CALENDARIO VALORIZADO DE OBRA

P. UNIT. PARCIAL MES 01 MES 02


ITEM DESCRIPCION UNIDAD METRADO
(S/.) (S/.) PARCIAL PARCIAL
CAMINO VECINAL OMIA 2,142,152.67 340,258.12 1,077,997.49
1 INFRAESTRUCTURA VIAL 2,098,349.13 332,058.12 1,073,755.03
1.1 OBRAS PROVISIONALES 14,401.48 14,401.48
1.1.01 CARTEL DE OBRA DE 3.60 x 2.40M u 1.00 1,574.48 1,574.48 1,574.48
1.1.02 CAMPAMENTO PROVICIONAL DE OBRA m2 100.00 128.27 12,827.00 12,827.00
1.2 OBRAS PRELIMINARES 68,223.89 68,223.89
1.2.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO glb 1.00 30,000.00 30,000.00 30,000.00
1.2.02 TRAZO Y REPLANTEO km 24.42 1,565.27 38,223.89 38,223.89
1.3 MOVIMIENTO DE TIERRAS 633,201.79 220,807.75 401,657.24
1.3.01 DESBROCE Y LIMPIEZA DE TERRENO ha 2.56 1,650.37 4,224.95 4,224.95
1.3.02 CORTE DE MATERIAL SUELTO C/MAQUINARIA m3 67,136.26 6.23 418,258.90 216,582.80 201,676.10
1.3.03 CORTE EN ROCA SUELTA (PERFORACION, DISPARO Y DESQUINCHE O LIMPIEZA) m3 10,236.32 15.22 155,796.79 155,796.79
1.3.04 CONFORMACION DE TERRAPLEN (RELLENO CON MATERIAL PROPIO) m3 6,228.73 3.98 24,790.35 24,790.35
1.3.05 PERFILADO Y COMPACTADO EN ZONA DE CORTE m2 25,320.00 1.19 30,130.80 19,394.00
1.4 PAVIMENTOS 697,764.00 553,070.27
1.4.01 ENROCADO E=0.20M 461,619.57 414,588.16
1.4.01.01 EXTRACCION Y APILAMIENTO DE ROCA m3 5,112.19 13.49 68,963.44 57,445.59
1.4.01.02 EXTENDIDO Y COMPACTADO DE ROCA m2 19,662.30 19.97 392,656.13 357,142.57
1.4.02 ENROCADO E=1M 46,268.89 9,206.93
1.4.02.01 EXTRACCION Y APILAMIENTO DE ROCA m3 682.50 13.49 9,206.93 9,206.93
1.4.02.02 EXTENDIDO Y COMPACTADO DE ROCA m2 542.00 68.38 37,061.96
1.4.03 AFIRMADO 189,875.54 129,275.18
1.4.03.01 MATERIAL GRANULAR DE CANTERA m3 5,867.60 11.68 68,533.57 59,949.04
1.4.03.02 AFIRMADO GRANULAR m3 4,694.08 25.85 121,341.97 69,326.14
1.5 DRENAJE, OBRAS DE ARTE Y SEALIZACION 684,757.97 28,625.00 119,027.52
1.5.01 CUNETAS 11,381.00 11,381.00
1.5.01.01 EXCAVACION DE CUNETAS A MAQUINA m 7,660.00 0.87 6,664.20 6,664.20
1.5.01.02 CUNETAS SIN REVESTIR EN ROCA SUELTA m 1,340.00 3.52 4,716.80 4,716.80
1.5.02 PONTON TIPO LOSA (L=8.00M) 169,774.22 20,465.02
1.5.02.01 TRABAJOS PRELIMINARES 1,010.82 943.47
1.5.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 130.26 2.45 319.14 319.14
1.5.02.01.02 TRAZO Y REPLANTEO DE ESTRUCTURAS m2 130.26 5.31 691.68 624.33
1.5.02.02 MOVIMIENTO DE TIERRAS 17,234.37 17,234.37
1.5.02.02.01 EXCAVACION MASIVA CON EQUIPO PESADO EN TERRENO SECO CON BOLONERIA m3 120.81 23.30 2,814.87 2,814.87
1.5.02.02.02 EXCAVACION MASIVA CON EQUIPO PESADO EN TERRENO CON BOLONERIA BAJO AGUA m3 134.03 30.54 4,093.28 4,093.28
1.5.02.02.03 CONFORMACION DE TERRAPLENES CON MATERIAL DE PRESTAMO EN ACCESO DE PUENTE m3 259.91 39.73 10,326.22 10,326.22
1.5.02.03 OBRAS DE CONCRETO SIMPLE 91,054.14 2,287.18
1.5.02.03.01 ENCOFRADO Y DESENCOFRADO BAJO AGUA PARA CIMENTACION m2 52.60 53.56 2,817.26 2,287.18
1.5.02.03.02 CONCRETO f'c=140 kg/cm2 + 30% PM PARA CIMENTACION m3 71.76 325.51 23,358.60
1.5.02.03.03 ENCOFRADO Y DESENCOFRADO CARAVISTA EN MURO m2 223.60 41.86 9,359.90
1.5.02.03.04 CONCRETO f'c=175 kg/cm2 + 30%PG PARA MUROS m3 148.68 348.51 51,816.47
1.5.02.03.05 CONCRETO f'c= 210 kg/cm2 PARA LOSA DE APROXIMACION m3 8.28 447.09 3,701.91
1.5.02.04 OBRAS DE CONCRETO ARMADO 27,230.74
1.5.02.04.01 CONCRETO f'c= 210 kg/cm2 PARA LOSA DE APROXIMACION m3 25.20 475.88 11,992.18
1.5.02.04.02 ENCOFRADO Y DESENCOFRADO CARAVISTA EN LOSA m2 60.80 78.10 4,748.48
1.5.02.04.03 ACERO DE REFUERZO FY = 4,200 KG/CM2 kg 1,833.93 5.72 10,490.08
1.5.02.05 VARIOS 33,244.15
1.5.02.05.01 FALSO PUENTE DE MADERA m2 44.00 293.22 12,901.68
1.5.02.05.02 APOYO DE NEOPRENE SHORE 70. DE 0.50 X 0.22 X 0.05 m u 4.00 2,460.34 9,841.36
1.5.02.05.03 JUNTAS ASFALTICAS m 12.10 7.30 88.33
1.5.02.05.04 TUBERIA PVC SAL 2" m 2.60 30.07 78.18
1.5.02.05.05 BARANDAS METALICAS PARA PUENTES m 20.00 500.00 10,000.00
1.5.02.05.06 PINTURA EN BARANDAS METALICAS m 20.00 16.73 334.60
1.5.03 ALCANTARILLAS TMC D=36" 212,007.57 12,725.80
1.5.03.01 TRAZO Y REPLANTEO m2 905.97 1.38 1,250.24
1.5.03.02 EXCAVACION DE ESTRUCTURAS m3 1,734.46 2.26 3,919.88
1.5.03.03 ENCOFRADO Y DESENCOFRADO m2 531.39 49.95 26,542.93 12,725.80
1.5.03.04 CAMA DE APOYO PARA ALCANTARILLA h=0.15 m m3 11.41 141.73 1,617.14
1.5.03.05 TUBERIA METALICA CIRCULAR TMC m 87.60 545.54 47,789.30

1.5.03.06 SOLADOS CONCRETO f'c=100 kg/cm2 m2 126.00 51.24 6,456.24

1.5.03.07 CONCRETO CICLOPEO f'c=140 kg/cm2 PARA EMBOQUILLADO. m3 42.66 389.00 16,594.74

1.5.03.08 Concreto f'c = 140 kg/cm2 m3 61.26 461.12 28,248.21

1.5.03.09 CONCRETO f'c=175 kg/cm2 m3 124.46 505.72 62,941.91

1.5.03.10 ACERO DE REFUERZO FY = 4,200 KG/CM2 kg 2,667.01 5.72 15,255.30

1.5.03.11 RELLENO COMPACTADO MANUAL MATERIAL PROPIO m3 53.26 26.13 1,391.68


1.5.04 SEALIZACION 8,366.58

1.5.04.01 SEALES INFORMATIVAS u 4.00 336.22 1,344.88

1.5.04.02 SEALES PREVENTIVAS u 20.00 304.86 6,097.20

1.5.04.03 HITOS KILOMETRICOS u 5.00 184.90 924.50

1.5.05 TRANSPORTE 277,703.60 23,100.00 74,455.70


1.5.05.01 ELIMINACION DE MATERIAL EXCEDENTE DE CORTE DM= 1KM m3 14,396.20 4.10 59,024.42 59,024.42
1.5.05.02 TRANSPORTE DE MATERIAL DE AFIRMADO m3 4,694.08 15.20 71,350.02 4,450.09
1.5.05.03 TRANSPORTE DE MATERIAL ROCOSO PARA ENRROCADO m3 5,794.69 18.99 110,041.16 10,981.19
1.5.05.04 ELIMINACION DE MATERIAL EXCEDENTE DE ALCANTARILLAS Y PONTON (30.00m3 1,159.15 12.24 14,188.00

1.5.05.05 FLETE TERRESTRE glb 1.00 23,100.00 23,100.00 23,100.00


1.5.06 RECUAPERACION DE CERCOS 5,525.00 5,525.00
1.5.06.01 REPOSICION DE CERCO PERIMETRICO - ALAMBRE DE PUA glb 85.00 65.00 5,525.00 5,525.00
2 IMPACTO AMBIENTAL 35,603.54 4,242.46
2.1 REVEGETACION ha 1.28 8,503.91 10,885.00

2.2 READECUACION AMBIENTAL DE CANTERAS m2 6,550.00 1.17 7,663.50

2.3 READECUACION AMBIENTAL DEL PATIO DE MAQUINAS m2 3,500.00 2.25 7,875.00

2.4 SEALES AMBIENTAL u 2.00 343.14 686.28

2.5 ACONDICIONAMIENTO DE DEPOSITO DE MATERIAL EXCEDENTE m3 14,396.20 0.59 8,493.76 4,242.46


3 CAPACITACION 8,200.00 8,200.00
3.1 CAPACITACION DEL PROYECTO glb 1.00 6,200.00 6,200.00 6,200.00
3.2 CAPACITACION EN EDUCACION AMBIENTAL glb 1.00 2,000.00 2,000.00 2,000.00

COSTO DIRECTO (CD) 2,142,152.67 340,258.12 1,077,997.49


GASTOS GENERALES (GG) 10% 214215.267 34025.812 107799.749
UTILIDAD (UTI) 5% 107107.6335 17012.906 53899.8745
:::::::::::::::::::
SUB TOTAL (ST) 2,463,475.57 391,296.84 1,239,697.11
IMPUESTO GENERAL ALA VENTA (IGV) 18% 443,425.60 70,433.43 223,145.48

SUPERVISION (SUP) 6% 128529.1602 20415.4872 64679.8494


EXPEDIENTE TECNICO (ET) 3% 64264.5801 10207.7436 32339.9247
:::::::::::::::::::
TOTAL PERUPUESTO (PT) 3099694.91 492353.50 1559862.37

PORCENTAJE DE AVANCE DE OBRA MENSUAL 15.88% 50.32%


PORCENTAJE DE AVANCE DE OBRA ACUMULADO 15.88% 66.21%
MES 03
PARCIAL
723,897.07
692,535.99

10,736.80

10,736.80
144,693.74
47,031.41
11,517.85
35,513.56
37,061.96

37,061.96
60,600.37
8,584.54
52,015.83
537,105.45

149,309.20
67.35
67.35

88,766.96
530.08
23,358.60
9,359.90
51,816.47
3,701.91
27,230.74
11,992.18
4,748.48
10,490.08
33,244.15
12,901.68
9,841.36
88.33
78.18
10,000.00
334.60
199,281.77
1,250.24
3,919.88
13,817.13
1,617.14
47,789.30
6,456.24
16,594.74
28,248.21
62,941.91
15,255.30
1,391.68
8,366.58
1,344.88
6,097.20
924.50
180,147.90

66,899.93
99,059.97
14,188.00

31,361.08
10,885.00
7,663.50
7,875.00
686.28
4,251.30

723,897.07
72389.707
36194.8535

832,481.63
149,846.69

43433.8242
21716.9121
1047479.06

33.79%
100.00%