PRESUPUESTO ANTERIOR

VALORIZACIONES UND. CANT. PU PP CANT. VAL


1 movimiento de tierra
1.1 excavacion masiva con maq. m3 15000 10 150000 0 0
2 columnas 0 0
2.1 concreto f'c=280 kg/cm2 m3 120 350 42000 0 0
2.2 encofrado y desencofradi m2 250 25 6250 0 0
2.3 acero fy=4200 kg/cm2 kg 8000 3.5 28000 0 0
3 losas aligerdas 0 0
3.1 concreto f'c=280 kg/cm2 m3 90 370 33300 0 0
3.2 encofrado y desencofrado m2 750 30 22500 0 0
3.3 ladrillo de techo 15x30x30 cm UND. 12000 1.5 18000 0 0
3.4 acero fy=4200 kg/cm2 kg 7800 3.5 27300 0 0

COSTO DIR. S/327,350.00


GG 7% S/22,914.50
UTL 5% S/16,367.50

SUB TOTAL S/366,632.00


IGV 18% S/65,993.76

PRESUPUESTOS/432,625.76
V-01
ANTERIOR ACTUAL ACUMULADO SALDO
% CANT. VAL % CANT. VAL % CANT.

0 15000 150000 100% 15000 150000 100% 0


0
0 36 12600 30% 36 12600 30% 84
0 75 1875 30% 75 1875 30% 175
0 2400 8400 30% 2400 8400 30% 5600
0
0 27 9990 30% 27 9990 30% 63
0 225 6750 30% 225 6750 30% 525
0 3600 5400 30% 3600 5400 30% 8400
0 2340 8190 30% 2340 8190 30% 5460
(ASUMIDOS) (ANT+ACT) (ANT+ACT) (PRES-ACUM)
COSTO DIR. 203205 COSTO DIR.
GG 7% 14224.35 GG 7%
UTL 5% 10160.25 UTL 5%

SUB TOTAL S/227,589.60 SUB TOTAL


IGV 18% S/40,966.13 IGV 18%

PRESUPUEST S/268,555.73 62.0757599 % PRESUPUESTO


V-02
SALDO ANTERIOR ACTUAL
VAL % CANT. VAL % CANT. VAL %

0 0.00% 15000 150000 100% 0 0 0%

29400 70.00% 36 12600 30% 12 4200 10%


4375 70.00% 75 1875 30% 25 625 10%
19600 70.00% 2400 8400 30% 1600 5600 20%
0 0
23310 70.00% 27 9990 30% 13 4810 14%
15750 70.00% 225 6750 30% 225 6750 30%
12600 70.00% 3600 5400 30% 1200 1800 10%
19110 70.00% 2340 8190 30% 2340 8190 30%

S/124,145.00
S/8,690.15
S/6,207.25

S/139,042.40
S/25,027.63

S/164,070.03 37.9242401 %
V-02
ACUMULADO SALDO
CANT. VAL % CANT. VAL %

15000 150000 100% 0 0 0.00%

48 16800 40% 72 25200 60.00%


100 2500 40% 150 3750 60.00%
4000 14000 50% 4000 14000 50.00%
0
40 14800 44% 50 18500 55.56%
450 13500 60% 300 9000 40.00%
4800 7200 40% 7200 10800 60.00%
4680 16380 60% 3120 10920 40.00%