PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD PEATONAL Y

VEHICULAR EN LA URBANIZACION ALAMEDA DE SAN ANDRES DEL


DISTRITO DE TRUJILLO, PROVINCIA DE TRUJILLO - LA LIBERTAD
PLAN I LLA D E M E TRAD O S

PARTIDA: 01.01. OBRAS PROVISIONALES


PARTIDA: 01.01. MOVILIZACION Y DESMOVILIZACION DE EQUIPOS UNIDAD : ( Glb.)
VECES QUE GLOBAL
DESCRIPCION SE REPITE ( Glb. )
(1) (2) = (1)

Movilizacion y desmovilizacion de equipo 1 1.00

T O TAL: 1.00

PARTIDA: 01.02. CARTEL DE OBRA DE 6.00 x 3.60m UNIDAD : ( Glb.)


VECES QUE GLOBAL
DESCRIPCION SE REPITE ( Glb. )
(1) (2) = (1)

Cartel de Obra 1 1.00

T O TAL: 1.00

PARTIDA: 01.03. DESVIO Y MANTENIMIENTO DE TRAFICO UNIDAD : ( Glb.)


VECES QUE GLOBAL
DESCRIPCION SE REPITE ( Glb. )
(1) (2) = (1)

Via a intervenir 1 1.00

T O TAL: 1.00

PARTIDA: 02.00. TRABAJOS PRELIMINARES


PARTIDA: 02.01. DEMOLICION DE VEREDAS DE CONCRETO A PULSO, e=10 cm. UNIDAD : ( m )
DIMENSIONES VECES QUE REA
DESCRIPCION LONGITUD ANCHO SE REPITE ( m )
(m) (m) (4)
(1) (2) (3) (1) x (2) x (3)

De Av. Cesar Vallejo a Av. Camino Rel


LADO IZQUIERDO
Martillo 1 A= 30.92 1 30.92
Rampa 1 3.60 0.60 1 2.16
3.60 0.70 1 2.52
Rampa 2 2.40 0.60 1 1.44
Rampa 3 2.53 0.60 1 1.52
D-1 3.70 1.76 1 6.51
D-2 triangulo 1.71 1.40 1 1.20
D-3 7.25 1.56 1 11.30
D-4 triangulo 1.43 1.51 1 1.08
D-5 143.40 1.50 1 215.10
Rampa 4 7.04 0.60 1 4.22
Rampa 5 3.50 0.57 1 2.00
Martillo 2 A= 15.19 1 15.19
LADO DERECHO
Martillo 3 A= 5.63 1 5.63
D-6 32.04 1.47 1 47.10
Martillo 4 A= 15.16 1 15.16
Rampa 6 2.46 0.45 1 1.11
Rampa 7 2.60 0.53 1 1.38
Martillo 5 A= 56.20 1 56.20
D-7 65.00 1.54 1 100.10
Rampa 8 3.00 0.70 1 2.10
Martillo 6 A= 9.15 1 9.15
D-8 6.37 1.71 1 10.89
Martillo 7 A= 7.24 1 7.24
Martillo 8 A= 2.03 1 2.03
D-9 35.71 1.58 1 56.24
D-10 36.92 1.41 1 52.06
Rampa 9 3.18 0.70 1 2.23
Rampa 10 2.18 0.70 1 1.53
Rampa 11 2.70 0.70 1 1.89
Rampa 12 4.20 0.70 1 2.94
D-11 21.41 1.32 1 28.26
D-12 12.26 1.22 1 14.96
D-13 17.97 1.20 1 21.56
Rampa 13 3.65 0.70 1 2.56
Rampa 14 6.12 0.70 1 4.28
Berma Central
B-1 A= 8.97 1 8.97
B-2 A= 7.69 1 7.69
PLAN I LLA D E M E TRAD O S

B-3 A= 7.42 1 7.42


B-4 A= 7.44 1 7.44
B-5 A= 6.88 1 6.88
B-6 prom 5.79 1.80 1 10.42
B-7 6.83 1.60 1 10.93
De Av. Camino Real a calle Tadeo Almeira
LADO IZQUIERDO
Martillo 9 A= 15.12 1 15.12
D-15 52.08 1.55 1 80.72
Rampa 15 2.65 0.50 1 1.33
Rampa 16 2.45 0.50 1 1.23
Rampa 17 2.35 0.50 1 1.18
Rampa 18 2.25 0.50 1 1.13
Rampa 19 2.30 0.50 1 1.15
Rampa 20 2.30 0.50 1 1.15
Rampa 21 2.20 0.50 1 1.10
D-16 29.20 1.50 1 43.65
D-17 28.71 1.45 1 41.63
Rampa 22 2.31 0.50 1 1.16
Rampa 23 2.31 0.50 1 1.16
Rampa 24 4.60 0.50 1 2.30
Rampa 25 2.60 0.50 1 1.30
Rampa 26 3.90 0.50 1 1.95
Rampa 27 4.50 0.50 1 2.25
D-18 42.24 1.44 1 60.83
D-19 54.91 1.44 1 79.07
D-20 3.70 2.00 1 7.40
Martillo 10 A= 6.36 1 6.36
D-21 44.87 2.15 1 96.47
D-22 8.20 2.10 1 17.22
D-23 16.55 2.15 1 35.58
Rampa 28 4.15 0.50 1 2.08
D-24 3.40 4.72 1 16.05
D-25 2.20 1.00 1 2.20
LADO DERECHO
D-14 10.23 1.42 1 14.53
Martillo 11 A= 7.02 1 7.02
Martillo 12 A= 8.61 1 8.61
D-26 39.80 1.47 1 58.51
Martillo 13 A= 1.33 1 1.33
D-27 3.70 1.30 1 4.81
D-28 28.39 1.20 1 34.07
D-29 31.90 1.20 1 38.28
D-30 60.79 1.50 1 91.19
D-31 33.76 1.50 1 50.64
Martillo 14 A= 27.63 1 27.63
D-32 42.02 1.41 1 59.25
D-33 6.97 2.00 1 13.94
D-34 2.00 1.00 2 4.00
Martillo 15 A= 19.30 1 19.30
Martillo 16 A= 14.34 1 14.34
D-35 21.10 1.50 1 31.65
Berma Central
B-8 7.10 1.60 1 11.36
B-9 6.55 1.70 1 11.14
B-10 A= 15.60 1 15.60
B-11 A= 12.92 1 12.92
B-12 A= 17.79 1 17.79
B-13 A= 18.14 1 18.14
B-14 6.78 1.20 1 8.14
B-15 A= 19.58 1 19.58
B-16 A= 18.23 1 18.23
De calle Tadeo Almeira a carretera Industrial
LADO IZQUIERDO
D-36 80.83 1.20 1 97.00
Martillo 17 A= 1.21 1 1.21
D-37 13.59 1.50 1 20.39
Rampa 29 2.85 0.50 1 1.43
D-38 6.30 1.00 1 6.30
D-39 5.20 1.80 1 9.36
D-40 3.80 1.00 1 3.80
D-41 24.10 1.37 1 33.02
D-42 4.60 2.40 1 11.04
D-43 4.30 1.27 1 5.46
D-44 59.57 1.35 1 80.42
D-45 10.41 1.20 1 12.49
D-46 6.32 1.20 1 7.58
D-47 5.05 0.80 1 4.04
LADO DERECHO
D-48 21.84 1.50 1 32.76
D-49 2.30 1.50 1 3.45
PLAN I LLA D E M E TRAD O S

D-50 2.57 1.50 1 3.86


Martillo 18 A= 20.96 1 20.96
Martillo 19 A= 22.26 1 22.26
D-51 53.39 1.45 1 77.42
D-52 2.40 1.95 1 4.68
Martillo 20 A= 29.64 1 29.64
D-53 13.23 1.50 1 19.85
Martillo 21 A= 13.69 1 13.69
Martillo 22 A= 17.43 1 17.43
D-54 3.50 3.45 1 12.08
D-55 14.59 3.50 1 51.07
D-56 3.02 1.60 1 4.83
D-57 8.78 1.60 1 14.05
D-58 2.11 1.52 1 3.21
D-59 4.40 1.50 1 6.60
D-60 4.84 3.06 1 14.81
D-61 18.80 1.55 1 29.14
D-62 10.00 1.00 1 10.00

T O TAL: 2,621.61

PARTIDA: 02.02. DEMOLICION DE SARDINEL A PULSO UNIDAD : ( m )


DIMENSIONES LONGITUD VECES QUE LONGITUD
DESCRIPCION ALTO ANCHO SE REPITE (m)
( m. ) ( m. ) ( m. ) (5)
(1) (2) (3) (4) (3) x (4)

De Av. Cesar Vallejo a carretera Industrial


SD1 4.18 1 4.18
SD2 29.54 1 29.54
SD3 29.58 1 29.58
SD4 63.84 1 63.84
SD5 63.75 1 63.75
SD6 29.85 1 29.85
SD7 29.66 1 29.66
SD8 5.26 1 5.26
SD9 5.70 1 5.70
SD10 10.23 1 10.23
SD11 121.05 1 121.05
SD12 110.95 1 110.95
SD13 6.53 1 6.53
SD14 6.53 1 6.53
SD15 12.77 1 12.77
SD16 12.87 1 12.87
SD17 12.38 1 12.38
SD18 13.03 1 13.03
SD19 12.93 1 12.93
SD20 6.80 1 6.80
SD21 6.80 1 6.80
SD22 46.64 1 46.64
SD23 46.00 1 46.00
SD24 6.25 1 6.25
SD25 6.25 1 6.25
SD26 64.44 1 64.44
SD27 63.40 1 63.40
SD28 62.85 1 62.85
SD29 62.36 1 62.36
SD30 31.71 1 31.71
SD31 31.59 1 31.59
SD32 44.67 1 44.67
SD33 45.00 1 45.00
SD34 10.98 1 10.98
SD35 6.11 1 6.11
SD36 10.95 1 10.95
SD37 5.95 1 5.95
SD38 8.49 1 8.49
SD39 7.54 1 7.54
SD40 8.81 1 8.81
SD41 7.36 1 7.36
SD42 6.57 1 6.57
SD43 51.39 1 51.39
SD44 51.39 1 51.39
SD45 25.68 1 25.68
SD46 25.76 1 25.76
SD47 7.00 1 7.00
SD48 6.34 1 6.34
SD49 5.34 1 5.34
SD50 3.50 1 3.50
PLAN I LLA D E M E TRAD O S

T O TAL: 1,354.55
PLAN I LLA D E M E TRAD O S

PARTIDA: 02.03. DEMOLICION DE CARPETA ASFALTICA UNIDAD : ( m )


DIMENSIONES VECES QUE REA
DESCRIPCION LONGITUD ANCHO SE REPITE ( m )
(m) (m) (4)
(1) (2) (3) (1) x (2) x (3)

De Av. Cesar Vallejo a Av. Camino Real


PD1 9.41 0.96 1 4.52
PD2 A = 18.69 1 18.69
PD3 9.01 0.90 1 4.05
PD4 A = 4.61 1 4.61
PD5 51.92 9.65 1 500.77
PD6 63.90 9.94 1 635.17
PD7 42.45 10.42 1 442.12
PD8 19.60 9.23 1 180.81
PD9 55.44 7.32 1 405.54
PD10 69.02 6.51 1 449.32
PD11 50.58 9.03 1 456.48
PD12 82.93 9.15 1 758.39
PD13 97.94 8.98 1 879.50
PD14 69.11 8.80 1 607.82
DE LA AV. CAMINO REAL A AV. HONORIO DELGADO
PD15 10.12 6.96 1 70.44
PD16 10.92 7.12 1 77.75
PD17 19.95 8.09 1 161.40
PD18 20.38 8.70 1 177.31
PD19 6.48 8.61 1 55.76
PD20 25.30 8.93 1 225.93
PD21 31.43 9.16 1 287.74
PD22 32.32 9.13 1 295.08
PD23 60.14 9.02 1 542.46
PD24 26.76 8.81 1 235.62
PD25 20.63 8.51 1 175.56
PD26 12.96 7.44 1 96.42
PD27 43.49 6.46 1 280.95
PD28 15.57 6.81 1 105.95
PD29 7.81 7.21 1 56.31
PD30 13.96 7.30 1 101.91
PD31 AREA 191.83 1 191.83
PD32 AREA 147.70 1 147.70
PD33 AREA 84.54 1 84.54
PD34 AREA 80.92 1 80.92
PD35 13.85 7.81 1 108.17
PD36 24.02 7.18 1 172.34
PD37 27.56 6.83 1 188.10
PD38 28.81 7.04 1 202.82
PD39 122.62 6.99 1 856.50
PD40 65.91 7.26 1 478.51
PD41 39.96 7.84 1 313.29
PD42 16.54 7.22 1 119.42
PD43 17.99 7.90 1 142.03
PD44 4.56 9.79 1 44.62
PD45 3.15 8.79 1 27.69
PD46 17.98 7.21 1 129.64
PD47 77.14 6.84 1 527.64
PD48 3.48 6.61 1 23.00
PD49 AREA 2.18 1 2.18
PD50 30.26 9.04 1 273.55
PD51 AREA 2.71 1 2.71
PD52 AREA 2.86 1 2.86
PD53 AREA 2.14 1 2.14
PD54 AREA 2.00 1 2.00
PD55 9.63 8.78 1 84.55
PD56 8.26 8.56 1 70.71
PD57 80.93 7.62 1 616.28
PD58 3.33 6.86 1 22.84
PD59 30.53 13.86 1 423.15
PD60 TRIANGULO 13.55 6.24 1 42.28
PD61 AREA 43.83 1 43.83
DE HONORIO DELGADO UN SOLO CARRIL
PD62 44.47 8.31 1 369.32
PD63 56.30 7.55 1 424.78
PD64 56.57 8.13 1 459.63
PD65 40.63 8.16 1 331.54
PD66 38.16 7.44 1 283.72
PD67 40.66 7.10 1 288.69
PD68 15.94 7.01 1 111.66
PD69 116.79 6.94 1 810.52
PD70 32.26 7.01 1 225.98
PLAN I LLA D E M E TRAD O S

PD71 16.35 7.03 1 114.94


PD72 28.90 7.10 1 205.05
PD73 32.26 7.03 1 226.79
PD74 81.73 6.85 1 559.44
PD75 44.90 6.60 1 296.12
PD76 69.48 6.62 1 459.96
PD77 18.65 6.94 1 129.34
PD78 17.48 6.83 1 119.39
PD79 48.30 6.46 1 311.78
PD80 58.85 6.20 1 364.87
PD81 47.02 6.57 1 308.69
PD82 8.80 7.00 1 61.60
PD83 AREA 16.50 1 16.50
PD84 AREA 11.13 1 11.13

T O TAL: 20,213.66

PARTIDA: 02.04. TRAZO Y REPLANTEO EN VEREDAS UNIDAD : ( m )


DIMENSIONES VECES QUE REA
DESCRIPCION LONGITUD ANCHO SE REPITE ( m )
(m) (m) (4)
(1) (2) (3) (1) x (2) x (3)

De Av. Cesar Vallejo a Av. Camino Real


N-1 martillo Area 27.83 1 27.83
N-2 martillo Area 19.29 1 19.29
D-1 3.70 2.00 1 7.40
D-2 43.64 2.00 1 87.28
D-3 29.56 1.80 1 53.21
D-4 rampa 2.45 1.75 1 4.29
D-5 rampa 2.60 1.75 1 4.55
N-3 martillo Area 24.26 1 24.26
N-4 martillo Area 65.00 1 65.00
D-6 37.59 1.97 1 73.86
D-7 21.19 1.85 1 39.10
D-8 7.40 1.74 1 12.84
D-9 63.00 1.80 1 113.40
D-10 rampa 3.00 1.88 1 5.64
N-5 martillo Area 25.33 1 25.33
N-6 martillo Area 28.60 1 28.60
D-11 7.33 1.68 1 12.27
D-12 14.55 1.73 1 25.17
D-13 15.83 2.58 1 40.76
D-14 rampa 4.90 1.65 1 8.09
D-15 6.07 1.80 1 10.92
D-16 137.93 1.80 1 248.27
N-7 martillo Area 19.16 1 19.16
N-8 martillo Area 24.43 1 24.43
D-17 69.11 1.80 1 124.40
D-18 rampa 3.20 3.17 1 10.14
D-19 rampa 2.20 2.92 1 6.42
D-20 rampa 2.75 2.50 1 6.88
D-21 21.37 1.80 1 38.47
D-22 4.43 2.17 1 9.61
D-23 25.80 1.96 1 50.44
N-9 martillo Area 21.10 1 21.10
De Av. Camino Real a Av. Honorio Delgado
D-24 10.24 1.80 1 18.43
N-10 martillo Area 18.95 1 18.95
N-11 martillo Area 9.05 1 9.05
N-12 martillo Area 8.95 1 8.95
D-25 14.63 2.29 1 33.50
D-26 24.30 1.80 1 43.74
D-27 3.53 1.26 1 4.45
D-28 3.00 1.26 1 3.78
N-13 martillo Area 4.73 1 4.73
3.70 1.00 1 3.70
N-14 martillo Area 6.24 1 6.24
3.70 1.00 1 3.70
D-29 33.26 1.80 1 59.87
D-30 rampa 6.19 2.23 1 13.80
D-31 6.15 1.80 1 11.07
D-32 32.52 1.80 1 58.54
D-33 rampa 1.75 2.66 1 4.66
D-34 203.23 1.80 1 365.81
N-15 martillo Area 35.80 1 35.80
N-16 martillo Area 13.13 1 13.13
D-35 58.36 1.80 1 105.05
N-17 martillo Area 17.90 1 17.90
PLAN I LLA D E M E TRAD O S

D-36 32.83 1.80 1 59.09


triangulo 1.10 1.80 1 0.99
N-18 martillo Area 5.84 1 5.84
N-19 martillo Area 31.27 1 31.27
D-37 44.81 1.88 1 84.02
D-38 31.10 1.82 1 56.60
D-39 16.90 1.80 1 30.42
D-40 8.45 1.51 1 12.76
D-41 16.35 1.80 1 29.43
D-42 6.99 1.70 1 11.88
D-43 42.02 1.80 1 75.64
N-20 martillo Area 22.61 1 22.61
N-21 martillo Area 19.86 1 19.86
N-22 martillo Area 6.08 1 6.08
N-23 martillo Area 8.35 1 8.35
D-44 21.10 1.80 1 37.98
D-45 2.99 1.70 1 5.08
D-45 rampa 2.30 1.70 1 3.91
D-46 22.78 1.80 1 41.00
D-47 rampa 2.57 1.70 1 4.37
N-24 martillo Area 21.58 1 21.58
N-25 martillo Area 24.17 1 24.17
D-48 rampa 4.35 1.75 1 7.61
D-49 rampa 2.40 1.75 1 4.20
D-50 54.81 1.80 1 98.66
N-26 martillo Area 28.02 1 28.02
N-27 martillo Area 17.91 1 17.91
D-51 125.61 2.10 1 263.78
N-28 martillo Area 4.49 1 4.49
N-29 martillo Area 7.49 1 7.49
DE AV. HONORIO DELGADO A CARRETERA INDUSTRIAL
D-52 146.10 1.80 1 262.98
D-53 1.90 1.90 1 3.61
D-54 3.70 1.80 1 6.66
D-55 225.29 1.80 1 405.52
N-30 martillo Area 27.79 1 27.79
N-31 martillo Area 35.50 1 35.50
D-56 32.00 1.80 1 57.60
D-57 4.90 1.70 1 8.33
D-58 5.61 1.70 1 9.54
D-59 24.18 2.37 1 57.19
D-60 19.37 2.00 1 38.74
D-61 37.15 1.75 1 65.01
D-62 38.21 1.80 1 68.78
D-63 4.40 1.70 1 7.48
N-32 martillo Area 37.32 1 37.32
N-33 martillo Area 29.36 1 29.36
D-64 49.64 1.65 1 81.91
D-65 3.86 1.68 1 6.48
D-66 23.31 1.75 1 40.79
D-67 16.95 1.82 1 30.76
D-68 6.04 1.70 1 10.27
D-69 18.81 1.98 1 37.15
D-70 18.70 1.91 1 35.72
D-71 2.45 1.70 1 4.17
D-72 2.50 1.70 1 4.25
D-73 13.68 1.92 1 26.27
D-74 14.34 2.02 1 28.97
D-75 rampa 5.90 1.70 1 10.03
D-76 34.52 1.90 1 65.59
N-34 martillo Area 8.33 1 8.33
D-77 57.69 1.80 1 103.84
circulo Area 2.54 1 2.54
N-35 martillo Area 7.86 1 7.86
N-36 martillo Area 27.72 1 27.72
N-37 martillo Area 28.50 1 28.50
D-78 19.03 1.80 1 34.25
D-79 23.77 1.80 1 42.79
D-80 141.62 1.80 1 254.92
D-81 47.46 1.80 1 85.43
D-82 rampa 6.30 1.95 1 12.29
D-83 rampa 8.60 1.98 1 17.03
D-84 rampa 7.60 2.00 1 15.20
D-85 rampa 4.80 1.94 1 9.31
D-86 rampa 5.00 1.90 1 9.50
D-87 53.06 1.80 1 95.51
N-38 martillo Area 23.28 1 23.28
N-39 martillo Area 13.27 1 13.27
D-88 rampa 5.71 1.70 1 9.71
D-89 19.03 1.80 1 34.25
D-90 rampa 6.16 1.70 1 10.47
PLAN I LLA D E M E TRAD O S

D-91 90.18 1.80 1 162.32


D-92 61.03 1.87 1 114.13
D-93 32.88 1.71 1 56.06
D-94 38.94 1.80 1 70.09
N-40 martillo Area 39.02 1 39.02
N-41 martillo Area 14.09 1 14.09
D-95 21.60 1.80 1 38.88
D-96 3.29 1.70 1 5.59
N-42 martillo Area 9.93 1 9.93
N-43 martillo Area 11.01 1 11.01
N-44 martillo Area 17.80 1 17.80
N-45 martillo Area 39.03 1 39.03
D-97 43.51 1.80 1 78.32
D-98 61.59 1.86 1 114.56
D-99 10.01 1.79 1 17.92
D-100 41.25 1.72 1 70.95
N-46 martillo Area 35.36 1 35.36
D-101 53.59 1.80 1 96.46
D-102 rampa 3.57 1.50 1 5.36
D-103 rampa 4.70 1.45 1 6.82
D-104 98.89 1.80 1 178.00
N-47 martillo Area 32.19 1 32.19
Berma Central
BC-1 Area 28.23 1 28.23
BC-2 Area 19.26 1 19.26
BC-3 Area 19.12 1 19.12
BC-4 Area 30.16 1 30.16
BC-5 Area 19.72 1 19.72
BC-6 5.24 1.60 1 8.38
BC-7 Area 18.28 1 18.28
BC-8 Area 11.91 1 11.91
BC-9 Area 20.62 1 20.62
BC-10 Area 15.50 1 15.50
BC-11 Area 19.92 1 19.92
BC-12 Area 27.58 1 27.58
BC-13 Area 19.54 1 19.54
BC-14 Area 19.60 1 19.60
BC-15 Area 17.24 1 17.24
BC-16 Area 19.17 1 19.17
BC-17 Area 19.91 1 19.91
BC-18 Area 23.08 1 23.08
BC-19 Area 22.94 1 22.94
BC-20 Area 18.43 1 18.43
BC-21 Area 17.94 1 17.94
BC-22 Area 16.97 1 16.97
BC-23 Area 12.07 1 12.07
BC-24 Area 18.16 1 18.16
BC-25 Area 12.48 1 12.48
BC-26 Area 18.33 1 18.33
BC-27 Area 18.40 1 18.40
BC-28 Area 19.74 1 19.74

T O TAL: 7,214.69

PARTIDA: 02.05. TRAZO Y REPLANTEO EN SARDINELES UNIDAD : ( ml. )


LONGITUD VECES QUE LONGITUD
SARDINEL SE REPITE
DESCRIPCION
( m. ) ( ml )
(1) (2) (3) = (1) * (2)
DE CESAR VALLEJO A CARRETERA INDUSTRIAL
SP-1 17.92 1.00 17.92
SP-2 12.60 1.00 12.60
SP-3 48.88 1.00 48.88
SP-4 13.95 1.00 13.95
SP-5 23.96 1.00 23.96
SP-6 4.41 1.00 4.41
SP-7 9.49 1.00 9.49
SP-8 10.23 1.00 10.23
SP-9 16.25 1.00 16.25
SP-10 62.50 1.00 62.50
SP-11 15.33 1.00 15.33
SP-12 5.89 1.00 5.89
SP-13 35.27 1.00 35.27
SP-14 24.06 1.00 24.06
SP-15 11.90 1.00 11.90
SP-16 66.07 1.00 66.07
SP-17 34.37 1.00 34.37
SP-18 14.46 1.00 14.46
SP-19 23.66 1.00 23.66
PLAN I LLA D E M E TRAD O S

SP-20 15.21 1.00 15.21


SP-21 7.14 1.00 7.14
SP-22 3.66 1.00 3.66
SP-23 9.60 1.00 9.60
SP-24 10.79 1.00 10.79
SP-25 10.52 1.00 10.52
SP-26 16.00 1.00 16.00
SP-27 9.20 1.00 9.20
SP-28 20.56 1.00 20.56
SP-29 18.21 1.00 18.21
SP-30 75.48 1.00 75.48
SP-31 53.41 1.00 53.41
SP-32 16.77 1.00 16.77
SP-33 9.38 1.00 9.38
SP-34 45.06 1.00 45.06
SP-35 9.82 1.00 9.82
SP-36 28.33 1.00 28.33
SP-37 42.81 1.00 42.81
SP-38 44.19 1.00 44.19
SP-39 7.85 1.00 7.85
SP-40 26.77 1.00 26.77
SP-41 21.95 1.00 21.95
SP-42 19.91 1.00 19.91
SP-43 5.60 1.00 5.60
SP-44 8.30 1.00 8.30
SP-45 17.60 1.00 17.60
SP-46 7.95 1.00 7.95
SP-47 29.21 1.00 29.21
SP-48 6.98 1.00 6.98
SP-49 9.41 1.00 9.41
SP-50 26.97 1.00 26.97
SP-51 60.71 1.00 60.71
SP-52 9.89 1.00 9.89
SP-53 12.59 1.00 12.59
SP-54 43.89 1.00 43.89
SP-55 28.66 1.00 28.66
SP-56 81.19 1.00 81.19
BERMA CENTRAL
SP-57 27.38 1.00 27.38
SP-58 6.86 1.00 6.86
SP-59 28.91 1.00 28.91
SP-60 62.13 1.00 62.13
SP-61 63.12 1.00 63.12
SP-62 6.89 1.00 6.89
SP-63 28.34 1.00 28.34
SP-64 28.34 1.00 28.34
SP-65 124.79 1.00 124.79
SP-67 12.60 1.00 12.60
SP-68 12.85 1.00 12.85
SP-69 13.33 1.00 13.33
SP-71 6.20 1.00 6.20
SP-72 6.20 1.00 6.20
SP-73 48.09 1.00 48.09
SP-75 70.41 1.00 70.41
SP-77 5.26 1.00 5.26
SP-78 61.79 1.00 61.79
SP-79 60.99 1.00 60.99
SP-80 5.88 1.00 5.88
SP-81 39.07 1.00 39.07
SP-82 39.37 1.00 39.37
SP-83 36.73 1.00 36.73
SP-84 36.67 1.00 36.67
SP-85 8.34 1.00 8.34
SP-86 8.30 1.00 8.30
SP-87 7.19 1.00 7.19
SP-88 11.31 1.00 11.31
SP-89 90.51 1.00 90.51
SP-90 90.53 1.00 90.53
SP-91 5.82 1.00 5.82
SP-92 8.69 1.00 8.69
SP-93 2.38 1.00 2.38
SP-94 8.33 1.00 8.33
SP-95 2.02 1.00 2.02
SP-96 5.11 1.00 5.11
SP-97 127.82 1.00 127.82
SP-98 127.84 1.00 127.84
PLAN I LLA D E M E TRAD O S

SP-99 5.47 1.00 5.47


SP-100 5.63 1.00 5.63
SP-101 75.75 1.00 75.75
SP-102 75.83 1.00 75.83
SP-103 38.45 1.00 38.45
SP-104 38.47 1.00 38.47
SP-105 6.31 1.00 6.31
SP-106 6.31 1.00 6.31
SP-107 33.03 1.00 33.03
SP-108 13.08 1.00 13.08
SP-109 80.29 1.00 80.29
SP-110 70.70 1.00 70.70
SP-111 62.82 1.00 62.82
SP-112 24.10 1.00 24.10
SP-113 5.32 1.00 5.32
SP-114 5.31 1.00 5.31
SP-115 101.44 1.00 101.44
SP-116 101.43 1.00 101.43
SP-117 5.15 1.00 5.15
SP-118 17.30 1.00 17.30
SP-119 17.37 1.00 17.37
SP-120 91.33 1.00 91.33
SP-121 91.27 1.00 91.27
SP-122 5.37 1.00 5.37
SP-123 21.50 1.00 21.50
SP-124 21.51 1.00 21.51
SP-125 5.45 1.00 5.45
SP-126 5.49 1.00 5.49
SP-127 43.04 1.00 43.04
SP-128 43.01 1.00 43.01
SP-129 100.98 1.00 100.98
SP-130 112.33 1.00 112.33
SP-131 7.46 1.00 7.46
SP-132 5.55 1.00 5.55

T O TAL: 4,003.01
PLAN I LLA D E M E TRAD O S

PARTIDA: 02.06. TRAZO Y REPLANTEO EN PAVIMENTACION UNIDAD : ( m2 )


DIMENSIONES VECES QUE REA
DESCRIPCION LONG. (m.) ANCHO. (m.) SE REPITE ( m )
(1) (2) (3) (4) = (1) x (2) x (3)

DE AV. CESAR VALLEJO A AV. CAMINO REAL


C-1 AREA 3.02 1.00 3.02
C-2 AREA 17.13 1.00 17.13
C-3 AREA 0.74 1.00 0.74
C-4 AREA 8.94 1.00 8.94
C-5 AREA 98.60 1.00 98.60
C-6 300.60 7.00 1.00 2,104.20
C-7 302.97 7.00 1.00 2,120.79
DE AV. CAMINO REAL A AV. HONORIO DELGADO
C-8 60.58 7.00 1.00 424.06
C-9 71.27 7.00 1.00 498.89
C-10 26.09 7.00 1.00 182.63
C-11 60.99 7.00 1.00 426.93
C-12 27.08 7.00 1.00 189.56
C-13 76.20 7.00 1.00 533.40
C-14 16.34 7.00 1.00 114.38
C-15 21.73 7.00 1.00 152.11
C-16 AREA 116.42 1.00 116.42
C-17 AREA 134.84 1.00 134.84
C-18 AREA 74.46 1.00 74.46
C-19 AREA 79.87 1.00 79.87
C-20 61.31 7.00 1.00 429.17
C-21 73.33 7.00 1.00 513.31
C-22 25.13 7.00 1.00 175.91
C-23 62.79 7.00 1.00 439.53
C-24 25.96 7.00 1.00 181.72
C-25 76.02 7.00 1.00 532.14
C-26 15.64 7.00 1.00 109.48
C-27 22.89 7.00 1.00 160.23
C-28 AREA 8.69 1.00 8.69
C-29 AREA 129.33 1.00 129.33
DE AV. HONORIO DELGADO A CARRETERA INDUSTRIAL
C-30 AREA 65.42 1.00 65.42
C-31 365.33 7.00 1.00 2,557.31
C-32 365.61 7.00 1.00 2,559.27
C-33 AREA 75.54 1.00 75.54
C-34 56.89 7.00 1.00 398.23
C-35 AREA 81.80 1.00 81.80
C-36 90.90 7.00 1.00 636.30
C-37 81.29 7.00 1.00 569.03
C-38 13.08 7.00 1.00 91.56
C-39 70.70 7.00 1.00 494.90
C-40 AREA 92.20 1.00 92.20
C-41 224.92 7.00 1.00 1,574.44
C-42 186.35 7.00 1.00 1,304.45
C-43 AREA 83.57 1.00 83.57
C-44 AREA 68.13 1.00 68.13
C-45 AREA 67.18 1.00 67.18
C-46 314.82 7.00 1.00 2,203.74
C-47 313.75 7.00 1.00 2,196.25
C-48 AREA 43.09 1.00 43.09
C-49 AREA 16.13 1.00 16.13
C-50 AREA 18.21 1.00 18.21

T O TAL: 25,157.23

PARTIDA: 02.07. LIMPIEZA DURANTE LA OBRA (Eliminacion de residuos solidos) UNIDAD : ( m )


AREA VECES QUE GLOBAL
DESCRIPCION SE REPITE ( m )
(1) (2) (3) = (1) * (2)

De la Partida 01.02.04 Trazo y replanteo en veredas 7,214.69 1 7,214.69


De la Partida 01.02.06 Trazo y replanteo en pavimentacion 25,157.23 1 25,157.23

T O TAL: 32,371.92

PARTIDA: 03.00. MOVIMIENTO DE TIERRAS


PARTIDA: 03.01. EXCAVACION DE ZANJAS PARA SARDINELES UNIDAD : ( m )
DIMENSIONES ALTURA DE VECES QUE LONGITUD
DESCRIPCION LONGITUD ANCHO EXCAVACION SE REPITE
( m. ) ( m. ) ( m. ) ( m)
(1) (2) (3) (4) (5) = (1) x (4)

PARTIDA: 02.05. TRAZO Y REPLANTEO EN SARDI 4,003.01 0.15 0.25 1 4,003.01


PLAN I LLA D E M E TRAD O S

T O TAL: 4,003.01
PLAN I LLA D E M E TRAD O S

PARTIDA: 03.02. CORTE EN TERRENO NATURAL PARA VEREDAS, e=0.10 m. UNIDAD : ( m )


DIMENSIONES VECES QUE REA
DESCRIPCION LONGITUD ANCHO SE REPITE ( m )
(m) (m) (4)
(1) (2) (3) (1) x (2) x (3)

PARTIDA: 02.04. TRAZO Y REPLANTEO EN VEREDAS 7,214.69

T O TAL: 7,214.69

PARTIDA 03.03 CORTE EN TERRENO NATURAL A NIVEL DE SUB RASANTE CON EQUIPO. UNIDAD : ( m3 )
DIMENSIONES VECES QUE VOLUMEN
DESCRIPCION AREA ALTURA SE REPITE ( m. )
(m) (m) (4)
(1) (2) (3) (1) x (2) x (3)

PARTIDA: 02.06. TRAZO Y REPLANTEO EN PAVIMENTACION 25,157.23 0.40 1 10,062.89

T O TAL: 10,062.89

PARTIDA 03.04 ELIMINACION DE MATERIAL EXCEDENTE CON ESPONJAMIENTO UNIDAD : ( m. )


V. E. N. COEFIC. VOLUMEN
DESCRIPCION ( m. ) ESPONJ. ( m. )
(1) (2) (3)=(1)x(2)

MATERIAL PROVENIENTE DE:


Demolicin de veredas de concreto a pulso, e=10 cm. 262.16 1.40 367.03
Demolicin de Sardineles, a=0.15 m, h=0.40 m. 81.27 1.40 113.78
Demolicin de Pavimento flexible, e=0.05 m 1,010.68 1.40 1,414.96
Excavacion de sanja para Sardineles, a=0.15 m, h=0.25 m. 150.11 1.25 187.64
Corte en terreno natural para veredas, e=10 cm. 721.47 1.25 901.84
Corte en terreno natural a nivel de Sub rasante, e=10 cm. 10,062.89 1.25 12,578.62

T O TAL: 15,563.87
PLAN I LLA D E M E TRAD O S

PARTIDA: 04.00. VEREDAS DE CONCRETO


PARTIDA: 04.01. PERFILADO, NIVELACION Y COMPACTACION EN SUB RASANTE PARA VEREDAS. UNIDAD : ( m )
PARTIDA: 04.02. BASE GRANULAR PARA VEREDAS, e=10 cm. UNIDAD : ( m )
PARTIDA: 04.03. VEREDA e=4" CONCRETO fc=175 Kg/cm2, a=1.80 m, UNA UA UNIDAD : ( m )
PARTIDA: 04.04. CURADO DE VEREDAS CON CURADOR QUIMICO UNIDAD : ( m )
DIMENSIONES VECES QUE REA
DESCRIPCION LONGITUD ANCHO SE REPITE ( m )
(m) (m) (4)
(1) (2) (3) (1) x (2) x (3)

De Av. Cesar Vallejo a Av. Camino Real


N-1 martillo Area 27.83 1 27.83
N-2 martillo Area 19.29 1 19.29
D-1 3.70 2.00 1 7.40
D-2 43.64 2.00 1 87.28
D-3 29.56 1.80 1 53.21
D-4 rampa 2.45 1.75 1 4.29
D-5 rampa 2.60 1.75 1 4.55
N-3 martillo Area 24.26 1 24.26
N-4 martillo Area 65.00 1 65.00
D-6 37.59 1.97 1 73.86
D-7 21.19 1.85 1 39.10
D-8 7.40 1.74 1 12.84
D-9 63.00 1.80 1 113.40
D-10 rampa 3.00 1.88 1 5.64
N-5 martillo Area 25.33 1 25.33
PLAN I LLA D E M E TRAD O S

N-6 martillo Area 28.60 1 28.60


D-11 7.33 1.68 1 12.27
D-12 14.55 1.73 1 25.17
D-13 15.83 2.58 1 40.76
D-14 rampa 4.90 1.65 1 8.09
D-15 6.07 1.80 1 10.92
D-16 137.93 1.80 1 248.27
N-7 martillo Area 19.16 1 19.16
N-8 martillo Area 24.43 1 24.43
D-17 69.11 1.80 1 124.40
D-18 rampa 3.20 3.17 1 10.14
D-19 rampa 2.20 2.92 1 6.42
D-20 rampa 2.75 2.50 1 6.88
D-21 21.37 1.80 1 38.47
D-22 4.43 2.17 1 9.61
D-23 25.80 1.96 1 50.44
N-9 martillo Area 21.10 1 21.10
De Av. Camino Real a Av. Honorio Delgado
D-24 10.24 1.80 1 18.43
N-10 martillo Area 18.95 1 18.95
N-11 martillo Area 9.05 1 9.05
N-12 martillo Area 8.95 1 8.95
D-25 14.63 2.29 1 33.50
D-26 24.30 1.80 1 43.74
D-27 3.53 1.26 1 4.45
D-28 3.00 1.26 1 3.78
N-13 martillo Area 4.73 1 4.73
3.70 1.00 1 3.70
N-14 martillo Area 6.24 1 6.24
3.70 1.00 1 3.70
D-29 33.26 1.80 1 59.87
D-30 rampa 6.19 2.23 1 13.80
D-31 6.15 1.80 1 11.07
D-32 32.52 1.80 1 58.54
D-33 rampa 1.75 2.66 1 4.66
D-34 203.23 1.80 1 365.81
N-15 martillo Area 35.80 1 35.80
N-16 martillo Area 13.13 1 13.13
D-35 58.36 1.80 1 105.05
N-17 martillo Area 17.90 1 17.90
D-36 32.83 1.80 1 59.09
triangulo 1.10 1.80 1 0.99
N-18 martillo Area 5.84 1 5.84
N-19 martillo Area 31.27 1 31.27
D-37 44.81 1.88 1 84.02
D-38 31.10 1.82 1 56.60
D-39 16.90 1.80 1 30.42
D-40 8.45 1.51 1 12.76
D-41 16.35 1.80 1 29.43
D-42 6.99 1.70 1 11.88
D-43 42.02 1.80 1 75.64
N-20 martillo Area 22.61 1 22.61
N-21 martillo Area 19.86 1 19.86
N-22 martillo Area 6.08 1 6.08
N-23 martillo Area 8.35 1 8.35
D-44 21.10 1.80 1 37.98
D-45 2.99 1.70 1 5.08
D-45 rampa 2.30 1.70 1 3.91
D-46 22.78 1.80 1 41.00
D-47 rampa 2.57 1.70 1 4.37
N-24 martillo Area 21.58 1 21.58
N-25 martillo Area 24.17 1 24.17
D-48 rampa 4.35 1.75 1 7.61
D-49 rampa 2.40 1.75 1 4.20
D-50 54.81 1.80 1 98.66
N-26 martillo Area 28.02 1 28.02
N-27 martillo Area 17.91 1 17.91
D-51 125.61 2.10 1 263.78
N-28 martillo Area 4.49 1 4.49
N-29 martillo Area 7.49 1 7.49
DE AV. HONORIO DELGADO A CARRETERA INDUSTRIAL
D-52 146.10 1.80 1 262.98
D-53 1.90 1.90 1 3.61
D-54 3.70 1.80 1 6.66
D-55 225.29 1.80 1 405.52
N-30 martillo Area 27.79 1 27.79
N-31 martillo Area 35.50 1 35.50
D-56 32.00 1.80 1 57.60
D-57 4.90 1.70 1 8.33
D-58 5.61 1.70 1 9.54
D-59 24.18 2.37 1 57.19
PLAN I LLA D E M E TRAD O S

D-60 19.37 2.00 1 38.74


D-61 37.15 1.75 1 65.01
D-62 38.21 1.80 1 68.78
D-63 4.40 1.70 1 7.48
N-32 martillo Area 37.32 1 37.32
N-33 martillo Area 29.36 1 29.36
D-64 49.64 1.65 1 81.91
D-65 3.86 1.68 1 6.48
D-66 23.31 1.75 1 40.79
D-67 16.95 1.82 1 30.76
D-68 6.04 1.70 1 10.27
D-69 18.81 1.98 1 37.15
D-70 18.70 1.91 1 35.72
D-71 2.45 1.70 1 4.17
D-72 2.50 1.70 1 4.25
D-73 13.68 1.92 1 26.27
D-74 14.34 2.02 1 28.97
D-75 rampa 5.90 1.70 1 10.03
D-76 34.52 1.90 1 65.59
N-34 martillo Area 8.33 1 8.33
D-77 57.69 1.80 1 103.84
circulo Area 2.54 1 2.54
N-35 martillo Area 7.86 1 7.86
N-36 martillo Area 27.72 1 27.72
N-37 martillo Area 28.50 1 28.50
D-78 19.03 1.80 1 34.25
D-79 23.77 1.80 1 42.79
D-80 141.62 1.80 1 254.92
D-81 47.46 1.80 1 85.43
D-82 rampa 6.30 1.95 1 12.29
D-83 rampa 8.60 1.98 1 17.03
D-84 rampa 7.60 2.00 1 15.20
D-85 rampa 4.80 1.94 1 9.31
D-86 rampa 5.00 1.90 1 9.50
D-87 53.06 1.80 1 95.51
N-38 martillo Area 23.28 1 23.28
N-39 martillo Area 13.27 1 13.27
D-88 rampa 5.71 1.70 1 9.71
D-89 19.03 1.80 1 34.25
D-90 rampa 6.16 1.70 1 10.47
D-91 90.18 1.80 1 162.32
D-92 61.03 1.87 1 114.13
D-93 32.88 1.71 1 56.06
D-94 38.94 1.80 1 70.09
N-40 martillo Area 39.02 1 39.02
N-41 martillo Area 14.09 1 14.09
D-95 21.60 1.80 1 38.88
D-96 3.29 1.70 1 5.59
N-42 martillo Area 9.93 1 9.93
N-43 martillo Area 11.01 1 11.01
N-44 martillo Area 17.80 1 17.80
N-45 martillo Area 39.03 1 39.03
D-97 43.51 1.80 1 78.32
D-98 61.59 1.86 1 114.56
D-99 10.01 1.79 1 17.92
D-100 41.25 1.72 1 70.95
N-46 martillo Area 35.36 1 35.36
D-101 53.59 1.80 1 96.46
D-102 rampa 3.57 1.50 1 5.36
D-103 rampa 4.70 1.45 1 6.82
D-104 98.89 1.80 1 178.00
N-47 martillo Area 32.19 1 32.19
Berma Central
BC-1 Area 28.23 1 28.23
BC-2 Area 19.26 1 19.26
BC-3 Area 19.12 1 19.12
BC-4 Area 30.16 1 30.16
BC-5 Area 19.72 1 19.72
BC-6 5.24 1.60 1 8.38
BC-7 Area 18.28 1 18.28
BC-8 Area 11.91 1 11.91
BC-9 Area 20.62 1 20.62
BC-10 Area 15.50 1 15.50
BC-11 Area 19.92 1 19.92
BC-12 Area 27.58 1 27.58
BC-13 Area 19.54 1 19.54
BC-14 Area 19.60 1 19.60
BC-15 Area 17.24 1 17.24
BC-16 Area 19.17 1 19.17
BC-17 Area 19.91 1 19.91
BC-18 Area 23.08 1 23.08
PLAN I LLA D E M E TRAD O S

BC-19 Area 22.94 1 22.94


BC-20 Area 18.43 1 18.43
BC-21 Area 17.94 1 17.94
BC-22 Area 16.97 1 16.97
BC-23 Area 12.07 1 12.07
BC-24 Area 18.16 1 18.16
BC-25 Area 12.48 1 12.48
BC-26 Area 18.33 1 18.33
BC-27 Area 18.40 1 18.40
BC-28 Area 19.74 1 19.74

T O TAL: 7,214.69

PARTIDA.04.05 : JUNTAS DE DILATACION EN VEREDAS CADA 4.00 m., e=1/2'' UNIDAD : ( ml. )
DIMENSIONES JUNTAS
DESCRIPCION LARGO ANCHO NUMERO LONGITUD
( m. ) ( m. ) JUNTAS ( m. )
(1) (2) (3)=(1)/4 (4)=(2)x(3)

De Av. Cesar Vallejo a Av. Camino Real


D-1 3.70 2.00 2.00 4.00
D-2 43.64 2.00 12.00 24.00
D-3 29.56 1.80 8.00 14.40
D-4 rampa 2.45 1.75 2.00 3.50
D-5 rampa 2.60 1.75 2.00 3.50
D-6 37.59 1.97 10.00 19.65
D-7 21.19 1.85 6.00 11.07
D-8 7.40 1.74 3.00 5.21
D-9 63.00 1.80 17.00 30.60
D-10 rampa 3.00 1.88 2.00 3.76
D-11 7.33 1.68 3.00 5.03
D-12 14.55 1.73 5.00 8.65
D-13 15.83 2.58 5.00 12.88
D-14 rampa 4.90 1.65 2.00 3.30
D-15 6.07 1.80 3.00 5.40
D-16 137.93 1.80 35.00 63.00
D-17 69.11 1.80 18.00 32.40
D-18 rampa 3.20 3.17 2.00 6.34
D-19 rampa 2.20 2.92 2.00 5.84
D-20 rampa 2.75 2.50 2.00 5.00
D-21 21.37 1.80 6.00 10.80
D-22 4.43 2.17 2.00 4.34
D-23 25.80 1.96 7.00 13.69
De Av. Camino Real a Av. Honorio Delgado
D-24 10.24 1.80 4.00 7.20
D-25 14.63 2.29 5.00 11.45
D-26 24.30 1.80 7.00 12.60
D-27 3.53 1.26 2.00 2.52
D-28 3.00 1.26 2.00 2.52
D-29 33.26 1.80 9.00 16.20
D-30 rampa 6.19 2.23 3.00 6.69
D-31 6.15 1.80 3.00 5.40
D-32 32.52 1.80 9.00 16.20
D-33 rampa 1.75 2.66 1.00 2.66
D-34 203.23 1.80 52.00 93.60
D-35 58.36 1.80 16.00 28.80
D-36 32.83 1.80 9.00 16.20
triangulo 1.10 1.80 1.00 1.80
D-37 44.81 1.88 12.00 22.50
D-38 31.10 1.82 9.00 16.38
D-39 16.90 1.80 5.00 9.00
D-40 8.45 1.51 3.00 4.53
D-41 16.35 1.80 5.00 9.00
D-42 6.99 1.70 3.00 5.10
D-43 42.02 1.80 12.00 21.60
D-44 21.10 1.80 6.00 10.80
D-45 2.99 1.70 2.00 3.40
D-45 rampa 2.30 1.70 2.00 3.40
D-46 22.78 1.80 7.00 12.60
D-47 rampa 2.57 1.70 2.00 3.40
D-48 rampa 4.35 1.75 2.00 3.50
D-49 rampa 2.40 1.75 2.00 3.50
D-50 54.81 1.80 15.00 27.00
D-51 125.61 2.10 32.00 67.20
DE AV. HONORIO DELGADO A CARRETERA INDUSTRIAL
D-52 146.10 1.80 38.00 68.40
D-53 1.90 1.90 1.00 1.90
D-54 3.70 1.80 2.00 3.60
D-55 225.29 1.80 57.00 102.60
PLAN I LLA D E M E TRAD O S

D-56 32.00 1.80 9.00 16.20


D-57 4.90 1.70 2.00 3.40
D-58 5.61 1.70 2.00 3.40
D-59 24.18 2.37 7.00 16.56
D-60 19.37 2.00 6.00 12.00
D-61 37.15 1.75 10.00 17.50
D-62 38.21 1.80 11.00 19.80
D-63 4.40 1.70 2.00 3.40
D-64 49.64 1.65 13.00 21.45
D-65 3.86 1.68 2.00 3.36
D-66 23.31 1.75 7.00 12.25
D-67 16.95 1.82 5.00 9.08
D-68 6.04 1.70 3.00 5.10
D-69 18.81 1.98 6.00 11.85
D-70 18.70 1.91 6.00 11.46
D-71 2.45 1.70 2.00 3.40
D-72 2.50 1.70 2.00 3.40
D-73 13.68 1.92 4.00 7.68
D-74 14.34 2.02 5.00 10.10
D-75 rampa 5.90 1.70 2.00 3.40
D-76 34.52 1.90 10.00 19.00
D-77 57.69 1.80 15.00 27.00
D-78 19.03 1.80 6.00 10.80
D-79 23.77 1.80 7.00 12.60
D-80 141.62 1.80 36.00 64.80
D-81 47.46 1.80 13.00 23.40
D-82 rampa 6.30 1.95 3.00 5.85
D-83 rampa 8.60 1.98 3.00 5.94
D-84 rampa 7.60 2.00 3.00 6.00
D-85 rampa 4.80 1.94 2.00 3.88
D-86 rampa 5.00 1.90 2.00 3.80
D-87 53.06 1.80 14.00 25.20
D-88 rampa 5.71 1.70 2.00 3.40
D-89 19.03 1.80 6.00 10.80
D-90 rampa 6.16 1.70 3.00 5.10
D-91 90.18 1.80 24.00 43.20
D-92 61.03 1.87 16.00 29.92
D-93 32.88 1.71 9.00 15.35
D-94 38.94 1.80 11.00 19.80
D-95 21.60 1.80 6.00 10.80
D-96 3.29 1.70 2.00 3.40
D-97 43.51 1.80 12.00 21.60
D-98 61.59 1.86 16.00 29.76
D-99 10.01 1.79 4.00 7.16
D-100 41.25 1.72 11.00 18.92
D-101 53.59 1.80 14.00 25.20
D-102 rampa 3.57 1.50 2.00 3.00
D-103 rampa 4.70 1.45 2.00 2.90
D-104 98.89 1.80 26.00 46.80

T O TAL: 1,619.75

PARTIDA: 05.00. SARDINELES


PARTIDA: 05.01. SARDINEL: 0.15x0.40 m.,CONCRETO fc= 175 kg/cm2 UNIDAD : ( m. )
DIMENSIONES LONGITUD VECES QUE LONGITUD
DESCRIPCION ALTURA ANCHO DE SARDINEL SE REPITE
( m. ) ( m. ) ( m. ) ( ml )
(1) (2) (3) (4) (5) = (1) * (4)

DE CESAR VALLEJO A CARRETERA INDUSTRIAL


SP-1 17.92 1.00 17.92
SP-2 12.60 1.00 12.60
SP-3 48.88 1.00 48.88
SP-4 13.95 1.00 13.95
SP-5 23.96 1.00 23.96
SP-6 4.41 1.00 4.41
SP-7 9.49 1.00 9.49
SP-8 10.23 1.00 10.23
SP-9 16.25 1.00 16.25
SP-10 62.50 1.00 62.50
SP-11 15.33 1.00 15.33
SP-12 5.89 1.00 5.89
SP-13 35.27 1.00 35.27
SP-14 24.06 1.00 24.06
SP-15 11.90 1.00 11.90
SP-16 66.07 1.00 66.07
SP-17 34.37 1.00 34.37
SP-18 14.46 1.00 14.46
SP-19 23.66 1.00 23.66
PLAN I LLA D E M E TRAD O S

SP-20 15.21 1.00 15.21


SP-21 7.14 1.00 7.14
SP-22 3.66 1.00 3.66
SP-23 9.60 1.00 9.60
SP-24 10.79 1.00 10.79
SP-25 10.52 1.00 10.52
SP-26 16.00 1.00 16.00
SP-27 9.20 1.00 9.20
SP-28 20.56 1.00 20.56
SP-29 18.21 1.00 18.21
SP-30 75.48 1.00 75.48
SP-31 53.41 1.00 53.41
SP-32 16.77 1.00 16.77
SP-33 9.38 1.00 9.38
SP-34 45.06 1.00 45.06
SP-35 9.82 1.00 9.82
SP-36 28.33 1.00 28.33
SP-37 42.81 1.00 42.81
SP-38 44.19 1.00 44.19
SP-39 7.85 1.00 7.85
SP-40 26.77 1.00 26.77
SP-41 21.95 1.00 21.95
SP-42 19.91 1.00 19.91
SP-43 5.60 1.00 5.60
SP-44 8.30 1.00 8.30
SP-45 17.60 1.00 17.60
SP-46 7.95 1.00 7.95
SP-47 29.21 1.00 29.21
SP-48 6.98 1.00 6.98
SP-49 9.41 1.00 9.41
SP-50 26.97 1.00 26.97
SP-51 60.71 1.00 60.71
SP-52 9.89 1.00 9.89
SP-53 12.59 1.00 12.59
SP-54 43.89 1.00 43.89
SP-55 28.66 1.00 28.66
SP-56 81.19 1.00 81.19
BERMA CENTRAL
SP-57 27.38 1.00 27.38
SP-58 6.86 1.00 6.86
SP-59 28.91 1.00 28.91
SP-60 62.13 1.00 62.13
SP-61 63.12 1.00 63.12
SP-62 6.89 1.00 6.89
SP-63 28.34 1.00 28.34
SP-64 28.34 1.00 28.34
SP-65 124.79 1.00 124.79
SP-67 12.60 1.00 12.60
SP-68 12.85 1.00 12.85
SP-69 13.33 1.00 13.33
SP-71 6.20 1.00 6.20
SP-72 6.20 1.00 6.20
SP-73 48.09 1.00 48.09
SP-75 70.41 1.00 70.41
SP-77 5.26 1.00 5.26
SP-78 61.79 1.00 61.79
SP-79 60.99 1.00 60.99
SP-80 5.88 1.00 5.88
SP-81 39.07 1.00 39.07
SP-82 39.37 1.00 39.37
SP-83 36.73 1.00 36.73
SP-84 36.67 1.00 36.67
SP-85 8.34 1.00 8.34
SP-86 8.30 1.00 8.30
SP-87 7.19 1.00 7.19
SP-88 11.31 1.00 11.31
SP-89 90.51 1.00 90.51
SP-90 90.53 1.00 90.53
SP-91 5.82 1.00 5.82
SP-92 8.69 1.00 8.69
SP-93 2.38 1.00 2.38
SP-94 8.33 1.00 8.33
SP-95 2.02 1.00 2.02
SP-96 5.11 1.00 5.11
SP-97 127.82 1.00 127.82
SP-98 127.84 1.00 127.84
SP-99 5.47 1.00 5.47
SP-100 5.63 1.00 5.63
SP-101 75.75 1.00 75.75
SP-102 75.83 1.00 75.83
SP-103 38.45 1.00 38.45
PLAN I LLA D E M E TRAD O S

SP-104 38.47 1.00 38.47


SP-105 6.31 1.00 6.31
SP-106 6.31 1.00 6.31
SP-107 33.03 1.00 33.03
SP-108 13.08 1.00 13.08
SP-109 80.29 1.00 80.29
SP-110 70.70 1.00 70.70
SP-111 62.82 1.00 62.82
SP-112 24.10 1.00 24.10
SP-113 5.32 1.00 5.32
SP-114 5.31 1.00 5.31
SP-115 101.44 1.00 101.44
SP-116 101.43 1.00 101.43
SP-117 5.15 1.00 5.15
SP-118 17.30 1.00 17.30
SP-119 17.37 1.00 17.37
SP-120 91.33 1.00 91.33
SP-121 91.27 1.00 91.27
SP-122 5.37 1.00 5.37
SP-123 21.50 1.00 21.50
SP-124 21.51 1.00 21.51
SP-125 5.45 1.00 5.45
SP-126 5.49 1.00 5.49
SP-127 43.04 1.00 43.04
SP-128 43.01 1.00 43.01
SP-129 100.98 1.00 100.98
SP-130 112.33 1.00 112.33
SP-131 7.46 1.00 7.46
SP-132 5.55 1.00 5.55

T O TAL: 4,003.01

PARTIDA 05.02: SARDINEL, ENCOFRADO Y DESENCOFRADO NORMAL, Altura de encofrado = 0.20 m. UNIDAD : ( m2 )
DIMENSIONES CARAS A VECES QUE REA
DESCRIPCION LONGITUD ALTURA ENCOFRAR SE REPITE ( m )
(m) (m)
(1) (2) (3) (4) (5)=(1)x(2)x(3)x(4)

DE CESAR VALLEJO A CARRETERA INDUSTRIAL


SP-1 17.92 0.40 2 1 14.34
SP-2 12.60 0.40 2 1 10.08
SP-3 48.88 0.40 2 1 39.10
SP-4 13.95 0.40 2 1 11.16
SP-5 23.96 0.40 2 1 19.17
SP-6 4.41 0.40 2 1 3.53
SP-7 9.49 0.40 2 1 7.59
SP-8 10.23 0.40 2 1 8.18
SP-9 16.25 0.40 2 1 13.00
SP-10 62.50 0.40 2 1 50.00
SP-11 15.33 0.40 2 1 12.26
SP-12 5.89 0.40 2 1 4.71
SP-13 35.27 0.40 2 1 28.22
SP-14 24.06 0.40 2 1 19.25
SP-15 11.90 0.40 2 1 9.52
SP-16 66.07 0.40 2 1 52.86
SP-17 34.37 0.40 2 1 27.50
SP-18 14.46 0.40 2 1 11.57
SP-19 23.66 0.40 2 1 18.93
SP-20 15.21 0.40 2 1 12.17
SP-21 7.14 0.40 2 1 5.71
SP-22 3.66 0.40 2 1 2.93
SP-23 9.60 0.40 2 1 7.68
SP-24 10.79 0.40 2 1 8.63
SP-25 10.52 0.40 2 1 8.42
SP-26 16.00 0.40 2 1 12.80
SP-27 9.20 0.40 2 1 7.36
SP-28 20.56 0.40 2 1 16.45
SP-29 18.21 0.40 2 1 14.57
SP-30 75.48 0.40 2 1 60.38
SP-31 53.41 0.40 2 1 42.73
SP-32 16.77 0.40 2 1 13.42
SP-33 9.38 0.40 2 1 7.50
SP-34 45.06 0.40 2 1 36.05
SP-35 9.82 0.40 2 1 7.86
SP-36 28.33 0.40 2 1 22.66
SP-37 42.81 0.40 2 1 34.25
SP-38 44.19 0.40 2 1 35.35
SP-39 7.85 0.40 2 1 6.28
SP-40 26.77 0.40 2 1 21.42
PLAN I LLA D E M E TRAD O S

SP-41 21.95 0.40 2 1 17.56


SP-42 19.91 0.40 2 1 15.93
SP-43 5.60 0.40 2 1 4.48
SP-44 8.30 0.40 2 1 6.64
SP-45 17.60 0.40 2 1 14.08
SP-46 7.95 0.40 2 1 6.36
SP-47 29.21 0.40 2 1 23.37
SP-48 6.98 0.40 2 1 5.58
SP-49 9.41 0.40 2 1 7.53
SP-50 26.97 0.40 2 1 21.58
SP-51 60.71 0.40 2 1 48.57
SP-52 9.89 0.40 2 1 7.91
SP-53 12.59 0.40 2 1 10.07
SP-54 43.89 0.40 2 1 35.11
SP-55 28.66 0.40 2 1 22.93
SP-56 81.19 0.40 2 1 64.95
BERMA CENTRAL
SP-57 27.38 0.40 2 1 21.90
SP-58 6.86 0.40 2 1 5.49
SP-59 28.91 0.40 2 1 23.13
SP-60 62.13 0.40 2 1 49.70
SP-61 63.12 0.40 2 1 50.50
SP-62 6.89 0.40 2 1 5.51
SP-63 28.34 0.40 2 1 22.67
SP-64 28.34 0.40 2 1 22.67
SP-65 124.79 0.40 2 1 99.83
SP-67 12.60 0.40 2 1 10.08
SP-68 12.85 0.40 2 1 10.28
SP-69 13.33 0.40 2 1 10.66
SP-71 6.20 0.40 2 1 4.96
SP-72 6.20 0.40 2 1 4.96
SP-73 48.09 0.40 2 1 38.47
SP-75 70.41 0.40 2 1 56.33
SP-77 5.26 0.40 2 1 4.21
SP-78 61.79 0.40 2 1 49.43
SP-79 60.99 0.40 2 1 48.79
SP-80 5.88 0.40 2 1 4.70
SP-81 39.07 0.40 2 1 31.26
SP-82 39.37 0.40 2 1 31.50
SP-83 36.73 0.40 2 1 29.38
SP-84 36.67 0.40 2 1 29.34
SP-85 8.34 0.40 2 1 6.67
SP-86 8.30 0.40 2 1 6.64
SP-87 7.19 0.40 2 1 5.75
SP-88 11.31 0.40 2 1 9.05
SP-89 90.51 0.40 2 1 72.41
SP-90 90.53 0.40 2 1 72.42
SP-91 5.82 0.40 2 1 4.66
SP-92 8.69 0.40 2 1 6.95
SP-93 2.38 0.40 2 1 1.90
SP-94 8.33 0.40 2 1 6.66
SP-95 2.02 0.40 2 1 1.62
SP-96 5.11 0.40 2 1 4.09
SP-97 127.82 0.40 2 1 102.26
SP-98 127.84 0.40 2 1 102.27
SP-99 5.47 0.40 2 1 4.38
SP-100 5.63 0.40 2 1 4.50
SP-101 75.75 0.40 2 1 60.60
SP-102 75.83 0.40 2 1 60.66
SP-103 38.45 0.40 2 1 30.76
SP-104 38.47 0.40 2 1 30.78
SP-105 6.31 0.40 2 1 5.05
SP-106 6.31 0.40 2 1 5.05
SP-107 33.03 0.40 2 1 26.42
SP-108 13.08 0.40 2 1 10.46
SP-109 80.29 0.40 2 1 64.23
SP-110 70.70 0.40 2 1 56.56
SP-111 62.82 0.40 2 1 50.26
SP-112 24.10 0.40 2 1 19.28
SP-113 5.32 0.40 2 1 4.26
SP-114 5.31 0.40 2 1 4.25
SP-115 101.44 0.40 2 1 81.15
SP-116 101.43 0.40 2 1 81.14
SP-117 5.15 0.40 2 1 4.12
SP-118 17.30 0.40 2 1 13.84
SP-119 17.37 0.40 2 1 13.90
SP-120 91.33 0.40 2 1 73.06
SP-121 91.27 0.40 2 1 73.02
SP-122 5.37 0.40 2 1 4.30
SP-123 21.50 0.40 2 1 17.20
SP-124 21.51 0.40 2 1 17.21
PLAN I LLA D E M E TRAD O S

SP-125 5.45 0.40 2 1 4.36


SP-126 5.49 0.40 2 1 4.39
SP-127 43.04 0.40 2 1 34.43
SP-128 43.01 0.40 2 1 34.41
SP-129 100.98 0.40 2 1 80.78
SP-130 112.33 0.40 2 1 89.86
SP-131 7.46 0.40 2 1 5.97
SP-132 5.55 0.40 2 1 4.44

T O TAL: 3,202.42

PARTIDA 05.03: JUNTAS DE DILATACION EN SARDINELES: C/3 m. ,e= 1/2" UNIDAD : ( m2 )


DIMENSIONES VECES QUE REA
DESCRIPCION LONGITUD ANCHO SE REPITE ( m )
( m. ) ( m. ) LA JUNTA
(1) (2) (3) (4)=(2)x(3)

DE CESAR VALLEJO A CARRETERA INDUSTRIAL


SP-1 17.92 0.15 7 1.05
SP-2 12.60 0.15 5 0.75
SP-3 48.88 0.15 17 2.55
SP-4 13.95 0.15 6 0.90
SP-5 23.96 0.15 9 1.35
SP-6 4.41 0.15 2 0.30
SP-7 9.49 0.15 4 0.60
SP-8 10.23 0.15 4 0.60
SP-9 16.25 0.15 6 0.90
SP-10 62.50 0.15 22 3.30
SP-11 15.33 0.15 6 0.90
SP-12 5.89 0.15 3 0.45
SP-13 35.27 0.15 13 1.95
SP-14 24.06 0.15 9 1.35
SP-15 11.90 0.15 5 0.75
SP-16 66.07 0.15 23 3.45
SP-17 34.37 0.15 12 1.80
SP-18 14.46 0.15 6 0.90
SP-19 23.66 0.15 9 1.35
SP-20 15.21 0.15 6 0.90
SP-21 7.14 0.15 3 0.45
SP-22 3.66 0.15 2 0.30
SP-23 9.60 0.15 4 0.60
SP-24 10.79 0.15 5 0.75
SP-25 10.52 0.15 5 0.75
SP-26 16.00 0.15 6 0.90
SP-27 9.20 0.15 4 0.60
SP-28 20.56 0.15 8 1.20
SP-29 18.21 0.15 7 1.05
SP-30 75.48 0.15 26 3.90
SP-31 53.41 0.15 19 2.85
SP-32 16.77 0.15 7 1.05
SP-33 9.38 0.15 4 0.60
SP-34 45.06 0.15 16 2.40
SP-35 9.82 0.15 4 0.60
SP-36 28.33 0.15 10 1.50
SP-37 42.81 0.15 15 2.25
SP-38 44.19 0.15 16 2.40
SP-39 7.85 0.15 4 0.60
SP-40 26.77 0.15 10 1.50
SP-41 21.95 0.15 8 1.20
SP-42 19.91 0.15 8 1.20
SP-43 5.60 0.15 3 0.45
SP-44 8.30 0.15 4 0.60
SP-45 17.60 0.15 7 1.05
SP-46 7.95 0.15 4 0.60
SP-47 29.21 0.15 11 1.65
SP-48 6.98 0.15 3 0.45
SP-49 9.41 0.15 4 0.60
SP-50 26.97 0.15 10 1.50
SP-51 60.71 0.15 21 3.15
SP-52 9.89 0.15 4 0.60
SP-53 12.59 0.15 5 0.75
SP-54 43.89 0.15 16 2.40
SP-55 28.66 0.15 11 1.65
SP-56 81.19 0.15 28 4.20
BERMA CENTRAL
SP-57 27.38 0.15 10 1.50
SP-58 6.86 0.15 3 0.45
SP-59 28.91 0.15 11 1.65
SP-60 62.13 0.15 22 3.30
PLAN I LLA D E M E TRAD O S

SP-61 63.12 0.15 22 3.30


SP-62 6.89 0.15 3 0.45
SP-63 28.34 0.15 10 1.50
SP-64 28.34 0.15 10 1.50
SP-65 124.79 0.15 43 6.45
SP-67 12.60 0.15 5 0.75
SP-68 12.85 0.15 5 0.75
SP-69 13.33 0.15 5 0.75
SP-71 6.20 0.15 3 0.45
SP-72 6.20 0.15 3 0.45
SP-73 48.09 0.15 17 2.55
SP-75 70.41 0.15 24 3.60
SP-77 5.26 0.15 3 0.45
SP-78 61.79 0.15 22 3.30
SP-79 60.99 0.15 21 3.15
SP-80 5.88 0.15 3 0.45
SP-81 39.07 0.15 14 2.10
SP-82 39.37 0.15 14 2.10
SP-83 36.73 0.15 13 1.95
SP-84 36.67 0.15 13 1.95
SP-85 8.34 0.15 4 0.60
SP-86 8.30 0.15 4 0.60
SP-87 7.19 0.15 3 0.45
SP-88 11.31 0.15 5 0.75
SP-89 90.51 0.15 31 4.65
SP-90 90.53 0.15 31 4.65
SP-91 5.82 0.15 3 0.45
SP-92 8.69 0.15 4 0.60
SP-93 2.38 0.15 2 0.30
SP-94 8.33 0.15 4 0.60
SP-95 2.02 0.15 2 0.30
SP-96 5.11 0.15 3 0.45
SP-97 127.82 0.15 44 6.60
SP-98 127.84 0.15 44 6.60
SP-99 5.47 0.15 3 0.45
SP-100 5.63 0.15 3 0.45
SP-101 75.75 0.15 26 3.90
SP-102 75.83 0.15 26 3.90
SP-103 38.45 0.15 14 2.10
SP-104 38.47 0.15 14 2.10
SP-105 6.31 0.15 3 0.45
SP-106 6.31 0.15 3 0.45
SP-107 33.03 0.15 12 1.80
SP-108 13.08 0.15 5 0.75
SP-109 80.29 0.15 28 4.20
SP-110 70.70 0.15 25 3.75
SP-111 62.82 0.15 22 3.30
SP-112 24.10 0.15 9 1.35
SP-113 5.32 0.15 3 0.45
SP-114 5.31 0.15 3 0.45
SP-115 101.44 0.15 35 5.25
SP-116 101.43 0.15 35 5.25
SP-117 5.15 0.15 3 0.45
SP-118 17.30 0.15 7 1.05
SP-119 17.37 0.15 7 1.05
SP-120 91.33 0.15 31 4.65
SP-121 91.27 0.15 31 4.65
SP-122 5.37 0.15 3 0.45
SP-123 21.50 0.15 8 1.20
SP-124 21.51 0.15 8 1.20
SP-125 5.45 0.15 3 0.45
SP-126 5.49 0.15 3 0.45
SP-127 43.04 0.15 15 2.25
SP-128 43.01 0.15 15 2.25
SP-129 100.98 0.15 35 5.25
SP-130 112.33 0.15 38 5.70
SP-131 7.46 0.15 3 0.45
SP-132 5.55 0.15 3 0.45

T O TAL: 219.15

PARTIDA: 06.00. PAVIMENTACION


PARTIDA:06.01 PREPARACION DE SUB RASANTE UNIDAD : ( m )
PARTIDA:06.02 SUB BASE GRANULAR, e = 20 cm. UNIDAD : ( m )
PARTIDA:06.03 BASE GRANULAR, e = 15 cm. UNIDAD : ( m )
PARTIDA:06.04 BARRIDO Y LIMPIEZA P/LA CARPETA ASFALTICA UNIDAD : ( m )
PARTIDA:06.05 IMPRIMACION ASFALTICA. UNIDAD : ( m )
PARTIDA:06.06 CARPETA ASFLTICA EN CALIENTE, e = 2.5" C/EQUIPO UNIDAD : ( m )
DIMENSIONES VECES QUE REA
DESCRIPCION LONG. (m.) ANCHO. (m.) SE REPITE ( m )
PLAN I LLA D E M E TRAD O S

(1) (2) (3) (4) = (1) x (2) x (3)

DE AV. CESAR VALLEJO A AV. CAMINO REAL


C-1 AREA 3.02 1.00 3.02
C-2 AREA 17.13 1.00 17.13
C-3 AREA 0.74 1.00 0.74
C-4 AREA 8.94 1.00 8.94
C-5 AREA 98.60 1.00 98.60
C-6 300.60 7.00 1.00 2,104.20
C-7 302.97 7.00 1.00 2,120.79
DE AV. CAMINO REAL A AV. HONORIO DELGADO
C-8 60.58 7.00 1.00 424.06
C-9 71.27 7.00 1.00 498.89
C-10 26.09 7.00 1.00 182.63
C-11 60.99 7.00 1.00 426.93
C-12 27.08 7.00 1.00 189.56
C-13 76.20 7.00 1.00 533.40
C-14 16.34 7.00 1.00 114.38
C-15 21.73 7.00 1.00 152.11
C-16 AREA 116.42 1.00 116.42
C-17 AREA 134.84 1.00 134.84
C-18 AREA 74.46 1.00 74.46
C-19 AREA 79.87 1.00 79.87
C-20 61.31 7.00 1.00 429.17
C-21 73.33 7.00 1.00 513.31
C-22 25.13 7.00 1.00 175.91
C-23 62.79 7.00 1.00 439.53
C-24 25.96 7.00 1.00 181.72
C-25 76.02 7.00 1.00 532.14
C-26 15.64 7.00 1.00 109.48
C-27 22.89 7.00 1.00 160.23
C-28 AREA 8.69 1.00 8.69
C-29 AREA 129.33 1.00 129.33
DE AV. HONORIO DELGADO A CARRETERA INDUSTRIAL
C-30 AREA 65.42 1.00 65.42
C-31 365.33 7.00 1.00 2,557.31
C-32 365.61 7.00 1.00 2,559.27
C-33 AREA 75.54 1.00 75.54
C-34 56.89 7.00 1.00 398.23
C-35 AREA 81.80 1.00 81.80
C-36 90.90 7.00 1.00 636.30
C-37 81.29 7.00 1.00 569.03
C-38 13.08 7.00 1.00 91.56
C-39 70.70 7.00 1.00 494.90
C-40 AREA 92.20 1.00 92.20
C-41 224.92 7.00 1.00 1,574.44
C-42 186.35 7.00 1.00 1,304.45
C-43 AREA 83.57 1.00 83.57
C-44 AREA 68.13 1.00 68.13
C-45 AREA 67.18 1.00 67.18
C-46 314.82 7.00 1.00 2,203.74
C-47 313.75 7.00 1.00 2,196.25
C-48 AREA 43.09 1.00 43.09
C-49 AREA 16.13 1.00 16.13
C-50 AREA 18.21 1.00 18.21

T O TAL: 25,157.23

PARTIDA: 07.00. SEALIZACION


PARTIDA:07.01 SEALIZACION HORIZONTAL UNIDAD : ( m )
DIMENSIONES VECES QUE AREA
DESCRIPCION LONGITUD ANCHO SE REPITE ( m2.)
(m) (m) (4)
(1) (2) (3) (1) x (2) x (3)

DE AV. CESAR VALLEJO A AV. CAMINO REAL


Cruce Peatonal 4.00 0.50 46 92.00
Linea de pare 7.15 0.50 1 3.58
Linea de pare 7.06 0.50 1 3.53
Linea de pare 7.00 0.50 1 3.50
Flecha direccional con giro A= 1.80 4 7.20
Flecha direccional con giro a la derecha y a la izquierda A= 2.10 - -
Flecha direccional A= 1.30 12 15.60
Lineas Continuas 15 0.10 3 4.50
Lineas Discontinuas 15 0.10 61 91.50
DE AV. CAMINO REAL A AV. HONORIO DELGADO
Cruce Peatonal 4.00 0.50 102 204.00
Linea de pare 7.00 0.50 7 24.50
Flecha direccional con giro A= 1.80 7 12.60
PLAN I LLA D E M E TRAD O S

Flecha direccional con giro a la derecha y a la izquierda A= 2.10 - -


Flecha direccional A= 1.30 19 24.70
Lineas Continuas 15 0.10 7 10.50
Lineas discontinuas 3 0.10 80 24.00
DE AV. HONORIO ELGADO A CARRETERA INDUSTRIAL
Cruce Peatonal 4.00 0.50 210 420.00
Linea de pare 7.00 0.50 14 49.00
Flecha direccional con giro A= 1.80 15 27.00
Flecha direccional con giro a la derecha y a la izquierda A= 2.10 - -
Flecha direccional A= 1.30 35 45.50
Lineas Continuas 15 0.10 14 21.00
Lineas discontinuas 3 0.10 55 16.50

Pintura en sardineles 4,003.01 0.25 1 1,000.75

T O TAL: 2,101.46

PARTIDA: 07.02 SEALIZACION VERTICAL 0.75x0.75m PEATON UNIDAD : ( Und. )


VECES QUE UNIDAD
DESCRIPCION SE REPITE ( Und.)
(1) (2) = (1)

SEAL VERTICAL 23 23.00

T O TAL: 23.00

PARTIDA: 07.03 SEALIZACION VERTICAL 0.90x0.60m PROHIBIDO ESTACIONAR UNIDAD : ( Und. )


VECES QUE UNIDAD
DESCRIPCION SE REPITE ( Und.)
(1) (2) = (1)

SEAL VERTICAL PROHIBIDO ESTACIONAR 2 2.00

T O TAL: 2.00

PARTIDA: 07.04 SEALIZACION VERTICAL 0.90x0.60m PROHIBIDO VOLTEAR EN U UNIDAD : ( Und. )


VECES QUE UNIDAD
DESCRIPCION SE REPITE ( Und.)
(1) (2) = (1)

SEAL VERTICAL PROHIBIDO VOLTEAR EN U 2 2.00

T O TAL: 2.00

PARTIDA: 08.00. VARIOS


PARTIDA:08.01 NIVELAR Y REPOSICION DE CAJAS DE AGUA UNIDAD : ( Und. )
VECES QUE UNIDAD
DESCRIPCION SE REPITE ( Und.)
(1) (2) = (1)

DE AV. CESAR VALLEJO A AV. CAMINO REAL 26 26.00


DE AV. CAMINO REAL A AV. HONORIO DELGADO 34 34.00
DE AV. HONORIO ELGADO A CARRETERA INDUSTRIAL 30 30.00

T O TAL: 90.00

PARTIDA:08.02 NIVELACION Y REPOSICION DE CAJAS DE DESAGUE UNIDAD : ( Und. )


VECES QUE UNIDAD
DESCRIPCION SE REPITE ( Und.)
(1) (2) = (1)

DE AV. CESAR VALLEJO A AV. CAMINO REAL 26 26.00


DE AV. CAMINO REAL A AV. HONORIO DELGADO 34 34.00
DE AV. HONORIO ELGADO A CARRETERA INDUSTRIAL 30 30.00

T O TAL: 90.00

PARTIDA: 09.00 MURO DE CONTENCION


PARTIDA 09.01: EXCAVACION PARA MURO DE CONTENCION UNIDAD : ( m3 )
DIMENSIONES VECES QUE VOLUMEN
DESCRIPCION LONGITUD ALTURA ANCHO SE REPITE ( m3)
(m) (m) (m)
(1) (2) (3) (4) (5)=(1)x(2)x(3)x(4)

DE CESAR VALLEJO A CARRETERA INDUSTRIAL


PLAN I LLA D E M E TRAD O S

MC-1 267.68 1.45 0.95 1 368.73

T O TAL: 368.73

PARTIDA 09.02: RELLENO CON MATERIAL PROPIO UNIDAD : ( m3 )


DIMENSIONES VECES QUE VOLUMEN
DESCRIPCION LONGITUD ALTURA ANCHO SE REPITE ( m3)
(m) (m) (m)
(1) (2) (3) (4) (5)=(1)x(2)x(3)x(4)

DE CESAR VALLEJO A CARRETERA INDUSTRIAL


MC-1 267.68 1.1 0.325 1 95.70
267.68 0.55 0.35 1 51.53

T O TAL: 147.22

PARTIDA 09.03: ELIMINACION DE MATERIAL EXCEDENTE UNIDAD : ( m3 )


DIMENSIONES FACTOR VOLUMEN
DESCRIPCION AREA VOLUMEN ( m3)
(m) (m)
(1) (2) (3)=(1)x(2)

PARTIDA 09.01: EXCAVACION PARA MURO DE CONTENCION 368.73 1.25 460.91


PARTIDA 09.02: RELLENO CON MATERIAL PROPIO (147.22) 1.25 (184.03)

T O TAL: 276.88

PARTIDA 09.04: SOLADO DE CONCRETO P/ZAPATAS C:H 1:12 e=4" UNIDAD : ( m2 )


DIMENSIONES VECES QUE AREA
DESCRIPCION LONGITUD ALTURA ANCHO SE REPITE ( m )
(m) (m) (m)
(1) (2) (3) (4) (5)=(1)x(2)x(3)x(4)

DE CESAR VALLEJO A CARRETERA INDUSTRIAL


MC-1 267.68 0.95 1 254.30
0

T O TAL: 254.30

PARTIDA 09.05: MURO DE CONTENCION CONCRETO FC=210 KG/CM2 UNIDAD : ( m3 )


DIMENSIONES VECES QUE VOLUMEN
DESCRIPCION LONGITUD ALTURA ANCHO SE REPITE ( m3)
(m) (m) (m)
(1) (2) (3) (4) (5)=(1)x(2)x(3)x(4)

DE CESAR VALLEJO A CARRETERA INDUSTRIAL


MC-1 BASE 267.68 0.25 0.95 1 63.57
CUERPO 267.68 1.25 0.275 1 92.02
T O TAL: 155.59

PARTIDA 09.05: MURO DE CONTENCION: ENCOFRADO Y DESENCOFRADO UNIDAD : ( m3 )


DIMENSIONES VECES QUE VOLUMEN
DESCRIPCION LONGITUD ALTURA ANCHO SE REPITE ( m3)
(m) (m) (m)
(1) (2) (3) (4) (5)=(1)x(2)x(3)x(4)

DE CESAR VALLEJO A CARRETERA INDUSTRIAL


MC-1 CUERPO 267.68 1.25 2 669.20

T O TAL: 669.20

PARTIDA 09.06: MURO DE CONTENCION: ACERO DE REFUERZO UNIDAD : ( Kg )


DIMENSIONES PESO KILOGRAMOS
DESCRIPCION LONGITUD VECES Q TOTAL VARILLA ( Kg)
(m) SE REPITE (m)
(1) (2) (3) (4) (5)=(1)x(2)x(3)x(4)

DE CESAR VALLEJO A CARRETERA INDUSTRIAL


MC-1
ACERO 3/8 267.58 6 1,605.48 0.58 931.18
1.875 1071 2,008.13 1.02 2,048.29
ACERO 1/2
0.8 1339 1,071.20 1.02 1,092.62
PARRILLA 267.53 5 1,337.65 1.02 1,364.40

T O TAL: 5,436.49
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD PEATONAL Y
VEHICULAR EN LA URBANIZACION ALAMEDA DE SAN ANDRES DEL
DISTRITO DE TRUJILLO, PROVINCIA DE TRUJILLO - LA LIBERTAD
PLAN I LLA D E M E TRAD O S

PARTIDA: 01.01.00. OBRAS PROVISIONALES


PARTIDA: 01.01.01. TRANSPORTE DE EQUIPO, HERRAMIENTAS Y MADERA UNIDAD : ( Glb.)
PARTIDA: 01.01.02. MOVILIZACION Y DESMOVILIZACION DE EQUIPOS UNIDAD : ( Glb.)
PARTIDA: 01.01.03. DESVIO Y MANTENIMIENTO DE TRAFICO UNIDAD : ( Glb.)
PARTIDA: 01.01.04. CARTEL DE OBRA UNIDAD : ( Glb.)
PARTIDA: 01.01.05. LIMPIEZA DURANTE LA OBRA (Eliminacion de residuos solidos) UNIDAD : ( m )
PARTIDA: 01.02.00. TRABAJOS PRELIMINARES
PARTIDA: 01.02.01. DEMOLICION DE VEREDAS DE CONCRETO A PULSO, e=10 cm. UNIDAD : ( m )
PARTIDA: 01.02.02. DEMOLICION DE SARDINELES EN L UNIDAD : ( m )
PARTIDA: 01.02.03. DEMOLICION DE PAVIMENTO FLEXIBLE UNIDAD : ( m )
PARTIDA: 01.02.04. TRAZO Y REPLANTEO EN VEREDAS UNIDAD : ( m )
PARTIDA: 01.02.05. TRAZO Y REPLANTEO EN SARDINELES UNIDAD : ( ml. )
PARTIDA: 01.02.06. TRAZO Y REPLANTEO EN PAVIMENTACION UNIDAD : ( m2 )
PARTIDA: 01.03.00. MOVIMIENTO DE TIERRAS
PARTIDA: 01.03.01. EXCAVACION DE ZANJAS PARA SARDINELES UNIDAD : ( m )
PARTIDA: 01.03.02. CORTE EN TERRENO NATURAL PARA VEREDAS, e=0.10 m. UNIDAD : ( m )
PARTIDA 01.03.03 CORTE EN TERRENO NATURAL A NIVEL DE SUB RASANTE CON EQUIPO. UNIDAD : ( m3 )
PARTIDA 01.03.04 ELIMINACION DE MATERIAL EXCEDENTE CON ESPONJAMIENTO UNIDAD : ( m. )
PARTIDA: 01.04.00. VEREDAS DE CONCRETO
PARTIDA: 01.04.01. PERFILADO, NIVELACION Y COMPACTACION EN SUB RASANTE PARA VEREDAS. UNIDAD : ( m )
PARTIDA: 01.04.02. BASE GRANULAR PARA VEREDAS, e=10 cm. UNIDAD : ( m )
PARTIDA: 01.04.03. VEREDA e=4" CONCRETO fc=175 Kg/cm2, a=1.20 m, UNA UA UNIDAD : ( m )
PARTIDA: 01.04.05. CURADO DE VEREDAS CON CURADOR QUIMICO UNIDAD : ( m )
PARTIDA.01.04.04 : JUNTAS DE DILATACION EN VEREDAS CADA 4.00 m., e=1/2'' UNIDAD : ( ml. )
PARTIDA: 01.05.00. SARDINELES
PARTIDA: 01.05.01. SARDINEL: 0.15x0.40 m.,CONCRETO fc= 175 kg/cm2 UNIDAD : ( m. )
PARTIDA 01.05.02: SARDINEL, ENCOFRADO Y DESENCOFRADO NORMAL, Altura de encofrado = 0.20 m. UNIDAD : ( m2 )
PARTIDA 01.05.03: JUNTAS DE DILATACION EN SARDINELES: C/3 m. ,e= 1/2" UNIDAD : ( m2 )
PARTIDA: 01.06.00. PAVIMENTACION
PARTIDA:01.06.01 PREPARACION DE SUB RASANTE UNIDAD : ( m )
PARTIDA:01.06.02 SUB BASE GRANULAR, e = 15 cm. UNIDAD : ( m )
PARTIDA:01.06.03 BASE GRANULAR, e = 20 cm. UNIDAD : ( m )
PARTIDA:01.06.04 IMPRIMACION ASFALTICA. UNIDAD : ( m )
PARTIDA:01.06.05 CARPETA ASFLTICA CON EMULSION, e = 2" C/EQUIPO UNIDAD : ( m )
PARTIDA:01.06.06 SLURRY SEAL, e = 10 mm. UNIDAD : ( m )
PARTIDA: 01.07.00. SEALIZACION
PARTIDA:01.07.01 SEALIZACION HORIZONTAL UNIDAD : ( m )
PARTIDA: 01.07.02. PINTURA PARA SARDINELES UNIDAD : ( ml. )
PARTIDA: 01.08.00. VARIOS
PARTIDA:01.08.01 NIVELAR CAJAS DE AGUA UNIDAD : ( Und. )
PARTIDA:01.08.02 NIVELAR CAJAS DE DESAGUE UNIDAD : ( Und. )
PARTIDA:01.08.03 LEVANTAR NIVEL DE TECHO DE BUZON hprom=0.10 m. UNIDAD : ( Und. )