MEMORIA DE METRADO

MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE, DESAGUE Y


PROYECTO PLANTA DE TRATAMIENTO DE LA LOCALIDAD DE CHUPA, DISTRITO DE CHUPA.
PROVINCIA DE AZANGARO - PUNO

01.03 CAMARA DE REUNION (01 UND)


N DE CAMARAS DE REUNION : 1
01.03.01 TRABAJOS PRELIMINARES
01.03.01.01 Limpieza de terreno manual
2.00 * 1.70 = 3.40 m2 * 1 = 3.40 m2
01.03.02 TRAZO Y REPLANTEO DE ESTRUCTURAS
1.80 * 1.30 = 2.34 m2 * 1 = 2.34 m2
01.03.03 REPLANTEO FINAL DE ESTRUCTURAS
1.80 * 1.30 = 2.34 m2 * 1 = 2.34 m2
01.03.02 MOVIMIENTO DE TIERRAS
01.03.02.01 Excavacin Manual
1.800 * 1.300 * 0.500 = 1.170 m3 * 1 = 1.17 m3

01.03.02.02 Refine, nivelacin y compactacin


1.300 * 1.300 = 1.690 m2 * 1 = 1.69 m2
01.03.02.03 Relleno con material propio Seleccionado
1.300 * 0.10 * 0.35 * 2 = 0.091
1.100 * 0.10 * 0.35 * 2 = 0.077
0.168 * 1 = 0.17 m3
01.03.02.04 Eliminacin de material excedente
Excavacin 1.170
Relleno 0.168 = 1.00 * 1.3 = 1.303
1.303 * 1 = 1.30 m3
01.03.03 CONCRETO SIMPLE
01.03.03.01 SOLADO DE CONCRETO f'c=100 kg/cm2, e=4"
Camara 1.300 * 1.300 = 1.690 m2 * 1 = 1.69 m2

01.03.04 CONCRETO ARMADO

0.10 0.10 0.90 0.10 0.10


0.10
0.10 0.10
0.10
0.10 0.90 0.50 0.90
0.30 0.10 1 0.60

0.10
0.10 0.15
0.10

0.10 0.1 0.30

01.03.04.01 CONCRETO F'C=175 KG/CM2 P/LOSA FONDO


Losa fondo Camara 1.300 * 1.300 * 0.15 = 0.254 m3
Muro Camara 1.10 * 0.90 * 0.10 * 2 = 0.198 m3
0.90 * 0.90 * 0.10 * 2 = 0.162 m3
caseta Losa 0.400 * 0.500 * 0.10 = 0.020 m3
caseta muros 0.40 * 0.50 * 0.10 * 2 = 0.040 m3
0.30 * 0.50 * 0.10 * 1 = 0.015 m3
0.689 m3 * 1 = 0.69 m3
01.03.04.02 CONCRETO F'C=210 KG/CM2 LOSA TAPA
Losa caja Hum. 1.10 * 1.10 * 0.10 = 0.121 m3
Tapa metalica 0.60 * 0.60 * 0.10 = 0.036 m3
0.085 m3 * 1 = 0.09 m3
01.03.04.03 Encofrado y desencofrado de Muros
1.10 * 0.90 * 4 = 3.960 m2
0.90 * 0.90 * 4 = 3.240 m2
muro caseta 0.40 * 0.50 * 4 = 0.800 m2
0.30 * 0.50 * 2 = 0.300 m2
8.300 m2 * 1 = 10.16 m2
Encofrado y desencofrado
1.00 * 1.00 = 1.00 m2
1.00 * 0.70 * 0.10 = 0.34 m2
Tapa metalica 1.30 * 1.30 * 0.10 = 0.52 m2
1.86 m2 * 1 =
01.03.04.04 Acero corrugado f'y=4200 kg/cm2 grado 60

LO SA DE FONDO MUROS

2
0.20
0.20
1.10
a 0. 30 m . 1.20

1 3/8 a 0.20m .
1.50 0.80
0.50
3/8 a 0.20m . a 0.20m .
0.70 3
1) 3/8" 1.50 * 6.00 * 1 = 9.00 * 0.58 kg/cm2 = 5.220
3/8" 0.70 * 8.00 * 1 = 5.60 * 0.58 kg/cm2 = 3.248
2) 3/8" 1.30 * 6.00 * 2 = 15.60 * 0.58 kg/cm2 = 9.048
3/8" 1.30 * 3.00 * 2 = 7.80 * 0.58 kg/cm2 = 4.524
3) 3/8" 4.20 * 5.00 * 1 = 21.00 * 0.58 kg/cm2 = 12.180
4) 3/8" 0.45 * 2.00 * 1 = 0.90 * 0.58 kg/cm2 = 0.522 camara seca
3/8" 1.50 * 3.00 * 1 = 4.50 * 0.58 kg/cm2 = 2.610 camara seca
3/8" 0.90 * 3.00 * 1 = 2.70 * 0.58 kg/cm2 = 1.566 camara seca
67.10 m 38.918 * 1 = 38.92 kg
Acero corrugado f'y=4200 kg/cm2 grado 60

0.10 1.20
0.10
1 / 4" 0 . 10 m 0.05 0.05

0.80
DISTRIBUCION DEL ACERO 0.05 0.05

1) 1/4" 0.55 * 8.00 * 1 = 4.40 * 0.28kg/cm2 = 1.232


1) 1/4" 0.10 * 18.00 * 1 = 1.80 * 0.28kg/cm2 = 0.504
2) 1/4" 0.90 * 8.00 * 1 = 7.20 * 0.28kg/cm3 = 2.016
3) 1/4" 1.30 * 1.00 * 2 = 2.60 * 0.28kg/cm4 = 0.728
16.00 4.480 * 1 = 4.48 Kg
Resumen acero (en metros lineales)
3/8" 67.10 * 1 = 67.10 m
1/4" 16.00 * 1 = 16.00 m
01.03.05 REVOQUES, ENLICIDOS Y MOLDURAS
01.03.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE 1:2, e=2.0 cm
Piso 0.90 * 0.90 * 1 = 0.81 m2
M. Lat 0.90 * 0.90 * 2 = 1.62 m2
M. Transv.
0.90 * 0.90 * 2 = 1.62 m2
4.05 m2 * 1 = 4.05 m2
01.03.05.02 TARRAJEO EN EXTERIORES (MORTERO 1:5), E=2cm
Cam. Hum 1.10 * 0.90 * 2 = 1.98 m2
caseta 1.10 * 0.90 * 2 = 1.98 m2
0.40 * 0.50 * 2 = 0.40 m2
0.50 * 0.50 * 1 = 0.25 m2
4.61 m2 * 1 = 4.61 m2
01.03.06 SUMINISTRO Y COLOCACIN DE ACCESORIOS
01.03.06.01 SUMINISTRO Y COLOC. TUBERIAS Y ACCESORIOS * 1 = 1.00 GLB
CAPTACION N 01
Salida 2 1/2"
Canastilla PVC SAP 2 1/2" = 1 Und. * 1 = 1.00 Und.

01.03.06.02 COLOCACION DE ACCESORIOS (VALVULAS) * 1 = 1.00 GLB


Vlvula de compuerta PVC bola 2 1/2" bidireccional 1 Und. * 1 = 1.00 Und.
Adaptador UPR PVC SAP 2 1/2" 2 Und. * 1 = 2.00 Und.
Rebose 2"
Cono de rebose 6"x 3" = 1 Und. * 1 = 1.00 Und.
Codo PVC SAL 3" x 90 = 2 Und. * 1 = 2.00 Und.
Tuberia PVC SAL SP de 3" = 3 ML * 3 = 9.00 ML
01.03.06.03 SUMINISTRO Y COLOCACION DE TAPA METALICA 60 cm x 60cm * 1 = 1.00 und
43.40