Está en la página 1de 10

COSTOS POR PROCESOS

EJERCICIOS REPASO PA EXAMEN


CASO 1 3 DPTOS RENOVACION SAS

DEPARTAMENTO 1

PASO 1: CORRIENE FISICA

ORIGEN

I.I.P.P 8,000
(+) UND PUESTAS EN PCC 99,000
TOTAL UND ORIGEN 107,000

PASO 2: PCC EQUIVALENTE

ELEMENTO I.F.P.P % AVANCE UND EQUIV UND T Y T


M.P. 12,840 70% 8,988 94,160
M.O.D. 12,840 80% 10,272 94,160
C.I.F. 12,840 50% 6,420 94,160

PASO 3: PCC EQUIVALENTE TOTAL

DEL I.I.P.P

M.P 2,500,000
M.O.D. 1,800,000
C.I.F. 645,000
4,945,000

DEL PERIODO

M.P 19,900,000
M.O.D. 11,000,000
C.I.F. 4,635,000
35,535,000

TOTA VALORIZACIONES 40,480,000

PASO 4: COSTO UNITARIO


ELEMENTO COSTOS: I.I.P.P + PERIODO TOTAL PCC EQUIV COSTO UNITARIO
M.P. 22,400,000 103,148 217.163687
M.O.D. 12,800,000 104,432 122.567795
C.I.F. 5,280,000 100,580 52.495526
C.U.P. 392.227008

PASO 5: VALORIZACIONES

5.1

UNDS T Y T (DPTO 2 ) 36,932,095

5.2

UND I.F.P.P.

ELEMENTO UNDS EQUIV COSTO UNITARIO TOTAL


M.P. 8,988 217.163687 1,951,867
M.O.D. 10,272 122.567795 1,259,016
C.I.F. 6,420 52.495526 337,021
INV FINAL 3,547,905

TOTAL VALORIZACIONES 40,480,000


DESTINO

UND T Y T (DPTO 2) 94,160


I.F.P.P (70% 80% 50% ) 12,840
TOTAL UND DESTINO 107,000

TOTAL UND EQUIV


103,148
104,432
100,580
DEPARTAMENTO 2

PASO 1: CORRIENE FISICA

ORIGEN

I.I.P.P -
UND RECIBIDASDPTO 1 94,160
UND PUESTAS EN PCC -
TOTAL UND ORIGEN 94,160

PASO 2: PCC EQUIVALENTE

ELEMENTO I.F.P.P % AVANCE UND EQUIV


DPTO 1 9,160 100% 9,160
M.P. 9,160 90% 8,244
M.O.D. 9,160 40% 3,664
C.I.F. 9,160 60% 5,496

PASO 3: PCC EQUIVALENTE TOTAL

3.1 COSTOS DEL DEPTO ANTERIOR (D1)

DEL I.I.P.P 2,350,000


(+) COSTO TRANSFERIDO 36,932,095
39,282,095

3.2 COSTOS DEL DPTO ACTUAL (D2)

DEL I.I.P.P

M.P 3,250,000
M.O.D. 2,340,000
C.I.F. 838,500
6,428,500

DEL PERIODO ACTUAL

M.P 25,870,000
M.O.D. 14,300,000
C.I.F. 6,025,500
46,195,500
TOTAL VALORIZACIONES 91,906,095

PASO 4: COSTO UNITARIO

ELEMENTO COSTOS: I.I.P.P + PERIODO ACT TOTAL PCC EQUIV COSTO UNITARIO
DPTO 1 39,282,095 94,160 417.184528
M.P. 29,120,000 93,244 312.298915
M.O.D. 16,640,000 88,664 187.674817
C.I.F. 6,864,000 90,496 75.848656
C.U.P. 993.006916

PASO 5: VALORIZACIONES

5.1

UNDS T Y T (DPTO 3 ) 84,405,588

5.2

UND I.F.P.P.

ELEMENTO UNDS EQUIV COSTO UNITARIO TOTAL


DPTO 1 9,160 417.184528 3,821,410
M.P. 8,244 312.298915 2,574,592
M.O.D. 3,664 187.674817 687,641
C.I.F. 5,496 75.848656 416,864
INV FINAL 7,500,507

TOTAL VALORIZACIONES 91,906,095


DESTINO

UND T Y T (DPTO 3) 85,000


I.F.P.P (100% 90% 40% 60% ) 9,160
TOTAL UND DESTINO 94,160

UND T Y T TOTAL UND EQUIV


85,000 94,160
85,000 93,244
85,000 88,664
85,000 90,496
DEPARTAMENTO 3

PASO 1: CORRIENE FISICA

ORIGEN

I.I.P.P 1,000
UND RECIBIDAS DPTO 2 85,000
UND PUESTAS EN PCC -
TOTAL UND ORIGEN 86,000

PASO 2: PCC EQUIVALENTE

ELEMENTO UND T Y T (ALMACEN) % AVANCE UND EQUIV


DPTO 2 - 100% 0
M.P. - 40% 0
M.O.D. - 80% 0
C.I.F. - 80% 0

PASO 3: PCC EQUIVALENTE TOTAL

3.1 COSTOS DEL DEPTO ANTERIOR (D3)

DEL I.I.P.P 3,300,000


(+) COSTO TRANSFERIDO 84,405,588
87,705,588

3.2 COSTOS DEL DPTO ACTUAL (D3)

DEL I.I.P.P

M.P 2,850,000
M.O.D. 1,995,000
C.I.F. 726,750
5,571,750

DEL PERIODO ACTUAL

M.P 46,566,000
M.O.D. 25,740,000
C.I.F. 10,845,900
83,151,900

TOTAL VALORIZACIONES 176,429,238


PASO 4: COSTO UNITARIO

ELEMENTO COSTOS: I.I.P.P + PERIODO ACT TOTAL PCC EQUIV COSTO UNITARIO
DPTO 1 87,705,588 86,000 1,019.832417
M.P. 49,416,000 86,000 574.604651
M.O.D. 27,735,000 86,000 322.500000
C.I.F. 11,572,650 86,000 134.565698
C.U.P. 2,051.502766

PASO 5: VALORIZACIONES

5.1 176,429,238

5.2 I.F.P.P NO HAY


DESTINO

UND T Y T (ALMACEN) 86,000


I.F.P.P (100% 40% 80% 80% ) -
TOTAL UND DESTINO 86,000

UND T Y T TOTAL UND EQUIV


86,000 86,000
86,000 86,000
86,000 86,000
86,000 86,000

También podría gustarte