LISTADO D

PROYECTO

AMPLIACIN MALL AVENTURA SANTA ANITA

N ESPECIALIDAD

ESTRUCTURAS

ARQUITECTURA
INSTALACIONES SANITARIAS
INSTALACIONES MECANICAS
INSTALACIONES ELECTRICAS
LISTADO DE LOS PLANOS ENVIADO
FECHA DE REVISIN

17.10.17

UBICACIN PLANO

EVACUACION EJEC
ESTRUCTURA PRAXIS E
EST GAQC
170928 EST GCAQ EJECUTIVO
BLOQUE 1 ASA M
ASA M
BLOQUE 2
ASA M
ASA M
ASA M
ASA M

BLOQUE 3 Y GENERALES
ASA M
ASA M
ASA M

ASA M
ASA M
ASA M
ASA M
ASA M
ASA M
ASA M

ARQUITECTURA EJE
170928 ARQUITECTURA EJECUTIVO
SERIE 1000 ASA L
SERIE 1200
SERIE 1300
SERIE 1400
SERIE 1500
ASA L
ASA L
ASA L
ASA L
ASA L
ASA L
ASA L
ASA L
SERIE 1600
SERIE 1700
SERIE 1800
SERIE 1900
SERIE 2000
ASA L
ASA L
ASA L
ASA L
ASA L

SERIE 2200
SERIE 2300

IISS EJECUTIV
170928 IISS EJECUTIVO
AGUA FA ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
DESAGE Y VENTILACIN
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ACI GABINETES
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ACI ROCIADORES
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P

IIMM EJECUTIV
170928 IIMM EJECUTIVO
AIRE ACONDICIONADO ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
VENTILACION
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
IIEE EJECUTIV
170928 IIEE EJECUTIVO
ALUMBRADO ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
COMUNICACIONES
CCTV ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P

MEGAFONIA ASA P
ASA P
ASA P
ASA P
SISTEMA CONTRAINCENDIO ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P

DATA ASA P
ASA P
ASA P
ASA P
ASA P

TOMACORRIENTES ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P

ALIMENTADORES BT ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P

DIAGRAMA DE MONTANTES
ASA P
UNIFILARES ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
SUBESTACIONES
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P
ASA P

DETALLES
PLANOS ENVIADOS EN LAS ENTREGAS 1, 2, 3 Y 4

PLANO

EVACUACION EJECUTIVO
ESTRUCTURA PRAXIS EJECUTIVO
EST GAQC

E1-1
E1-31

E2-30
E2-31
E2-32
E2-33

E3-25
E3-26
E3-27

EG-9/107
EG-10/107
EG-11/107
EG-12/107
EG-13/107
EG-14
EG-15

ARQUITECTURA EJECUTIVO

1001
1500
1501
1502
1503
1504
1505
1506
1507

2001
2002
2003
2004
2005

IISS EJECUTIVO

IS-01
IS-02
IS-03
IS-04
IS-05
IS-06
IS-07
IS-08
IS-09
IS-10
IS-11
IS-12
IS-13
IS-14
IS-15
IS-16
IS-17
IS-18
IS-19
IS-19'
IS-20
IS21
IS22
IS23
IS24

IS25
IS26
IS27
IS28
IS29
IS30
IS31

IS32
IS33
IS34
IS35
IS36
IS37
IS38
IS39
IS40

IIMM EJECUTIVO

AA-01
AA-02
AA-03
AA-04
AA-05
AA-06
AA-07

IM-01
IM-02
IM-03
IM-04
IM-05
IM-06
IM-07
IM-08
IM-09
IIEE EJECUTIVO

AL-01
AL-02
AL-03
AL-04
AL-05
AL-06
AL-07
AL-08
AL-09

01
02
03
04
05
06
07
08
09

01
02
03
04
01
02
03
04
05
06
07
08
09

01
02
03
04
05

TOM-01
TOM-02
TOM-03
TOM-04
TOM-05
TOM-06
TOM-07
TOM-08
TOM-09

ALM-01
ALM-02
ALM-03
ALM-04
ALM-05
ALM-06
ALM-07
ALM-08
ALM-09

DM-01
UNI -01
UNI -02
UNI -03
UNI -04
UNI -05
UNI -06
UNI -07

CJ-01
MT-01
MT-02
MT-03
MT-04
MT-05
MT-06
MT-07
MT-08
MT-09
MT-10
MT-11
MT-12
MT-13

PLANO DE DETALLES

PLANOS ADICIONADOS EL 03.10.17


PLANOS ADICIONADOS EL 12.10.17
PLANOS ADICIONADOS EL 17.10.17
EN LAS ENTREGAS 1, 2, 3 Y 4

DETALLE

IVO
CUTIVO

PLANTA DE CIMENTACION
ELEVACION DE TIJERALES (N+16.55)

ELEVACION DE TIJERALES (I) (N+16.55) - BLOQUE 2


ELEVACION DE TIJERALES (II) (N+16.55) - BLOQUE 2
TECHO METALICO DE CINES + VIGAS
ELEVACION DE TIJERALES CINES

ELEVACION DE TIJERALES (I) - BLOQUE 3


ELEVACION DE TIJERALES (II) - BLOQUE 3
ELEVACION DE TIJERALES (III) - BLOQUE 3

ESCALERAS (I) 1@ 6 Y 21
ESCALERAS (II) 7, 8, 9
ESCALERAS (III) 15, 16
ESCALERAS (IV) 17, 19, 20
ESCALERAS(V) 22-22', 23, 24
LOSA DE PISO
DETALLES GENERALES DE CAJAS Y CANALIZ.

TIVO

PLANTA DISTRIBUCION NIVEL M-2 -15.30


DETALLE DE ESCALERA METALICA E1
DETALLE DE ESCALERA METALICA E2
DETALLE DE ESCALERA METALICA E3
DETALLE DE ESCALERA METALICA E4
DETALLE DE ESCALERA METALICA E5
DETALLE DE ESCALERA METALICA E6
DETALLE DE ESCALERA METALICA E21
DETALLES TIPICOS DE ESCALERAS

DETALLE CORTE DE MALL


DETALLE TIPICO CENEFA Y BARANDA
DETALLE TIPICOS DE FRENTINES Y REVESTIMIENTO COLUMNAS
DETALLE TIPICOS DE COLUMNAS
DETALLE TIPICO DE CUBIERTAS

SOTANO 3 N-15.30
SOTANO 2 N-9.30
SOTANO 1 N-6.15
NIVEL 1 +- 0.00
NIVEL 2 + 5.50
NIVEL 3 +11.00
NIVEL 4 +16.60
DETALLES SSHH-1
DETALLES SSHH-2
CISTERNA PLANTA Y CORTE
CISTERNA PLANTA Y CORTE
DETALLES GENERALES AGUA
SOTANO 3 -15.30
SOTANO 2 -9.30
SOTANO 1 -6.15
NIVEL 1 +- 0.00
NIVEL 2 + 5.50
NIVEL 3 +11.00
NIVEL 4 +16.60
DETALLES SSHH-1 DESAGUE Y VENTIL.
DETALLES SSHH-2 DESAGUE Y VENTIL.
DETALLES SSHH-1 VENTILACION
DETALLES SSHH-2 VENTILACION
TRAMPA DE GRASAS CAMARA DE BOMBEO DE DESAGUE
DETALLES GENERALES DESAGUE

SOTANO 3 GABINETES CONTRA INCENDIO -15.30


NIVEL -12.30 GABINETES CONTRA INCENDIO -12.30
SOTANO 2 GABINETES CONTRA INCENDIO -9.30
SOTANO 1 GABINETES CONTRA INCENDIO -6.15
NIVEL 1 GABINETES CONTRA INCENDIO +-0.00
NIVEL 2 GABINETES CONTRA INCENDIO +5.50
NIVEL 3 GABINETES CONTRA INCENDIO +11.00

SOTANO 3 -15.30
N -12.30
SOTANO 2 -9.30
SOTANO 1 -6.15
NIVEL 1 +- 0.00
NIVEL 2 + 5.50
NIVEL 3 11.00
DETALLES GENERALES A.C.I.
DETALLES GENERALES A.C.I.

AIRE ACONDICIONADO NIVEL SOTANO 2 -15.30


AIRE ACONDICIONADO NIVEL SOTANO 1 -9.30
AIRE ACONDICIONADO NIVEL M0 +-6.15
AIRE ACONDICIONADO NIVEL M1 +- 0.00
AIRE ACONDICIONADO NIVEL M2 + 5.50
AIRE ACONDICIONADO NIVEL M3 + 11.00
AIRE ACONDICIONADO NIVEL M4 + 16.50

INSTALACIONES MECNICAS NIVEL SOTANO 2: -15.30


INSTALACIONES MECNICAS MEZANINE: -12.30
INSTALACIONES MECNICAS NIVEL SOTANO 1: -9.30
INSTALACIONES MECNICAS NIVEL M0: -6.15
INSTALACIONES MECNICAS MEZANINE -3.15
INSTALACIONES MECNICAS NIVEL M1: +-0.00
INSTALACIONES MECNICAS NIVEL M2: +5.50
INSTALACIONES MECNICAS NIVEL M3: +11.00
INSTALACIONES MECNICAS NIVEL M4: +16.50

ALUMBRADO NIVEL SOTANO 2: -15.30


ALUMBRADO MEZANINE: -12.30
ALUMBRADO NIVEL SOTANO 1: -9.30
ALUMBRADO NIVEL M0: -6.15
ALUMBRADO MEZANINE: -3.15
ALUMBRADO NIVEL M1: +-0.00
ALUMBRADO NIVEL M2: +5.50
ALUMBRADO NIVEL M3: +11.00
ALUMBRADO NIVEL M4: +16.50

ICVD NIVEL SOTANO 2 : -15.30


ICVD MEZANINE : -12.30
ICVD NIVEL SOTANO 1 : -9.30
ICVD NIVEL M0: -6.15
ICVD NIVEL -3.15
ICVD NIVEL M1:+-0.00
ICVD NIVEL M2:+5.50
ICVD NIVEL M3:+11.00
ICVD NIVEL M4:+16.50

MMEG NIVEL M0: -6.15


MMEG NIVEL M1: +-0.00
MMEG NIVEL M2: +5.50
MMEG NIVEL M3: +11.00
DAI NIVEL SOTANO 2: -15.30
DAI MEZANINE: -12.30
DAI NIVEL SOTANO 1: -9.30
DAI NIVEL M0: -6.15
DAI MEZANINE -3.15
DAI NIVEL M1: +-0.00
DAI NIVEL M2: +5.50
DAI NIVEL M3: +11.00
DAI NIVEL M4: +16.50

DATA NIVEL SOTANO 1: -9.30


DATA NIVEL M0: -6.15
DATA NIVEL M1: +-0.00
DATA NIVEL M2: +5.50
DATA NIVEL M3: +11.00

TOMACORRIENTE NIVEL SOTANO 2:-15.30


TOMACORRIENTE MEZANINE: -12.30
TOMACORRIENTE NIVEL SOTANO 1:-9.30
TOMACORRIENTE NIVEL M0:-6.15
TOMACORRIENTE MEZANINE -3.15
TOMACORRIENTE NIVEL M1 :+-0.00
TOMACORRIENTE NIVEL M2 :+5.50
TOMACORRIENTE NIVEL M3:+11.00
TOMACORRIENTE NIVEL M4:+16.50

ALIMENTADORES BT NIVEL SOTANO 3: -15.30


ALIMENTADORES BT MEZANINE: -12.30
ALIMENTADORES BT NIVEL SOTANO 2: -9.30
ALIMENTADORES BT NIVEL M0: -6.15
ALIMENTADORES BT MEZANINE -3.15
ALIMENTADORES BT NIVEL M1:+-0.00
ALIMENTADORES BT NIVEL M2:+5.50
ALIMENTADORES BT NIVEL M3:+11.00
ALIMENTADORES BT NIVEL M4:+16.50

DIAGRAMA DE MONTANTES
DIAGRAMA UNIFILAR
DIAGRAMA UNIFILAR
DIAGRAMA UNIFILAR
DIAGRAMA UNIFILAR
DIAGRAMA UNIFILAR
DIAGRAMA UNIFILAR
DIAGRAMA UNIFILAR

ESQUEMA UNIFILAR DE PRINCIPIO


MEDIA TENSION MONTANTE ELCTRICA EXISTENTE
MEDIA TENSION MONTANTE ELCTRICA PROYECTADA
RECORRIDO ALIMENTADORES NIVEL M1:+-0.00
RECORRIDO ALIMENTADORES NIVEL M0:-6.15
RECORRIDO ALIMENTADORES NIVEL SOTANO 1: -9.30
RECORRIDO ALIMENTADORES NIVEL SOTANO 2: -15.30
MEDIA TENSION CORTES Y DETALLES SUB ESTACIONES A',D,E,F
MEDIA TENSION DETALLES VARIOS
SISTEMA DE PUESTA A TIERRA NIVEL SOTANO 2: -15.30
SISTEMA DE PUESTA A TIERRA NIVEL SOTANO 1: -9.30
SISTEMA DE PUESTA A TIERRA NIVEL M0: -6.15
SISTEMA DE PUESTA A TIERRA DETALLES
ESQUEMA UNIFILAR