Item Descripcin Unid. Cant. Precio Parcial Sub Total

1 SISTEMA DE PUESTA A TIERRA Y PARARRAYOS S/. 143,447.26

1.1 TRABAJOS CIVILES S/. 73,075.28


1.1.1 EXCAVACION TERRENO NORMAL CON MAQUINARIA m 150 S/. 42.09 S/. 6,313.80
1.1.2 EXCAVACION EN TERRENO NORMAL MANUAL m 125 S/. 48.50 S/. 6,062.50
1.1.3 SRV DEMOL COLUM. CONCRETO ARMADO MANUAL m 50 S/. 194.50 S/. 9,725.00
1.1.4 COLOCACION DE CONCRETO CON CEMENTO CONDUCTIVO m 140 S/. 95.36 S/. 13,350.40
1.1.5 RELLENO Y COMPACTACION DE CAMA DE TIERRA CERNIDA MEZCLADA CON BENTONITA SODICA m 150 S/. 55.88 S/. 8,382.00
1.1.6 COLOCACION Y COMPACTACION DE CAMA DE TIERRA NEGRA DE CULTIVO m 125 S/. 86.55 S/. 10,818.75
1.1.7 NIVELACION Y COMPACTACION CON MATERIAL PROPIO m 200 S/. 48.11 S/. 9,622.00
1.1.8 ACARREO DE MATERIAL EXCEDENTE DISTANCIA m 50 S/. 25.50 S/. 1,275.00
1.1.8 ACARREO DE MAUAL DE POSTES m 4 S/. 288.75 S/. 1,155.00
1.1.9 IZAJE E INSTALACION DE POSTE CAC DE 13/300 (INCLUYE APERTURA DE HOYO, EMPEDRADO) und 7 S/. 512.69 S/. 3,588.83
1.1.10 IZAJE E INSTALACION DE POSTE CAC DE 18/300 (INCLUYE APERTURA DE HOYO, EMPEDRADO) und 4 S/. 695.50 S/. 2,782.00
1.2 TRABAJO ELECTROMECANICO S/. 70,371.98
1.2.1 TENDIDO DE CABLES DE PAT (INCLUYE TRASLADO DESDE ALMACENES CALCESUR) S/. 12,978.00
1.2.1.1 INST CABLE DESNUDO 70-120MM2.ENTERRADO m 1200 S/. 10.05 S/. 12,060.00
1.2.1.2 INST CABLE DESNUDO 70-120MM2.AEREO m 150 S/. 2.77 S/. 415.50
1.2.1.2 INST CABLE DESNUDO 35MM2.ENTERRADO m 50 S/. 10.05 S/. 502.50
1.2.2 INSTALACIONES ELECTROMECANICAS (INCLUYE TRASLADO DESDE ALMACENES CALCESUR) S/. 57,393.98
1.2.2.1 INSTALACION D/VARILLAS COOPERWELD 5/8" und 350 S/. 44.87 S/. 15,704.50
1.2.2.2 INST D/CONECTOR CABLE-VARILLA BURNDY (INLCUYE SUMINISTRO) und 70 S/. 14.81 S/. 1,036.70
1.2.2.3 INST D/CONECTOR BRONCE D/VIA 70 MM2 (INCLUYE SUMINISTRO) und 20 S/. 12.67 S/. 253.40
1.2.2.3 INST D/CONECTOR BRONCE D/VIA 120 MM2 (INCLUYE SUMINISTRO) und 20 S/. 27.59 S/. 551.80
1.2.2.4 INSTALACION POSTE TUBO GALVANIZADO 3"x 6 M (INCLUYE SUMINISTRO) und 2 S/. 480.63 S/. 961.26
1.2.2.5 INSTALACIN PARARRAYOS PDCE (INCLUYE GRAPAS DE SUJECION) und 2 S/. 963.21 S/. 1,926.42
1.2.2.6 INSTALACION DE SOLDADURA EXOTERMICA 120 MM2 T/"X" (INCLUYE SUMINISTRO) pto 25 S/. 122.89 S/. 3,072.25
1.2.2.7 INSTALACION DE SOLDADURA EXOTERMICA 120 MM2 T/"T" (INCLUYE SUMINISTRO) pto 20 S/. 122.89 S/. 2,457.80
1.2.2.8 INSTALACION DE SOLDADURA EXOTERMICA 120 MM2 T/"EMPALME" (INCLUYE SUMINISTRO) pto 10 S/. 122.89 S/. 1,228.90
1.2.2.9 INSTALACION DE SOLDADURA EXOTERMICA 70 MM2 T/"X" (INCLUYE SUMINISTRO) pto 85 S/. 101.35 S/. 8,614.75
1.2.2.10 INSTALACION DE SOLDADURA EXOTERMICA 70 MM2 T/"T" (INCLUYE SUMINISTRO) pto 65 S/. 101.35 S/. 6,587.75
1.2.2.11 INSTALACION DE SOLDADURA EXOTERMICA 70 MM2 T/"EMPALME" (INCLUYE SUMINISTRO) pto 35 S/. 101.35 S/. 3,547.25
1.2.2.12 INSTALACION DE SOLDADURA EXOTERMICA 35 MM2 T/"X" (INCLUYE SUMINISTRO) pto 50 S/. 83.66 S/. 4,183.00
1.2.2.13 INSTALACION DE SOLDADURA EXOTERMICA 35 MM2 T/"T" (INCLUYE SUMINISTRO) pto 25 S/. 83.66 S/. 2,091.50
1.2.2.14 INSTALACION DE SOLDADURA EXOTERMICA 35 MM2 T/"EMPALME" (INCLUYE SUMINISTRO) pto 15 S/. 83.66 S/. 1,254.90
1.2.2.15 INSTALACION CAJA PARA REGISTRO A TIERRA. (INCLUYE SUMINISTRO) und 20 S/. 81.72 S/. 1,634.40
1.2.2.16 MONTAJE DE PPT EN CONCRETO und 10 S/. 228.74 S/. 2,287.40
2 INSTALACIONES ELECTRICAS COMPLEMENTARIAS S/. 51,957.32
2.1 REUBICACION DE SUBESTACION MOVIL S/. 30,142.59
2.1.1 SRV. DESCONEX. DE CABLES /DESMONTAJES CABLES, TUBERIAS Y ACOMETIDAS ELECTRICAS EN SUB ESTACION MOVIL SRV 1 S/. 845.17 S/. 845.17
2.1.2 INSTALACIN D/RETENIDA SIMPLE/VERTICAL (INCLUYE APERTURA DE HOYO, RELLENO Y COMPACTACION) und 2 S/. 486.38 S/. 972.76
2.1.3 SRV INST TUBER F.GDO.STAND.ISO I 1 1/2" PARA CONDUCTOR MT Tipo N2SXY DE POSTE A BUZON m 5 S/. 236.93 S/. 1,184.65
2.1.4 TENDIDO DE CABLE 1X25 MM2 N2SXY m 60 S/. 10.99 S/. 659.40
2.1.5 ARMADO TERMINACION P/CABLE N2XSY 25 mm2 und 2 S/. 540.89 S/. 1,081.78
2.1.6 INSTALACION-ARMADO PR3-3,TS-3,PTV-3 (INCLUYE AISLADORES TIPO PIN y RPP, CRUCETA) kit 21 S/. 918.86 S/. 19,296.06
2.1.7 SRV INSTALACION D/SECCIONADOR CUT OUT jgo 1 S/. 285.09 S/. 285.09
2.1.8 SRV DESMON. CABLES 1X35 MM2 (AAAC) km 0.4 S/. 559.51 S/. 223.80
2.1.8 SRV DESMON. CABLES 1X95 MM2 (AAAC) km 0.15 S/. 746.02 S/. 111.90
2.1.9 SRV TENDID/FLECHAD D/CONDU AAAC 35-70mm2 km 1.5 S/. 1,119.02 S/. 1,678.53
2.1.10 CONEXIONADO DE CABLE 1G 70 MM2 (AAAC) und 4 S/. 74.25 S/. 297.00
2.1.11 CONEXIONADO DE CABLE 1G 35 MM2 (AAAC) und 8 S/. 52.69 S/. 421.52
2.1.12 SRV TRASLADO CONTEINER D/SUBESTACION und 1 S/. 736.39 S/. 736.39
2.1.13 SRV MANTTO. TRANSF. D/ POTENCIA 2.3/4.6KV und 1 S/. 1,500.03 S/. 1,500.03
2.1.14 PRUEBAS ELECTRICAS SUB ESTACIN gbl 1 S/. 848.50 S/. 848.50
2.2 SUMINISTRO DE MATERIALES S/. 11,992.77
2.2.1 SUMINIS.ACCESOR./RETENIDA SIMPLE/VERTI und 4 S/. 314.30 S/. 1,257.20
2.2.2 SUMINIS. CRUCETA DE FG X 2.00 MTS. und 1 S/. 278.57 S/. 278.57
2.2.3 SUMINIS. PERNO OJO DE 5/8"X10" AG und 20 S/. 19.00 S/. 380.00
ANEXO N 02 : PROPUESTA ECONMICA
SERVICIO DE INSTALACIONES ELCTRICAS COMPLEMENTARIAS, PUESTA A TIERRA Y PARARRAYOS FASE 2
(CP-E-002-2017-PC-HRC)

PROYECTO : APU LNEA DE CAL DE 1000 TMPD FASE 2


PROPIETARIO : CAL&CEMENTO SUR S.A.
UBICACION : DPTO:PUNO PROV:SAN ROMAN DIST:CARACOTO
FECHA PROYECTO : 9/21/2017

Item Descripcin Unid. Cant. Precio Parcial Sub Total

2.2.4 SUMINISTRO DE CONSUMIBLES ELECTRICOS und 1 S/. 225.00 S/. 225.00


2.2.5 SUMINIS.TERMINAL T/N2XSY - 25mm2 kit 2 S/. 750.00 S/. 1,500.00
2.2.6 SUMINIS. CONECTOR DOBLE VIA AAAC und 8 S/. 18.00 S/. 144.00
2.2.7 SUMINIS. FUSIBLE T/CHICOTE DE 65A und 3 S/. 35.00 S/. 105.00
2.2.8 SUMINIS. D/SECCIONADOR CUT OUT 27KV 100A und 3 S/. 380.00 S/. 1,140.00
2.2.9 FABRICACION DE SOPORTES SEGN TIPICO kg 150 S/. 46.42 S/. 6,963.00
ANEXO N 02 : PROPUESTA ECONMICA
SERVICIO DE INSTALACIONES ELCTRICAS COMPLEMENTARIAS, PUESTA A TIERRA Y PARARRAYOS FASE 2
(CP-E-002-2017-PC-HRC)

PROYECTO : APU LNEA DE CAL DE 1000 TMPD FASE 2


PROPIETARIO : CAL&CEMENTO SUR S.A.
UBICACION : DPTO:PUNO PROV:SAN ROMAN DIST:CARACOTO
FECHA PROYECTO : 9/21/2017

Item Descripcin Unid. Cant. Precio Parcial Sub Total

2.3 TRABAJOS MISCELANEOS S/. 9,821.96


2.3.1 TENDIDO DE CABLE DE 4X6 MM2 m 70 S/. 6.01 S/. 420.70
2.3.2 TENDIDO DE CABLE DE CONTROL DE 5X1.5 MM2 m 70 S/. 10.36 S/. 725.20
2.3.3 SRV INST.TUB CONDUIT RMC FG3/4" m 20 S/. 21.91 S/. 438.20
2.3.4 SRV INST.TUB CONDUIT FLEX.C/FORR PVC3/4" m 5 S/. 19.18 S/. 95.90
2.3.5 SRV INST.TUB CONDUIT RMC FG1" m 20 S/. 26.31 S/. 526.20
2.3.6 SRV INST.TUB CONDUIT FLEX.C/FORR PVC1" m 5 S/. 28.29 S/. 141.45
2.3.7 CONEXIONADO DE CABLE 4G 6 MM2 und 2 S/. 50.34 S/. 100.68
2.3.8 CONEXIONADO DE CABLE 5G 1.5 MM2 und 2 S/. 50.34 S/. 100.68
2.3.9 MONTAJE DE TRANSFORMADOR DE NUCLEO PARTIDO und 7 S/. 131.51 S/. 920.57
2.3.10 TENDIDO DE CABLE DE 4TR#18 AWG m 1500 S/. 2.50 S/. 3,750.00
2.3.11 CONEXIONADO DE CABLE DE 3TR#18 AWG und 7 S/. 50.34 S/. 352.38
2.3.11 Tecnico Electricista I hr 150 S/. 15.00 S/. 2,250.00

Costo Directo S/. 195,404.58


Gastos Generales 45.00% S/. 87,932.06
Utilidad 12% S/. 23,448.55
TOTAL : S/. 306,785.19

[Son: Trescientos Cuarenta y Seis Mil Ciento Cuarenta y Nueve Soles con Sesenta y Nueve Cntimos]