FACULTAD DE CONTADURA Y
CIENCIAS ADMINISTRATIVAS
MATERIAL DIDCTICO DE
EJERCICIOS RESUELTOS
DE COSTOS ESTNDAR
SPTIMO SEMESTRE
ELABORADO POR:
DRA. VIRGINIA HERNNDEZ SILVA
EL OBJETIVO PRINCIPAL DE
ESTE MATERIAL DIDCTICO ES
QUE EL ALUMNO APLIQUE
SUS CONOCIMIENTOS
PRCTICOS DE COSTOS
ESTNDAR
MATERIALES
A $ 220.00
MATERIALES
B $ 225.00
MATERIALES
C $ 230.00
MATERIALES
D $ 235.00 $ 910.00
$1,612.00
BANCOS $800,000.00
CLIENTES $ 200,000.00
PROVEEDORES $1,600,000.00
TOTAL $766,900.00
TOTAL $680,900.00
TOTAL -$1,000.00
6. SE APLICAN EN LA PRODUCCION LOS COSTOS
INDIRECTOS
7. LA EMPRESA PRODUCE LA CANTIDAD
DE 1,000 UNIDADES
TOTAL $ 100,000.00
ESTANDAR REAL
UNDS.
CONCEPTO UNIDADES A TERMINS. DIFR. EN UNDS PRECIO REAL DESVIACION
CEDULA #7 1,000
CEDULA #8 144
TOTAL 1,144
DESVIACION -$20,000.00
REAL $2,500.00
ESTANDAR $6,720.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$4,220.00 $68.00 -$ 286,960.00
-$2,000.00 DESVIACION
REAL $2,500.00
ESTANDAR $2,000.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$500.00 $49.00 -$ 24,500.00
REAL 2,500
ESTANDAR 6,720 COSTO ESTDR. DESVIACION
DIFERENCIA - 4,220 $ 49.00 -$ 206,780.00
ESQUEMAS DE MAYOR
$ 95,000.00 (5
$ 100,000.00 (11
$1,288,620.00 $ 1,950,280.00
5) -$ 350.00
$700,000.00 $ - -$ 480,350.00 $ -
$700,000.00 -$ 480,350.00
5) -$ 300.00
-$ 170,300.00 $ -
DRA. VIRGINIA HERNNDEZ SILVA 10
-$ 170,300.00
$ 613,520.00 (1
$ - $ 2,213,520.00
$ 2,213,520.00
$ 131,040.00 (8
-$ 1,100.00 (14
-$ 359,040.00 (15
$680,900.00 $ 680,900.00
DESVIACION DESVIACION
$ 35,280.00 (8
-$ 2,000.00 (18
-$ 24,500.00 (19
-$ 206,780.00 (20
$ 96,000.00 $ 96,000.00
1) $ 766,900.00
$
2,000,000.00 $ - $ 1,966,900.00 $ 680,900.00
$
620,000.00 $ - $ 2,542,000.00 $ 1,612,000.00
$
620,000.00 $ 930,000.00
5) -$ 350.00
-$ 206,350.00 $ -
-$ 206,350.00
$ 48,960.00 (8
-$ 20,000.00 (16
-$286,960.00 (17
DESVIACION DESVIACION
DESVIACION
ESTADO DE RESULTADOS
VENTAS $ 1,400,000.00
COSTO DE LO VENDIDO $ 1,612,000.00
PERDIDA BRUTA -$ 212,000.00
COSTO DE DISTRIBUCION
GASTO DE VENTA $ 40,000.00
GASTO DE ADMON. $ 36,000.00
GASTOS FINANCIEROS $ 24,000.00 $ 100,000.00
PERDIDA DE OPERACIN -$ 312,000.00
COSTO DE DESVIACION
DESVIACION ENTRE C.R. Y C. ESTD. -$ 900,380.00
PROVISION ISR $ 80,000.00
PROVISION PTU $ 22,000.00 -$ 798,380.00
PERDIDA DEL EJERCICIO -$ 486,380.00
CLIENTES $ 620,000.00
PROVEEDORES $ 2,213,520.00
MATERIALES $ 1,041,040.00
MATERIALES A $ 150.00
MATERIALES B $158.00
MATERIALES C $162.00
$1,116.00
BANCOS $ 800,000.00
CLIENTES $200,000.00
PROVEEDORES $1,600,000.00
TOTAL $198,840.00
TOTAL $176,400.00
TOTAL -$1,000.00
6. SE APLICAN EN LA PRODUCCION LOS COSTOS
INDIRECTOS
TOTAL $1,116,000.00
UNIDADES A UN GRADO DE
8. EL INVENTARIO FINAL DE PRODUCION EN PROCESO ES DE 200 AVANCE DEL
TOTAL $198,720.00
TOTAL $ 100,000.00
ESTANDAR REAL
UNIDADES PRECIO PRECIO
CONCEPTO A ESTD. TOTAL REAL TOTAL DESVIACION
$
MATERIAL A 700 $ 54.00 $37,800.00 $150.00 105,000.00 $ 67,200.00
$
MATERIAL B 800 $ 60.00 $48,000.00 $ 158.00 126,400.00 $ 78,400.00
$
MATERIAL C 900 $58.00 $52,200.00 $162.00 145,800.00 $ 93,600.00
$
MATERIAL D 600 $ 64.00 $38,400.00 $ 160.00 96,000.00 $ 57,600.00
$ $
TOTAL 176,400.00 TOTAL 473,200.00 $296,800.00
DIFR. EN
CONCEPTO UNIDADES A UNDS. TERMINS. UNDS PRECIO REAL DESVIACION
TOTAL -$277,760.00
CEDULA #7 1,000
CEDULA #8 192
TOTAL 1,192
DESVIACION $ 22,000.00
REAL $2,200.00
1,160 SUMA
$14,000.00 DESVIACION
REAL $2,200.00
REAL 2,200
$1,160.00 SUMA
SE PIDE:
1) DETERMINACION DE LAS DESVIACIONES ENTRE LOS COSTOS REALES Y LOS COSTOS ESTANDAR
ESQUEMAS DE MAYOR
$ 700,000.00 $ - -$ 480,350.00 $ -
$ 700,000.00 -$ 480,350.00
-$ 170,300.00 $ -
-$ 170,300.00
$ - $ 1,759,072.00
$ 176,400.00 $ 176,400.00
DESVIACION DESVIACION
MAREIALES PRECIO MAREIALES CANTIDAD
DESVIACION DESVIACION
G.I.F. EN PRESUPUESTO G.I.F. EN CAPACIDAD
-$ 206,350.00 $ -
-$ 206,350.00
$ 110,000.00 $ 110,000.00
DESVIACION DESVIACION
DRA. VIRGINIA HERNNDEZ SILVA 27
SUELDOS Y S. PRECIO SUELDOS Y S. CANTIDAD
16) $ 22,000.00 $ 22,000.00 (21 17) -$ 190,400.00 -$ 190,400.00 (21
DESVIACION
G.I.F. EN EFICIENCIA COSTOS INDIRECTOS
20) -$ 195,160.00 -$ 195,160.00 (21 5) $ 96,000.00 $ 96,000.00 (6
ESTADO DE DESVIACIONES
MATERIALES
EN PRECIO $ 296,800.00
EN CANTIDAD -$ 277,760.00 $ 19,040.00
MANO DE OBRA DIRECTA
EN PRECIO $ 22,000.00
EN TIEMPO -$ 190,400.00 -$ 168,400.00
GTOS. IND. DE FABRICACION
EN PRESUPUESTO $ 14,000.00
EN CAPACIDAD -$ 8,200.00
EN EFICIENCIA -$ 195,160.00 -$ 189,360.00
ESTADO DE RESULTADOS
VENTAS $ 700,000.00
COSTO DE LO VENDIDO $ 1,116,000.00
PERDIDA BRUTA -$ 416,000.00
COSTO DE DISTRIBUCION
COSTO DE VENTA $ 40,000.00
COSTO DE ADMON. $ 36,000.00
COSTOS FINANCIEROS $ 24,000.00 $ 100,000.00
PERDIDA DE OPERACIN -$ 516,000.00
COSTO DE DESVIACION
DESVIACION ENTRE C.R. Y C. ESTD. -$ 338,720.00
PROVISION ISR $ 80,000.00
PROVISION PTU $ 22,000.00 -$ 236,720.00
PERDIDA DEL EJERCICIO -$ 752,720.00
MATERIALES A $ 20.00
MATERIALES B $ 22.00
MATERIALES C $ 30.00
MATERIALES D $ 28.00 $ 100.00
BANCOS $ 800,000.00
INV. PROD. EN PROC. $ 1,735,000.00
MAQ. EQUIPO $ 2,000,000.00
INV. MATERIALES $ 1,200,000.00
EQUIPO DE OFICINA $ 700,000.00
DEP. MAQUINARIA Y EQ. -$ 480,000.00
CLIENTES $ 200,000.00
INV. ART. TERMINADOS $ 130,000.00
EQUIPO DE TRANSPORTE $ 980,000.00
DEP. EQU. DE OFICINA -$ 70,000.00
DEUDORES DIVERSOS $ 180,000.00
DEP. EQU. DE TRANSP. -$ 206,000.00
PROVEEDORES $ 600,000.00
ACREEDORES DIVERSOS $ 985,000.00
ACREEDORES HIPRS. $ 3,000,000.00
UTDS. POR APLICAR $ 584,000.00
CAPITAL SOCIAL $ 2,000,000.00
SUMAS IGUALES $ 7,169,000.00 $ 7,169,000.00
UNIDADES
CONCEPTO A PRECIO ESTD. TOTAL
UNIDADES
CONCEPTO A PRECIO ESTD. TOTAL
UNIDADES
9. SE VENDEN 800 A $ 400.00 CADA UNA, DE LAS CUALES EL 70%
ES DE CONTADO Y EL RESTO A CREDITO
COSTO DE
VENTAS $10,000.00
COSTO DE
ADMON. $6,000.00
ESTNDAR REAL
UNIDADES
CONCEPTO A PRECIO ESTD. TOTAL PRECIO REAL TOTAL DESVIACION
TOTAL -$ 86,600.00
CEDULA #7 700
CEDULA #8 920
DRA. VIRGINIA HERNNDEZ SILVA 35
TOTAL 1,620
REAL $ 2,400.00
ESTANDAR $ 4,650.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 2,250.00 $ 20.00 -$ 45,000.00
REAL $ 2,400.00
ESTANDAR $ 2,000.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 400.00 $ 18.00 -$ 7,200.00
REAL 2,400
ESTANDAR 4,650 COSTO ESTDR. DESVIACION
DIFERENCIA - 2,250 $ 18.00 -$ 40,500.00
SE PIDE:
1) DETERMINACION DE LAS DESVIACIONES ENTRE LOS COSTOS REALES Y LOS COSTOS ESTANDAR
2) REGISTRAR LAS OPERACIONES EN ESQUEMAS DE MAYOR
3) ELABORAR EL ESTADO DE COSTO DE PRODUCCION Y EDO. DE COSTO DE LO VENDIDO
4)ELABORAR EL ESTADO DE RESULTADOS
5)ELABORAR EL BALANCE GENERAL
6)ELABORAR EL ESTADO DE DESVIACION
ESQUEMAS DE MAYOR
$ 700,000.00 $ - -$ 481,500.00 $ -
$ 700,000.00 -$ 481,500.00
-$ 72,100.00 $ -
-$ 72,100.00
$ - $ 672,720.00
$ 672,720.00
$ 80,900.00 $ 80,900.00
DESVIACION DESVIACION
MAREIALES PRECIO MAREIALES CANTIDAD
DESVIACION DESVIACION
G.I.F. EN PRESUPUESTO G.I.F. EN CAPACIDAD
-$ 208,400.00 $ -
-$ 208,400.00
$ 60,000.00 $ 60,000.00
DESVIACION DESVIACION
SUELDOS Y S. PRECIO SUELDOS Y S. CANTIDAD
16) $ 12,000.00 $ 12,000.00 (21 17) -$ 45,000.00 -$ 45,000.00 (21
DESVIACION
G.I.F. EN EFICIENCIA COSTOS INDIRECTOS
20) -$ 40,500.00 -$ 40,500.00 (21 5) $ 20,000.00 $ 20,000.00 (6
MATERIALES
EN PRECIO -$ 5,500.00
EN CANTIDAD -$ 86,600.00 -$ 92,100.00
MANO DE OBRA DIRECTA
EN PRECIO $ 12,000.00
EN TIEMPO -$ 45,000.00 -$ 33,000.00
GTOS. IND. DE FABRICACION
EN PRESUPUESTO -$ 62,000.00
EN CAPACIDAD $ 7,200.00
EN EFICIENCIA -$ 40,500.00 -$ 95,300.00
DESVIACION TOTAL -$ 220,400.00
ESTADO DE RESULTADOS
VENTAS $ 320,000.00
COSTO DE LO VENDIDO $ 171,200.00
PERDIDA BRUTA $ 148,800.00
COSTO DE DISTRIBUCION
COSTO DE VENTA $ 171,200.00
COSTO DE ADMON. $ 6,000.00
COSTOS FINANCIEROS $ 4,000.00 $ 181,200.00
PERDIDA DE OPERACIN $ 330,000.00
COSTO DE DESVIACION
DESVIACION ENTRE C.R. Y C. ESTD. -$ 220,400.00
PROVISION ISR $ 60,000.00
PROVISION PTU $ 120,000.00 -$ 40,400.00
PERDIDA DEL EJERCICIO $ 289,600.00
MATERIALES A $ 8.00
MATERIALES B $ 7.00
MATERIALES C $ 9.00
MATERIALES D $ 6.00 $ 30.00
BANCOS $ 2,724,000.00
INV. PROD. EN PROC. $ 1,735,000.00
MAQ. EQUIPO $ 1,300,000.00
INV. MATERIALES $ 150,000.00
EQUIPO DE OFICINA $ 250,000.00
DEP. MAQUINARIA Y EQ. -$ 100,000.00
CLIENTES $ 200,000.00
CUENTAS POR COBRAR $ 326,598.00
INV. ART. TERMINADOS $ 2,000.00
EQUIPO DE TRANSPORTE $ 1,000,000.00
DEP. EQU. DE OFICINA -$ 100,000.00
DEUDORES DIVERSOS $ 200,000.00
DEP. EQU. DE TRANSP. -$ 100,000.00
PROVEEDORES $ 110,000.00
ACREEDORES DIVERSOS $ 200,000.00
ACREEDORES HIPRS. $ 3,000,000.00
CUENTAS POR PAGAR A L.P. $ 2,177,598.00
UTDS. POR APLICAR $ 100,000.00
CAPITAL SOCIAL $ 2,000,000.00
SUMAS IGUALES $ 7,587,598.00 $ 7,587,598.00
ESTANDAR REAL
UNIDADES PRECIO
CONCEPTO A ESTD. TOTAL PRECIO REAL TOTAL DESVIACION
UNIDADES UNDS.
CONCEPTO A TERMINS. DIFR. EN UNDS PRECIO REAL DESVIACION
CEDULA #7 1,800
CEDULA #8 31
TOTAL 1,831
REAL $ 11,000.00
ESTANDAR $ 18,312.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 7,312.00 $ 10.00 -$ 73,120.00
REAL 11,000
ESTANDAR 18,312 COSTO ESTDR. DESVIACION
DIFERENCIA - 7,312 $ 41.00 -$ 299,792.00
SE PIDE:
1) DETERMINACION DE LAS DESVIACIONES ENTRE LOS COSTOS REALES Y LOS COSTOS ESTANDAR
2) REGISTRAR LAS OPERACIONES EN ESQUEMAS DE MAYOR
3) ELABORAR EL ESTADO DE COSTO DE PRODUCCION Y EDO. DE COSTO DE LO VENDIDO
4)ELABORAR EL ESTADO DE RESULTADOS
5)ELABORAR EL BALANCE GENERAL
6)ELABORAR EL ESTADO DE DESVIACION
ESQUEMAS DE MAYOR
$ 250,000.00 $ - -$ 101,750.00 $ -
$ 250,000.00 -$ 101,750.00
-$ 101,500.00 $ -
-$ 101,500.00
$ - $ 116,680.00
$ 116,680.00
$ 11,400.00 $ 11,400.00
DESVIACION DESVIACION
MAREIALES PRECIO MAREIALES CANTIDAD
DESVIACION DESVIACION
G.I.F. EN PRESUPUESTO G.I.F. EN CAPACIDAD
DRA. VIRGINIA HERNNDEZ SILVA 49
18) -$ 16,000.00 -$ 16,000.00 (21 19) -$ 369,000.00 -$ 369,000.00 (21
-$ 101,750.00 $ -
-$ 101,750.00
$ 1,320,000.00 $ 1,320,000.00
DESVIACION DESVIACION
SUELDOS Y S. PRECIO SUELDOS Y S. CANTIDAD
16) $ 1,210,000.00 $ 1,210,000.00 (21 17) -$ 73,120.00 -$ 73,120.00 (21
DESVIACION
G.I.F. EN EFICIENCIA COSTOS INDIRECTOS
20) -$ 299,792.00 -$ 299,792.00 (21 5) $ 66,000.00 $ 66,000.00 (6
ESTADO DE DESVIACIONES
MATERIALES
EN PRECIO -$ 3,650.00
EN CANTIDAD -$ 47,186.00 -$ 50,836.00
MANO DE OBRA DIRECTA
EN PRECIO $ 1,210,000.00
EN TIEMPO -$ 73,120.00 $ 1,136,880.00
GTOS. IND. DE FABRICACION
EN PRESUPUESTO -$ 16,000.00
EN CAPACIDAD $ 369,000.00
EN EFICIENCIA -$ 299,792.00 $ 53,208.00
DESVIACION TOTAL $ 1,139,252.00
ESTADO DE RESULTADOS
VENTAS $ 600,000.00
COSTO DE LO VENDIDO $ 540,000.00
PERDIDA BRUTA $ 60,000.00
COSTO DE DISTRIBUCION
COSTO DE VENTA $ 540,000.00
COSTO DE ADMON. $ 50,000.00
COSTOS FINANCIEROS $ 24,000.00 $ 614,000.00
PERDIDA DE OPERACIN -$ 554,000.00
COSTO DE DESVIACION
DESVIACION ENTRE C.R. Y C. ESTD. $ 1,139,252.00
PROVISION ISR $ 40,000.00
PROVISION PTU $ 15,000.00 $ 1,194,252.00
MATERIALES A $ 22.00
MATERIALES B $ 20.00
MATERIALES C $ 30.00
MATERIALES D $ 28.00
$ 100.00
MANO DE OBRA DIRECTA:
EL PRESUPUESTO DE COSTOS
INDIRECTOS PARA LAS 2,000 HRS ES DE
$ 98,000.00
LA EMPRESA INICIA EL PERIODO DE LOS COSTOS CON LOS
SIGUIENTES SALDOS:
BANCOS $ 800,000.00
INV. PROD. EN PROC. $ 1,735,000.00
MAQ. EQUIPO $ 2,000,000.00
INV.
MATERIALES $ 1,200,000.00
EQUIPO DE OFICINA $ 700,000.00
DEP. MAQUINARIA Y EQ. -$ 480,000.00
CLIENTES $ 200,000.00
INV. ART. TERMINADOS $ 130,000.00
EQUIPO DE TRANSPORTE $ 980,000.00
DEP. EQU. DE OFICINA -$ 70,000.00
DEUDORES DIVERSOS $ 180,000.00
DEP. EQU. DE TRANSP. -$ 206,000.00
PROVEEDORES $ 600,000.00
ACREEDORES HIPRS. $ 3,000,000.00
UTDS. POR APLICAR $ 584,000.00
DRA. VIRGINIA HERNNDEZ SILVA 55
CAPITAL
SOCIAL $ 2,985,000.00
SUMAS
IGUALES $ 7,169,000.00 $ 7,169,000.00
1. SE COMPRAN MATERIALES POR LO
SIGUIENTE:
UNIDADE
CONCEPTO SA PRECIO ESTD. TOTAL
UNIDADE
CONCEPTO SA PRECIO ESTD. TOTAL
2,400 $ - $ - $ 5,000.00
ESTANDAR REAL
PRECIO
CONCEPTO UNIDADES A ESTD. TOTAL PRECIO REAL TOTAL DESVIACION
MATERIAL A 700 $22.00 $ 15,400.00 $ 22.00 $ 15,400.00 $ -
MATERIAL B 800 $20.00 $16,000.00 $ 20.00 $16,000.00 $ -
MATERIAL C 900 $35.00 $31,500.00 $ 30.00 $27,000.00 -$ 4,500.00
MATERIAL D 600 $30.00 $18,000.00 $ 28.00 $16,800.00 -$ 1,200.00
TOTAL $ 80,900.00 TOTAL $75,200.00 -$ 5,700.00
CEDULA #7 1,000
CEDULA #8 92
TOTAL 1,092
REAL $ 2,400.00
ESTANDAR $ 5,425.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 3,025.00 $ 20.00 -$ 60,500.00
REAL $ 2,400.00
ESTANDAR $ 2,000.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 400.00 $ 18.00 -$ 7,200.00
REAL 2,400
ESTANDAR 5,425 COSTO ESTDR. DESVIACION
DIFERENCIA - 3,025 $ 18.00 -$ 54,450.00
SE PIDE:
1) DETERMINACION DE LAS DESVIACIONES ENTRE LOS COSTOS REALES Y LOS COSTOS ESTANDAR
2) REGISTRAR LAS OPERACIONES EN ESQUEMAS DE MAYOR
3) ELABORAR EL ESTADO DE COSTO DE PRODUCCION Y EDO. DE COSTO DE LO VENDIDO
4)ELABORAR EL ESTADO DE RESULTADOS
5)ELABORAR EL BALANCE GENERAL
DRA. VIRGINIA HERNNDEZ SILVA 60
6)ELABORAR EL ESTADO DE DESVIACION
ESQUEMAS DE MAYOR
BANCOS INV. PROD. EN PROC.
A) $ 800,000.00 $ 18,180.00 (1 A) $ 1,735,000.00 ------------------
9) $ 280,000.00 $ - (3 8) $ 25,350.00
$ 14,000.00 (5
$ 20,000.00 (11
$ 1,080,000.00 $ 52,180.00 $ 1,760,350.00 $ -
$ 1,027,820.00 $ 1,760,350.00
$ - $ 672,720.00
$ 672,720.00
DESVIACION DESVIACION
MAREIALES PRECIO MAREIALES CANTIDAD
DESVIACION DESVIACION
G.I.F. EN PRESUPUESTO G.I.F. EN CAPACIDAD
DESVIACION DESVIACION
SUELDOS Y S. PRECIO SUELDOS Y S. CANTIDAD
16) -$ 48,000.00 -$ 48,000.00 (21 17) -$ 60,500.00 -$ 60,500.00 (21
DESVIACION
G.I.F. EN EFICIENCIA COSTOS INDIRECTOS
20) -$ 54,450.00 -$ 54,450.00 (21 5) $ 20,000.00 $ 20,000.00 (6
ESTADO DE DESVIACIONES
MATERIALES
EN PRECIO -$ 5,700.00
EN CANTIDAD -$ 34,000.00 -$ 39,700.00
MANO DE OBRA DIRECTA
EN PRECIO -$ 48,000.00
EN TIEMPO -$ 60,500.00 -$ 108,500.00
GTOS. IND. DE FABRICACION
EN PRESUPUESTO -$ 78,000.00
EN CAPACIDAD $ 7,200.00
EN EFICIENCIA -$ 54,450.00 -$ 125,250.00
DESVIACION TOTAL -$ 273,450.00
ESTADO DE RESULTADOS
VENTAS $ 400,000.00
COSTO DE LO VENDIDO $ 290,000.00
PERDIDA BRUTA $ 110,000.00
COSTO DE DISTRIBUCION
COSTO DE VENTA $ 290,000.00
COSTO DE ADMON. $ 6,000.00
COSTOS FINANCIEROS $ 4,000.00 $ 300,000.00
PERDIDA DE OPERACIN -$ 190,000.00
MATERIALES A $ 220.00
MATERIALES B $ 225.00
MATERIALES C $ 230.00 $ 910.00
MATERIALES D $ 235.00
BANCOS $ 800,000.00
INV. PROD. EN PROC. $ 1,735,000.00
MAQ. EQUIPO $ 2,000,000.00
INV. MATERIALES $ 1,200,000.00
EQUIPO DE OFICINA $ 700,000.00
DEP. MAQUINARIA Y EQ. -$ 480,000.00
CLIENTES $ 200,000.00
INV. ART. TERMINADOS $ 930,000.00
EQUIPO DE TRANSPORTE $ 980,000.00
DEP. EQU. DE OFICINA -$ 170,000.00
DEUDORES DIVERSOS $ 180,000.00
DEP. EQU. DE TRANSP. -$ 206,000.00
PROVEEDORES $ 1,600,000.00
ACREEDORES HIPRS. $ 3,000,000.00
UTDS. POR APLICAR $ 584,000.00
CAPITAL SOCIAL $ 2,685,000.00
SUMAS IGUALES $ 7,869,000.00 $ 7,869,000.00
UNIDADES A UN GRADO DE
8. EL INVENTARIO FINAL DE PRODUCION EN PROCESO ES DE 150 AVANCE DEL
96% EN MATERIALES Y DEL 80% EN M.O.D. Y G.I.F.
TOTAL $ 215,280.00
UNIDADES
9. SE VENDEN 1,000 A $ 1,400.00 CADA UNA, DE LAS CUALES EL 70%
ES DE CONTADO Y EL RESTO A CREDITO
ESTANDAR REAL
PRECIO PRECIO
CONCEPTO UNDS A ESTD. TOTAL REAL TOTAL DESVIACION
UNDS. PRECIO
CONCEPTO UNDS A TERMINS. DIFR. EN UNDS REAL DESVIACION
CEDULA #7 1,000
CEDULA #8 144
TOTAL 1,144
REAL $ 2,500.00
ESTANDAR $ 6,720.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 4,220.00 $ 68.00 -$ 286,960.00
REAL $ 2,500.00
ESTANDAR $ 2,000.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 500.00 $ 49.00 -$ 24,500.00
REAL 2,500
ESTANDAR 6,720 COSTO ESTDR. DESVIACION
DIFERENCIA - 4,220 $ 49.00 -$ 206,780.00
SE PIDE:
1) DETERMINACION DE LAS DESVIACIONES ENTRE LOS COSTOS REALES Y LOS COSTOS
ESTANDAR
2) REGISTRAR LAS OPERACIONES EN ESQUEMAS DE MAYOR
3) ELABORAR EL ESTADO DE COSTO DE PRODUCCION Y EDO. DE COSTO DE LO VENDIDO
4)ELABORAR EL ESTADO DE RESULTADOS
5)ELABORAR EL BALANCE GENERAL
6)ELABORAR EL ESTADO DE DESVIACION
ESQUEMAS DE MAYOR
DESVIACION DESVIACION
MAREIALES PRECIO MAREIALES CANTIDAD
DESVIACION DESVIACION
G.I.F. EN PRESUPUESTO G.I.F. EN CAPACIDAD
DESVIACION DESVIACION
SUELDOS Y S. PRECIO SUELDOS Y S. CANTIDAD
16) -$ 20,000.00 -$ 20,000.00 (21 17) -$ 286,960.00 -$ 286,960.00 (21
DESVIACION
G.I.F. EN EFICIENCIA COSTOS INDIRECTOS
20) -$ 206,780.00 -$ 206,780.00 (21 5) $ 96,000.00 $ 96,000.00 (6
MATERIALES
EN PRECIO -$ 1,100.00
EN CANTIDAD -$ 359,040.00 -$ 360,140.00
MANO DE OBRA DIRECTA
EN PRECIO -$ 20,000.00
EN TIEMPO -$ 286,960.00 -$ 306,960.00
GTOS. IND. DE FABRICACION
EN PRESUPUESTO -$ 2,000.00
EN CAPACIDAD -$ 24,500.00
EN EFICIENCIA -$ 206,780.00 -$ 233,280.00
DESVIACION TOTAL -$ 900,380.00
ESTADO DE RESULTADOS
VENTAS $ 1,400,000.00
COSTO DE DISTRIBUCION
COSTO DE DESVIACION
CLIENTES $ 620,000.00
PROVEEDORES $ 2,213,520.00
MATERIALES A $ 150.00
MATERIALES B $ 158.00
MATERIALES C $ 162.00 $ 630.00
DRA. VIRGINIA HERNNDEZ SILVA 78
MATERIALES D $ 160.00
BANCOS $ 800,000.00
INV. PROD. EN PROC. $ 1,735,000.00
MAQ. EQUIPO $ 2,000,000.00
INV. MATERIALES $ 1,200,000.00
EQUIPO DE OFICINA $ 700,000.00
DEP. MAQUINARIA Y EQ. -$ 480,000.00
CLIENTES $ 200,000.00
INV. ART. TERMINADOS $ 930,000.00
EQUIPO DE TRANSPORTE $ 980,000.00
DEP. EQU. DE OFICINA -$ 170,000.00
DEUDORES DIVERSOS $ 180,000.00
DEP. EQU. DE TRANSP. -$ 206,000.00
PROVEEDORES $ 1,600,000.00
ACREEDORES HIPRS. $ 3,000,000.00
UTDS. POR APLICAR $ 584,000.00
CAPITAL SOCIAL $ 2,685,000.00
SUMAS IGUALES $ 7,869,000.00 $ 7,869,000.00
ESTNDAR REAL
UND
CONCEPTO SA PRECIO ESTD. TOTAL PRECIO REAL TOTAL DESVIACION
CEDULA #7 1,000
CEDULA #8 192
TOTAL 1,192
REAL $ 2,200.00
ESTANDAR $ 6,960.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 4,760.00 $ 40.00 -$ 190,400.00
REAL $ 2,200.00
ESTANDAR $ 2,000.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 200.00 $ 41.00 -$ 8,200.00
REAL 2,200
ESTANDAR 6,960 COSTO ESTDR. DESVIACION
DIFERENCIA - 4,760 $ 41.00 -$ 195,160.00
SE PIDE:
1) DETERMINACION DE LAS DESVIACIONES ENTRE LOS COSTOS REALES Y LOS COSTOS ESTANDAR
2) REGISTRAR LAS OPERACIONES EN ESQUEMAS DE MAYOR
3) ELABORAR EL ESTADO DE COSTO DE PRODUCCION Y EDO. DE COSTO DE LO VENDIDO
4)ELABORAR EL ESTADO DE RESULTADOS
5)ELABORAR EL BALANCE GENERAL
6)ELABORAR EL ESTADO DE DESVIACION
ESQUEMAS DE MAYOR
DESVIACION DESVIACION
MAREIALES PRECIO MAREIALES CANTIDAD
DESVIACION DESVIACION
G.I.F. EN PRESUPUESTO G.I.F. EN CAPACIDAD
DRA. VIRGINIA HERNNDEZ SILVA 84
18) $ 14,000.00 $ 14,000.00 (21 19) -$ 8,200.00 -$ 8,200.00 (21
DESVIACION DESVIACION
SUELDOS Y S. PRECIO SUELDOS Y S. CANTIDAD
16) $ 22,000.00 $ 22,000.00 (21 17) -$ 190,400.00 -$ 190,400.00 (21
DESVIACION
G.I.F. EN EFICIENCIA COSTOS INDIRECTOS
20) -$ 195,160.00 -$ 195,160.00 (21 5) $ 96,000.00 $ 96,000.00 (6
MATERIALES
EN PRECIO $ 296,800.00
EN CANTIDAD -$ 277,760.00 $ 19,040.00
MANO DE OBRA DIRECTA
EN PRECIO $ 22,000.00
EN TIEMPO -$ 190,400.00 -$ 168,400.00
GTOS. IND. DE FABRICACION
EN PRESUPUESTO $ 14,000.00
EN CAPACIDAD $ 8,200.00
EN EFICIENCIA -$ 195,160.00 -$ 172,960.00
DESVIACION TOTAL -$ 322,320.00
ESTADO DE RESULTADOS
VENTAS $ 700,000.00
COSTO DE LO VENDIDO $ 1,116,000.00
PERDIDA BRUTA -$ 416,000.00
COSTO DE DISTRIBUCION
COSTO DE VENTA $ 1,116,000.00
COSTO DE ADMON. $ 36,000.00
COSTOS FINANCIEROS $ 24,000.00 $ 1,176,000.00
PERDIDA DE OPERACIN -$ 1,592,000.00
COSTO DE DESVIACION
DESVIACION ENTRE C.R. Y C. ESTD. -$ 322,320.00
PROVISION ISR $ 80,000.00
PROVISION PTU $ 22,000.00 -$ 220,320.00
PERDIDA DEL EJERCICIO $ 1,371,680.00
MATERIALES A $ 30.00
MATERIALES B $ 34.00
MATERIALES C $ 40.00 $ 140.00
MATERIALES D $ 36.00
BANCOS $ 800,000.00
INV. PROD. EN PROC. $ 1,735,000.00
MAQ. EQUIPO $ 2,000,000.00
INV. MATERIALES $ 1,200,000.00
EQUIPO DE OFICINA $ 700,000.00
DEP. MAQUINARIA Y EQ. -$ 480,000.00
DRA. VIRGINIA HERNNDEZ SILVA 89
CLIENTES $ 200,000.00
INV. ART. TERMINADOS $ 130,000.00
EQUIPO DE TRANSPORTE $ 980,000.00
DEP. EQU. DE OFICINA -$ 70,000.00
DEUDORES DIVERSOS $ 180,000.00
DEP. EQU. DE TRANSP. -$ 206,000.00
PROVEEDORES $ 600,000.00
ACREEDORES HIPRS. $ 3,000,000.00
UTDS. POR APLICAR $ 584,000.00
CAPITAL SOCIAL $ 2,985,000.00
SUMAS IGUALES $ 7,169,000.00 $ 7,169,000.00
UNDS A UN GRADO DE
8. EL INVENTARIO FINAL DE PRODUCION EN PROCESO ES DE 90 AVANCE DEL
94% EN MATERIALES Y DEL 86% EN M.O.D. Y G.I.F.
ESTANDAR REAL
CONCEPTO UNDS A PRECIO ESTD. TOTAL PRECIO REAL TOTAL DESVIACION
MATERIA
L A 700 $ 34.00 $ 23,800.00 $ 30.00 $ 21,000.00 -$ 2,800.00
MATERIA
L B 800 $ 30.00 $ 24,000.00 $ 34.00 $ 27,200.00 $ 3,200.00
MATERIA
L C 900 $ 45.00 $ 40,500.00 $ 40.00 $ 36,000.00 -$ 4,500.00
MATERIA
L D 600 $ 40.00 $ 24,000.00 $ 36.00 $ 21,600.00 -$ 2,400.00
TOTAL $ 112,300.00 TOTAL $ 105,800.00 -$ 6,500.00
CEDULA #7 1,200
CEDULA #8 85
TOTAL 1,285
DESVIACION $ 2,800.00
REAL $ 1,400.00
77 PRODUC. EN PROCESO
1,277 SUMA
$ 3,600.00 DESVIACION
REAL $ 1,400.00
REAL 1,400
$ 1,277.40 SUMA
SE PIDE:
1) DETERMINACION DE LAS DESVIACIONES ENTRE LOS COSTOS REALES Y LOS COSTOS ESTANDAR
ESQUEMAS DE MAYOR
DESVIACION DESVIACION
G.I.F. EN PRESUPUESTO G.I.F. EN CAPACIDAD
1) $ 126,300.00
$ 2,000,000.00 $ 1,214,000.00
9) $ 225,000.00 7) $ 417,600.00
$ 425,000.00 $ 25,600.00
5) -$ 3,200.00
-$ 209,200.00 $ -
-$ 209,200.00
$ 9,288.00 (8
$ 2,800.00 (16
-$ 111,288.00 (17
$ 44,800.00 $ 44,800.00
DESVIACION
G.I.F. EN EFICIENCIA COSTOS INDIRECTOS
20) -$ 81,611.20 -$ 81,611.20 (21 5) $ 30,000.00 $ 30,000.00 (6
ESTADO DE DESVIACIONES
MATERIALES
EN PRECIO -$ 6,500.00
EN CANTIDAD -$ 74,044.00 -$ 80,544.00
MANO DE OBRA DIRECTA
EN PRECIO $ 2,800.00
EN TIEMPO -$ 111,288.00 -$ 108,488.00
GTOS. IND. DE FABRICACION
EN PRESUPUESTO $ 3,600.00
EN CAPACIDAD $ 4,400.00
EN EFICIENCIA -$ 81,611.20 -$ 73,611.20
DESVIACION TOTAL -$ 262,643.20
ESTADO DE RESULTADOS
DRA. VIRGINIA HERNNDEZ SILVA 98
VENTAS $ 750,000.00
COSTO DE LO VENDIDO $ 522,000.00
PERDIDA BRUTA $ 228,000.00
COSTO DE DISTRIBUCION
COSTO DE VENTA $ 522,000.00
COSTO DE ADMON. $ 6,000.00
COSTOS FINANCIEROS $ 4,000.00 $ 532,000.00
PERDIDA DE OPERACIN -$ 304,000.00
COSTO DE DESVIACION
DESVIACION ENTRE C.R. Y C. ESTD. -$ 262,643.20
PROVISION ISR $ 60,000.00
PROVISION PTU $ 12,000.00 -$ 190,643.20
PERDIDA DEL EJERCICIO $ 113,356.80
BANCOS $ 1,300,000.00
INV. PROD. EN PROC. $ 1,100,000.00
MAQ. EQUIPO $ 2,800,000.00
INV. MATERIALES $ 800,000.00
EQUIPO DE OFICINA $ 500,000.00
DEP. MAQUINARIA Y EQ. -$ 480,000.00
CLIENTES $ 250,000.00
INV. ART. TERMINADOS $ 930,000.00
EQUIPO DE TRANSPORTE $ 1,000,000.00
DEP. EQU. DE OFICINA -$ 200,000.00
DEUDORES DIVERSOS $ 1,800,000.00
DEP. EQU. DE TRANSP. -$ 400,000.00
PROVEEDORES $ 800,000.00
DOCUMENTOS POR PAGAR $ 370,000.00
ACREEDORES DIVERSOS $ 260,000.00
ACREEDORES HIPOTECARIOS $ 1,500,000.00
UTDS. POR APLICAR $ 1,300,000.00
RESERVA LEGAL $ 800,000.00
CAPITAL SOCIAL $ 4,370,000.00
SUMAS IGUALES $ 9,400,000.00 $ 9,400,000.00
1. SE COMPRAN MATERIALES POR LO SIGUIENTE:
CEDULA #7 800
CEDULA #8 126
TOTAL 926
REAL $ 2,200.00
ESTANDAR $ 6,442.80 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 4,242.80 $ 50.00 -$ 212,140.00
REAL $ 2,200.00
ESTANDAR $ 2,300.00 COSTO ESTDR. DESVIACION
DIFERENCIA $ 100.00 $ 44.00 $ 4,400.00
REAL 2,200
ESTANDAR 6,443 COSTO ESTDR. DESVIACION
DIFERENCIA - 4,243 $ 44.00 -$ 186,683.20
SE PIDE:
1) DETERMINACION DE LAS DESVIACIONES ENTRE LOS COSTOS REALES Y LOS COSTOS ESTANDAR
2) REGISTRAR LAS OPERACIONES EN ESQUEMAS DE MAYOR
3) ELABORAR EL ESTADO DE COSTO DE PRODUCCION Y EDO. DE COSTO DE LO VENDIDO
4)ELABORAR EL ESTADO DE RESULTADOS
5)ELABORAR EL BALANCE GENERAL
6)ELABORAR EL ESTADO DE DESVIACION
ESQUEMAS DE MAYOR
DESVIACION DESVIACION
MAREIALES PRECIO MAREIALES CANTIDAD
DESVIACION DESVIACION
SUELDOS Y S. PRECIO SUELDOS Y S. CANTIDAD
16) -$ 11,000.00 -$ 11,000.00 (21 17) -$ 212,140.00 -$ 212,140.00 (21
DESVIACION
G.I.F. EN EFICIENCIA COSTOS INDIRECTOS
20) -$ 186,683.20 -$ 186,683.20 (21 5) $ 90,000.00 $ 90,000.00 (6
ESTADO DE DESVIACIONES
MATERIALES
EN PRECIO -$ 1,960.00
EN CANTIDAD -$ 51,760.00 -$ 53,720.00
MANO DE OBRA DIRECTA
EN PRECIO -$ 11,000.00
EN TIEMPO -$ 212,140.00 -$ 223,140.00
GTOS. IND. DE FABRICACION
EN PRESUPUESTO -$ 11,200.00
EN CAPACIDAD -$ 4,400.00
EN EFICIENCIA -$ 186,683.20 -$ 202,283.20
DESVIACION TOTAL -$ 479,143.20
ESTADO DE RESULTADOS
VENTAS $ 840,000.00
COSTO DE LO VENDIDO $ 782,600.00
PERDIDA BRUTA $ 57,400.00
COSTO DE DISTRIBUCION
COSTO DE VENTA $ 782,600.00
COSTO DE ADMON. $ 6,000.00
COSTOS FINANCIEROS $ 4,000.00 $ 792,600.00
PERDIDA DE OPERACIN -$ 735,200.00
COSTO DE DESVIACION
DESVIACION ENTRE C.R. Y C. ESTD. -$ 479,143.20
PROVISION ISR $ 60,000.00
PROVISION PTU $ 12,000.00 -$ 407,143.20
PERDIDA DEL EJERCICIO $ 328,056.80
DRA. VIRGINIA HERNNDEZ SILVA 109
ESTADO DE COSTO DE PRODUCCION DE LO VENDIDO
MATERIALES A $ 200.00
MATERIALES B $ 160.00
MATERIALES C $ 240.00 $ 600.00
MATERIALES D $ -
BANCOS $ 900,000.00
INV. PROD. EN PROC. $ 1,200,000.00
MAQ. EQUIPO $ 980,000.00
INV. MATERIALES $ 1,600,000.00
EQUIPO DE OFICINA $ 800,000.00
DEP. MAQUINARIA Y EQ. -$ 380,000.00
CLIENTES $ 200,000.00
INV. ART. TERMINADOS $ 500,000.00
EQUIPO DE TRANSPORTE $ 600,000.00
DEP. EQU. DE OFICINA -$ 320,000.00
DEUDORES DIVERSOS $ -
DEP. EQU. DE TRANSP. -$ 300,000.00
PROVEEDORES $ 1,500,000.00
ACREEDORES HIPRS. $ 2,000,000.00
UTDS. POR APLICAR $ 700,000.00
CAPITAL SOCIAL $ 1,580,000.00
SUMAS IGUALES $ 5,780,000.00 $ 5,780,000.00
UNDS A UN GRADO DE
8. EL INVENTARIO FINAL DE PRODUCION EN PROCESO ES DE 200 AVANCE DEL
96% EN MATERIALES Y DEL 80% EN M.O.D. Y G.I.F.
TOTAL $ 271,680.00
ESTANDAR REAL
CONCEPTO UNDS A PRECIO ESTD. TOTAL PRECIO REAL TOTAL DESVIACION
MATERIA
L A 700 $ 215.00 $ 150,500.00 $ 200.00 $ 140,000.00 -$ 10,500.00
MATERIA
L B 800 $ 210.00 $ 168,000.00 $ 160.00 $ 128,000.00 -$ 40,000.00
MATERIA
L C 900 $ 235.00 $ 211,500.00 $ 240.00 $ 216,000.00 $ 4,500.00
MATERIA
L D - $ - $ - $ - $ - $ -
TOTAL $ 530,000.00 TOTAL $ 484,000.00 -$ 46,000.00
CEDULA #7 1,200
CEDULA #8 192
TOTAL 1,392
REAL $ 2,500.00
ESTANDAR $ 8,160.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 5,660.00 $ 65.00 -$ 367,900.00
REAL $ 2,500.00
ESTANDAR $ 1,000.00 COSTO ESTDR. DESVIACION
DRA. VIRGINIA HERNNDEZ SILVA 115
DIFERENCIA -$ 1,500.00 $ 98.00 -$ 147,000.00
REAL 2,500
ESTANDAR 8,160 COSTO ESTDR. DESVIACION
DIFERENCIA - 5,660 $ 98.00 -$ 554,680.00
SE PIDE:
1) DETERMINACION DE LAS DESVIACIONES ENTRE LOS COSTOS REALES Y LOS COSTOS ESTANDAR
2) REGISTRAR LAS OPERACIONES EN ESQUEMAS DE MAYOR
3) ELABORAR EL ESTADO DE COSTO DE PRODUCCION Y EDO. DE COSTO DE LO VENDIDO
4)ELABORAR EL ESTADO DE RESULTADOS
5)ELABORAR EL BALANCE GENERAL
6)ELABORAR EL ESTADO DE DESVIACION
ESQUEMAS DE MAYOR
$ 90,000.00 (5
$ 100,000.00 (11
$ 1,527,940.00 $ 1,471,680.00
5) -$ 2,100.00
$ 800,000.00 $ - -$ 382,100.00 $ -
$ 800,000.00 -$ 382,100.00
5) -$ 1,800.00
-$ 321,800.00 $ -
-$ 321,800.00
$ 456,240.00 (1
$ - $ 1,956,240.00
$ 1,956,240.00
$ 115,200.00 (8
$ 46,000.00 (14
-$ 351,200.00 (15
$ 530,000.00 $ 530,000.00
DESVIACION DESVIACION
$ 94,080.00 (8
-$ 2,000.00 (18
-$ 147,000.00 (19
-$ 554,680.00 (20
$ 96,000.00 $ 96,000.00
1) $ 570,300.00
$ 980,000.00 $ 1,640,300.00
9) $ 450,000.00 7) $ 1,893,600.00
5) -$ 2,100.00
-$ 302,100.00 $ -
-$ 302,100.00
$ 62,400.00 (8
-$ 37,500.00 (16
-$ 367,900.00 (17
$ 125,000.00 $ 125,000.00
DESVIACION DESVIACION
DESVIACION
G.I.F. EN EFICIENCIA COSTOS INDIRECTOS
$
20) -$ 554,680.00 -$ 554,680.00 (21 5) 96,000.00 $ 96,000.00 (6
ESTADO DE DESVIACIONES
MATERIALES
ESTADO DE RESULTADOS
VENTAS $ 1,500,000.00
COSTO DE LO VENDIDO $ 1,578,000.00
PERDIDA BRUTA -$ 78,000.00
COSTO DE DISTRIBUCION
COSTO DE VENTA $ 1,578,000.00
COSTO DE ADMON. $ 36,000.00
COSTOS FINANCIEROS $ 24,000.00 $ 1,638,000.00
PERDIDA DE OPERACIN -$ 1,716,000.00
COSTO DE DESVIACION
DESVIACION ENTRE C.R. Y C. ESTD. -$ 1,212,280.00
PROVISION ISR $ 90,000.00
PROVISION PTU $ 22,000.00 -$ 1,100,280.00
PERDIDA DEL EJERCICIO $ 615,720.00
MATERIALES A $ 80.00
MATERIALES B $ 75.00
MATERIALES C $ 83.00
MATERIALES D $ 85.00 $ 323.00
BANCOS $ 1,200,000.00
INV. PROD. EN PROC. $ 180,000.00
MAQ. EQUIPO $ 2,900,000.00
INV. MATERIALES $ 2,100,000.00
EQUIPO DE OFICINA $ 780,000.00
DEP. MAQUINARIA Y EQ. -$ 380,000.00
CLIENTES $ 1,900,000.00
INV. ART. TERMINADOS $ 1,700,000.00
EQUIPO DE TRANSPORTE $ 1,200,000.00
UNIDADES A UN GRADO DE
8. EL INVENTARIO FINAL DE PRODUCION EN PROCESO ES DE 150 AVANCE DEL
EN M.O.D. Y
96% EN MATERIALES Y DEL 80% G.I.F.
ESTANDAR REAL
PRECIO
CONCEPTO UNDS A ESTD. TOTAL PRECIO REAL TOTAL DESVIACION
MATERIAL A 700 $ 20.00 $ 14,000.00 $ 80.00 $ 56,000.00 $ 42,000.00
MATERIAL B 800 $ 35.00 $ 28,000.00 $ 75.00 $ 60,000.00 $ 32,000.00
MATERIAL C 900 $ 22.00 $ 19,800.00 $ 83.00 $ 74,700.00 $ 54,900.00
MATERIAL D 600 $ 30.00 $ 18,000.00 $ 85.00 $ 51,000.00 $ 33,000.00
TOTAL $ 79,800.00 TOTAL $ 241,700.00 $ 161,900.00
UNDS
CONCEPTO A UNDS. TERMINS. DIFR. EN UNDS PRECIO REAL DESVIACION
CEDULA #7 1,000
CEDULA #8 144
REAL $ 2,500.00
ESTANDAR $ 4,480.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 1,980.00 $ 20.00 -$ 39,600.00
REAL $ 2,500.00
ESTANDAR $ 3.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 2,497.00 $ 15.00 -$ 37,455.00
REAL 2,500
ESTANDAR 4,480 COSTO ESTDR. DESVIACION
DIFERENCIA - 1,980 $ 15.00 -$ 29,700.00
SE PIDE:
1) DETERMINACION DE LAS DESVIACIONES ENTRE LOS COSTOS REALES Y LOS COSTOS ESTANDAR
2) REGISTRAR LAS OPERACIONES EN ESQUEMAS DE MAYOR
3) ELABORAR EL ESTADO DE COSTO DE PRODUCCION Y EDO. DE COSTO DE LO VENDIDO
4)ELABORAR EL ESTADO DE RESULTADOS
5)ELABORAR EL BALANCE GENERAL
6)ELABORAR EL ESTADO DE DESVIACION
ESQUEMAS DE MAYOR
BANCOS INV. PROD. EN PROC.
A) $ 1,200,000.00 $ 22,150.00 (1 A) $ 180,000.00 ------------------
9) $ 980,000.00 $ 143,000.00 (3 8) $ 63,312.00
$ 95,000.00 (5
$ 100,000.00 (11
$ 2,180,000.00 $ 360,150.00 $ 243,312.00 $ -
$ 1,819,850.00 $ 243,312.00
DESVIACION DESVIACION
MAREIALES PRECIO MAREIALES CANTIDAD
DESVIACION DESVIACION
G.I.F. EN PRESUPUESTO G.I.F. EN CAPACIDAD
DESVIACION DESVIACION
SUELDOS Y S. PRECIO SUELDOS Y S. CANTIDAD
16) $ 100,000.00 $ 100,000.00 (21 17) -$ 39,600.00 -$ 39,600.00 (21
DESVIACION
G.I.F. EN EFICIENCIA COSTOS INDIRECTOS
ESTADO DE DESVIACIONES
MATERIALES
EN PRECIO $ 161,900.00
EN CANTIDAD -$ 127,812.00 $ 34,088.00
MANO DE OBRA DIRECTA
EN PRECIO $ 100,000.00
EN TIEMPO -$ 39,600.00 $ 60,400.00
GTOS. IND. DE FABRICACION
EN PRESUPUESTO $ 51,000.00
EN CAPACIDAD $ 37,455.00
EN EFICIENCIA -$ 29,700.00 $ 58,755.00
DESVIACION TOTAL $ 153,243.00
ESTADO DE RESULTADOS
VENTAS $ 1,400,000.00
COSTO DE LO VENDIDO $ 463,000.00
MATERIALES $ 369,512.00
BANCOS $ 900,000.00
INV. PROD. EN PROC. $ 1,730,000.00
MAQ. EQUIPO $ 1,000,000.00
INV. MATERIALES $ 1,200,000.00
EQUIPO DE OFICINA $ 800,000.00
DEP. MAQUINARIA Y EQ. -$ 450,000.00
CLIENTES $ 300,000.00
INV. ART. TERMINADOS $ 150,000.00
EQUIPO DE TRANSPORTE $ 980,000.00
DEP. EQU. DE OFICINA -$ 80,000.00
DEUDORES DIVERSOS $ 190,000.00
DEP. EQU. DE TRANSP. -$ 209,000.00
PROVEEDORES $ 700,000.00
ACREEDORES HIPRS. $ 3,000,000.00
UTDS. POR APLICAR $ 580,000.00
CAPITAL SOCIAL $ 2,231,000.00
SUMAS IGUALES $ 6,511,000.00 $ 6,511,000.00
UNDS A UN GRADO DE
8. EL INVENTARIO FINAL DE PRODUCION EN PROCESO ES DE 80 AVANCE DEL
95% EN MATERIALES Y DEL 85% EN M.O.D. Y G.I.F.
ESTANDAR REAL
CONCEPTO UNDS A PRECIO ESTD. TOTAL PRECIO REAL TOTAL DESVIACION
MATERIAL A $ 30.00 $ 24,000.00 $ 35.00 $ 28,000.00 $ 4,000.00
DRA. VIRGINIA HERNNDEZ SILVA 136
800
CEDULA #7 1,300
CEDULA #8 76
TOTAL 1,376
REAL $ 1,400.00
ESTANDAR $ 5,472.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 4,072.00 $ 65.00 -$ 264,680.00
REAL $ 1,400.00
ESTANDAR $ 2,000.00 COSTO ESTDR. DESVIACION
DIFERENCIA $ 600.00 $ 49.00 $ 29,400.00
REAL 1,400
ESTANDAR 5,472 COSTO ESTDR. DESVIACION
DIFERENCIA - 4,072 $ 49.00 -$ 199,528.00
SE PIDE:
1) DETERMINACION DE LAS DESVIACIONES ENTRE LOS COSTOS REALES Y LOS COSTOS ESTANDAR
2) REGISTRAR LAS OPERACIONES EN ESQUEMAS DE MAYOR
3) ELABORAR EL ESTADO DE COSTO DE PRODUCCION Y EDO. DE COSTO DE LO VENDIDO
4)ELABORAR EL ESTADO DE RESULTADOS
5)ELABORAR EL BALANCE GENERAL
6)ELABORAR EL ESTADO DE DESVIACION
ESQUEMAS DE MAYOR
BANCOS INV. PROD. EN PROC.
DRA. VIRGINIA HERNNDEZ SILVA 138
A) $ 900,000.00 $ 35,064.00 (1 A) $ 1,730,000.00 ------------------
9) $ 396,000.00 $ 46,400.00 (3 8) $ 41,876.00
$ 31,000.00 (5
$ 22,000.00 (11
$ 1,296,000.00 $ 134,464.00 $ 1,771,876.00 $ -
$ 1,161,536.00 $ 1,771,876.00
DESVIACION DESVIACION
MAREIALES PRECIO MAREIALES CANTIDAD
DESVIACION DESVIACION
SUELDOS Y S. PRECIO SUELDOS Y S. CANTIDAD
16) -$ 40,600.00 -$ 40,600.00 (21 17) -$ 264,680.00 -$ 264,680.00 (21
DESVIACION
G.I.F. EN EFICIENCIA COSTOS INDIRECTOS
20) -$ 199,528.00 -$ 199,528.00 (21 5) $ 40,000.00 $ 40,000.00 (6
MATERIALES
EN PRECIO -$ 4,600.00
EN CANTIDAD -$ 104,768.00 -$ 109,368.00
MANO DE OBRA DIRECTA
EN PRECIO -$ 40,600.00
EN TIEMPO -$ 264,680.00 -$ 305,280.00
GTOS. IND. DE FABRICACION
EN PRESUPUESTO -$ 58,000.00
EN CAPACIDAD -$ 29,400.00
EN EFICIENCIA -$ 199,528.00 -$ 286,928.00
DESVIACION TOTAL -$ 701,576.00
ESTADO DE RESULTADOS
VENTAS $ 660,000.00
COSTO DE DISTRIBUCION
COSTO DE DESVIACION
BANCOS $ 1,161,536.00
CLIENTES $ 564,000.00
PROVEEDORES $ 781,816.00
-$ 61,452.00
-$ 30,726.00
BANCOS $ 900,000.00
INV. PROD. EN PROC. $ 1,730,000.00
MAQ. EQUIPO $ 1,000,000.00
INV. MATERIALES $ 1,200,000.00
EQUIPO DE OFICINA $ 800,000.00
DEP. MAQUINARIA Y EQ. -$ 450,000.00
CLIENTES $ 300,000.00
INV. ART. TERMINADOS $ 150,000.00
EQUIPO DE TRANSPORTE $ 980,000.00
DEP. EQU. DE OFICINA -$ 80,000.00
DEUDORES DIVERSOS $ 190,000.00
DEP. EQU. DE TRANSP. -$ 209,000.00
PROVEEDORES $ 700,000.00
ACREEDORES HIPRS. $ 3,000,000.00
UTDS. POR APLICAR $ 580,000.00
CAPITAL SOCIAL $ 2,231,000.00
SUMAS IGUALES $ 6,511,000.00 $ 6,511,000.00
UNDS A UN GRADO
8. EL INVENTARIO FINAL DE PRODUCION EN PROCESO ES DE 80 DE AVANCE DEL
95% EN MATERIALES Y DEL 85% EN M.O.D. Y G.I.F.
ESTANDAR REAL
CONCEPTO UNDS A PRECIO ESTD. TOTAL PRECIO REAL TOTAL DESVIACION
DRA. VIRGINIA HERNNDEZ SILVA 148
MATERIAL A 800 $ 30.00 $ 24,000.00 $ 35.00 $ 28,000.00 $ 4,000.00
TOTAL -$ 104,768.00
CEDULA #7 1,300
CEDULA #8 76
TOTAL 1,376
REAL $ 1,400.00
ESTANDAR $ 5,472.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 4,072.00 $ 65.00 -$ 264,680.00
REAL $ 1,400.00
ESTANDAR $ 2,000.00 COSTO ESTDR. DESVIACION
DIFERENCIA $ 600.00 $ 49.00 $ 29,400.00
REAL 1,400
ESTANDAR 5,472 COSTO ESTDR. DESVIACION
DIFERENCIA - 4,072 $ 49.00 -$ 199,528.00
SE PIDE:
1) DETERMINACION DE LAS DESVIACIONES ENTRE LOS COSTOS REALES Y LOS COSTOS ESTANDAR
2) REGISTRAR LAS OPERACIONES EN ESQUEMAS DE MAYOR
3) ELABORAR EL ESTADO DE COSTO DE PRODUCCION Y EDO. DE COSTO DE LO VENDIDO
4)ELABORAR EL ESTADO DE RESULTADOS
5)ELABORAR EL BALANCE GENERAL
6)ELABORAR EL ESTADO DE DESVIACION
ESQUEMAS DE MAYOR
$ - $ 781,816.00
$ 781,816.00
DESVIACION DESVIACION
MAREIALES PRECIO MAREIALES CANTIDAD
DESVIACION DESVIACION
SUELDOS Y S. PRECIO SUELDOS Y S. CANTIDAD
16) -$ 40,600.00 -$ 40,600.00 (21 17) -$ 264,680.00 -$ 264,680.00 (21
DESVIACION
G.I.F. EN EFICIENCIA COSTOS INDIRECTOS
20) -$ 199,528.00 -$ 199,528.00 (21 5) $ 40,000.00 $ 40,000.00 (6
ESTADO DE DESVIACIONES
MATERIALES
EN PRECIO -$ 4,600.00
EN CANTIDAD -$ 104,768.00 -$ 109,368.00
MANO DE OBRA DIRECTA
EN PRECIO -$ 40,600.00
EN TIEMPO -$ 264,680.00 -$ 305,280.00
GTOS. IND. DE FABRICACION
EN PRESUPUESTO -$ 58,000.00
EN CAPACIDAD -$ 29,400.00
EN EFICIENCIA -$ 199,528.00 -$ 286,928.00
DESVIACION TOTAL -$ 701,576.00
ESTADO DE RESULTADOS
VENTAS $ 660,000.00
COSTO DE DISTRIBUCION
COSTO DE DESVIACION
BANCOS $ 1,161,536.00
CLIENTES $ 564,000.00
PROVEEDORES $ 781,816.00
-$ 61,452.00
-$ 30,726.00
MATERIALES $ 196,768.00
MATERIALES A $ 20.00
MATERIALES B $ 35.00
MATERIALES C $ 28.00
$ 335.00
BANCOS $ 1,000,000.00
INV. PROD. EN PROC. $ -
MAQ. EQUIPO $ 1,800,000.00
INV. MATERIALES $ 200,000.00
EQUIPO DE OFICINA $ -
DEP. MAQUINARIA Y EQ. -$ 200,000.00
CLIENTES $ 250,000.00
INV. ART. TERMINADOS $ 900,000.00
EQUIPO DE TRANSPORTE $ 1,500,000.00
DEP. EQU. DE OFICINA $ -
DEUDORES DIVERSOS $ -
DEP. EQU. DE TRANSP. -$ 400,000.00
PROVEEDORES $300,000.00
TOTAL $ 17,379.00
ESTANDAR REAL
CONCEPTO UNDS A PRECIO ESTD. TOTAL PRECIO REAL TOTAL DESVIACION
MATERIAL A 300 $ 25.00 $ 7,500.00 $ 20.00 $ 6,000.00 -$ 1,500.00
MATERIAL B 350 $ 32.00 $ 11,200.00 $ 35.00 $ 12,250.00 $ 1,050.00
MATERIAL C 270 $ 26.00 $ 7,020.00 $ 28.00 $ 7,560.00 $ 540.00
MATERIAL D 400 $ 38.00 $ 15,200.00 $ 32.00 $ 12,800.00 -$ 2,400.00
TOTAL $ 40,920.00 TOTAL $ 38,610.00 -$ 2,310.00
TOTAL -$ 48,445.00
CEDULA #7 700
CEDULA #8 57
TOTAL 757
REAL $ 500.00
ESTANDAR $ 2,500.00 COSTO ESTDR. DESVIACION
DIFERENCIA $ 2,000.00 $ 14.00 $ 28,000.00
REAL 500
ESTANDAR 3,746 COSTO ESTDR. DESVIACION
DIFERENCIA - 3,246 $ 14.00 -$ 45,444.00
SE PIDE:
1) DETERMINACION DE LAS DESVIACIONES ENTRE LOS COSTOS REALES Y LOS COSTOS ESTANDAR
2) REGISTRAR LAS OPERACIONES EN ESQUEMAS DE MAYOR
3) ELABORAR EL ESTADO DE COSTO DE PRODUCCION Y EDO. DE COSTO DE LO VENDIDO
4)ELABORAR EL ESTADO DE RESULTADOS
ESQUEMAS DE MAYOR
DESVIACION DESVIACION
G.I.F. EN PRESUPUESTO G.I.F. EN CAPACIDAD
DESVIACION DESVIACION
SUELDOS Y S. PRECIO SUELDOS Y S. CANTIDAD
DESVIACION
G.I.F. EN EFICIENCIA COSTOS INDIRECTOS
20) -$ 45,444.00 -$ 45,444.00 (21 5) $ 15,000.00 $ 15,000.00 (6
ESTADO DE DESVIACIONES
MATERIALES
EN PRECIO -$ 2,310.00
EN CANTIDAD -$ 48,445.00 -$ 50,755.00
MANO DE OBRA DIRECTA
EN PRECIO $ 7,500.00
EN TIEMPO -$ 97,380.00 -$ 89,880.00
GTOS. IND. DE FABRICACION
EN PRESUPUESTO -$ 20,000.00
EN CAPACIDAD $ 28,000.00
EN EFICIENCIA -$ 45,444.00 -$ 37,444.00
DESVIACION TOTAL -$ 178,079.00
ESTADO DE RESULTADOS
DRA. VIRGINIA HERNNDEZ SILVA 166
VENTAS $ 500,000.00
COSTO DE LO VENDIDO $ 335,000.00
PERDIDA BRUTA $ 165,000.00
COSTO DE DISTRIBUCION
COSTO DE VENTA $ 7,000.00
COSTO DE ADMON. $ 5,000.00
COSTOS FINANCIEROS $ 8,000.00 $ 20,000.00
PERDIDA DE OPERACIN $ 145,000.00
COSTO DE DESVIACION
DESVIACION ENTRE C.R. Y C. ESTD. -$ 178,079.00
PROVISION ISR $ 70,000.00
PROVISION PTU $ 15,000.00 -$ 93,079.00
PERDIDA DEL EJERCICIO $ 51,921.00
MATERIALES $ 87,055.00
MATERIALES C $ 30.00
MATERIALES D $ 28.00
$ 214.00
TOTAL -$ 6,000.00
TOTAL $ 149,800.00
TOTAL $ 18,890.00
ESTANDAR REAL
TOTAL -$ 3,800.00
CEDULA #7 700
CEDULA #8 92
TOTAL 792
REAL $ 2,400.00
ESTANDAR $ 1,000.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 1,400.00 $ 18.00 -$ 25,200.00
REAL 2,400
ESTANDAR 2,355 COSTO ESTDR. DESVIACION
DIFERENCIA 45 $ 18.00 $ 810.00
ESQUEMAS DE MAYOR
$ 14,000.00 (5
$ 12,000.00 (11
$ 924,820.00 $ 1,753,890.00
5) -$ 1,500.00
$ 700,000.00 $ - -$ 207,500.00 $ -
$ 700,000.00 -$ 207,500.00
-$ 72,100.00 $ -
-$ 72,100.00
$ 72,720.00 (1
$ - $ 672,720.00
$ 672,720.00
$ 9,200.00 (8
$ 5,500.00 (14
-$ 3,800.00 (15
$ 80,900.00 $ 80,900.00
DESVIACION DESVIACION
DESVIACION DESVIACION
$ 4,590.00 (8
$ 2,000.00 (18
-$ 25,200.00 (19
$ 810.00 (20
$ 20,000.00 $ 20,000.00
DESVIACION DESVIACION
SUELDOS Y S. PRECIO SUELDOS Y S. CANTIDAD
DESVIACION
G.I.F. EN EFICIENCIA COSTOS INDIRECTOS
20) $ 810.00 $ 810.00 (21 5) $ 20,000.00 $ 20,000.00 (6
ESTADO DE DESVIACIONES
MATERIALES
EN PRECIO -$ 5,500.00
EN CANTIDAD -$ 3,800.00 -$ 9,300.00
MANO DE OBRA DIRECTA
EN PRECIO $ 12,000.00
EN TIEMPO $ 900.00 $ 12,900.00
GTOS. IND. DE FABRICACION
EN PRESUPUESTO $ 2,000.00
EN CAPACIDAD -$ 25,200.00
EN EFICIENCIA $ 810.00 -$ 22,390.00
DESVIACION TOTAL -$ 18,790.00
ESTADO DE RESULTADOS
VENTAS $ 320,000.00
COSTO DE LO VENDIDO $ 171,200.00
PERDIDA BRUTA $ 148,800.00
COSTO DE DISTRIBUCION
COSTO DE VENTA $ 6,000.00
COSTO DE ADMON. $ 4,000.00
COSTOS FINANCIEROS $ 2,000.00 $ 12,000.00
PERDIDA DE OPERACIN $ 136,800.00
COSTO DE DESVIACION
DESVIACION ENTRE C.R. Y C. ESTD. -$ 18,790.00
PROVISION ISR $ 60,000.00
PROVISION PTU $ 120,000.00 $ 161,210.00
DRA. VIRGINIA HERNNDEZ SILVA 178
PERDIDA DEL EJERCICIO $ 298,010.00
TOTAL $ 28,450.80
UNIDADES
9. SE VENDEN 1,150 A $ 500.00 CADA UNA, DE LAS CUALES EL 70%
ES DE CONTADO Y EL RESTO A CREDITO
ESTANDAR REAL
CONCEPTO UNDS PRECIO ESTD. TOTAL PRECIO REAL TOTAL DESVIACION
TOTAL -$ 62,671.60
CEDULA #7 1,200
CEDULA #8 85
TOTAL 1,285
REAL $ 1,400.00
ESTANDAR $ 5,109.60 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 3,709.60 $ 30.00 -$ 111,288.00
REAL $ 1,400.00
ESTANDAR $ 1,200.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 200.00 $ 22.00 -$ 4,400.00
REAL 1,400
ESTANDAR 5,110 COSTO ESTDR. DESVIACION
DIFERENCIA - 3,710 $ 22.00 -$ 81,611.20
SE PIDE:
1) DETERMINACION DE LAS DESVIACIONES ENTRE LOS COSTOS REALES Y LOS COSTOS ESTANDAR
2) REGISTRAR LAS OPERACIONES EN ESQUEMAS DE MAYOR
3) ELABORAR EL ESTADO DE COSTO DE PRODUCCION Y EDO. DE COSTO DE LO VENDIDO
4)ELABORAR EL ESTADO DE RESULTADOS
5)ELABORAR EL BALANCE GENERAL
6)ELABORAR EL ESTADO DE DESVIACION
ESQUEMAS DE MAYOR
$ 22,000.00 (5
$ 20,000.00 (11
5) -$ 1,600.00
$ 700,000.00 $ - -$ 481,600.00 $ -
$ 700,000.00 -$ 481,600.00
5) -$ 3,200.00
-$ 73,200.00 $ -
-$ 73,200.00
$ 76,635.00 (1
$ - $ 1,036,635.00
$ 1,036,635.00
$ 12,351.60 (8
$ 3,020.00 (14
-$ 62,671.60 (15
DRA. VIRGINIA HERNNDEZ SILVA 186
$ 127,900.00 $ 127,900.00
DESVIACION DESVIACION
DESVIACION DESVIACION
$ 6,811.20 (8
$ 3,600.00 (18
-$ 4,400.00 (19
-$ 81,611.20 (20
$ 30,000.00 $ 30,000.00
DESVIACION DESVIACION
DESVIACION
G.I.F. EN EFICIENCIA COSTOS INDIRECTOS
20) -$ 81,611.20 -$ 81,611.20 (21 5) $ 30,000.00 $ 30,000.00 (6
ESTADO DE DESVIACIONES
MATERIALES
EN PRECIO -$ 3,020.00
EN PRECIO $ 2,800.00
EN PRESUPUESTO $ 3,600.00
EN CAPACIDAD -$ 4,400.00
ESTADO DE RESULTADOS
COSTO DE DISTRIBUCION
COSTO DE DESVIACION
UNIDADES A UN GRADO DE
8. EL INVENTARIO FINAL DE PRODUCION EN PROCESO ES DE 200 AVANCE DEL
96% EN MATERIALES Y DEL 80% EN M.O.D. Y G.I.F.
ESTANDAR REAL
CONCEPTO UNDS A PRECIO ESTD. TOTAL PRECIO REAL TOTAL DESVIACION
TOTAL -$ 100,960.00
CEDULA #7 1,000
CEDULA #8 192
TOTAL 1,192
REAL $ 2,200.00
ESTANDAR $ 6,960.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 4,760.00 $ 40.00 -$ 190,400.00
REAL $ 2,200.00
ESTANDAR $ - COSTO ESTDR. DESVIACION
DIFERENCIA -$ 2,200.00 $ 41.00 -$ 90,200.00
REAL 2,200
ESTANDAR 6,960 COSTO ESTDR. DESVIACION
DIFERENCIA - 4,760 $ 41.00 -$ 195,160.00
SE PIDE:
1) DETERMINACION DE LAS DESVIACIONES ENTRE LOS COSTOS REALES Y LOS COSTOS ESTANDAR
ESQUEMAS DE MAYOR
$ 86,000.00 (5
$ 100,000.00 (11
$ 751,232.00 $ 1,856,920.00
5) -$ 3,500.00
$ 700,000.00 $ - -$ 483,500.00 $ -
$ 700,000.00 -$ 483,500.00
5) -$ 3,000.00
-$ 173,000.00 $ -
-$ 173,000.00
$ 159,072.00 (1
$ - $ 1,759,072.00
$ 1,759,072.00
$ 44,160.00 (8
$ 3,200.00 (14
-$ 100,960.00 (15
$ 176,400.00 $ 176,400.00
DESVIACION DESVIACION
DESVIACION DESVIACION
$ 39,360.00 (8
$ 14,000.00 (18
-$ 90,200.00 (19
-$ 195,160.00 (20
$ 96,000.00 $ 14,000.00
1) $ 198,840.00
$ 2,000,000.00 $ 1,222,440.00
9) $ 120,000.00 7) $ 716,000.00
$ 320,000.00 $ 930,000.00
5) -$ 3,500.00
-$ 209,500.00 $ -
-$ 209,500.00
$ 38,400.00 (8
$ 22,000.00 (16
-$ 190,400.00 (17
$ 110,000.00 $ 110,000.00
DESVIACION
ESTADO DE DESVIACIONES
MATERIALE
S
EN PRECIO -$ 3,200.00
DRA. VIRGINIA HERNNDEZ SILVA 201
EN
CANTIDAD -$ 100,960.00 -$ 104,160.00
EN PRECIO $ 22,000.00
EN PRESUPUESTO $ 14,000.00
EN CAPACIDAD -$ 90,200.00
ESTADO DE RESULTADOS
VENTAS $ 400,000.00
COSTO DE DISTRIBUCION
COSTO DE DESVIACION
MATERIALES C $ 230.00
DRA. VIRGINIA HERNNDEZ SILVA 204
MATERIALES D $ 260.00 $ 935.00
$ 1,637.00
PROVEEDORES $1,600,000.00
TOTAL -$ 10,000.00
TOTAL $ 1,637,000.00
8. EL INVENTARIO FINAL DE PRODUCION EN PROCESO ES DE 150 UNIDADES A UN GRADO DE AVANCE DEL
EN M.O.D. Y
96% EN MATERIALES Y DEL 80% G.I.F.
TOTAL $ 218,880.00
$ $
100% 1,000.00 400.00 $ 400,000.00
70% $ 400,000.00 $ 280,000.00
30% $ 400,000.00 $ 120,000.00
$
$ 1,637.00 1,000.00 $ 1,637,000.00
ESTANDAR REAL
UNIDADES
CONCEPTO A UNDS. TERMINS. DIFR. EN UNDS PRECIO REAL DESVIACION
MATERIAL A 700 1,144 - 444 $ 220.00 -$ 97,680.00
MATERIAL B 800 1,144 - 344 $ 225.00 -$ 77,400.00
MATERIAL C 900 1,144 - 244 $ 230.00 -$ 56,120.00
MATERIAL D 600 1,144 - 544 $ 260.00 -$ 141,440.00
TOTAL -$ 372,640.00
CEDULA
#7 1,000
CEDULA
#8 144
TOTAL 1,144
REAL $ 2,500.00
ESTANDAR $ 6,720.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 4,220.00 $ 68.00 -$ 286,960.00
1,000 ART. TERMINADOS
120 PRODUC. EN PROCESO
1,120 SUMA
6 HRS. CADA UNA
6,720 TOTAL HORAS
REAL $ 2,500.00
ESTANDAR $ 2,000.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 500.00 $ 49.00 -$ 24,500.00
REAL 2,500
ESTANDAR 6,720 COSTO ESTDR. DESVIACION
DIFERENCIA - 4,220 $ 49.00 -$ 206,780.00
SE PIDE:
1) DETERMINACION DE LAS DESVIACIONES ENTRE LOS COSTOS REALES Y LOS COSTOS ESTANDAR
2) REGISTRAR LAS OPERACIONES EN ESQUEMAS DE MAYOR
3) ELABORAR EL ESTADO DE COSTO DE PRODUCCION Y EDO. DE COSTO DE LO VENDIDO
4)ELABORAR EL ESTADO DE RESULTADOS
5)ELABORAR EL BALANCE GENERAL
6)ELABORAR EL ESTADO DE DESVIACION
-$ 173,000.00 $ -
-$ 173,000.00
DESVIACION DESVIACION
MAREIALES PRECIO MAREIALES CANTIDAD
DESVIACION DESVIACION
G.I.F. EN PRESUPUESTO G.I.F. EN CAPACIDAD
DESVIACION DESVIACION
SUELDOS Y S. PRECIO SUELDOS Y S. CANTIDAD
DESVIACION
G.I.F. EN EFICIENCIA COSTOS INDIRECTOS
ESTADO DE DESVIACIONES
MATERIALE
S
EN PRECIO $ 19,100.00
EN
CANTIDAD -$ 372,640.00 -$ 353,540.00
MANO DE OBRA DIRECTA
EN PRECIO -$ 20,000.00
EN TIEMPO -$ 286,960.00 -$ 306,960.00
GTOS. IND. DE
FABRICACION
EN PRESUPUESTO -$ 2,000.00
EN CAPACIDAD -$ 24,500.00
EN EFICIENCIA -$ 206,780.00 -$ 233,280.00
DESVIACION TOTAL -$ 893,780.00
ESTADO DE RESULTADOS
VENTAS $ 400,000.00
COSTO DE LO VENDIDO $ 1,637,000.00
PERDIDA BRUTA -$ 1,237,000.00
COSTO DE DISTRIBUCION
COSTO DE VENTA $ 40,000.00
COSTO DE ADMON. $ 36,000.00
COSTOS FINANCIEROS $ 24,000.00 $ 100,000.00
PERDIDA DE OPERACIN -$ 1,337,000.00
COSTO DE DESVIACION
DESVIACION ENTRE C.R. Y C. ESTD. -$ 893,780.00
PROVISION ISR $ 80,000.00
PROVISION PTU $ 20,000.00 -$ 793,780.00
PERDIDA DEL EJERCICIO -$ 2,130,780.00
TOTAL $ 168,560.00
ESTANDAR REAL
CONCEPTO UNDS A PRECIO ESTD. TOTAL PRECIO REAL TOTAL DESVIACION
CEDULA #7 1,200
CEDULA #8 344
TOTAL 1,544
REAL $ 1,800.00
ESTANDAR $ 7,400.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 5,600.00 $ 35.00 -$ 196,000.00
REAL 1,800
ESTANDAR 7,400 COSTO ESTDR. DESVIACION
DIFERENCIA - 5,600 $ 46.60 -$ 260,960.00
SE PIDE:
1) DETERMINACION DE LAS DESVIACIONES ENTRE LOS COSTOS REALES Y LOS COSTOS ESTANDAR
2) REGISTRAR LAS OPERACIONES EN ESQUEMAS DE MAYOR
3) ELABORAR EL ESTADO DE COSTO DE PRODUCCION Y EDO. DE COSTO DE LO VENDIDO
4)ELABORAR EL ESTADO DE RESULTADOS
5)ELABORAR EL BALANCE GENERAL
6)ELABORAR EL ESTADO DE DESVIACION
ESQUEMAS DE MAYOR
$ 43,500.00 (5
$ 70,000.00 (11
$ 3,022,585.00 $ 1,968,560.00
$ 180,000.00 -$ 7,500.00
5) -$ 7,500.00
-$ 257,500.00 $ -
-$ 257,500.00
$ 62,985.00 (1
$ - $ 812,985.00
$ 812,985.00
$ 63,640.00 (8
-$ 29,200.00 (14
-$ 144,640.00 (15
$ 111,800.00 $ 111,800.00
DESVIACION DESVIACION
DESVIACION DESVIACION
$ 55,920.00 (8
-$ 4,000.00 (18
-$ 13,980.00 (19
-$ 260,960.00 (20
$ 66,000.00 $ 660.00
DESVIACION DESVIACION
SUELDOS Y S. PRECIO SUELDOS Y S. CANTIDAD
16) $ 45,000.00 $ 45,000.00 (21 17) -$ 196,000.00 -$ 196,000.00 (21
DESVIACION
G.I.F. EN EFICIENCIA COSTOS INDIRECTOS
20) -$ 260,960.00 -$ 260,960.00 (21 5) $ 66,000.00 $ 66,000.00 (6
MATERIALES
EN PRECIO $ 29,200.00
EN PRECIO $ 45,000.00
EN CAPACIDAD -$ 13,980.00
ESTADO DE RESULTADOS
VENTAS $ 270,000.00
COSTO DE DISTRIBUCION
COSTO DE
VENTA $ 25,000.00
COSTO DE DESVIACION
MATERIALES $ 285,640.00
BANCOS $ 800,000.00
INV. PROD. EN PROC. $ 1,735,000.00
MAQ. EQUIPO $ 200,000.00
INV. MATERIALES $ 1,200,000.00
EQUIPO DE OFICINA $ 700,000.00
DEP. MAQUINARIA Y EQ. -$ 480,000.00
CLIENTES $ 200,000.00
INV. ART. TERMINADOS $ 130,000.00
EQUIPO DE TRANSPORTE $ 980,000.00
DEP. EQU. DE OFICINA -$ 70,000.00
DEUDORES DIVERSOS $ 180,000.00
DEP. EQU. DE TRANSP. -$ 206,000.00
PROVEEDORES $ 600,000.00
ACREEDORES HIPRS. $ 300,000.00
UTDS. POR APLICAR $ 584,000.00
CAPITAL SOCIAL $ 3,885,000.00
SUMAS IGUALES $ 5,369,000.00 $ 5,369,000.00
TOTAL 21,344.40
TOTAL $ 74,000.00
ESTANDAR REAL
UNIDADES
CONCEPTO A UNDS. TERMINS. DIFR. EN UNDS PRECIO REAL DESVIACION
MATERIA
L A 500 785 - 285 $ 22.00 -$ 6,261.20
MATERIA
L B 600 785 - 185 $ 18.00 -$ 3,322.80
MATERIA
L C 700 785 - 85 $ 10.00 -$ 846.00
MATERIA
L D 800 785 15 $ 12.00 $ 184.80
TOTAL -$ 10,245.20
CEDULA #7 700
CEDULA #8 85
TOTAL 785
REAL 1,400
ESTANDAR 3,110 COSTO ESTDR. DESVIACION
DIFERENCIA - 1,710 $ 22.00 -$ 37,611.20
SE PIDE:
1) DETERMINACION DE LAS DESVIACIONES ENTRE LOS COSTOS REALES Y LOS COSTOS ESTANDAR
2) REGISTRAR LAS OPERACIONES EN ESQUEMAS DE MAYOR
3) ELABORAR EL ESTADO DE COSTO DE PRODUCCION Y EDO. DE COSTO DE LO VENDIDO
4)ELABORAR EL ESTADO DE RESULTADOS
5)ELABORAR EL BALANCE GENERAL
6)ELABORAR EL ESTADO DE DESVIACION
ESQUEMAS DE MAYOR
$ 22,000.00 (5
$ 74,000.00 (11
$ 1,148,200.00 $ 1,756,344.40
5) -$ 1,600.00
$ 700,000.00 $ - -$ 481,600.00 $ -
$ 700,000.00 -$ 481,600.00
5) -$ 3,200.00
-$ 73,200.00 $ -
-$ 73,200.00
$ 24,000.00 (1
$ - $ 624,000.00
$ 624,000.00
DRA. VIRGINIA HERNNDEZ SILVA 231
MATS. PRODUC. PROC. SUELDOS Y SALARIOS
$ 5,245.20 (8
$ 31,600.00 (14
-$ 10,245.20 (15
$ 70,000.00 $ 70,000.00
DESVIACION DESVIACION
DESVIACION DESVIACION
$ 6,811.20 (8
$ 3,600.00 (18
-$ 4,400.00 (19
-$ 37,611.20 (20
$ 30,000.00 $ 30,000.00
DRA. VIRGINIA HERNNDEZ SILVA 232
COSTO DE ADMON. COSTO FINANCIERO
$ 44,800.00 $ 44,800.00
DESVIACION
G.I.F. EN EFICIENCIA COSTOS INDIRECTOS
20) -$ 37,611.20 -$ 37,611.20 (21 5) $ 30,000.00 $ 30,000.00 (6
ESTADO DE DESVIACIONES
MATERIALE
S
EN PRECIO -$ 31,600.00
EN
CANTIDAD -$ 10,245.20 -$ 41,845.20
MANO DE OBRA DIRECTA
EN PRECIO $ 2,800.00
EN TIEMPO -$ 51,288.00 -$ 48,488.00
GTOS. IND. DE
FABRICACION
EN PRESUPUESTO $ 3,600.00
EN CAPACIDAD -$ 4,400.00
EN EFICIENCIA -$ 37,611.20 -$ 38,411.20
DESVIACION TOTAL -$ 128,744.40
ESTADO DE RESULTADOS
VENTAS $ 700,000.00
COSTO DE LO VENDIDO $ 270,000.00
PERDIDA BRUTA $ 430,000.00
COSTO DE DISTRIBUCION
DRA. VIRGINIA HERNNDEZ SILVA 234
COSTO DE VENTA $ 10,000.00
COSTO DE ADMON. $ 60,000.00
COSTOS FINANCIEROS $ 4,000.00 $ 74,000.00
PERDIDA DE OPERACIN $ 356,000.00
COSTO DE DESVIACION
DESVIACION ENTRE C.R. Y C. ESTD. -$ 128,744.40
PROVISION ISR $ 60,000.00
PROVISION PTU $ 12,000.00 -$ 56,744.40
PERDIDA DEL EJERCICIO $ 299,255.60
TOTAL $ 10,000.00
TOTAL $ 26,000.00
TOTAL $ 51,904.00
9. SE VENDEN UNIDADES A $ 500.00 CADA UNA, DE LAS CUALES EL
ESTANDAR REAL
UNDS PRECIO
CONCEPTO A ESTD. TOTAL PRECIO REAL TOTAL DESVIACION
CEDULA #7 900
CEDULA #8 192
TOTAL 1,092
REAL $ 1,400.00
ESTANDAR $ 4,240.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 2,840.00 $ 30.00 -$ 85,200.00
REAL $ 1,400.00
ESTANDAR $1,200.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 200.00 $ 22.00 -$ 4,400.00
REAL 1,400
ESTANDAR 4,240 COSTO ESTDR. DESVIACION
DIFERENCIA - 2,840 $ 22.00 -$ 62,480.00
DRA. VIRGINIA HERNNDEZ SILVA 241
$ 900.00 ART. TERMINADOS
$ 160.00 PRODUC. EN PROCESO
$ 1,060.00 SUMA
$ 4.00 HRS. CADA UNA
$ 4,240.00 TOTAL HORAS
SE PIDE:
1) DETERMINACION DE LAS DESVIACIONES ENTRE LOS COSTOS REALES Y LOS COSTOS ESTANDAR
2) REGISTRAR LAS OPERACIONES EN ESQUEMAS DE MAYOR
3) ELABORAR EL ESTADO DE COSTO DE PRODUCCION Y EDO. DE COSTO DE LO VENDIDO
4)ELABORAR EL ESTADO DE RESULTADOS
5)ELABORAR EL BALANCE GENERAL
6)ELABORAR EL ESTADO DE DESVIACION
ESQUEMAS DE MAYOR
DESVIACION DESVIACION
MAREIALES PRECIO MAREIALES CANTIDAD
DESVIACION DESVIACION
G.I.F. EN PRESUPUESTO G.I.F. EN CAPACIDAD
-$ 3,200.00 $ -
-$ 3,200.00
DESVIACION DESVIACION
SUELDOS Y S. PRECIO SUELDOS Y S. CANTIDAD
16) $ 2,800.00 $ 2,800.00 (21 17) -$ 85,200.00 -$ 85,200.00 (21
DESVIACION
G.I.F. EN EFICIENCIA COSTOS INDIRECTOS
20) -$ 62,480.00 -$ 62,480.00 (21 5) $ 30,000.00 $ 30,000.00 (6
ESTADO DE DESVIACIONES
MATERIALE
S
EN PRECIO $ 17,500.00
EN
CANTIDAD -$ 62,424.00 -$ 44,924.00
EN PRECIO $ 2,800.00
EN PRESUPUESTO $ 3,600.00
EN CAPACIDAD -$ 4,400.00
ESTADO DE RESULTADOS
VENTAS $ 575,000.00
COSTO DE DISTRIBUCION
DRA. VIRGINIA HERNNDEZ SILVA 245
COSTO DE VENTA $ 10,000.00
COSTO DE DESVIACION
MATERIALES A $ 10.00
MATERIALES B $ 10.00
MATERIALES C $ 10.00
MATERIALES D $ 10.00 $ 40.00
BANCOS $ -
INV. PROD. EN PROC. $ -
MAQ. EQUIPO $ -
INV. MATERIALES $ -
EQUIPO DE OFICINA $ -
DEP. MAQUINARIA Y EQ. $ -
CLIENTES $ -
INV. ART. TERMINADOS $ -
EQUIPO DE TRANSPORTE $ -
DEP. EQU. DE OFICINA $ -
DEUDORES DIVERSOS $ -
DEP. EQU. DE TRANSP. $ -
PROVEEDORES $ -
ACREEDORES HIPRS. $ -
UTDS. POR APLICAR $ -
CAPITAL SOCIAL $ -
SUMAS IGUALES $ - $ -
TOTAL $ 144,000.00
ESTANDAR REAL
UNIDADES PRECIO
CONCEPTO A ESTD. TOTAL PRECIO REAL TOTAL DESVIACION
TOTAL -$ 21,384.00
CEDULA #7 1,200
CEDULA #8 85
TOTAL 1,285
REAL $ 1,400.00
ESTANDAR $ 5,109.60 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 3,709.60 $ 30.00 -$ 111,288.00
REAL 1,400
ESTANDAR 5,110 COSTO ESTDR. DESVIACION
SE PIDE:
1) DETERMINACION DE LAS DESVIACIONES ENTRE LOS COSTOS REALES Y LOS COSTOS ESTANDAR
2) REGISTRAR LAS OPERACIONES EN ESQUEMAS DE MAYOR
3) ELABORAR EL ESTADO DE COSTO DE PRODUCCION Y EDO. DE COSTO DE LO VENDIDO
4)ELABORAR EL ESTADO DE RESULTADOS
5)ELABORAR EL BALANCE GENERAL
6)ELABORAR EL ESTADO DE DESVIACION
ESQUEMAS DE MAYOR
BANCOS INV. PROD. EN PROC.
A) $ - $ 25,260.00 (1 A) $ - ------------------
9) $ 402,500.00 $ 39,800.00 (3 8) $ 19,483.20
$ 22,000.00 (5
$ 144,000.00 (11
$ 402,500.00 $ 231,060.00 $ 19,483.20 $ -
$ 171,440.00 $ 19,483.20
DESVIACION DESVIACION
MAREIALES PRECIO MAREIALES CANTIDAD
DESVIACION DESVIACION
G.I.F. EN PRESUPUESTO G.I.F. EN CAPACIDAD
DESVIACION DESVIACION
SUELDOS Y S. PRECIO SUELDOS Y S. CANTIDAD
16) $ 2,800.00 $ 2,800.00 (21 17) -$ 111,288.00 -$ 111,288.00 (21
DESVIACION
G.I.F. EN EFICIENCIA COSTOS INDIRECTOS
20) -$ 81,611.20 -$ 81,611.20 (21 5) 00 $ 30,000.00 (6
ESTADO DE DESVIACIONES
MATERIALE
S
EN PRECIO -$ 82,300.00
EN
CANTIDAD -$ 21,384.00 -$ 103,684.00
MANO DE OBRA DIRECTA
EN PRECIO $ 2,800.00
EN TIEMPO -$ 111,288.00 -$ 108,488.00
GTOS. IND. DE
FABRICACION
EN PRESUPUESTO $ 3,600.00
EN CAPACIDAD -$ 4,400.00
EN EFICIENCIA -$ 81,611.20 -$ 82,411.20
DESVIACION TOTAL -$ 294,583.20
ESTADO DE RESULTADOS
VENTAS $ 575,000.00
COSTO DE LO VENDIDO $ 285,200.00
PERDIDA BRUTA $ 289,800.00
COSTO DE DISTRIBUCION
COSTO DE VENTA $ 70,000.00
COSTO DE ADMON. $ 50,000.00
COSTOS FINANCIEROS $ 24,000.00 $ 144,000.00
PERDIDA DE OPERACIN $ 145,800.00
COSTO DE DESVIACION
DESVIACION ENTRE C.R. Y C. ESTD. -$ 294,583.20
PROVISION ISR $ 60,000.00
PROVISION PTU $ 12,000.00 -$ 222,583.20
PERDIDA DEL EJERCICIO -$ 76,783.20
MATERIALES A $ 30.00
MATERIALES B $ 34.00
MATERIALES C $ 40.00
MATERIALES D $ 36.00 $ 140.00
BANCOS $ 800,000.00
INV. PROD. EN PROC. $ 1,735,000.00
MAQ. EQUIPO $ 2,000,000.00
INV. MATERIALES $ 1,200,000.00
EQUIPO DE OFICINA $ 700,000.00
DEP. MAQUINARIA Y EQ. -$ 480,000.00
CLIENTES $ 200,000.00
INV. ART. TERMINADOS $ 130,000.00
EQUIPO DE TRANSPORTE $ 980,000.00
DEP. EQU. DE OFICINA -$ 70,000.00
DEUDORES DIVERSOS $ 180,000.00
DEP. EQU. DE TRANSP. -$ 206,000.00
PROVEEDORES $ 600,000.00
ACREEDORES HIPRS. $ 3,000,000.00
UTDS. POR APLICAR $ 584,000.00
CAPITAL SOCIAL $ 2,985,000.00
SUMAS IGUALES $ 7,169,000.00 $ 7,169,000.00
ESTANDAR REAL
PRECIO
CONCEPTO UNDS A PRECIO ESTD. TOTAL REAL TOTAL DESVIACION
MATERIAL A 400 $ 10.00 $ 4,000.00 $ 30.00 $ 12,000.00 $ 8,000.00
MATERIAL B 500 $ 11.00 $ 5,500.00 $ 34.00 $ 17,000.00 $ 11,500.00
MATERIAL C 600 $ 12.00 $ 7,200.00 $ 40.00 $ 24,000.00 $ 16,800.00
MATERIAL D 700 $ 13.00 $ 9,100.00 $ 36.00 $ 25,200.00 $ 16,100.00
TOTAL $ 25,800.00 TOTAL $ 78,200.00 $ 52,400.00
TOTAL -$ 101,644.00
CEDULA #7 1,200
CEDULA #8 85
TOTAL 1,285
REAL $ 1,600.00
ESTANDAR $ 5,109.60 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 3,509.60 $ 30.00 -$ 105,288.00
REAL 1,600
ESTANDAR 5,110 COSTO ESTDR. DESVIACION
DIFERENCIA - 3,510 $ 22.00 -$ 77,211.20
SE PIDE:
1) DETERMINACION DE LAS DESVIACIONES ENTRE LOS COSTOS REALES Y LOS COSTOS ESTANDAR
2) REGISTRAR LAS OPERACIONES EN ESQUEMAS DE MAYOR
3) ELABORAR EL ESTADO DE COSTO DE PRODUCCION Y EDO. DE COSTO DE LO VENDIDO
4)ELABORAR EL ESTADO DE RESULTADOS
5)ELABORAR EL BALANCE GENERAL
6)ELABORAR EL ESTADO DE DESVIACION
ESQUEMAS DE MAYOR
$ 19,000.00 (5
$ 20,000.00 (11
$ 1,117,100.00 $ 1,762,943.20
5) -$ 1,200.00
$ 700,000.00 $ - -$ 481,200.00 $ -
$ 700,000.00 -$ 481,200.00
5) -$ 2,400.00
-$ 72,400.00
$ 9,600.00 (1
$ - $ 609,600.00
$ 609,600.00
$ 11,844.00 (8
-$ 52,400.00 (14
-$ 101,644.00 (15
$ 25,800.00 $ 25,800.00
DESVIACION DESVIACION
DESVIACION DESVIACION
$ 6,811.20 (8
-$ 1,400.00 (18
-$ 8,800.00 (19
-$ 77,211.20 (20
$ 25,000.00 $ 25,000.00
DESVIACION DESVIACION
SUELDOS Y S. PRECIO SUELDOS Y S. CANTIDAD
16) $ - $ - (21 17) -$ 105,288.00 -$ 105,288.00 (21
DESVIACION
G.I.F. EN EFICIENCIA COSTOS INDIRECTOS
20) -$ 77,211.20 -$ 77,211.20 (21 5) $ 25,000.00 $ 25,000.00 (6
ESTADO DE RESULTADOS
VENTAS $ 575,000.00
COSTO DE LO VENDIDO $ 400,200.00
PERDIDA BRUTA $ 174,800.00
COSTO DE DISTRIBUCION
COSTO DE VENTA $ 10,000.00
COSTO DE ADMON. $ 6,000.00
COSTOS FINANCIEROS $ 4,000.00 $ 20,000.00
PERDIDA DE OPERACIN $ 154,800.00
COSTO DE DESVIACION
DESVIACION ENTRE C.R. Y C. ESTD. -$ 241,943.20
PROVISION ISR $ 60,000.00
PROVISION PTU $ 12,000.00 -$ 169,943.20
PERDIDA DEL EJERCICIO -$ 15,143.20
MATERIALES A $ 1,250.00
MATERIALES B $ 1,290.00
MATERIALES C $ 1,340.00
MATERIALES D $ - $ 3,880.00
BANCOS $ 4,206,700.00
MAQ. EQUIPO $ -
EQUIPO DE OFICINA $ -
EQUIPO DE TRANSPORTE $ -
PROVEEDORES $ 150,000.00
MATERIAL D - $ - $ -
TOTAL $ 3,723,750.00
60% CONTADO $ 2,234,250.00
40% CREDITO $ 1,489,500.00
TOTAL $ 549,440.00
ESTANDAR REAL
PRECIO
CONCEPTO UNdS A PRECIO ESTD. TOTAL REAL TOTAL DESVIACION
DRA. VIRGINIA HERNNDEZ SILVA 271
MATERIAL A 830 $ 1,275.00 $1,058,250.00 $ 1,250.00 $ 1,037,500.00 -$ 20,750.00
MATERIAL D - $ - $ - $ - $ - $ -
TOTAL $2,644,250.00 TOTAL $2,605,500.00 -$ 38,750.00
UNDS.
CONCEPTO UNDS A TERMINS. DIFR. EN UNDS PRECIO REAL DESVIACION
CEDULA #7 1,750
CEDULA #8 88
TOTAL 1,838
REAL $ 13,500.00
ESTANDAR $ 18,300.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 4,800.00 $ 140.00 -$ 672,000.00
REAL $ 13,500.00
ESTANDAR $ 12,200.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 1,300.00 $ 120.00 -$ 156,000.00
REAL 13,500
ESTANDAR 18,300 COSTO ESTDR. DESVIACION
DIFERENCIA - 4,800 $ 120.00 -$ 576,000.00
SE PIDE:
1) DETERMINACION DE LAS DESVIACIONES ENTRE LOS COSTOS REALES Y LOS COSTOS ESTANDAR
2) REGISTRAR LAS OPERACIONES EN ESQUEMAS DE MAYOR
3) ELABORAR EL ESTADO DE COSTO DE PRODUCCION Y EDO. DE COSTO DE LO VENDIDO
4)ELABORAR EL ESTADO DE RESULTADOS
5)ELABORAR EL BALANCE GENERAL
6)ELABORAR EL ESTADO DE DESVIACION
ESQUEMAS DE MAYOR
DESVIACION DESVIACION
MAREIALES PRECIO MAREIALES CANTIDAD
DESVIACION DESVIACION
G.I.F. EN PRESUPUESTO G.I.F. EN CAPACIDAD
1) $ 3,723,750.00
$ - $ - $ 5,874,750.00 $ 2,644,250.00
$ - $ 3,230,500.00
9) $ 6,840,000.00 7) $ 11,340,000.00
$ 8,830,300.00 -$ 972,000.00
5) -$ 45,000.00
-$ 1,118,900.00 $ -
-$ 1,118,900.00
$ 112,000.00 (8
$ 135,000.00 (16
-$ 672,000.00 (17
$ 2,025,000.00 $ 2,025,000.00
DESVIACION DESVIACION
DESVIACION
ESTADO DE RESULTADOS
VENTAS $ 22,800,000.00
COSTO DE LO VENDIDO $ 12,312,000.00
PERDIDA BRUTA $ 10,488,000.00
COSTO DE DISTRIBUCION
COSTO DE VENTA $ 600,000.00
COSTO DE ADMON. $ 400,000.00
COSTOS FINANCIEROS $ 200,000.00 $ 1,200,000.00
PERDIDA DE OPERACIN $ 9,288,000.00
COSTO DE DESVIACION
DESVIACION ENTRE C.R. Y C. ESTD. -$ 5,897,690.00
PROVISION ISR $ 465,000.00
PROVISION PTU $ 330,000.00 -$ 5,102,690.00
PERDIDA DEL EJERCICIO $ 4,185,310.00
TOTAL $4,083,500.00
ESTANDAR REAL
PRECIO
CONCEPTO UNDS A ESTD. TOTAL PRECIO REAL TOTAL DESVIACION
MATERIAL D - $ - $ - $ - $ - $ -
CEDULA #7 1,800
CEDULA #8 343
TOTAL 2,143
REAL $ 12,000.00
ESTANDAR $ 21,432.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 9,432.00 $ 165.00 -$ 1,556,280.00
REAL $ 12,000.00
ESTANDAR $ 11,500.00 COSTO ESTDR. DESVIACION
DIFERENCIA -$ 500.00 $ 200.00 -$ 100,000.00
REAL 12,000
ESTANDAR 21,432 COSTO ESTDR. DESVIACION
SE PIDE:
1) DETERMINACION DE LAS DESVIACIONES ENTRE LOS COSTOS REALES Y LOS COSTOS ESTANDAR
2) REGISTRAR LAS OPERACIONES EN ESQUEMAS DE MAYOR
3) ELABORAR EL ESTADO DE COSTO DE PRODUCCION Y EDO. DE COSTO DE LO VENDIDO
4)ELABORAR EL ESTADO DE RESULTADOS
5)ELABORAR EL BALANCE
GENERAL
6)ELABORAR EL ESTADO DE DESVIACION
ESQUEMAS DE MAYOR
DESVIACION DESVIACION
MAREIALES PRECIO MAREIALES CANTIDAD
DESVIACION DESVIACION
G.I.F. EN PRESUPUESTO G.I.F. EN CAPACIDAD
$ 2,160,000.00 $ 2,160,000.00
DESVIACION DESVIACION
SUELDOS Y S. PRECIO SUELDOS Y S. CANTIDAD
16) $ 180,000.00 $ 180,000.00 (21 17) -$ 1,556,280.00 -$ 1,556,280.00 (21
DESVIACION
G.I.F. EN EFICIENCIA COSTOS INDIRECTOS
20) -$ 1,886,400.00 -$1,886,400.00 (21 5) $ 1,280,000.00 $ 1,280,000.00 (6
ESTADO DE DESVIACIONES
MATERIALE
S
EN PRECIO $ 126,800.00
EN
CANTIDAD -$ 4,105,316.00 -$ 3,978,516.00
MANO DE OBRA DIRECTA
EN PRECIO $ 180,000.00
EN TIEMPO -$ 1,556,280.00 -$ 1,376,280.00
GTOS. IND. DE
FABRICACION
EN PRESUPUESTO -$ 1,020,000.00
EN CAPACIDAD -$ 100,000.00
EN EFICIENCIA -$ 1,886,400.00 -$ 3,006,400.00
DESVIACION TOTAL -$ 8,361,196.00
ESTADO DE RESULTADOS
VENTAS $ 9,240,000.00
COSTO DE LO VENDIDO $ 9,036,000.00
PERDIDA BRUTA $ 204,000.00
COSTO DE DISTRIBUCION
COSTO DE VENTA $ 200,000.00
COSTO DE ADMON. $ 470,000.00
COSTOS FINANCIEROS $ 430,000.00 $ 1,100,000.00
PERDIDA DE OPERACIN -$ 896,000.00
COSTO DE DESVIACION
DESVIACION ENTRE C.R. Y C. ESTD. -$ 8,361,196.00
PROVISION ISR $ 170,000.00
PROVISION PTU $ 130,000.00 -$ 8,061,196.00