Está en la página 1de 8

CALENDARIO DE AVANCE VALORIZADO DE OBRA

CREACIÓN DE PISTAS Y VEREDAS EN EL CENTRO POBLADO DE AUTAMA, DISTRITO DE SANTIAGO DE


PROYECTO
PAUCARAY, PROVINCIA DE SUCRE, REGIÓN AYACUCHO.

VALORIZACION - MES 01 VALORIZACION - MES 02 VALORIZACION - MES 03


Costo
ITEM DESCRIPCION UND Metrado Parcial (S/.) COSTO TOTAL
Unitario VALORIZACION VALORIZACION VALORIZACION
Metrado % Metrado % Metrado %
MENSUAL MENSUAL MENSUAL

01.01 OBRAS PROVISIONALES 500.00


01.01.01 CARTEL DE OBRA (3.60x2.40 m.) mes 1.00 500.00 500.00 1.00 500.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 500.00
01.02 TRABAJOS PRELIMINARES 186.59
01.02.01 LIMPIEZA DEL TERRENO MANUAL m2 82.56 1.32 108.98 82.56 108.98 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 108.98
01.02.02 TRAZO , NIVELACION Y REPLANTEO PRELIMINAR m2 82.56 0.94 77.61 82.56 77.61 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 77.61
03 MOVIMIENTOS DE TIERRAS 1,225.33
03.01 EXCAVACION DE CIMIENTO m3 35.15 16.48 579.27
35.15 579.27 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 579.27
03.02 RELLENO CON MATERIAL PROPIO m3 10.55 12.36 130.40
10.55 130.40 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 130.40
03.03 ELIMINACION DE MATERIAL EXCEDENTE m3 24.61 10.99 270.46
24.61 270.46 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 270.46
03.04 REFINE, NIVELACION Y COMPACTACION m2 82.56 2.97 245.20
82.56 245.20 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 245.20
04 OBRAS DE CONCRETO SIMPLE 4,884.79
04.01 SOLADO PARA ZAPATAS C:H = 1:12, E=4" m2 7.20 30.09 216.65
7.20 216.65 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 216.65
04.02 CONCRETO PARA CIMIENTO CORRIDO, CONCRETO C:H = 1:10 + 30% P.G. m3 15.72 140.67 2,211.33
15.72 2,211.33 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2,211.33
04.03 CONCRETO EN SOBRECIMIENTO, CONCRETO C:H = 1:8 + 25% P.M. m3 5.99 281.10 1,683.79
5.99 1,683.79 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,683.79
04.04 SOBRECIMIENTO, ENCOFRADO Y DESENCOFRADO m2 25.75 30.02 773.02
25.75 773.02 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 773.02
05 OBRAS DE CONCRETO ARMADO 12,414.26
05.01 ZAPATAS, CONCRETO F'c=210 kg/cm2 m3 5.04 372.25 1,876.14
0.00 0.00 0.00% 5.04 1,876.14 100.00% 0.00 0.00 0.00% 1,876.14
05.02 ZAPATAS, ACERO Fy=4200 kg/cm2 kg 70.69 5.08 359.11
0.00 0.00 0.00% 70.69 359.11 100.00% 0.00 0.00 0.00% 359.11
05.03 COLUMNA, CONCRETO F'c=175 kg/cm2 m3 3.39 387.53 1,313.73
0.00 0.00 0.00% 3.39 1,313.73 100.00% 0.00 0.00 0.00% 1,313.73
05.04 COLUMNAS, ENCOFRADO Y DESENCOFRADO m2 34.20 27.81 951.10
0.00 0.00 0.00% 34.20 951.10 100.00% 0.00 0.00 0.00% 951.10
05.05 COLUMNAS, ACERO Fy=4200 kg/cm2 kg 482.28 5.19 2,503.03
0.00 0.00 0.00% 482.28 2,503.03 100.00% 0.00 0.00 0.00% 2,503.03
05.06 VIGAS, CONCRETO F'c=210 kg/cm2 m3 3.64 389.54 1,417.93
0.00 0.00 0.00% 3.64 1,417.93 100.00% 0.00 0.00 0.00% 1,417.93
05.07 VIGAS, ENCOFRADO Y DESENCOFRADO m2 39.77 36.43 1,448.82
0.00 0.00 0.00% 39.77 1,448.82 100.00% 0.00 0.00 0.00% 1,448.82
05.08 VIGAS, ACERO Fy=4200 kg/cm2 kg 490.25 5.19 2,544.40
0.00 0.00 0.00% 490.25 2,544.40 100.00% 0.00 0.00 0.00% 2,544.40
06 MUROS Y TABIQUES DE ALBAÑILERIA 6,813.96
06.01 MURO DE LADRILLO KK DE ARCILLA 23x13x9 SOGA / J=1.5 cm. m2 140.61 48.46 6,813.96
0.00 0.00 0.00% 140.61 6,813.96 100.00% 0.00 0.00 0.00% 6,813.96
07 REVOQUES Y ENLUCIDOS 7,164.99
07.01 TARRAJEO EN MUROS INTERIORES (MEZCLA 1:5) m2 195.75 15.79 3,090.89
0.00 0.00 0.00% 0.00 0.00 0.00% 195.75 3,090.89 100.00% 3,090.89
07.02 TARRAJEO EN SOBRECIMIENTO (MEZCLA 1:5) m2 150.30 16.18 2,431.85
0.00 0.00 0.00% 0.00 0.00 0.00% 150.30 2,431.85 100.00% 2,431.85
07.03 TARRAJEO EN COLUMNAS (MEZCLA 1:5) m2 31.80 19.35 615.33
0.00 0.00 0.00% 0.00 0.00 0.00% 31.80 615.33 100.00% 615.33
07.04 TARRAJEO EN VIGAS (MEZCLA 1:5) m2 37.84 22.90 866.54
0.00 0.00 0.00% 0.00 0.00 0.00% 37.84 866.54 100.00% 866.54
07.05 VESTIDURA DE DERRAMES m 22.40 7.16 160.38
0.00 0.00 0.00% 0.00 0.00 0.00% 22.40 160.38 100.00% 160.38
08 CIELORRASOS 2,904.81
08.01 CIELO RASO DE TRIPLAY DE 4mm m2 73.67 39.43 2,904.81
0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00
09 PISOS Y PAVIMENTOS 5,027.37
09.01 FALSO PISO DE E = 4" MEZCLA C:H = 1:10 m2 56.74 28.25 1,602.91
0.00 0.00 0.00% 0.00 0.00 0.00% 56.74 1,602.91 100.00% 1,602.91
09.02 PISO DE CERAMICO DE 0.30x0.30 m. m2 56.74 40.37 2,290.59
0.00 0.00 0.00% 0.00 0.00 0.00% 56.74 2,290.59 100.00% 2,290.59
09.03 VEREDA, CONCRETO FROTACHADO DE E = 4" m2 17.30 40.18 695.11
0.00 0.00 0.00% 0.00 0.00 0.00% 17.30 695.11 100.00% 695.11
09.04 VEREDA, ENCOFRADO Y DESENCOFRADO m2 10.98 39.96 438.76
0.00 0.00 0.00% 0.00 0.00 0.00% 10.98 438.76 100.00% 438.76
10 ZOCALOS Y CONTRAZOCALOS 4,329.72
10.01 CONTRAZOCALO DE CEMENTO, EXTERIOR h = 30 cm. m 12.10 8.30 100.43
0.00 0.00 0.00% 0.00 0.00 0.00% 12.10 100.43 100.00% 100.43
10.02 ZOCALO DE CERAMICO DE 0.20x0.30 m. m2 90.10 46.94 4,229.29
0.00 0.00 0.00% 0.00 0.00 0.00% 90.10 4,229.29 100.00% 4,229.29
11 ESTRUCTURA DE MADERA 9,596.59
11.01 TIJERALES DE MADERTA SEGUN DISEÑO GLB 6.00 548.81 3,292.86
0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 3,292.86 100.00% 3,292.86
11.02 CORREAS DE MADERA TORNILLO 2"X3" m 121.80 16.92 2,060.86
0.00 0.00 0.00% 0.00 0.00 0.00% 121.80 2,060.86 100.00% 2,060.86
11.03 COBERTURA CON TEJA ANDINA m2 88.74 44.93 3,987.09
0.00 0.00 0.00% 0.00 0.00 0.00% 88.74 3,987.09 100.00% 3,987.09
11.04 CUMBRERA ARTICULADA ETERNIT m 8.70 29.40 255.78
0.00 0.00 0.00% 0.00 0.00 0.00% 8.70 255.78 100.00% 255.78
12 CARPINTERIA METALICA Y HERRERIA 9,178.20
12.01 PUERTA DE ALUMINIO + PLANCHA DE MULTIPLACA m2 12.25 180.00 2,205.00
0.00 0.00 0.00% 0.00 0.00 0.00% 12.25 2,205.00 100.00% 2,205.00
12.02 TABIQUERIA DE ALUMINIO + PLANCHA DE MULTIPLACA m2 28.08 230.00 6,458.40
0.00 0.00 0.00% 0.00 0.00 0.00% 28.08 6,458.40 100.00% 6,458.40
12.03 VENTANAS METALICAS m2 4.68 110.00 514.80
0.00 0.00 0.00% 0.00 0.00 0.00% 4.68 514.80 100.00% 514.80
13 CERRAJERIA 550.82
13.01 BISAGRA CAPUCHINA DE 3" und 12.00 13.90 166.80
0.00 0.00 0.00% 0.00 0.00 0.00% 12.00 166.80 100.00% 166.80
13.02 CERRADURAS PARA PUERTAS DE MADERA DE 02 GOLPES und 4.00 80.21 320.84
0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 320.84 100.00% 320.84
13.03 CERROJO DE 3" PARA PUERTAS DE SS. HH. und 9.00 7.02 63.18
0.00 0.00 0.00% 0.00 0.00 0.00% 9.00 63.18 100.00% 63.18
14 VIDRIOS 356.76
14.01 VIDRIO SEMIDOBLE p2 51.48 6.93 356.76
0.00 0.00 0.00% 0.00 0.00 0.00% 51.48 356.76 100.00% 356.76
15 PINTURA 3,851.98
15.01 PINTURA LATEX, EN MUROS INTERIORES m2 195.75 7.52 1,472.04
0.00 0.00 0.00% 0.00 0.00 0.00% 195.75 1,472.04 100.00% 1,472.04
15.02 PINTURA LATEX, EN MUROS EXTERIORES m2 150.30 7.52 1,130.26
0.00 0.00 0.00% 0.00 0.00 0.00% 150.30 1,130.26 100.00% 1,130.26
15.03 PINTURA LATEX, EN COLUMNAS Y COLUMNETAS m2 31.80 7.29 231.82
0.00 0.00 0.00% 0.00 0.00 0.00% 31.80 231.82 100.00% 231.82
15.04 PINTURA LATEX, EN VIGAS m2 37.83 9.12 345.01
0.00 0.00 0.00% 0.00 0.00 0.00% 37.83 345.01 100.00% 345.01
15.05 PINTURA LATEX, EN CIELO RASO m2 73.67 8.34 614.41
0.00 0.00 0.00% 0.00 0.00 0.00% 73.67 614.41 100.00% 614.41
15.06 PINTURA ESMALTE, EN CONTRAZOCALOS m 12.10 4.83 58.44
0.00 0.00 0.00% 0.00 0.00 0.00% 12.10 58.44 100.00% 58.44
16 VARIOS 417.36
16.01 JUNTA DE DILATACION DE 1" m 34.68 6.36 220.56
34.68 220.56 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 220.56
16.02 PERFILES (Rodoplast) m 30.00 6.56 196.80
30.00 196.80 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 196.80
17 APARATOS SANITARIOS Y ACCESORIOS 3,498.60
17.01 APARATOS SANITARIOS 2 GLB 1.00 1,780.00 1,780.00
1.00 1,780.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,780.00
17.02 ACCESORIOS SANITARIOS 2 GLB 5.00 10.00 50.00
5.00 50.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 50.00
17.03 COLOCACION DE APARATOS SANITARIOS und 15.00 74.16 1,112.40
15.00 1,112.40 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,112.40
17.04 COLOCACION DE ACCESORIOS SANITARIOS und 15.00 37.08 556.20
15.00 556.20 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 556.20
18 INSTALACIONES SANITARIAS 3,814.32
18.01 SALIDA DE DESAGUE pto 10.00 88.25 882.50
10.00 882.50 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 882.50
18.02 RED COLECTORA PVC SAL 4" m 20.00 27.28 545.60
20.00 545.60 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 545.60
18.03 RED COLECTORA PVC SAL 6" m 10.00 28.28 282.80
10.00 282.80 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 282.80
CALENDARIO DE AVANCE VALORIZADO DE OBRA

CREACIÓN DE PISTAS Y VEREDAS EN EL CENTRO POBLADO DE AUTAMA, DISTRITO DE SANTIAGO DE


PROYECTO
PAUCARAY, PROVINCIA DE SUCRE, REGIÓN AYACUCHO.

VALORIZACION - MES 01 VALORIZACION - MES 02 VALORIZACION - MES 03


Costo
ITEM DESCRIPCION UND Metrado Parcial (S/.) COSTO TOTAL
Unitario VALORIZACION VALORIZACION VALORIZACION
Metrado % Metrado % Metrado %
MENSUAL MENSUAL MENSUAL

18.04 RED COLECTORA PVC SAL 2" m 20.00 17.08 341.60


20.00 341.60 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 341.60
18.05 SALIDA DE VENTILACION, PVC SAL 2" pto 8.00 83.39 667.12
8.00 667.12 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 667.12
18.06 REGISTRO DE BRONCE DE 2" und 5.00 41.30 206.50
5.00 206.50 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 206.50
18.07 SUMIDERO DE BRONCE DE 2" und 8.00 61.20 489.60
8.00 489.60 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 489.60
18.08 CAJA DE REGISTRO DE DESAGUE 12" X 24" und 2.00 199.30 398.60
2.00 398.60 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 398.60
19 SISTEMA DE AGUA FRIA 1,824.34
19.01 SALIDA DE AGUA FRIA PVC SAP pto 14.00 59.99 839.86
14.00 839.86 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 839.86
19.02 TUBERIA PVC SAP, CLASE 10, 3/4" m 8.00 10.28 82.24
8.00 82.24 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 82.24
19.03 TUBERIA PVC SAP, CLASE 10, 1/2" m 40.00 8.43 337.20
40.00 337.20 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 337.20
19.04 GRIFERIA DE 1/2" und 11.00 37.66 414.26
11.00 414.26 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 414.26
19.05 VALVULA DE COMPUERTA DE BRONCE DE 1/2" und 2.00 52.06 104.12
2.00 104.12 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 104.12
19.06 VALVULA CHECK DE 3/4" und 1.00 46.66 46.66
1.00 46.66 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 46.66
20 SISTEMA DE AGUA DE LLUVIA 268.32
20.01 TUBERIA DE BAJADA Y DISTRIBUCION PVC 3" m 12.00 22.36 268.32
12.00 268.32 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 268.32
21 INSTALACIONES ELECTRICAS 2,191.87
21.01 SALIDA PARA CENTRO DE LUZ pto 7.00 77.05 539.35
7.00 539.35 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 539.35
21.02 EQUIPO FLUORESCENTE RECTANGULAR 1X40 W und 7.00 92.66 648.62
7.00 648.62 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 648.62
21.03 TABLERO METALICO DE DISTRIBUCION - SS. HH. und 1.00 320.66 320.66
1.00 320.66 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 320.66
21.04 POZO DE CONEXION A TIERRA und 1.00 683.24 683.24
1.00 683.24 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 683.24
22 TRABAJOS PRELIMINARES 179.81
22.01 LIMPIEZA DEL TERRENO MANUAL m2 79.56 1.32 105.02
79.56 105.02 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 105.02
22.02 TRAZO Y REPLANTEO PRELIMINAR m2 79.56 0.94 74.79
79.56 74.79 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 74.79
23 MOVIMIENTOS DE TIERRAS 895.16
23.01 EXCAVACION DE ZANJAS m3 24.41 16.48 402.28
24.41 402.28 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 402.28
23.02 RELLENO CON MATERIAL PROPIO m3 7.32 9.41 68.88
7.32 68.88 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 68.88
23.03 ACARREO DE MATERIAL EXCEDENTE HASTA dprom=30 m. m3 17.08 10.99 187.71
17.08 187.71 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 187.71
23.04 REFINE, NIVELACION Y COMPACTACION m2 79.56 2.97 236.29
79.56 236.29 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 236.29
24 OBRAS DE CONCRETO SIMPLE 4,204.45
24.01 SOLADO PARA ZAPATAS C:H = 1:12, E=4" m2 4.80 30.09 144.43
0.00 0.00 0.00% 4.80 144.43 100.00% 0.00 0.00 0.00% 144.43
24.02 CIMIENTO CORRIDO, CONCRETO C:H = 1:10 + 30% P.G. m3 11.04 134.18 1,481.35
0.00 0.00 0.00% 11.04 1,481.35 100.00% 0.00 0.00 0.00% 1,481.35
24.03 SOBRECIMIENTO, CONCRETO C:H = 1:8 + 25% P.M. m3 7.06 281.10 1,984.57
0.00 0.00 0.00% 7.06 1,984.57 100.00% 0.00 0.00 0.00% 1,984.57
24.04 SOBRECIMIENTO, ENCOFRADO Y DESENCOFRADO m2 19.79 30.02 594.10
0.00 0.00 0.00% 19.79 594.10 100.00% 0.00 0.00 0.00% 594.10
25 OBRAS DE CONCRETO ARMADO 19,008.08
25.01 ZAPATAS, CONCRETO F'c=210 kg/cm2 m3 2.88 358.17 1,031.53
0.00 0.00 0.00% 2.88 1,031.53 100.00% 0.00 0.00 0.00% 1,031.53
25.02 ZAPATAS, ACERO Fy=4200 kg/cm2 kg 58.75 5.08 298.45
0.00 0.00 0.00% 58.75 298.45 100.00% 0.00 0.00 0.00% 298.45
25.03 COLUMNAS, CONCRETO F'c=210 kg/cm2 m3 2.60 393.96 1,024.30
0.00 0.00 0.00% 2.60 1,024.30 100.00% 0.00 0.00 0.00% 1,024.30
25.04 COLUMNAS, ENCOFRADO Y DESENCOFRADO m2 29.70 27.81 825.96
0.00 0.00 0.00% 29.70 825.96 100.00% 0.00 0.00 0.00% 825.96
25.05 COLUMNAS, ACERO Fy=4200 kg/cm2 kg 431.49 5.08 2,191.97
0.00 0.00 0.00% 431.49 2,191.97 100.00% 0.00 0.00 0.00% 2,191.97
25.06 VIGAS, CONCRETO F'c=210 kg/cm2 m3 2.70 364.10 983.07
0.00 0.00 0.00% 2.70 983.07 100.00% 0.00 0.00 0.00% 983.07
25.07 VIGAS, ENCOFRADO Y DESENCOFRADO m2 29.36 36.43 1,069.58
0.00 0.00 0.00% 29.36 1,069.58 100.00% 0.00 0.00 0.00% 1,069.58
25.08 VIGAS, ACERO Fy=4200 kg/cm2 kg 420.50 5.08 2,136.14
0.00 0.00 0.00% 420.50 2,136.14 100.00% 0.00 0.00 0.00% 2,136.14
25.09 LOSA ALIGERADA, CONCRETO F'c=210 kg/cm² m3 8.62 370.99 3,197.93
0.00 0.00 0.00% 8.62 3,197.93 100.00% 0.00 0.00 0.00% 3,197.93
25.10 LOSA ALIGERADA, ENCOFRADO Y DESENCOFRADO m2 25.08 22.93 575.08
0.00 0.00 0.00% 25.08 575.08 100.00% 0.00 0.00 0.00% 575.08
25.11 LOSA ALIGERADA, ACERO Fy=4200 kg/cm² kg 521.74 5.08 2,650.44
0.00 0.00 0.00% 521.74 2,650.44 100.00% 0.00 0.00 0.00% 2,650.44
25.12 LOSA ALIGERADA, LADRILLO HUECO DE 30x30x12 cm. und 422.22 2.48 1,047.11
0.00 0.00 0.00% 422.22 1,047.11 100.00% 0.00 0.00 0.00% 1,047.11
25.13 CUNETA PARA EVACUACION PLUVIAL, CONCRETO F'c=175 kg/cm² m3 2.15 349.08 750.52
0.00 0.00 0.00% 2.15 750.52 100.00% 0.00 0.00 0.00% 750.52
25.14 CUNETA PARA EVACUACION PLUVIAL, ENCOFRADO Y DESENCOFRADO m2 6.00 39.78 238.68
0.00 0.00 0.00% 6.00 238.68 100.00% 0.00 0.00 0.00% 238.68
25.15 CUNETA PARA EVACUACION PLUVIAL, ACERO Fy=4200 kg/cm² kg 91.00 5.08 462.28
0.00 0.00 0.00% 91.00 462.28 100.00% 0.00 0.00 0.00% 462.28
25.16 MESA, CONCRETO F'c = 175 kg/cm² m3 0.48 395.75 189.96
0.00 0.00 0.00% 0.48 189.96 100.00% 0.00 0.00 0.00% 189.96
25.17 MESA, ENCOFRADO Y DESENCOFRADO m2 0.96 33.53 32.19
0.00 0.00 0.00% 0.96 32.19 100.00% 0.00 0.00 0.00% 32.19
25.18 MESA, ACERO Fy = 4200 kg/cm² kg 56.51 5.36 302.89
0.00 0.00 0.00% 56.51 302.89 100.00% 0.00 0.00 0.00% 302.89
26 MUROS Y TABIQUES DE ALBAÑILERIA 4,436.51
26.01 MURO DE LADRILLO KK DE ARCILLA 23x13x9 SOGA / J=1.5 cm. m2 91.55 48.46 4,436.51
0.00 0.00 0.00% 91.55 4,436.51 100.00% 0.00 0.00 0.00% 4,436.51
27 CUBIERTAS 2,936.08
27.01 TECHO DE FIBRA VEGETAL 3.05X1.1X2mm m2 49.88 32.60 1,626.09
0.00 0.00 0.00% 0.00 0.00 0.00% 49.88 1,626.09 100.00% 1,626.09
27.02 COBERTURA TECHA PLUS CLARITA 1.8*0.81 m2 34.32 38.17 1,309.99
0.00 0.00 0.00% 0.00 0.00 0.00% 34.32 1,309.99 100.00% 1,309.99
28 REVOQUES Y ENLUCIDOS 5,725.26
28.01 TARRAJEO EN MUROS INTERIORES (MEZCLA 1:5) m2 103.33 15.79 1,631.58
0.00 0.00 0.00% 0.00 0.00 0.00% 103.33 1,631.58 100.00% 1,631.58
28.02 TARRAJEO EN MURO EXTERIOR m2 82.76 25.45 2,106.24
0.00 0.00 0.00% 0.00 0.00 0.00% 82.76 2,106.24 100.00% 2,106.24
28.03 TARRAJEO EN COLUMNAS (MEZCLA 1:5) m2 21.00 19.35 406.35
0.00 0.00 0.00% 0.00 0.00 0.00% 21.00 406.35 100.00% 406.35
28.04 TARRAJEO EN VIGAS (MEZCLA 1:5) m2 46.55 22.90 1,066.00
0.00 0.00 0.00% 0.00 0.00 0.00% 46.55 1,066.00 100.00% 1,066.00
28.05 TARRAJEO PRIMARIO Y RAYADO (MEZCLA 1:5) m2 26.64 13.96 371.89
0.00 0.00 0.00% 0.00 0.00 0.00% 26.64 371.89 100.00% 371.89
28.06 VESTIDURA DE DERRAMES m 20.00 7.16 143.20
0.00 0.00 0.00% 0.00 0.00 0.00% 20.00 143.20 100.00% 143.20
29 CIELORRASOS 1,220.17
29.01 TARRAJEO DE CIELO RASO m2 41.46 29.43 1,220.17

30 PISOS Y PAVIMENTOS 4,350.81


30.01 FALSO PISO DE E = 4" MEZCLA C:H = 1:10 m2 34.32 28.25 969.54
0.00 0.00 0.00% 0.00 0.00 0.00% 34.32 969.54 100.00% 969.54
30.02 PISO DE CERAMICO DE 0.30x0.30 m. m2 34.32 40.37 1,385.50
0.00 0.00 0.00% 0.00 0.00 0.00% 34.32 1,385.50 100.00% 1,385.50
30.03 VEREDA, CONCRETO FROTACHADO DE E = 4" m2 40.72 40.18 1,636.13
0.00 0.00 0.00% 0.00 0.00 0.00% 40.72 1,636.13 100.00% 1,636.13
30.04 VEREDA, ENCOFRADO Y DESENCOFRADO m2 9.00 39.96 359.64
0.00 0.00 0.00% 0.00 0.00 0.00% 9.00 359.64 100.00% 359.64
31 ZOCALOS Y CONTRAZOCALOS 604.18
31.01 CONTRAZOCALO DE CEMENTO, EXTERIOR h = 30 cm. m 22.12 8.30 183.60
0.00 0.00 0.00% 0.00 0.00 0.00% 22.12 183.60 100.00% 183.60
31.02 ZOCALO DE CERAMICO DE 0.20x0.30 m. m2 8.96 46.94 420.58
0.00 0.00 0.00% 0.00 0.00 0.00% 8.96 420.58 100.00% 420.58
32 CARPINTERIA DE MADERA 913.46
32.01 PUERTA APANELADA DE MADERA CEDRO m2 4.20 217.49 913.46
0.00 0.00 0.00% 0.00 0.00 0.00% 4.20 913.46 100.00% 913.46
CALENDARIO DE AVANCE VALORIZADO DE OBRA

CREACIÓN DE PISTAS Y VEREDAS EN EL CENTRO POBLADO DE AUTAMA, DISTRITO DE SANTIAGO DE


PROYECTO
PAUCARAY, PROVINCIA DE SUCRE, REGIÓN AYACUCHO.

VALORIZACION - MES 01 VALORIZACION - MES 02 VALORIZACION - MES 03


Costo
ITEM DESCRIPCION UND Metrado Parcial (S/.) COSTO TOTAL
Unitario VALORIZACION VALORIZACION VALORIZACION
Metrado % Metrado % Metrado %
MENSUAL MENSUAL MENSUAL

33 ESTRUCTURA METALICA 3,440.00


33.01 VIGAS METALICAS m 12.00 118.00 1,416.00
0.00 0.00 0.00% 0.00 0.00 0.00% 12.00 1,416.00 100.00% 1,416.00
33.02 CORREAS METALICAS m 44.00 46.00 2,024.00
0.00 0.00 0.00% 0.00 0.00 0.00% 44.00 2,024.00 100.00% 2,024.00
34 CARPINTERIA METALICA Y HERRERIA 941.60
34.01 VENTANAS METALICAS m2 8.56 110.00 941.60
0.00 0.00 0.00% 0.00 0.00 0.00% 8.56 941.60 100.00% 941.60
35 CERRAJERIA 243.82
35.01 BISAGRA CAPUCHINA DE 3" und 6.00 13.90 83.40
0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 83.40 100.00% 83.40
35.02 CERRADURAS PARA PUERTAS DE MADERA DE 02 GOLPES und 2.00 80.21 160.42
0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 160.42 100.00% 160.42
36 VIDRIOS 686.07
36.01 VIDRIO SEMIDOBLE p2 99.00 6.93 686.07
0.00 0.00 0.00% 0.00 0.00 0.00% 99.00 686.07 100.00% 686.07
37 PINTURA 2,432.15
37.01 PINTURA LATEX, EN GRADERIAS m2 103.33 7.52 777.04
0.00 0.00 0.00% 0.00 0.00 0.00% 103.33 777.04 100.00% 777.04
37.02 PINTURA LATEX, EN MUROS EXTERIORES m2 82.76 7.52 622.36
0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00
37.03 PINTURA LATEX, EN COLUMNAS Y COLUMNETAS m2 21.00 7.29 153.09
0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00
37.04 PINTURA LATEX, EN VIGAS m2 46.55 9.12 424.54
0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00
37.05 PINTURA LATEX, EN CIELO RASO m2 41.76 8.34 348.28
0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00
37.06 PINTURA ESMALTE, EN CONTRAZOCALOS m 22.12 4.83 106.84
0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00
38 INSTALACIONES ELECTRICAS 1,591.60
38.01 SALIDA PARA CENTRO DE LUZ pto 4.00 77.05 308.20
0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 308.20 100.00% 308.20
38.02 SALIDA PARA TOMACORRIENTE A PRUEBA DE HUMEDAD pto 10.00 75.21 752.10
0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 752.10 100.00% 752.10
38.03 EQUIPO FLUORESCENTE RECTANGULAR 1X40 W und 4.00 52.66 210.64
0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 210.64 100.00% 210.64
38.04 TABLERO METALICO DE DISTRIBUCION - SS. HH. und 1.00 320.66 320.66
0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 320.66 100.00% 320.66
39 VARIOS 3,132.52
39.01 JUNTA DE DILATACION DE 1" m 15.00 6.36 95.40
0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 95.40 100.00% 95.40
39.02 TUBO DE FIERRO PESADO D = 4" m 16.80 180.00 3,024.00
0.00 0.00 0.00% 0.00 0.00 0.00% 16.80 3,024.00 100.00% 3,024.00
39.03 PERFILES (Rodoplast) m 2.00 6.56 13.12
0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 13.12 100.00% 13.12
40 TRABAJOS PROVISIONALES 1,988.80
40.01 LIMPIEZA DEL TERRENO MANUAL m2 880.00 1.32 1,161.60
0.00 0.00 0.00% 0.00 0.00 0.00% 880.00 1,161.60 100.00% 1,161.60
40.02 TRAZO Y REPLANTEO PRELIMINAR m2 880.00 0.94 827.20
0.00 0.00 0.00% 0.00 0.00 0.00% 880.00 827.20 100.00% 827.20
41 MOVIMIENTO DE TIERRAS 17,512.93
41.01 CORTE MASIVO DE TERRENO m3 831.00 6.87 5,708.97
831.00 5,708.97 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5,708.97
41.02 EXCAVACION MASIVA CON MAQ m3 240.00 6.87 1,648.80
240.00 1,648.80 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,648.80
41.03 RELLENO CON MATERIAL PROPIO m3 492.00 12.36 6,081.12
492.00 6,081.12 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6,081.12
41.04 REFINE, NIVELACION Y COMPACTACION m2 800.00 2.97 2,376.00
800.00 2,376.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2,376.00
41.05 AFIRMADO DE LOSA DE 4" m3 110.40 9.41 1,038.86
110.40 1,038.86 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,038.86
41.06 ELIMINACION DE MATERIAL EXCEDENTE m3 105.30 6.26 659.18
105.30 659.18 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 659.18
42 OBRAS DE CONCRETO SIMPLE 51,369.77
42.01 ENCOFRADO Y DESENCOFRADO LOSA, SARDINEL, CUNETA m2 79.40 31.36 2,489.98
0.00 0.00 0.00% 79.40 2,489.98 100.00% 0.00 0.00 0.00% 2,489.98
42.02 CONCRETO EN LOSA, CUNETA , SARDINEL F'c=175 kg/cm² m3 121.68 385.40 46,895.47
0.00 0.00 0.00% 121.68 46,895.47 100.00% 0.00 0.00 0.00% 46,895.47
42.03 JUNTA DE DILATACION DE 1" m 312.00 6.36 1,984.32
0.00 0.00 0.00% 312.00 1,984.32 100.00% 0.00 0.00 0.00% 1,984.32
43 CARPINTERIA METALICA 11,700.00
43.01 ARCO DE FUTBOL Y TABLERO DE BASKETBOL und 2.00 5,000.00 10,000.00
0.00 0.00 0.00% 2.00 10,000.00 100.00% 0.00 0.00 0.00% 10,000.00
43.02 POSTE DE VOLEYBOL (INC MALLA Y CABLE TENSOR) und 2.00 850.00 1,700.00
0.00 0.00 0.00% 2.00 1,700.00 100.00% 0.00 0.00 0.00% 1,700.00
44 PINTURA 965.81
44.01 PINTURA EN LINEAS DEMARCATORIAS DE LOSA m2 372.90 2.59 965.81
0.00 0.00 0.00% 372.90 965.81 100.00% 0.00 0.00 0.00% 965.81
45 VARIOS 900.00
45.01 PLACA RECORDATORIA METALICA DE 0.40 x 0.40 m. und 1.00 350.00 350.00
0.00 0.00 0.00% 1.00 350.00 100.00% 0.00 0.00 0.00% 350.00
45.02 DISEÑO DE MEZCLA DEL CONCRETO und 1.00 550.00 550.00
0.00 0.00 0.00% 1.00 550.00 100.00% 0.00 0.00 0.00% 550.00
46 TRABAJOS PROVISIONALES 118.65
46.01 LIMPIEZA DEL TERRENO MANUAL m2 52.50 1.32 69.30
52.50 69.30 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 69.30
46.02 TRAZO Y REPLANTEO PRELIMINAR m2 52.50 0.94 49.35
52.50 49.35 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 49.35
47 MOVIMIENTO DE TIERRAS 77.18
47.01 EXCAVACION DE ZANJAS m3 2.94 16.48 48.45
2.94 48.45 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 48.45
47.02 ELIMINACION DE MATERIAL EXCEDENTE m3 4.59 6.26 28.73
4.59 28.73 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 28.73
48 OBRAS DE CONCRETO SIMPLE 12,339.79
48.01 CONCRETO DE GRADERIAS F'c=140 kg/cm² 30% PG m3 45.60 248.74 11,342.54
45.60 11,342.54 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11,342.54
48.02 ENCOFRADO Y DESENCOFRADO DE GRADERIAS m2 31.80 31.36 997.25
31.80 997.25 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 997.25
49 REVOQUES Y ENLUCIDOS 2,259.29
49.01 TARRAJEO EN GRADERIAS m2 85.40 25.45 2,173.43
0.00 0.00 0.00% 85.40 2,173.43 100.00% 0.00 0.00 0.00% 2,173.43
49.02 JUNTA DE DILATACION DE 1" m 13.50 6.36 85.86
0.00 0.00 0.00% 13.50 85.86 100.00% 0.00 0.00 0.00% 85.86
50 PINTURA 613.63
50.01 PINTURA LATEX, EN GRADERIAS m2 81.60 7.52 613.63
0.00 0.00 0.00% 81.60 613.63 100.00% 0.00 0.00 0.00% 613.63
51 ESTRUCTURA METALICA 8,439.80
51.01 VIGAS METALICAS m 34.10 118.00 4,023.80
0.00 0.00 0.00% 34.10 4,023.80 100.00% 0.00 0.00 0.00% 4,023.80
51.02 CORREAS METALICAS m 96.00 46.00 4,416.00
0.00 0.00 0.00% 96.00 4,416.00 100.00% 0.00 0.00 0.00% 4,416.00
52 CUBIERTAS 2,425.44
52.01 TECHO DE FIBRA VEGETAL 3.05X1.1X2mm m2 74.40 32.60 2,425.44
0.00 0.00 0.00% 74.40 2,425.44 100.00% 0.00 0.00 0.00% 2,425.44
53 MOVIMIENTO DE TIERRAS 1,397.29
53.01 REFINE, NIVELACION Y COMPACTACION m2 11.55 2.97 34.30
11.55 34.30 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 34.30
53.02 EXCAVACION DE ZANJAS m3 44.00 16.48 725.12
44.00 725.12 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 725.12
53.03 RELLENO CON MATERIAL PROPIO m3 44.00 12.36 543.84
44.00 543.84 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 543.84
53.04 ELIMINACION DE MATERIAL EXCEDENTE m3 15.02 6.26 94.03
15.02 94.03 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 94.03
54 OBRAS DE CONCRETO SIMPLE 6,079.58
54.01 CIMIENTO CORRIDO, CONCRETO C:H = 1:10 + 30% P.G. m3 11.75 134.18 1,576.62
11.75 1,576.62 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,576.62
54.02 CONCRETO DE LOSA F'c=175 kg/cm² m2 44.00 102.34 4,502.96
44.00 4,502.96 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4,502.96
55 OBRAS DE CONCRETO ARMADO 10,256.59
55.01 PLACA, CONCRETO F'c=175 kg/cm2 m3 5.28 352.64 1,861.94
0.00 0.00 0.00% 5.28 1,861.94 100.00% 0.00 0.00 0.00% 1,861.94
CALENDARIO DE AVANCE VALORIZADO DE OBRA

CREACIÓN DE PISTAS Y VEREDAS EN EL CENTRO POBLADO DE AUTAMA, DISTRITO DE SANTIAGO DE


PROYECTO
PAUCARAY, PROVINCIA DE SUCRE, REGIÓN AYACUCHO.

VALORIZACION - MES 01 VALORIZACION - MES 02 VALORIZACION - MES 03


Costo
ITEM DESCRIPCION UND Metrado Parcial (S/.) COSTO TOTAL
Unitario VALORIZACION VALORIZACION VALORIZACION
Metrado % Metrado % Metrado %
MENSUAL MENSUAL MENSUAL

55.02 PLACA, ENCOFRADO Y DESENCOFRADO m2 300.13 23.54 7,065.06


0.00 0.00 0.00% 300.13 7,065.06 100.00% 0.00 0.00 0.00% 7,065.06
55.03 PLACA, ACERO Fy=4200 kg/cm2 kg 261.73 5.08 1,329.59
0.00 0.00 0.00% 261.73 1,329.59 100.00% 0.00 0.00 0.00% 1,329.59
56 ESTRUCTURA METALICA 6,052.00
56.01 VIGAS METALICAS m 24.00 118.00 2,832.00
0.00 0.00 0.00% 24.00 2,832.00 100.00% 0.00 0.00 0.00% 2,832.00
56.02 CORREAS METALICAS m 70.00 46.00 3,220.00
0.00 0.00 0.00% 70.00 3,220.00 100.00% 0.00 0.00 0.00% 3,220.00
57 CUBIERTAS 1,320.30
57.01 TECHO DE FIBRA VEGETAL 3.05X1.1X2mm m2 40.50 32.60 1,320.30
0.00 0.00 0.00% 40.50 1,320.30 100.00% 0.00 0.00 0.00% 1,320.30
58 TRABAJOS PRELIMINARES 383.61
58.01 LIMPIEZA DEL TERRENO MANUAL m2 119.86 1.32 158.22
119.86 158.22 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 158.22
58.02 TRAZO , NIVELACION Y REPLANTEO PRELIMINAR m2 119.86 0.94 112.67
119.86 112.67 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 112.67
58.03 TRAZO , NIVELACION Y REPLANTEO DURANTE LA OBRA m2 119.92 0.94 112.72
119.92 112.72 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 112.72
59 MOVIMIENTOS DE TIERRAS 1,356.51
59.01 EXCAVACION DE CIMIENTO m3 30.11 16.48 496.21
30.11 496.21 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 496.21
59.02 ACARREO DE MATERIAL EXCEDENTE m3 39.14 10.99 430.15
39.14 430.15 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 430.15
59.03 ELIMINACION DE MATERIAL EXCEDENTE m3 39.14 10.99 430.15
39.14 430.15 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 430.15
60 OBRAS DE CONCRETO SIMPLE 11,406.25
60.01 CONCRETO PARA CIMIENTO CORRIDO, CONCRETO C:H = 1:10 + 30% P.G. m3 19.56 140.67 2,751.51
0.00 0.00 0.00% 19.56 2,751.51 100.00% 0.00 0.00 0.00% 2,751.51
60.02 CONCRETO EN SOBRECIMIENTO, CONCRETO C:H = 1:8 + 25% P.M. m3 8.41 281.10 2,364.05
0.00 0.00 0.00% 8.41 2,364.05 100.00% 0.00 0.00 0.00% 2,364.05
60.03 SOBRECIMIENTO, ENCOFRADO Y DESENCOFRADO m2 209.55 30.02 6,290.69
0.00 0.00 0.00% 209.55 6,290.69 100.00% 0.00 0.00 0.00% 6,290.69
61 OBRAS DE CONCRETO ARMADO 13,706.71
61.01 COLUMNA 9,679.49

61.01.01 COLUMNA, CONCRETO F'c=210 kg/cm2 m3 10.25 385.02 3,946.46


0.00 0.00 0.00% 10.25 3,946.46 100.00% 0.00 0.00 0.00% 3,946.46
61.01.02 COLUMNAS, ENCOFRADO Y DESENCOFRADO m2 61.47 27.81 1,709.48
0.00 0.00 0.00% 61.47 1,709.48 100.00% 0.00 0.00 0.00% 1,709.48
61.01.03 COLUMNAS, ACERO Fy=4200 kg/cm2 kg 775.25 5.19 4,023.55
0.00 0.00 0.00% 775.25 4,023.55 100.00% 0.00 0.00 0.00% 4,023.55
61.02 VIGA 4,027.22

61.02.01 VIGAS, CONCRETO F'c=210 kg/cm2 m3 3.20 389.54 1,246.53


0.00 0.00 0.00% 3.20 1,246.53 100.00% 0.00 0.00 0.00% 1,246.53
61.02.02 VIGAS, ENCOFRADO Y DESENCOFRADO m2 30.00 36.43 1,092.90
0.00 0.00 0.00% 30.00 1,092.90 100.00% 0.00 0.00 0.00% 1,092.90
61.02.03 VIGAS, ACERO Fy=4200 kg/cm2 kg 325.20 5.19 1,687.79
0.00 0.00 0.00% 325.20 1,687.79 100.00% 0.00 0.00 0.00% 1,687.79
62 MUROS Y TABIQUES DE ALBAÑILERIA 10,364.62
62.01 MURO DE LADRILLO KK DE ARCILLA 23x13x9 SOGA / J=1.5 cm. m2 213.88 48.46 10,364.62
0.00 0.00 0.00% 213.88 10,364.62 100.00% 0.00 0.00 0.00% 10,364.62
63 REVOQUES Y ENLUCIDOS 8,674.12
63.01 TARRAJEO EN COLUMNAS (MEZCLA 1:5) m2 125.60 19.35 2,430.36
0.00 0.00 0.00% 0.00 0.00 0.00% 125.60 2,430.36 100.00% 2,430.36
63.02 TARRAJEO EN VIGAS (MEZCLA 1:5) m2 57.00 22.90 1,305.30
0.00 0.00 0.00% 0.00 0.00 0.00% 57.00 1,305.30 100.00% 1,305.30
63.03 TARRAJEO EN SOBRECIMIENTO (MEZCLA 1:5) m2 305.22 16.18 4,938.46
0.00 0.00 0.00% 0.00 0.00 0.00% 305.22 4,938.46 100.00% 4,938.46
64 CARPINTERIA METALICA Y HERRERIA 4,782.24
64.01 REJAS METALICAS SEGUN DISEÑO m 24.00 199.26 4,782.24
0.00 0.00 0.00% 0.00 0.00 0.00% 24.00 4,782.24 100.00% 4,782.24
65 PINTURA 6,067.80
65.01 PINTURA BARNIZ EN MURO CARAVISTA (2 MANOS) m2 406.37 6.38 2,592.64
0.00 0.00 0.00% 0.00 0.00 0.00% 406.37 2,592.64 100.00% 2,592.64
65.02 PINTURA LATEX, EN COLUMNAS m2 83.00 7.29 605.07
0.00 0.00 0.00% 0.00 0.00 0.00% 83.00 605.07 100.00% 605.07
65.03 PINTURA LATEX, EN VIGAS m2 57.00 8.34 475.38
0.00 0.00 0.00% 0.00 0.00 0.00% 57.00 475.38 100.00% 475.38
65.04 PINTURA ESMALTE SINTETICO SOBRECIEMIENTO m2 305.22 7.12 2,173.17
0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00
65.05 PINTURA ESMALTE Y ANTICORROSICA EN CARPINTERIA METALICA m 22.00 10.07 221.54
0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00
66 VARIOS 456.07
66.01 JUNTA DE CONSTRUCCION DE 1" m 36.75 12.41 456.07
0.00 0.00 0.00% 36.75 456.07 100.00% 0.00 0.00 0.00% 456.07
67 TRABAJOS PRELIMINARES 56.05
67.01 LIMPIEZA DEL TERRENO MANUAL m2 24.80 1.32 32.74
24.80 32.74 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 32.74
67.02 TRAZO , NIVELACION Y REPLANTEO PRELIMINAR m2 24.80 0.94 23.31
24.80 23.31 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 23.31
68 MOVIMIENTOS DE TIERRAS 531.27
68.01 EXCAVACION DE CIMIENTO m3 19.34 16.48 318.72
19.34 318.72 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 318.72
68.02 ELIMINACION DE MATERIAL EXCEDENTE m3 19.34 10.99 212.55
19.34 212.55 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 212.55
69 OBRAS DE CONCRETO SIMPLE 3,474.67
69.01 SOLADO PARA ZAPATAS C:H = 1:12, E=4" m2 15.00 30.09 451.35
0.00 0.00 0.00% 15.00 451.35 100.00% 0.00 0.00 0.00% 451.35
69.02 CONCRETO EN SOBRECIMIENTO, CONCRETO C:H = 1:8 + 25% P.M. m3 3.90 281.10 1,096.29
0.00 0.00 0.00% 3.90 1,096.29 100.00% 0.00 0.00 0.00% 1,096.29
69.03 MURO, CONCRETO F'c=175 kg/cm2 DADOS m3 0.80 325.27 260.22
0.00 0.00 0.00% 0.80 260.22 100.00% 0.00 0.00 0.00% 260.22
69.04 MURO, ENCOFRADO Y DESENCOFRADO m2 68.20 24.44 1,666.81
0.00 0.00 0.00% 68.20 1,666.81 100.00% 0.00 0.00 0.00% 1,666.81
70 CARPINTERIA METALICA Y HERRERIA 3,146.00
70.01 CERCO MALLA METALICA m2 28.60 110.00 3,146.00
0.00 0.00 0.00% 28.60 3,146.00 100.00% 0.00 0.00 0.00% 3,146.00
71 PINTURA 302.10
71.01 PINTURA ESMALTE Y ANTICORROSICA EN CARPINTERIA METALICA m 30.00 10.07 302.10
0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00
72 TRABAJOS PRELIMINARES 400.00
72.01 LIMPIEZA DEL TERRENO MANUAL m2 125.00 1.32 165.00
0.00 0.00 0.00% 125.00 165.00 100.00% 0.00 0.00 0.00% 165.00
72.02 TRAZO , NIVELACION Y REPLANTEO PRELIMINAR m2 125.00 0.94 117.50
0.00 0.00 0.00% 125.00 117.50 100.00% 0.00 0.00 0.00% 117.50
72.03 TRAZO , NIVELACION Y REPLANTEO DURANTE LA OBRA m2 125.00 0.94 117.50
0.00 0.00 0.00% 125.00 117.50 100.00% 0.00 0.00 0.00% 117.50
73 MOVIMIENTOS DE TIERRAS 142.99
73.01 EXCAVACION DE CIMIENTO m3 3.12 16.48 51.42
0.00 0.00 0.00% 3.12 51.42 100.00% 0.00 0.00 0.00% 51.42
73.02 RELLENO CON MATERIAL PROPIO m3 3.00 12.36 37.08
0.00 0.00 0.00% 3.00 37.08 100.00% 0.00 0.00 0.00% 37.08
73.03 REFINE, NIVELACION Y COMPACTACION m2 10.50 2.97 31.19
0.00 0.00 0.00% 10.50 31.19 100.00% 0.00 0.00 0.00% 31.19
73.04 ACARREO DE MATERIAL EXCEDENTE m3 1.06 10.99 11.65
0.00 0.00 0.00% 1.06 11.65 100.00% 0.00 0.00 0.00% 11.65
73.05 ELIMINACION DE MATERIAL EXCEDENTE m3 1.06 10.99 11.65
0.00 0.00 0.00% 1.06 11.65 100.00% 0.00 0.00 0.00% 11.65
74 OBRAS DE CONCRETO SIMPLE 7,309.91
74.01 VEREDA, CONCRETO FROTACHADO DE E = 4" m2 45.00 40.18 1,808.10
0.00 0.00 0.00% 45.00 1,808.10 100.00% 0.00 0.00 0.00% 1,808.10
74.02 PISO DE BLOQUES DE CONCRETO DE 0.20x0.10 m. m2 60.00 48.66 2,919.60
0.00 0.00 0.00% 60.00 2,919.60 100.00% 0.00 0.00 0.00% 2,919.60
74.03 VEREDA, ENCOFRADO Y DESENCOFRADO m2 25.20 39.96 1,006.99
0.00 0.00 0.00% 25.20 1,006.99 100.00% 0.00 0.00 0.00% 1,006.99
74.04 CONCRETO PARA CIMIENTO CORRIDO, CONCRETO C:H = 1:10 + 30% P.G. m3 6.60 140.67 928.42
0.00 0.00 0.00% 6.60 928.42 100.00% 0.00 0.00 0.00% 928.42
74.05 CONCRETO EN SOBRECIMIENTO, CONCRETO C:H = 1:8 + 25% P.M. m3 1.50 281.10 421.65
0.00 0.00 0.00% 1.50 421.65 100.00% 0.00 0.00 0.00% 421.65
74.06 SOBRECIMIENTO, ENCOFRADO Y DESENCOFRADO m2 7.50 30.02 225.15
0.00 0.00 0.00% 7.50 225.15 100.00% 0.00 0.00 0.00% 225.15
CALENDARIO DE AVANCE VALORIZADO DE OBRA

CREACIÓN DE PISTAS Y VEREDAS EN EL CENTRO POBLADO DE AUTAMA, DISTRITO DE SANTIAGO DE


PROYECTO
PAUCARAY, PROVINCIA DE SUCRE, REGIÓN AYACUCHO.

VALORIZACION - MES 01 VALORIZACION - MES 02 VALORIZACION - MES 03


Costo
ITEM DESCRIPCION UND Metrado Parcial (S/.) COSTO TOTAL
Unitario VALORIZACION VALORIZACION VALORIZACION
Metrado % Metrado % Metrado %
MENSUAL MENSUAL MENSUAL

75 OBRAS DE CONCRETO ARMADO 1,741.75


75.01 COLUMNA 698.84

75.01.01 COLUMNA, CONCRETO F'c=210 kg/cm2 m3 0.38 385.02 146.31


0.00 0.00 0.00% 0.38 146.31 100.00% 0.00 0.00 0.00% 146.31
75.01.02 COLUMNAS, ENCOFRADO Y DESENCOFRADO m2 10.80 27.81 300.35
0.00 0.00 0.00% 10.80 300.35 100.00% 0.00 0.00 0.00% 300.35
75.01.03 COLUMNAS, ACERO Fy=4200 kg/cm2 kg 48.59 5.19 252.18
0.00 0.00 0.00% 48.59 252.18 100.00% 0.00 0.00 0.00% 252.18
75.02 VIGA 501.66

75.02.01 VIGAS, CONCRETO F'c=210 kg/cm2 m3 0.40 389.54 155.82


0.00 0.00 0.00% 0.40 155.82 100.00% 0.00 0.00 0.00% 155.82
75.02.02 VIGAS, ENCOFRADO Y DESENCOFRADO m2 6.00 36.43 218.58
0.00 0.00 0.00% 6.00 218.58 100.00% 0.00 0.00 0.00% 218.58
75.02.03 VIGAS, ACERO Fy=4200 kg/cm2 kg 24.52 5.19 127.26
0.00 0.00 0.00% 24.52 127.26 100.00% 0.00 0.00 0.00% 127.26
75.03 LOSA 541.25

75.03.01 LOSA, CONCRETO F'c=175 kg/cm2 m3 0.80 324.04 259.23


0.00 0.00 0.00% 0.80 259.23 100.00% 0.00 0.00 0.00% 259.23
75.03.02 LOSA, ENCOFRADO Y DESENCOFRADO m2 5.60 36.43 204.01
0.00 0.00 0.00% 5.60 204.01 100.00% 0.00 0.00 0.00% 204.01
75.03.03 LOSA, ACERO Fy=4200 kg/cm2 kg 15.03 5.19 78.01
0.00 0.00 0.00% 15.03 78.01 100.00% 0.00 0.00 0.00% 78.01
76 REVOQUES Y ENLUCIDOS 842.22
76.01 TARRAJEO EN COLUMNAS (MEZCLA 1:5) m2 5.40 19.35 104.49
0.00 0.00 0.00% 0.00 0.00 0.00% 5.40 104.49 100.00% 104.49
76.02 TARRAJEO EN VIGAS (MEZCLA 1:5) m2 3.60 22.90 82.44
0.00 0.00 0.00% 0.00 0.00 0.00% 3.60 82.44 100.00% 82.44
76.03 TARRAJEO EN SOBRECIMIENTO (MEZCLA 1:5) m2 40.50 16.18 655.29
0.00 0.00 0.00% 0.00 0.00 0.00% 40.50 655.29 100.00% 655.29
77 CIELORRASOS 127.14
78 TARRAJEO DE CIELO RASO m2 4.32 29.43 127.14
0.00 0.00 0.00% 0.00 0.00 0.00% 1.70 50.00 39.33% 50.00
79 CARPINTERIA METALICA Y HERRERIA 2,842.50
79.01 PUERTA METALICA SEGUN DISEÑO m2 7.50 379.00 2,842.50
0.00 0.00 0.00% 0.00 0.00 0.00% 7.50 2,842.50 100.00% 2,842.50
80 PINTURA 393.78
80.01 PINTURA LATEX, EN COLUMNAS m2 5.40 7.29 39.37
0.00 0.00 0.00% 0.00 0.00 0.00% 5.40 39.37 100.00% 39.37
80.02 PINTURA LATEX, EN VIGAS m2 3.60 8.34 30.02
0.00 0.00 0.00% 0.00 0.00 0.00% 3.60 30.02 100.00% 30.02
80.03 PINTURA ESMALTE SINTETICO SOBRECIEMIENTO m2 40.50 7.12 288.36
0.00 0.00 0.00% 0.00 0.00 0.00% 40.50 288.36 100.00% 288.36
80.04 PINTURA CIELO RASO m2 4.32 8.34 36.03
0.00 0.00 0.00% 0.00 0.00 0.00% 4.32 36.03 100.00% 36.03
81 VARIOS 74.46
81.01 JUNTA DE CONSTRUCCION DE 1" m 6.00 12.41 74.46
0.00 0.00 0.00% 6.00 74.46 100.00% 0.00 0.00 0.00% 74.46
82 ALUMBRADO ELECTRICO 6,644.50
82.01 ALUMBRADO ELECTRICO GLB 1.00 6,644.50 6,644.50
0.30 2,000.00 30.10% 0.45 3,000.00 45.15% 0.25 1,644.50 24.75% 6,644.50
83 MITIGACION AMBIENTAL 2,000.00
83.01 MITIGACION AMBIENTAL GLB 1.00 2,000.00 2,000.00
1.00 2,000.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2,000.00
84 COMPRA DE TERRENO 50,000.00
84.01 COMPRA DE TERRENO GLB 1.00 50,000.00 50,000.00
1.00 50,000.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 50,000.00
85 VARIOS 16,476.10
85.01 FLETE TERRESTRE GLB 1.00 16,476.10 16,476.10
1.00 16,476.10 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16,476.10

COSTO DIRECTO 427,462.93 130,215.45 30.46% 198,403.32 46.41% 90,290.12 21.12% 418,908.89

GASTOS GENERALES (10%) 42,746.29 13,021.55 19,840.33 9,029.01 41,890.90

UTILIDAD (8%) 34,197.03 10,417.24 15,872.27 7,223.21 33,512.73

SUB TOTAL 504,406.25 153,654.24 234,115.92 106,542.34 494,312.52

IGV (18%) 90,793.13 27,657.76 42,140.87 19,177.62 88,976.25

SUPERVISIÒN (3%) 17,855.98 4,978.40 7,585.36 3,451.97 16,015.73

COSTO DE OBRA (CO) 613,055.36 186,290.40 30.39% 276,256.79 45.06% 125,719.96 20.51% 588,267.17
CALENDARIO DE REQUERIMIENTO DE MANO DE OBRA

FECHA: 2016 TIEMPO


CREACIÓN DE PISTAS Y VEREDAS EN EL CENTRO POBLADO DE AUTAMA, DISTRITO DE SANTIAGO DE PAUCARAY,
PROYECTO DE EJECUCIÓN: 9 MESES LUGAR: CP
PROVINCIA DE SUCRE, REGIÓN AYACUCHO.
AUTAMA

REQUERIMIENTO - MES 01 REQUERIMIENTO - MES 02 REQUERIMIENTO - MES 03 REQUERIMIENTO - MES 04 REQUERIMIENTO - MES 05 REQUERIMIENTO - MES 06 REQUERIMIENTO - MES 07 REQUERIMIENTO - MES 08 REQUERIMIENTO - MES 09
Costo
ITEM DESCRIPCION UND CANTIDAD Parcial (S/.) COSTO TOTAL
Unitario
Cantidad Presupuestado % Cantidad Presupuestado % Cantidad Presupuestado % Cantidad Presupuestado % Cantidad Presupuestado % Cantidad Presupuestado % Cantidad Presupuestado % Cantidad Presupuestado % Cantidad Presupuestado %

0147000032 TOPOGRAFO hh 803.59 19.30 15,509.32 411.29 7,937.90 51.18% 231.94 4,476.44 28.86% 160.36 3,094.98 19.96% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15,509.32
0147010002 OPERARIO hh 6,976.17 19.30 134,640.06 24.75 477.68 0.35% 186.82 3,605.63 2.68% 519.02 10,017.09 7.44% 725.78 14,007.55 10.40% 973.35 18,785.66 13.95% 1,662.01 32,076.79 23.82% 1,400.45 27,028.69 20.07% 889.85 17,174.11 12.76% 594.14 11,466.88 8.52% 134,640.06
0147010003 OFICIAL hh 8,907.37 16.01 142,606.93 205.13 3,284.13 2.30% 201.06 3,218.97 2.26% 519.02 8,309.51 5.83% 725.78 11,619.74 8.15% 987.10 15,803.47 11.08% 2,543.59 40,722.88 28.56% 2,134.20 34,168.54 23.96% 1,018.87 16,312.11 11.44% 572.62 9,167.58 6.43% 142,606.93
0147010004 PEON hh 44,492.28 14.40 640,688.85 2,487.45 35,819.28 5.59% 1,466.39 21,116.02 3.30% 2,549.97 36,719.57 5.73% 3,187.72 45,903.17 7.16% 5,539.03 79,762.03 12.45% 11,525.04 165,960.58 25.90% 9,544.45 137,440.08 21.45% 4,481.00 64,526.40 10.07% 3,711.23 53,441.73 8.34% 640,688.85

COSTO DIRECTO 933,445.16 47,518.98 5.09% 32,417.05 3.47% 58,141.14 6.23% 71,530.46 7.66% 114,351.16 12.25% 238,760.24 25.58% 198,637.31 21.28% 98,012.61 10.50% 74,076.20 7.94% 933,445.17
CALENDARIO DE REQUERIMIENTO DE MATERIALES

FECHA: 2016 TIEMPO


PROYECTO CREACIÓN DE PISTAS Y VEREDAS EN EL CENTRO POBLADO DE AUTAMA, DISTRITO DE SANTIAGO DE PAUCARAY, PROVINCIA DE SUCRE, REGIÓN AYACUCHO. DE EJECUCIÓN: 9 MESES LUGAR: CP
AUTAMA

REQUERIMIENTO - MES 01 REQUERIMIENTO - MES 02 REQUERIMIENTO - MES 03 REQUERIMIENTO - MES 04 REQUERIMIENTO - MES 05 REQUERIMIENTO - MES 06 REQUERIMIENTO - MES 07 REQUERIMIENTO - MES 08 REQUERIMIENTO - MES 09
Costo
ITEM DESCRIPCION UND CANTIDAD Parcial (S/.) COSTO TOTAL
Unitario
Cantidad Presupuestado % Cantidad Presupuestado % Cantidad Presupuestado % Cantidad Presupuestado % Cantidad Presupuestado % Cantidad Presupuestado % Cantidad Presupuestado % Cantidad Presupuestado % Cantidad Presupuestado %

0201920001 ALMACEN DE COMBUSTIBLE Y LUBRICANTES mes 9.00 254.24 2,288.16 1.03 261.87 11.44% 1.00 254.24 11.11% 1.00 254.24 11.11% 1.00 254.24 11.11% 1.00 254.24 11.11% 1.03 261.87 11.44% 1.00 254.24 11.11% 1.00 254.24 11.11% 0.94 238.99 10.44% 2,288.16
0201920002 ALMACEN DE MATERIALES COMUNES mes 9.00 254.24 2,288.16 1.03 261.87 11.44% 1.00 254.24 11.11% 1.00 254.24 11.11% 1.00 254.24 11.11% 1.00 254.24 11.11% 1.03 261.87 11.44% 1.00 254.24 11.11% 1.00 254.24 11.11% 0.94 238.99 10.44% 2,288.16
0201920003 ALMACEN DE CEMENTOS mes 9.00 254.24 2,288.16 1.03 261.87 11.44% 1.00 254.24 11.11% 1.00 254.24 11.11% 1.00 254.24 11.11% 1.00 254.24 11.11% 1.03 261.87 11.44% 1.00 254.24 11.11% 1.00 254.24 11.11% 0.94 238.99 10.44% 2,288.16
0201920005 OFICINA DE OBRA mes 9.00 254.24 2,288.16 1.03 261.87 11.44% 1.00 254.24 11.11% 1.00 254.24 11.11% 1.00 254.24 11.11% 1.00 254.24 11.11% 1.03 261.87 11.44% 1.00 254.24 11.11% 1.00 254.24 11.11% 0.94 238.99 10.44% 2,288.16
0201920008 SERVICIO HIGIENICO MOVIL DE CASETA und 2.00 1,271.19 2,542.38 0.25 317.80 12.50% 0.24 305.09 12.00% 0.24 305.09 12.00% 0.24 305.09 12.00% 0.24 305.09 12.00% 0.25 317.80 12.50% 0.24 305.09 12.00% 0.24 305.09 12.00% 0.06 76.27 3.00% 2,542.38
0201920032 MALLA PLASTIFICADA DE PROTECCION m 400.00 8.47 3,388.00 400.00 3,388.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3,388.00
0201920033 EXTINTOR und 2.00 42.37 84.74 2.00 84.74 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 84.74
0202000007 ALAMBRE NEGRO RECOCIDO # 16 kg 149.73 4.66 697.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 66.47 309.75 44.39% 83.26 387.98 55.61% 697.72
0202000008 ALAMBRE NEGRO RECOCIDO # 8 kg 1,323.13 4.66 6,165.77 0.00 0.00 0.00% 0.00 0.00 0.00% 78.60 366.28 5.94% 137.38 640.19 10.38% 243.69 1,135.59 18.42% 408.61 1,904.12 30.88% 342.13 1,594.32 25.86% 111.53 519.73 8.43% 1.19 5.54 0.09% 6,165.77
0202010005 CLAVOS PARA MADERA C/C 3" kg 479.76 4.66 2,235.70 1.00 4.66 0.21% 0.00 0.00 0.00% 39.30 183.14 8.19% 68.69 320.10 14.32% 78.66 366.56 16.40% 105.54 491.82 22.00% 79.46 370.28 16.56% 58.00 270.28 12.09% 49.11 228.87 10.24% 2,235.70
0202010007 CLAVOS PARA MADERA C/C 4" kg 1.00 4.66 4.66 1.00 4.66 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.66
0202970046 ESTACAS DE FIERRO Ø 1/2" var 201.20 25.42 5,114.45 0.00 0.00 0.00% 0.00 0.00 0.00% 27.21 691.68 13.52% 47.56 1,208.98 23.64% 47.56 1,208.98 23.64% 49.39 1,255.49 24.55% 29.48 749.32 14.65% 0.00 0.00 0.00% 0.00 0.00 0.00% 5,114.45
0202970047 ESTACAS DE FIERRO Ø 3/8" var 381.02 12.71 4,842.80 115.83 1,472.20 30.40% 116.39 1,479.32 30.55% 90.09 1,145.04 23.64% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.56 70.67 1.46% 7.66 97.36 2.01% 23.00 292.33 6.04% 22.49 285.88 5.90% 4,842.80
0204000000 ARENA FINA m3 498.19 110.17 54,885.44 0.00 0.00 0.00% 0.00 0.00 0.00% 31.42 3,461.54 6.31% 58.87 6,485.71 11.82% 58.87 6,485.71 11.82% 105.68 11,642.77 21.21% 117.82 12,980.23 23.65% 74.40 8,196.65 14.93% 51.13 5,632.84 10.26% 54,885.44
0205010004 ARENA GRUESA m3 2,486.18 110.17 273,902.02 0.00 0.00 0.00% 0.00 0.00 0.00% 201.16 22,161.80 8.09% 351.61 38,736.87 14.14% 381.09 41,984.69 15.33% 619.41 68,240.40 24.91% 511.90 56,396.02 20.59% 266.23 29,330.56 10.71% 154.78 17,051.68 6.23% 273,902.02
0205010013 MATERIAL CLASIFICADO PARA BASE m3 8,719.60 50.84 443,304.56 0.00 0.00 0.00% 3,682.44 187,215.25 42.23% 4,054.40 206,125.70 46.50% 0.00 0.00 0.00% 0.00 0.00 0.00% 586.15 29,799.87 6.72% 396.61 20,163.74 4.55% 0.00 0.00 0.00% 0.00 0.00 0.00% 443,304.56
0205030076 PIEDRA ZARANDEADA DE 3/4" m3 2,519.55 127.12 320,285.26 0.00 0.00 0.00% 0.00 0.00 0.00% 218.36 27,757.92 8.67% 381.67 48,517.89 15.15% 412.98 52,498.02 16.39% 595.55 75,706.32 23.64% 478.88 60,875.23 19.01% 276.20 35,110.54 10.96% 155.91 19,819.34 6.19% 320,285.26
0213000006 ASFALTO RC-250 gln 1,881.42 13.22 24,872.42 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 22.87 302.34 1.22% 741.10 9,797.34 39.39% 764.39 10,105.24 40.63% 214.50 2,835.69 11.40% 138.56 1,831.81 7.36% 24,872.42
0221000000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 35,797.10 20.34 728,113.08 1.00 20.34 0.00% 0.00 0.00 0.00% 3,260.14 66,311.25 9.11% 5,698.39 115,905.25 15.92% 6,089.15 123,853.31 17.01% 8,403.33 170,923.73 23.47% 6,556.06 133,350.26 18.31% 3,635.85 73,953.19 10.16% 2,153.18 43,795.74 6.01% 728,113.08
0229030002 YESO EN BOLSAS DE 25 KG. BOL 322.30 5.93 1,911.21 230.31 1,365.74 71.46% 61.95 367.36 19.22% 30.04 178.11 9.32% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,911.21
0232000058 FLETE TERRESTRE AYACUCHO A OBRA GLB 1.00 164,467.92 164,467.92 0.86 141,442.41 86.00% 0.14 23,025.51 14.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 164,467.92
0232970006 MOVILIZACION Y DESMOVILIZACION DE MAQUINARIAS GLB 1.00 19,985.84 19,985.84 1.00 19,985.84 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 19,985.84
0232970007 EMERGENCIA EN SEGURIDAD GLB 1.00 423.73 423.73 1.00 423.73 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 423.73
0232970008 EMERGENCIA EN SALUD GLB 1.00 677.97 677.97 1.00 677.97 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 677.97
0238000004 HORMIGON (PUESTO EN OBRA) m3 0.36 76.27 27.46 0.36 27.46 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.46
0239050000 AGUA m3 9,206.59 0.85 7,825.60 0.00 0.00 0.00% 1,200.69 1,020.59 13.04% 1,416.07 1,203.66 15.38% 1,093.44 929.42 11.88% 1,203.95 1,023.36 13.08% 1,785.04 1,517.28 19.39% 1,543.75 1,312.19 16.77% 588.00 499.80 6.39% 375.65 319.30 4.08% 7,825.60
0239060006 ESCOBILLA DE ACERO pza 101.03 5.93 599.11 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 101.03 599.11 100.00% 599.11
0239500100 TACHOS PLASTICOS und 10.00 21.19 211.90 1.25 26.49 12.50% 1.21 25.64 12.10% 1.21 25.64 12.10% 1.21 25.64 12.10% 1.21 25.64 12.10% 1.26 26.70 12.60% 1.21 25.64 12.10% 1.21 25.64 12.10% 0.23 4.87 2.30% 211.90
0239900100 CARTEL DE OBRA 2.4x3.6m GIGANTOGRAFIA und 1.00 338.98 338.98 1.00 338.98 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 338.98
0239900102 SEÑAL PREVENTIVA STANDAR und 60.00 127.11 7,626.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 60.00 7,626.60 100.00% 7,626.60
0243160052 REGLA DE MADERA p2 1,059.72 4.75 5,033.66 0.00 0.00 0.00% 0.00 0.00 0.00% 143.30 680.67 13.52% 250.48 1,189.78 23.64% 250.48 1,189.78 23.64% 260.11 1,235.52 24.55% 155.35 737.91 14.66% 0.00 0.00 0.00% 0.00 0.00 0.00% 5,033.66
0243400034 SEÑALES DE INFORMACION und 50.00 16.95 847.50 50.00 847.50 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 847.50
0243570052 LEÑA CGA 141.46 16.95 2,397.75 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.72 29.15 1.22% 55.72 944.45 39.39% 57.48 974.28 40.63% 16.13 273.40 11.40% 10.41 176.46 7.36% 2,397.75
0244000016 MADERA TORNILLO CEPILLADA p2 70.00 4.75 332.50 70.00 332.50 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 332.50
0244010000 ESTACA DE MADERA p2 429.73 3.81 1,637.26 383.42 1,460.83 89.22% 46.31 176.44 10.78% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,637.26
0245010001 MADERA TORNILLO INC.CORTE P/ENCOFRADO p2 25,997.29 4.75 123,487.12 0.00 0.00 0.00% 0.00 0.00 0.00% 728.55 3,460.61 2.80% 1,273.44 6,048.84 4.90% 3,818.08 18,135.88 14.69% 7,976.09 37,886.43 30.68% 7,336.28 34,847.33 28.22% 3,776.66 17,939.13 14.53% 1,088.19 5,168.89 4.19% 123,487.12
0254110090 PINTURA ESMALTE gln 10.74 38.14 409.75 3.86 147.22 35.93% 3.88 147.98 36.12% 3.00 114.54 27.95% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 409.75
0254440098 DISOLVENTE - THINER gln 10.10 12.71 128.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.10 128.41 100.00% 128.41
0254450003 PINTURA TRANSITO gln 222.27 42.37 9,417.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 222.27 9,417.50 100.00% 9,417.50

COSTO DIRECTO 2,227,379.41 173,416.53 7.79% 214,780.13 9.64% 335,189.62 15.05% 221,330.72 9.94% 249,561.05 11.20% 412,808.17 18.53% 335,901.40 15.08% 170,878.74 7.67% 113,513.03 5.10% 2,227,379.41
CALENDARIO DE REQUERIMIENTO DE MAQUINARIA Y EQUIPO

FECHA: 2016
CREACIÓN DE PISTAS Y VEREDAS EN EL CENTRO POBLADO DE AUTAMA, DISTRITO DE SANTIAGO DE PAUCARAY, PROVINCIA DE SUCRE, REGIÓN
PROYECTO TIEMPO DE EJECUCIÓN: 9 MESES
AYACUCHO.
LUGAR: CP AUTAMA

REQUERIMIENTO - MES 01 REQUERIMIENTO - MES 02 REQUERIMIENTO - MES 03 REQUERIMIENTO - MES 04 REQUERIMIENTO - MES 05 REQUERIMIENTO - MES 06 REQUERIMIENTO - MES 07 REQUERIMIENTO - MES 08 REQUERIMIENTO - MES 09
Costo COSTO
ITEM DESCRIPCION UND CANTIDAD Parcial (S/.)
Unitario TOTAL
Cantidad Presup. % Cantidad Presup. % Cantidad Presup. % Cantidad Presup. % Cantidad Presup. % Cantidad Presup. % Cantidad Presup. % Cantidad Presup. % Cantidad Presup. %

0337010100 BOTAS DE JEBE PAR 45.00 21.19 953.55 45.00 953.55 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 953.55
0337600001 GUANTES DE CUERO PAR 90.00 12.71 1,143.90 90.00 1,143.90 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,143.90
0337800013 BOTIQUIN DE PRIMEROS AUXILIOS und 1.00 211.86 211.86 1.00 211.86 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 211.86
0337800015 CASCOS DE PROTECCION und 45.00 16.95 762.75 45.00 762.75 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 762.75
0337800016 CHALECOS und 45.00 38.14 1,716.30 45.00 1,716.30 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,716.30
0337990100 LENTES DE PROTECCION und 45.00 12.71 571.95 45.00 571.95 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 571.95
0348010011 MEZCLADORA DE CONCRETO DE 9 -11P3 hm 2,123.51 6.36 13,505.54 0.00 0.00 0.00% 0.00 0.00 0.00% 70.07 445.61 3.30% 123.96 788.39 5.84% 204.81 1,302.56 9.64% 447.34 2,845.08 21.07% 436.56 2,776.52 20.56% 495.85 3,153.58 23.35% 344.94 2,193.79 16.24% 13,505.54
0348110004 VOLQUETE DE 10 M3 hm 747.67 101.69 76,030.67 390.25 39,684.52 52.20% 252.97 25,724.52 33.83% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.75 788.10 1.04% 0.00 0.00 0.00% 90.90 9,243.62 12.16% 5.80 589.91 0.78% 76,030.67
0348120002 CAMION CISTERNA 4X2 (AGUA) 2,000 GAL. hm 112.96 110.17 12,444.58 0.00 0.00 0.00% 74.00 8,152.58 65.51% 38.96 4,292.00 34.49% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12,444.58
0349030001 COMPACTADOR VIBR. TIPO PLANCHA 4 HP hm 709.77 6.36 4,514.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 435.80 2,771.69 61.40% 273.97 1,742.44 38.60% 0.00 0.00 0.00% 0.00 0.00 0.00% 4,514.13
0349030007 RODILLO LISO VIBR AUTOP 101-135HP 10-12T hm 280.07 186.45 52,219.76 0.00 0.00 0.00% 176.29 32,869.27 62.94% 103.78 19,350.49 37.06% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 52,219.76
0349040010 CARGADOR S/LLANTAS 125-155 HP 3 YD3. hm 207.39 211.86 43,938.07 97.56 20,669.06 47.04% 63.24 13,398.03 30.49% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.14 2,995.70 6.82% 8.26 1,749.96 3.98% 22.73 4,815.58 10.96% 1.46 309.74 0.70% 43,938.07
0349040033 TRACTOR DE ORUGAS DE 140-160 HP hm 309.44 313.56 97,027.13 205.29 64,370.73 66.34% 104.15 32,656.40 33.66% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 97,027.13
0349070004 VIBRADOR DE CONCRETO 4 HP 2.40" hm 1,650.49 6.36 10,497.13 0.00 0.00 0.00% 0.00 0.00 0.00% 159.25 1,012.83 9.65% 278.35 1,770.31 16.86% 294.55 1,873.34 17.85% 392.10 2,493.76 23.76% 297.91 1,894.71 18.05% 145.18 923.35 8.80% 83.15 528.84 5.04% 10,497.13
0349090003 MOTONIVELADORA DE 130-135 HP hm 280.07 313.56 87,819.94 0.00 0.00 0.00% 176.29 55,277.49 62.94% 103.78 32,542.45 37.06% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 87,819.94
0349180010 GRUA HIDRAULICA AUTOP. 127HP 18TON-9M. hm 10.80 105.93 1,144.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.40 148.30 12.96% 9.40 995.74 87.04% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,144.04
0349190001 TEODOLITO hm 803.59 6.36 5,110.84 411.29 2,615.80 51.18% 231.94 1,475.14 28.86% 160.36 1,019.90 19.96% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5,110.84
0349890001 NIVEL TOPOGRAFICO hm 803.59 4.24 3,407.23 411.29 1,743.87 51.18% 231.94 983.43 28.86% 160.36 679.93 19.96% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3,407.23
0349900062 MAQUINA PARA PINTAR MARCAS EN PAVIMENTO hm 201.42 13.56 2,731.25 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 201.42 2,731.25 100.00% 2,731.25
HERRAMIENTAS MANUALES Glb 1.00 28,422.03 28,422.03 1.00 28,422.03 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 28,422.03

COSTO DIRECTO 444,172.65 162,866.33 36.67% 170,536.85 38.39% 59,343.21 13.36% 2,558.70 0.58% 3,324.20 0.75% 12,890.06 2.90% 8,163.63 1.84% 18,136.12 4.08% 6,353.54 1.43% 444,172.66