAMO 3-4 1.00 2.21 0.15 0.10 0.03
EJE F TRAMO 3-4 1.00 1.85 0.15 0.10 0.03
EJE 1 TRAMO A-G 1.00 15.70 0.15 0.10 0.24
SOBRECIMIENTO ALTURA= 0.75 1.24
EJE B' TRAMO 1-2 1.00 2.60 0.15 0.4 0.16
EJE D' TRAMO 1-2 1.00 2.40 0.15 0.4 0.14
EJE D' TRAMO 1-2 1.00 2.10 0.15 0.4 0.13
EJE E' TRAMO 1-3 1.00 2.10 0.15 0.4 0.13
EJE F' TRAMO 1-3 1.00 2.10 0.15 0.4 0.13
EJE E' TRAMO 3-4 1.00 1.63 0.15 0.4 0.10
EJE 1' TRAMO D-G 1.00 5.40 0.15 0.4 0.32
EJE 3' TRAMO D-E 1.00 2.30 0.15 0.4 0.14
SOBRECIMIENTO DE ANCHO 0.25 0.06
EJE 2 TRAMO B-C 1.00 2.55 0.25 0.10 0.06
1.2.3 SOBRECIMIENTOS
1.2.3.1 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTOS CON MADERA TORNILLO 77.99 M2
1.2.3.1.1 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTOS A=0.40 CM 11.33
EJE A TRAMO 2-4 2.00 1.96 0.40 1.57
EJE G TRAMO 1-4 2.00 5.25 0.40 4.20
EJE 2 TRAMO A-D 2.00 4.35 0.40 3.48
EJE 3 TRAMO A-D 2.00 2.35 0.40 1.88
EJE 1' TRAMO D-G 2.00 0.25 0.40 0.20
1.2.3.1.2 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTOS A=0.45 CM 33.68
EJE 1 TRAMO A-G 2.00 15.70 0.45 14.13
EJE B TRAMO 2-4 2.00 1.96 0.45 1.76
EJE E TRAMO 3-4 2.00 2.21 0.45 1.99
EJE F TRAMO 3-4 2.00 1.85 0.45 1.67
EJE 4 TRAMO A-G 2.00 15.70 0.45 14.13
1.2.3.1.3 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTOS A=0.75 CM 30.95
EJE B' TRAMO 1-2 2.00 2.60 0.75 3.90
EJE D' TRAMO 1-2 2.00 2.40 0.75 3.60
EJE D' TRAMO 1-2 2.00 2.10 0.75 3.15
EJE E' TRAMO 1-3 2.00 2.10 0.75 3.15
EJE F' TRAMO 1-3 2.00 2.10 0.75 3.15
EJE E' TRAMO 3-4 2.00 1.63 0.75 2.45
EJE 1' TRAMO D-G 2.00 5.40 0.75 8.10
EJE 3' TRAMO D-E 2.00 2.30 0.75 3.45
1.2.3.1.4 ENCOFRADO Y DESENCOFRADO SOBRECIMIENTO DE ANCHO 0.25 2.04
EJE 2 TRAMO B-C 2.00 2.55 0.40 2.04
1.3.3 COLUMNAS
1.3.3.1 CONCRETO PARA COLUMNAS F'C=210 KG/CM2 4.73 M3
COLUMNA - 1 5.00 0.30 0.25 3.00 1.13
COLUMNA - 2 14.00 0.30 0.25 3.00 3.15
COLUMNA - 3 2.00 0.50 0.15 3.00 0.45
1.3.3.2 ENCOFRADO Y DESENCOFRADO DE COLUMNAS DE MADERA TORNILLO 47.32 M2
PERIMETRO
COLUMNA 1
EJE 2-D 1.00 0.85 2.80 2.38
EJE 3-E 1.00 0.80 2.80 2.24
EJE 2-B,C 2.00 0.70 2.80 3.92
EJE 3-F 1.00 0.65 2.80 1.82
COLUMNA 2
EJE 1-A; 2-A 2.00 0.95 2.80 5.32
EJE 1-C,D,E,F,G ; 4-A,D,F,G ; 3-G 10.00 0.80 2.80 22.4
EJE 4-B,E 2.00 0.65 2.80 3.64
COLUMNA 3
EJE 1-B ; 4-C 2.00 1.00 2.80 5.60
1.3.4 VIGAS
1.3.4.1 CONCRETO PARA VIGAS F'C =210 KG/CM2 6.15 M3
VIGAS PERALTADAS
V-101 EJE 1 TRAMO A-G 1.00 16.70 0.25 0.30 1.25
-1.00 0.50 0.15 0.30 -0.02
V-101 EJE 2;3 TRAMO A-G 1.00 16.53 0.25 0.30 1.24
V-101 EJE 4 TRAMO A-G 1.00 15.90 0.25 0.30 1.19
-1.00 0.50 0.15 0.30 -0.02
VIGAS CHATAS
VA EJE B;C;D;E;F TRAMO 1-4 5.00 5.26 0.30 0.20 1.58
VA' EJE A;F TRAMO 1-4 2.00 5.26 0.25 0.20 0.53
VB VOLADIZO 1.00 3.35 0.15 0.20 0.10
VB EJE 2' TRAMO A-B 1.00 3.00 0.15 0.20 0.09
VB EJE 3' TRAMO D-E 1.00 2.10 0.15 0.20 0.06
VB EJE 1' TRAMO F-G 1.00 2.15 0.15 0.20 0.06
VB EJE F' TRAMO 1-3 1.00 3.05 0.15 0.20 0.09
1.3.4.2 ENCOFRADO Y DESENCOFRADO DE VIGAS MADERA TORNILLO 21.96 M2
VIGAS PERALTADAS PERIMETRO
V-101 EJE 1 TRAMO A-G 1.00 16.70 0.45 7.52
-1.00 0.50 0.15 -0.08
V-101 EJE 2;3 TRAMO A-G 1.00 16.53 0.45 7.44
V-101 EJE 4 TRAMO A-G 1.00 15.90 0.45 7.16
-1.00 0.50 0.15 -0.08
1.3.5 LOSA ALIGERADA
1.3.5.1 CONCRETO EN LOA ALIGERADA F'C =210 KG/CM2 5.85 M3
CANTIDAD DE CONCRETO EN 1M2 0.0875
ACERO EN VIGAS CHATAS DE LOSA ALIGERADA F'Y 4200 KG/CM GRADO 60 CORRUGADO
PESO DE LAS VARILLAS DE A
VA' 5.00 6.00 5/8 6.25 - -
ESTRIBOS EJE A;B;C ENTRE 1;2 3.00 13.00 3/8 0.80 - 31.20
ESTRIBOS EJE A;B;C ENTRE 2;4 3.00 16.00 3/8 0.80 - 38.40
ESTRIBOS EJE A;B;C ENTRE 1;2 2.00 17.00 3/8 0.80 - 27.20
ESTRIBOS EJE A;B;C ENTRE 2;4 2.00 13.00 3/8 0.80 - 20.80
VA - -
EJE A;G ENTRE 1;4 2.00 4.00 5/8 6.25 - -
ESTRIBOS EJE A ENTRE 1;2 1.00 13.00 3/8 0.70 - 9.10
ESTRIBOS EJE A ENTRE 2;4 1.00 16.00 3/8 0.70 - 11.20
ESTRIBOS EJE A;B;C ENTRE 1;2 1.00 17.00 3/8 0.70 - 11.90
ESTRIBOS EJE A;B;C ENTRE 2;4 1.00 13.00 3/8 0.70 - 9.10
VB - -
VOLADIZO 1.00 4.00 1/2 3.85 - -
ESTRIBOS 1.00 23.00 3/8 0.50 - 11.50
EJE 2' ENTRE A;B 1.00 4.00 1/2 3.15 - -
ESTRIBOS 1.00 17.00 3/8 0.50 - 8.50
EJE 3' ENTRE D;E 1.00 4.00 1/2 2.65 - -
ESTRIBOS 1.00 14.00 3/8 0.50 - 7.00
EJE 1' ENTRE F;G 1.00 4.00 1/2 2.55 - -
ESTRIBOS 1.00 15.00 3/8 0.50 - 7.50
EJE F' ENTRE 1;3 1.00 4.00 1/2 3.50 - -
ESTRIBOS 1.00 19.00 3/8 0.5 - 9.50
- - - - - -
- 38.50 - 59.68
- 38.50 - 59.68
- - -
- 35.00 - 54.25
- 35.00 - 54.25
- - -
- 14.40 - 22.32
- 14.40 - 22.32
O - 272.49
-
50.40 - -
6.30 - -
- - - 11.42
- - - 14.85
63.00 - -
- - - 11.42
- - - 14.85
75.60 - -
7.80 - -
- - - 22.28
- - - 17.14
- - -
91.50 - -
- - - 6.28
- - - 6.28
- - - 6.28
- - - 5.71
- - - 6.85
- - - 8.00
91.50 - -
- - - 6.28
- - - 6.28
- - - 6.28
- - - 5.71
- - - 6.85
- - - 8.00
91.65 - -
- - - 6.28
- - - 6.28
- - - 6.28
- - - 5.71
- - - 6.85
- - - 8.00
- 210.20
-
- 220.95 - 342.47
- - - 69.16
- - 55.86
- 58.92 - 91.33
- - - 36.69
- - - 29.64
- - -
- 130.00 - 201.50
- - - 55.86
- 55.86
52.00 - - 51.48
- - - 29.64
- - - 29.64
- - -
- 776.44 - 1203.48
- - - 193.65
- - - 156.41
- - - 156.41
- - - 156.41
- - -
55.48 - - 54.93
-
-
-
-
-
-
-
-
-
CORRUGADO 119.42 62.17 368.13
LAS VARILLAS DE ACERO 0.22 0.56 0.99 1.55
- 187.50 290.63
- - 17.47
- - 21.50
- - 15.23
- - 11.65
- -
- 50.00 77.50
- - 5.10
- - 6.27
- - 12.46
- - 5.10
- -
15.40 - 15.25
- - 6.44
12.60 - 12.47
- - 4.76
10.60 - 10.49
- - 3.92
10.20 - 10.10
- - 4.20
14.00 - 13.86
- - 5.32