Item Descripcin Und. Metrado Precio S/. Parcial S/. Subtotal S/.
02 MOVIMIENTO DE TIERRAS
04 TERRAPLEN 1,338,221.74
04.01 RELLENO CON MATERIAL PROPIO m3 91,195.93 5.58 508,873.29
04.02 RELLENO CON MATERIAL EXCEDENTE DE CORTE (MATERIAL CONSIDERADO EN TRASP.) m3 84,945.00 5.58 473,993.10
04.03 PREPARACION DE TERRENO EN ZONAS DE RELLENO, INVOLUCRANDO SUELO EXISTENTE m2 29,764.78 1.44 42,861.28
04.04 PREPARACION DE TERRENO EN ZONAS DE RELLENO, EMPLEANDO MATERIAL ADICIONADO m3 26,436.99 9.05 239,254.76
04.05 REMOCIN DE DERRUMBES (SOLO REFINE) m3 43,594.83 1.68 73,239.31
05 PAVIMENTOS 6,827,681.70
05.01 SUB BASE GRANULAR m3 90,238.57 24.77 2,235,209.38
05.02 BASE GRANULAR m3 54,700.30 38.90 2,127,841.67
05.03 IMPRIMACION BITUMINOSA m2 328,698.64 0.47 154,488.36
05.04 TRATAMIENTO SUPERFICIAL BICAPA m2 327,075.63 2.49 814,418.32
05.05 ASFALTO LIQUIDO RC-250 gln 84,146.85 4.34 365,197.33
05.06 ASFALTO DILUIDO MC-30 gln 215,869.91 4.59 990,842.89
05.07 KEROSENE gln 21,036.71 6.64 139,683.75
Item Descripcin Und. Metrado Precio S/. Parcial S/. Subtotal S/.
10.07 ALIVIADEROS Y EMBOQUILLADO DE PIEDRA (E=0.15M) m2 855.19 41.49 35,481.83
13 BADENES 1,549,610.65
13.01 EXCAVACION PARA ESTRUCTURAS (MAQUINARIA) m3 5,085.30 4.55 23,138.12
13.02 EXCAVACIN PARA ESTRUCTURAS (MANUAL) m3 395.18 21.17 8,365.96
13.03 BASE e=0.20m m3 1,424.94 33.67 47,977.73
13.04 ENCOFRADO Y DESENCOFRADO m2 1,798.90 30.62 55,082.32
13.05 ACERO DE REFUERZO f'y = 4200 kg/cm2 kg 119,982.53 3.57 428,337.63
13.06 CONCRETO fc 245 kg/cm2 m3 1,713.93 308.15 528,147.53
13.07 JUNTA ASFALTICA LONGITUDINAL m 1,311.50 27.84 36,512.16
13.08 ALIVIADEROS Y EMBOQUILLADO DE PIEDRA (E=0.30M) m2 4,340.00 39.38 170,909.20
13.09 ENROCADO CON MORTERO m3 2,000.00 125.57 251,140.00
Item Descripcin Und. Metrado Precio S/. Parcial S/. Subtotal S/.
16.03 ZANJA LATERAL (TIERRA) m3 621.00 4.55 2,825.55
17 BAJADAS 45,822.92
17.01 EXCAVACION PARA ESTRUCTURAS m3 360.38 21.17 7,629.24
17.02 MAMPOSTERA DE PIEDRA (E=0.15 M) m2 1,369.44 27.89 38,193.68
18 RAPIDAS
18.01 EXCAVACION PARA ESTRUCTURAS m3 141.40 21.17 2,993.44
18.02 CONCRETO CICLOPEO fc 140 kg/cm2 + 30% PM m3 22.01 191.10 4,206.11
18.03 ENCOFRADO Y DESENCOFRADO m2 90.34 30.62 2,766.21
18.04 MAMPOSTERA DE PIEDRA (E=0.15 M) m2 15.00 27.89 418.35
18.05 RELLENO DE ESTRUCTURAS m3 119.19 50.40 6,007.18
19 MUROS 5,250,743.61
19.01 EXCAVACION PARA ESTRUCTURAS (MAQUINARIA) m3 24,009.18 4.55 109,241.77
19.02 EXCAVACIN PARA ESTRUCTURAS (MANUAL) m3 79.10 21.17 1,674.55
19.03 ENCOFRADO Y DESENCOFRADO m2 33,458.86 30.62 1,024,510.29
19.04 ACERO DE REFUERZO f'y = 4200 kg/cm2 kg 15,871.41 7.07 112,210.87
19.05 SOLADO DE CONCRETO fc 100 kg/cm2, E=0.075 M m3 9.45 15.01 141.84
19.06 CONCRETO fc 210 kg/cm2 m3 276.83 289.75 80,211.49
19.07 CONCRETO CICLOPEO fc 175 kg/cm2 + 30% PM, PARA MUROS m3 13,785.89 209.09 2,882,491.74
19.08 RELLENO DE ESTRUCTURAS m3 10,909.47 50.40 549,837.29
19.09 FILTRO m3 3,587.36 79.70 285,912.59
19.10 DREN PVC 4" m 5,137.05 14.81 76,079.71
19.11 LLORADORES PVC 4" m 3,317.70 14.81 49,135.14
19.12 GEOTEXTIL m2 11,467.97 5.11 58,601.33
19.13 MATERIAL IMPERMEABLE m3 366.80 49.72 18,237.30
19.14 ENROCADO m3 70.02 35.10 2,457.70
21 GAVIONES 1,023,408.03
21.01 EXCAVACION PARA GAVIONES m3 32,939.29 5.92 195,000.60
21.02 GAVIONES m3 5,217.00 158.79 828,407.43
22 SEALIZACIN 187,149.91
22.02 SEAL PREVENTIVA (0.75 m x 0.75 m) und 302.00 514.76 155,457.52
22.03 SEAL REGLAMENTARIA und 43.00 648.33 27,878.19
Item Descripcin Und. Metrado Precio S/. Parcial S/. Subtotal S/.
24.06 RESTAURACION DE AREA AFECTADA POR PATIO DE MAQUINAS m2 600.00 2.22 1,332.00
24.07 SELLADO DE LETRINAS und 5.00 360.63 1,803.15
25 TRANSPORTES 11,714,699.33
25.01 TRANSPORTE DE MATERIALES GRANULARES PARA D <= 1.00 KM M3K 219,051.26 4.35 952,872.98
25.02 TRANSPORTE DE MATERIALES GRANULARES PARA D > 1.00 KM M3K 3,575,838.21 0.91 3,254,012.77
25.03 TRANSPORTE DE ESCOMBROS PARA D <= 1.00 KM M3K 1,121,706.92 4.35 4,879,425.10
25.04 TRANSPORTE DE ESCOMBROS PARA D > 1.00 KM M3K 730,610.21 0.91 664,855.29
25.05 TRANSPORTE DE MATERIAL PARA RELLENO D <= 1.00 KM M3K 204,157.53 4.35 888,085.26
25.06 TRANSPORTE DE MATERIAL PARA RELLENO D >= 1.00 KM M3K 1,181,810.91 0.91 1,075,447.93
26 VARIOS 614,236.24
26.01 MANTENIMIENTO DE TRANSITO TEMPORAL Y SEGURIDAD VIAL GLB 1.00 614,236.24 614,236.24
-----------------------
Sub-Total 67,969,334.86
IGV 19.00% 12,914,173.62
-------------------------
SON : OCHENTA MILLONES OCHOCIENTOS OCHENTITRES MIL QUINIENTOS OCHO Y 48/100 NUEVOS SOLES