P6_TR3_CEYCA_SEM40_REV1 Classic WBS Layout 12-Oct-11 04:03 PM

Activity ID Activity Name Original Start Finish Remaining Schedule Total September 2011 October 2011 November 2011 December 2011 January 2012
Duration % Float
04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15
Duration Complete
1 P6_TR3_CEYCA_SEM40_REV1 85.7d 08-Sep-11
13-Jan-12 69.8d 0% 0.0d 13-Jan-12 03:00 PM, 1 P6_TR3_CEYCA_
06:01 03:00
1.1 HITOS DEL PROYECTO 69.8d 10-Oct-11
13-Jan-12
06:00 AM03:00
69.8d
PM 0% 0.0d 13-Jan-12 03:00 PM, 1.1 HITOS DEL PRO

A2520 INICIO DE PROYECTO 0.0d 10-Oct-11 06:00 AM 0.0d 0% 0.0d INICIO DE PROYECTO
A2530 FIN DE PROYECTO 0.0d 13-Jan-12 03:000.0d
PM 0% 0.0d FIN DE PROYECTO
A2540 INICIO DE MOVILIZACIN 0.0d 10-Oct-11 06:00 AM 0.0d 0% 4.0d INICIO DE MOVILIZACIN
A2550 INICIO ESTACIN DE BOMBEO 0.0d 17-Oct-11 10:00 AM 0.0d 0% 0.0d INICIO ESTACIN DE BOMBEO
A2560 FIN ESTACIN DE BOMBEO 0.0d 15-Dec-11 05:000.0d
PM 0% 0.0d FIN ESTACIN DE BOMBEO
A2570 INICIO SUB ESTACIN ELCTRICA 0.0d 14-Oct-11 03:00 PM 0.0d 0% 15.0d INICIO SUB ESTACIN ELCTRICA
A2573 ENTREGA DE PLANOS INGENIERIA DETALLES 0.0d 13-Oct-11 08:00 AM 0.0d 0% 15.0d ENTREGA DE PLANOS INGENIERIA DETALLES
A2580 FIN SUB ESTACIN ELCTRICA 0.0d 26-Dec-11 03:000.0d
PM 0% 11.0d FIN SUB ESTACIN ELCTRICA
A2583 FIN DE TRABAJOS MECANICOS 0.0d 15-Dec-11 05:000.0d
PM 0% 0.0d FIN DE TRABAJOS MECANICOS
A2585 FIN TRABAJOS ESTRUCTURALES TABLEROS 0.0d 07-Nov-11 08:000.0d
AM 0% 34.0d FIN TRABAJOS ESTRUCTURALES TABLEROS
A2590 INICIO TRABAJOS PERIMETRALES 0.0d 02-Nov-11 08:00 AM 0.0d 0% 31.0d INICIO TRABAJOS PERIMETRALES
A2600 FIN TRABAJOS PERIMETRALES 0.0d 10-Dec-11 05:000.0d
PM 0% 29.0d FIN TRABAJOS PERIMETRALES

1.2 TRAMITES ADMINISTRATIVOS 27.8d 08-Sep-11


11-Oct-11
06:01 AM03:01
A 0.0d
PM A 0% 11-Oct-11 03:01 PM A, 1.2 T RAMITES ADMINISTRATIVOS
A2609 OBTENCIN DE FOTOCHECK 21.0d 08-Sep-11
05-Oct-11
06:01 AM03:01
A 0.0d
PM A 17.85% OBTENCIN DE FOTOCHECK
A2610 GESTION DE CAMBIO 12.0d 08-Sep-11
22-Sep-11
08:01 AM03:01
A 0.0d
PM A 0% GESTION DE CAMBIO
A2620 PLAN DE MANEJO AMBIENTAL 12.0d 08-Sep-11
22-Sep-11
08:01 AM03:01
A 0.0d
PM A 0% PLAN DE MANEJO AMBIENTAL
A2630 PLAN DE CONTROL DE CALIDAD 2.0d 16-Sep-11
11-Oct-11
08:01 AM03:01
A 0.0d
PM A 100% PLAN DE CONTROL DE CALIDAD
1.3 CONSTRUCCIN 73.5d 05-Oct-11
13-Jan-12
10:01 AM03:00
A 67.5d
PM 0% 0.0d 13-Jan-12 03:00 PM, 1.3 CONSTRUCCI

1.3.1 TRABAJOS PRELIMINARES 6.7d 05-Oct-11


13-Oct-11
10:01 AM08:00
A 0.8d
AM 0% 0.0d 13-Oct-11 08:00 AM, 1.3.1 TRABAJOS PRELIMINARES
A2640
MOVILIZACIN 5.0d 05-Oct-11
11-Oct-11
10:01 AM10:01
A 0.0d
AM A 89.96% MOVILIZACIN
A2650
INSTALACIN DE OFICINAS, ALMACEN Y REFUGIO 2.0d 05-Oct-11
11-Oct-11
10:01 AM06:01
A 0.0d
AM A 100% INSTALACIN DE OFICINAS, ALMACEN Y REFUGIO
A2660
T RAZO Y REPLANTEO 1.0d 12-Oct-11
13-Oct-11
10:00 AM08:001.0d
AM 0% 0.0d TRAZO Y REPLANTEO
1.3.2 ESTACION DE BOMBEO 66.8d 13-Oct-11
13-Jan-12
08:00 AM03:00
66.8d
PM 0% 0.0d 13-Jan-12 03:00 PM, 1.3.2 ESTACION DE
1.3.2.1 SISTEMA DE PUESTA A TIERRA 25.0d 13-Oct-11
16-Nov-11
08:00 AM05:00
25.0d
PM 0% 0.0d 16-Nov-11 05:00 PM, 1.3.2.1 SISTEMA DE PUESTA A TIERRA
1.3.2.1.CIV CIVIL 10.0d 13-Oct-11
27-Oct-11
08:00 AM08:00
10.0d
AM 0% 0.0d 27-Oct-11 08:00 AM, 1.3.2.1.CIV CIVIL
EXCAVACION PARA MALLA A TIERRA 4.0d 13-Oct-11
17-Oct-11
08:00 AM10:004.0d
AM 0% 0.0d EXCAVACION PARA MALLA A TIERRA
RELLENO CON TIERRA DE CHACRA 3.0d 17-Oct-11
19-Oct-11
10:00 AM03:003.0d
PM 0% 0.0d RELLENO CON TIERRA DE CHACRA
RELLENO COMPACTADO CON MATERI AL PROPIO DE MALLAS
4.0d 24-Oct-11
27-Oct-11
06:00 AM08:004.0d
AM 0% 0.0d RELLENO COMPACTADO CON MATERIAL PROPIO DE MALLAS
1.3.2.1.ELE ELECTRICA 22.8d 17-Oct-11
16-Nov-11
10:00 AM05:00
22.8d
PM 0% 0.0d 16-Nov-11 05:00 PM, 1.3.2.1.ELE ELECTRICA
TENDIDO DE CABLE DE COBRE DESNUDO 4.0d 17-Oct-11
20-Oct-11
10:00 AM12:004.0d
PM 0% 0.0d TENDIDO DE CABLE DE COBRE DESNUDO
SOLDADURA CADWELD PARA MALLA 3.0d 20-Oct-11
22-Oct-11
12:00 PM05:003.0d
PM 0% 0.0d SOLDADURA CADWELD PARA MALLA
ATERRAMIENTO DE ESTRUCTURAS Y EQUIPOS 3.0d 14-Nov-11
16-Nov-11
12:00 PM05:003.0d
PM 0% 0.0d ATERRAMIENTO DE ESTRUCTURAS Y EQUIPOS
1.3.2.2 CIMIENTO DE LOSA 26.9d 24-Oct-11
30-Nov-11
08:30 AM08:00
26.9d
AM 0% 0.0d 30-Nov-11 08:00 AM, 1.3.2. 2 C IMIENTO DE LOSA
1.3.2.2.CIV CIVIL 18.7d 24-Oct-11
17-Nov-11
08:30 AM03:00
18.7d
PM 0% 0.0d 17-Nov-11 03:00 PM, 1.3.2.2.CIV CIVIL
EXCAVACION PARA LOSA DE PISO Y PEDESTALES 4.0d 24-Oct-11
28-Oct-11
08:30 AM10:304.0d
AM 0% 2.8d EXCAVACION PARA LOSA DE PISO Y PEDESTALES
RELLENO COMPACTADO 1.0d 17-Nov-11
17-Nov-11
06:00 AM03:001.0d
PM 0% 0.0d RELLENO COMPACTADO
EXCAVACION DE SUMIDERO 1.0d 02-Nov-11
03-Nov-11
12:30 PM10:301.0d
AM 0% 15.4d EXCAVACION DE SUMIDERO
1.3.2.2.CON CONCRETO 8.3d 17-Nov-11
30-Nov-11
03:00 PM08:008.3d
AM 0% 0.0d 30-Nov-11 08:00 AM, 1.3.2. 2.CO N CO NCR ETO
COLOCACIN DE ACERO EN LOSA Y SARDINEL 3.0d 17-Nov-11
21-Nov-11
03:00 PM08:003.0d
AM 0% 0.0d COLOCACIN DE ACERO EN LOSA Y SARDINEL
COLOCACION DE PERNOS DE ANCLAJE EN LOSA Y PEDESTALES
2.0d 21-Nov-11
22-Nov-11
08:00 AM03:002.0d
PM 0% 0.0d COLOCACION DE PERNOS DE ANCLAJE EN LOSA Y PEDESTALES
ENCOFRADO DE LOSA, PEDESTALES Y SARDINEL 3.0d 22-Nov-11
25-Nov-11
03:00 PM08:003.0d
AM 0% 0.0d ENCOFRADO DE LOSA, PEDESTALES Y SARDINEL
COLOCACIN DE CONCRETO DE LOSA, SARDINEL Y PEDESTALES
3.0d 24-Nov-11
26-Nov-11
10:00 AM03:003.0d
PM 0% 0.0d COLOCACIN DE CONCRETO DE LOSA, SARDINEL Y PEDESTALES
DESENCOFRADO DE LOSA, PEDESTALES Y SARDINEL1.0d 26-Nov-11
28-Nov-11
03:00 PM12:001.0d
PM 0% 0.0d DESENCOFRADO DE LOSA, PEDESTALES Y SARDINEL
REALIZACION DE JUNTAS DE DILATACIO N 2.0d 28-Nov-11
30-Nov-11
12:00 PM08:002.0d
AM 0% 0.0d REALIZACION DE JUNTAS DE DILATACIO N
1.3.2.3 CIMIENTO DE BOMBAS 13.3d 27-Oct-11
15-Nov-11
08:00 AM10:00
13.3d
AM 0% 8.8d 15-Nov-11 10:00 AM, 1.3.2. 3 CIMIENTO DE BOMBAS
1.3.2.3.1 CIVIL 5.0d 27-Oct-11
02-Nov-11
08:00 AM05:005.0d
PM 0% 0.0d 02-Nov-11 05:00 PM, 1.3.2.3.1 CIVIL
EXCAVACION PARA CIMENTACION DE BOMBAS 2.0d 27-Oct-11
28-Oct-11
08:00 AM03:002.0d
PM 0% 0.0d EXCAVACION PARA CIMENTACION DE BOMBAS
COLOCACION DE ACERO PARA PEDESTAL DE BOMBAS3.0d 29-Oct-11
02-Nov-11
12:00 PM05:003.0d
PM 0% 0.0d COLOCACION DE ACERO PAR A PEDESTAL DE BOMBAS
1.3.2.3.2 CONCRETO 11.5d 28-Oct-11
15-Nov-11
03:00 PM10:00
11.5d
AM 0% 8.8d 15-Nov-11 10:00 AM, 1.3.2. 3.2 CON CRETO
COLOCACION DE SOLADO 1.0d 28-Oct-11
29-Oct-11
03:00 PM12:001.0d
PM 0% 0.0d COLOCACION DE SOLADO
ENCOFRADO DE PEDESTAL DE BOMBAS 3.0d 03-Nov-11
05-Nov-11
06:00 AM10:003.0d
AM 0% 0.0d ENCOFRADO DE PEDESTAL DE BOMBAS
COLOCACION DE CONCRETO EN PEDESTAL DE BOMBAS
2.0d 05-Nov-11
07-Nov-11
10:00 AM05:002.0d
PM 0% 0.0d COLOCACION DE CONCRETO EN PEDESTAL DE BOMBAS
DESENCOFRADO DE BASES DE BOMBAS 1.0d 08-Nov-11
08-Nov-11
06:00 AM03:001.0d
PM 0% 0.0d DESENCOFRADO DE BASES DE BOMBAS
GROUTEO DE PEDESTAL DE BOMBAS 1.0d 14-Nov-11
15-Nov-11
12:00 PM10:001.0d
AM 0% 13.0d GROUTEO DE PEDESTAL DE BOMBAS
1.3.2.4 CIMIENTO DE TANQUE 5.8d 27-Oct-11
03-Nov-11
08:00 AM03:005.8d
PM 0% 2.3d 03-Nov-11 03:00 PM, 1.3.2.4 CIMIENTO DE TANQUE
1.3.2.4.1 CIVIL 2.0d 27-Oct-11
29-Oct-11
08:00 AM12:002.0d
PM 0% 3.8d 29-Oct-11 12:00 PM, 1.3.2.4.1 CIVIL
EXCAVACION PARA CIMENTACION DE TANQUE 2.0d 27-Oct-11
28-Oct-11
08:00 AM03:002.0d
PM 0% 0.0d EXCAVACION PARA CIMENTACION DE TANQUE
COLOCACION DE RELLENO COMPACTADO 1.0d 28-Oct-11
29-Oct-11
03:00 PM12:001.0d
PM 0% 4.0d COLOCACION DE RELLENO COMPACTADO
1.3.2.4.2 CONCRETO 3.8d 29-Oct-11
03-Nov-11
12:00 PM03:003.8d
PM 0% 2.3d 03-Nov-11 03:00 PM, 1.3.2.4.2 CONCRETO
ENCOFRADO DE BASE DE TANQUE 2.0d 29-Oct-11
02-Nov-11
12:00 PM08:002.0d
AM 0% 4.0d ENCOFRADO DE BASE DE TANQUE
COLOCACION DE CONCRETO EN BASE DE TANQUE 1.0d 02-Nov-11
02-Nov-11
08:00 AM05:001.0d
PM 0% 4.0d COLOCACION DE CONCRETO EN BASE DE TANQUE
DESENCOFRADO DE BASES DE TANQUE 1.0d 03-Nov-11
03-Nov-11
06:00 AM03:001.0d
PM 0% 4.0d DESENCOFRADO DE BASES DE TANQUE

Actual Work Critical Remaining Work % Complete Page 1 of 4 TASK filter: All Activities

Remaining Work Milestone Summary (c) Primavera Systems, Inc.


P6_TR3_CEYCA_SEM40_REV1 Classic WBS Layout 12-Oct-11 04:03 PM
Activity ID Activity Name Original Start Finish
Remaining Schedule Total September 2011 October 2011 November 2011 December 2011 January 2012
Duration % Float
04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15
Duration Complete
1.3.2.5 FABRICACION DE TANQ UE 33.5d 27-Oct-1113-Dec-11
08:00 AM12:00
33.5d
PM 0% 0.0d 13-Dec-11 12:00 PM, 1.3.2.5 FABR ICACION DE TANQ UE
1.3.2.5.1 ESTRUCTURA 8.0d 27-Oct-1107-Nov-11
08:00 AM05:008.0d
PM 0% 0.0d 07-Nov-11 05:00 PM, 1.3.2.5.1 ESTRUCTURA
METRADOS PROCURA DE MAT ERIALES, CO NSUMIBLES,
3.0dETC
27-Oct-11
29-Oct-11
08:00 AM12:003.0d
PM 0% 0.0d METRADOS PROCURA DE MAT ERIALES, CO NSUMIBLES, ETC
FABRICACION DE PLATAFORMA DE TANQUE EN TALLERES
4.0d 29-Oct-11
03-Nov-11
12:00 PM03:004.0d
PM 0% 0.0d FABRICACION DE PLATAFORMA DE TANQUE EN TALLERES
FABRICACION DE ESCALERA DE GATO EN TALLERES 3.0d 03-Nov-11
07-Nov-11
03:00 PM08:003.0d
AM 0% 0.0d FABRICACION DE ESCALERA DE GATO EN TALLERES
TRASLADO DE ESTRUCTURAS FABRICADAS A MINA 1.0d 07-Nov-11
07-Nov-11
08:00 AM05:001.0d
PM 0% 0.0d TRASLADO DE ESTRUCTURAS FABRICADAS A MINA
1.3.2.5.2 MECANICO 25.5d 08-Nov-11
13-Dec-11
06:00 AM12:00
25.5d
PM 0% 0.0d 13-Dec-11 12:00 PM, 1.3.2.5.2 MECANICO
TRABAJOS PRELIMINARES, FABRICACION DE DISPOSITIVO
3.0d 08-Nov-11
MECANICO10-Nov-11
06:00 AM10:003.0d
AM 0% 0.0d TRABAJOS PRELIMINARES, FABRICACION DE DISPOSITIVO MECANICO
SOLDADURA ENTRE EL 1ER Y 2DA VIROLA DE TANQUE4.0d 10-Nov-11
14-Nov-11
10:00 AM12:004.0d
PM 0% 0.0d SOLDADURA ENTRE EL 1ER Y 2DA VIROLA DE TANQUE
SOLDADURA ENTRE EL 2DA Y 3ERA VIROLA DE TANQUE
4.0d 16-Nov-11
19-Nov-11
08:00 AM10:004.0d
AM 0% 0.0d SOLDADURA ENTRE EL 2DA Y 3ERA VIROLA DE TANQUE
SOLDADURA ENTRE LA 1ERA VIROLA Y AN ILLO DE RI GIDEZ
4.0d 19-Nov-11
DEL TANQUE
23-Nov-11
10:00 AM12:004.0d
PM 0% 0.0d SOLDADURA ENTRE LA 1ERA VIROLA Y ANILLO DE RIGIDEZ DEL TANQUE
SOLDADURA DE BASE DEL TANQUE CON EL 3ERA VIROLA
4.0dDE
23-Nov-11
TANQUE26-Nov-11
12:00 PM03:004.0d
PM 0% 0.0d SOLDADURA DE BASE DEL TANQUE CON EL 3ERA VIROLA DE TANQUE
SOLDADURA DE ACCESORIOS: BOQUILLAS, SOPORTE4.0d
A TANQUE
26-Nov-11
30-Nov-11
03:00 PM05:004.0d
PM 0% 0.0d SOLDADURA DE ACCESORIOS: BOQUILLAS, SOPORTE A TANQUE
ARENADO Y PINTURA BASE DE SUPERFICIE EXTERIOR4.0d
DE TANQUE
01-Dec-11
05-Dec-11
06:00 AM08:004.0d
AM 0% 0.0d ARENADO Y PINTURA BASE DE SUPERFICIE EXTERIOR DE TANQUE
PINTURA DE ACABADO, ARREGLOS FINALES Y TOUCH5.0d
UP DE
05-Dec-11
TANQUE10-Dec-11
08:00 AM08:005.0d
AM 0% 0.0d PINTURA DE ACABADO, ARREGLOS FINALES Y TOUCH UP DE TANQUE
PRUEBAS Y PROTOCOLOS DE ESTANQUEIDAD DEL TANQUE
3.0d 10-Dec-11
13-Dec-11
08:00 AM12:003.0d
PM 0% 0.0d PRUEBAS Y PROTOCOLOS DE ESTAN QUEIDAD DEL TANQUE
1.3.2.6 MONTAJE DE TANQUE Y TUBERIAS 38.0d 14-Nov-11
05-Jan-12
12:00 PM12:00
38.0d
PM 0% 0.0d 05-Jan-12 12:00 PM, 1.3.2.6 MONTAJE DE TANQUE Y T
1.3.2.6.EST ESTRUCTURA 19.0d 21-Nov-11
15-Dec-11
08:00 AM05:00
19.0d
PM 0% 0.0d 15-Dec-11 05:00 PM, 1.3.2.6.EST ESTRUCTURA
MONTAJE DE TANQUE 2.0d 12-Dec-11
13-Dec-11
06:00 AM12:002.0d
PM 0% 0.0d MONTAJE DE TANQUE
MONTAJE DE PLATAFO RMA DE TANQUE 2.0d 13-Dec-11
15-Dec-11
12:00 PM08:002.0d
AM 0% 0.0d MONTAJE DE PLATAFO RMA DE TANQUE
MONTAJE DE ESCALERA DE GATO EN TANQUE 1.0d 13-Dec-11
14-Dec-11
12:00 PM10:001.0d
AM 0% 0.0d MONTAJE DE ESCALERA DE GATO EN TANQUE
HABILITACION Y FABRICACION DE SOPORTES 3.0d 21-Nov-11
23-Nov-11
08:00 AM12:003.0d
PM 0% 4.0d HABILITACION Y FABRICACION DE SOPORTES
MONTAJE DE SOPORTES 2.0d 24-Nov-11
25-Nov-11
10:00 AM05:002.0d
PM 0% 4.0d MONTAJE DE SOPORTES
GROUTEO DE BASE DE SOPORTES 2.0d 14-Dec-11
15-Dec-11
10:00 AM05:002.0d
PM 0% 0.0d GROUTEO DE BASE DE SOPORTES
1.3.2.6.TUB TUBERIAS 19.5d 14-Nov-1110-Dec-11
12:00 PM05:00
19.5d
PM 0% 0.0d 10-Dec-11 05:00 PM, 1.3.2.6.TUB TUBERIAS
HABILITACION Y FABRICACION DE LINEA 1760- WMA- 16-AF
4.0d1-14-Nov-11
16039 17-Nov-11
12:00 PM03:004.0d
PM 0% 4.0d HABILITACION Y FABRICACION DE LINEA 1760- WMA- 16-AF 1- 16039
MONTAJE DE MANIFOLD 1760-WMA-16-AF1-16039 3.0d 30-Nov-11
02-Dec-11
08:00 AM12:003.0d
PM 0% 0.0d MONTAJE DE MANIFOLD 1760-WMA-16-AF1-16039
HABILITACION Y FABRICACION DE LINEA 1760- WMA- 16-AF
4.0d1-17-Nov-11
16014 21-Nov-11
03:00 PM05:004.0d
PM 0% 7.0d HABILITACION Y FABRICACION DE LINEA 1760- WMA- 16-AF 1- 16014
MONTAJE DE MANIFOLD 1760-WMA-16-AF1-16014 4.0d 22-Nov-11
25-Nov-11
06:00 AM08:004.0d
AM 0% 8.0d MONTAJE DE MANIFOLD 1760-WMA-16-AF1-16014
HABILITACION Y FABRICACION DE SPOOLS SECUNDARIOS
5.0d 22-Nov-11
25-Nov-11
06:00 AM05:005.0d
PM 0% 7.0d HABILITACION Y FABRICACION DE SPOOLS SECUNDARIOS
MONTAJE DE SOOLS SECUNDARIOS AUXILIARES 5.0d 02-Dec-11
07-Dec-11
12:00 PM12:005.0d
PM 0% 0.0d MONTAJE DE SOOLS SECUNDARIOS AUXILIARES
HABILITACION Y FABRICACION DE DRENAJE DE TANQUE
2.0d 22-Nov-11
23-Nov-11
06:00 AM12:002.0d
PM 0% 10.0d HABILITACION Y FABRICACION DE DRENAJE DE TANQUE
MONTAJE DE DRENAJE DE TANQUE 1.0d 23-Nov-11
24-Nov-11
12:00 PM10:001.0d
AM 0% 10.0d MONTAJE DE DRENAJE DE TANQUE
FABRICACION Y MONTAJE DE REBOSE DE TANQUE 2.0d 24-Nov-11
25-Nov-11
10:00 AM05:002.0d
PM 0% 10.0d FABRICACION Y MONTAJE DE REBOSE DE TANQUE
MONTAJE DE VALVULAS EN LI NEA DE TUBERIA 5.0d 06-Dec-11
10-Dec-11
06:00 AM05:005.0d
PM 0% 0.0d MONTAJE DE VALVU LAS EN LINEA DE TUBERIA
1.3.2.6.ELE ELECTRICA 5.3d 12-Dec-11
19-Dec-11
06:00 AM10:005.3d
AM 0% 0.0d 19-Dec-11 10:00 AM, 1.3.2.6.ELE ELECT RICA
HABILITACION Y FABRICACION DE SOPORTES PARA TUB
2.0dCONDUIT
12-Dec-11
13-Dec-11
06:00 AM12:002.0d
PM 0% 0.0d HABILITACION Y FABRICACION DE SOPORTES PARA TUB CONDUIT
MONTAJE DE SOPORTE PARA TUBERIA CONDUIT 2.0d 13-Dec-11
15-Dec-11
12:00 PM08:002.0d
AM 0% 0.0d MONTAJE DE SOPORTE PARA TUBERIA CONDUIT
INSTALACION DE TUBERIA CONDUIT FUERZA Y CONTROL
4.0d 15-Dec-11
19-Dec-11
08:00 AM10:004.0d
AM 0% 0.0d INSTALACION DE TUBERIA CONDUIT FUERZA Y CONTROL
1.3.2.6.INS INSTRUMENTACION 13.3d 19-Dec-11
05-Jan-12
10:00 AM12:00
13.3d
PM 0% 0.0d 05-Jan-12 12:00 PM, 1.3.2.6.INS INSTRUMENTACION
HABILITACION Y FABRICACION DE SOPORTES 2.0d 19-Dec-11
20-Dec-11
10:00 AM05:002.0d
PM 0% 0.0d HABILITACION Y FABRICACION DE SOPORTES
MONTAJE DE SOPORTES PARA TUBERIA CONDUIT 1.0d 21-Dec-11
21-Dec-11
06:00 AM03:001.0d
PM 0% 0.0d MONTAJE DE SOPORTES PARA TUBERIA CONDUIT
INSTALACION DE TUBERIA CONDUIT ANALOGICOS 3.0d 21-Dec-11
24-Dec-11
03:00 PM08:003.0d
AM 0% 0.0d INSTALACION DE TUBERIA CONDUIT ANALOGICOS
INSTALACION DE INSTRUMENTOS LE, PI, FIT 3.0d 24-Dec-11
27-Dec-11
08:00 AM12:003.0d
PM 0% 0.0d INSTALACION DE INSTRUMENTOS LE, PI, FIT
INSTALACION DE FLUJOMENTRO FE-1716058 1.0d 27-Dec-11
28-Dec-11
12:00 PM10:001.0d
AM 0% 0.0d INSTALACION DE FLUJOMENTRO FE-1716058
INSTALACION DE VALVULAS F V-176050 / 176052 / 176054
3.0d
/ 176056
28-Dec-11
30-Dec-11
10:00 AM03:003.0d
PM 0% 0.0d INSTALACION DE VALVULAS F V-176050 / 176052 / 176054 / 17605
INSTALACION DE VALVULAS LCV-1716042 1.0d 30-Dec-11
31-Dec-11
03:00 PM12:001.0d
PM 0% 0.0d INSTALACION DE VALVU LAS LCV-1716042
CONEXIONADO DE CABLES A EQUIPOS 2.0d 31-Dec-11
03-Jan-12
12:00 PM08:002.0d
AM 0% 0.0d CONEXIONADO DE CABLES A EQUIPOS
PRUEBAS DE INSTRUMENTACION 3.0d 03-Jan-12
05-Jan-12
08:00 AM12:003.0d
PM 0% 0.0d PRUEBAS DE INSTRUMENTACION
1.3.2.7 INSTALACION DE BOMBAS 11.5d 08-Nov-11
24-Nov-11
03:00 PM10:00
11.5d
AM 0% 8.5d 24-Nov-11 10:00 AM, 1.3.2.7 INSTALACION DE BOMBAS
1.3.2.7.EST ESTRUCTURAS 1.5d 08-Nov-11
10-Nov-11
03:00 PM10:001.5d
AM 0% 1.8d 10-Nov-11 10:00 AM, 1.3.2.7.EST ESTRUCTURAS
INSTALACION DE LAINAS DE NIVELACION 2.0d 08-Nov-11
10-Nov-11
03:00 PM10:002.0d
AM 0% 3.0d INSTALACION DE LAINAS DE NIVELACION
1.3.2.7.MEC MECANICA 3.8d 08-Nov-11
14-Nov-11
03:00 PM12:003.8d
PM 0% 0.0d 14-Nov-11 12:00 PM, 1.3.2.7.MEC MECANICA
MONTAJE DE BOMBAS 1760-PU-16013 0.5d 08-Nov-11
09-Nov-11
03:00 PM08:000.5d
AM 0% 0.0d MONTAJE DE BOMBAS 1760-PU-16013
MONTAJE DE MOTOR 1760-PU-16013 1.0d 09-Nov-11
09-Nov-11
08:00 AM05:001.0d
PM 0% 0.0d MONTAJE DE MOTOR 1760-PU-16013
MONTAJE DE BOMBA 1760-PU-16014 0.5d 10-Nov-11
10-Nov-11
06:00 AM10:000.5d
AM 0% 0.0d MONTAJE DE BOMBA 1760-PU-16014
MONTAJE DE MOTOR 1760-PU-16014 1.0d 10-Nov-11
11-Nov-11
10:00 AM08:001.0d
AM 0% 0.0d MONTAJE DE MOTOR 1760-PU-16014
MONTAJE DE BOMBA 1760-PU-16015 0.5d 11-Nov-11
11-Nov-11
08:00 AM12:000.5d
PM 0% 0.0d MONTAJE DE BOMBA 1760-PU -16015
MONTAJE DE MOTOR 1760-PU-16015 1.0d 11-Nov-11
12-Nov-11
12:00 PM10:001.0d
AM 0% 0.0d MONTAJE DE MOTOR 1760-PU-16015
MONTAJE DE BOMBA 1760-PU-16016 0.5d 12-Nov-11
12-Nov-11
10:00 AM03:000.5d
PM 0% 0.0d MONTAJE DE BOMBA 1760-PU -16016
MONTAJE DE MOTOR 1760-PU-16016 1.0d 12-Nov-11
14-Nov-11
03:00 PM12:001.0d
PM 0% 0.0d MONTAJE DE MOTOR 1760-PU-16016
1.3.2.7.ELE ELECTRICA 7.0d 15-Nov-11
24-Nov-11
10:00 AM10:007.0d
AM 0% 8.5d 24-Nov-11 10:00 AM, 1.3.2.7.ELE ELECT RICA
CONEXIONADO DE MOTORES 4.0d 15-Nov-11
18-Nov-11
10:00 AM12:004.0d
PM 0% 13.0d CONEXIONADO DE MOTORES
INSTALACION DE BOTONERAS 1.0d 18-Nov-11
19-Nov-11
12:00 PM10:001.0d
AM 0% 13.0d INSTALACION DE BOTONERAS
CONEXIONADO DE BOTONERAS 2.0d 19-Nov-11
21-Nov-11
10:00 AM05:002.0d
PM 0% 13.0d CONEXIONADO DE BOTONERAS

Actual Work Critical Remaining Work % Complete Page 2 of 4 TASK filter: All Activities

Remaining Work Milestone Summary (c) Primavera Systems, Inc.


P6_TR3_CEYCA_SEM40_REV1 Classic WBS Layout 12-Oct-11 04:03 PM
Activity ID Activity Name Original Start Finish Remaining Schedule Total September 2011 October 2011 November 2011 December 2011 January 2012
Duration % Float
04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15
Duration Complete
PRUEBAS ELECTRICAS 3.0d 22-Nov-11
24-Nov-11
06:00 AM10:003.0d
AM 0% 13.0d PRUEBAS ELECTRICAS
1.3.2.8 ALUMBRADO DE ESTACIONES DE BOMBEO 14.5d 16-Dec-11
05-Jan-12
06:00 AM12:00
14.5d
PM 0% 0.0d 05-Jan-12 12:00 PM, 1.3.2.8 ALUMBRADO DE ESTACIO
1.3.2.8.CIV CIVIL 1.0d 16-Dec-11
17-Dec-11
06:00 AM12:001.0d
PM 0% 0.0d 17-Dec-11 12:00 PM, 1.3.2.8.CIV CIVIL
EXCAVACION PARA CIMENTACION DE POSTE 2.0d 16-Dec-11
17-Dec-11
06:00 AM12:002.0d
PM 0% 0.0d EXCAVACION PARA CIMENTACION DE POSTE
1.3.2.8.CON CONCRETO 3.5d 17-Dec-11
22-Dec-11
12:00 PM12:003.5d
PM 0% 0.0d 22-Dec-11 12:00 PM, 1.3.2.8.CON CONCRETO
ENCOFRADO PARA CIMENTACION DE POSTE 1.0d 20-Dec-11
20-Dec-11
08:00 AM05:001.0d
PM 0% 0.0d ENCOFRADO PARA CIMENTACION DE POSTE
INSTALACION DE CONCRETO 1.0d 21-Dec-11
21-Dec-11
06:00 AM03:001.0d
PM 0% 0.0d INSTALACION DE CONCRETO
DESENCOFRADO DE CIMENTACION DE POSTE 1.0d 21-Dec-11
22-Dec-11
03:00 PM12:001.0d
PM 0% 0.0d DESENCOFRADO DE CIMENTACION DE POSTE
COLOCACIN DE FIERRO DE REFUERZO 2.0d 17-Dec-11
20-Dec-11
12:00 PM08:002.0d
AM 0% 0.0d COLOCACIN DE FIERRO DE REFUERZO
1.3.2.8.EST ESTRUCTURA 6.3d 19-Dec-11
27-Dec-11
10:00 AM12:006.3d
PM 0% 0.0d 27-Dec-11 12:00 PM, 1.3.2.8.EST ESTRUCTURA
INSTALACION DE PERNO TIPO J (ESPARRAGOS) 1.0d 19-Dec-11
20-Dec-11
10:00 AM08:001.0d
AM 0% 2.0d INSTALACION DE PERNO TIPO J (ESPARRAGOS)
MONTAJE DE POSTES DE ALUMBRADO 4.0d 21-Dec-11
24-Dec-11
03:00 PM05:004.0d
PM 0% 0.0d MONTAJE DE POSTES DE ALUMBRADO
INSTALACION DE PASTORAL 2.0d 26-Dec-11
27-Dec-11
06:00 AM12:002.0d
PM 0% 0.0d INSTALACION DE PASTORAL
1.3.2.8.ELE ELECTRICO 7.0d 27-Dec-11
05-Jan-12
12:00 PM12:007.0d
PM 0% 0.0d 05-Jan-12 12:00 PM, 1.3.2.8.ELE ELECTRICO
INSTALACION DE REFLECTORES 3.0d 27-Dec-11
29-Dec-11
12:00 PM05:003.0d
PM 0% 0.0d INSTALACION DE REFLECTORES
INSTALACION DE CABLE NLT ''SOOW'' 2.0d 30-Dec-11
31-Dec-11
06:00 AM12:002.0d
PM 0% 0.0d INSTALACION DE CABLE NLT ''SOOW''
INSTALACION DE LAS CAJAS DE PASO 2.0d 31-Dec-11
03-Jan-12
12:00 PM08:002.0d
AM 0% 0.0d INSTALACION DE LAS CAJAS DE PASO
CONEXIONADO DE REFLECTORES 1.0d 03-Jan-12
03-Jan-12
08:00 AM05:001.0d
PM 0% 0.0d CONEXIONADO DE REFLECTORES
PRUEBAS ELECTRICAS 2.0d 04-Jan-12
05-Jan-12
06:00 AM12:002.0d
PM 0% 0.0d PRUEBAS ELECTRICAS
1.3.2.9 GESTION DE CIERRE DE SISTEMA 6.3d 05-Jan-12
13-Jan-12
12:00 PM03:006.3d
PM 0% 0.0d 13-Jan-12 03:00 PM, 1.3.2.9 GESTION D
CAMINATAS DE CONSTRUCCION 3.0d 05-Jan-12
07-Jan-12
12:00 PM05:003.0d
PM 0% 0.0d CAMINATAS DE CONSTRUCCION
CAMINATAS NARANJA 2.0d 12-Jan-12
13-Jan-12
08:00 AM03:002.0d
PM 0% 0.0d CAMINATAS NARANJA
1.3.3 SUB ESTACION ELECTRICA 55.0d 14-Oct-11
30-Dec-11
03:00 PM03:00
55.0d
PM 0% 10.0d 30-Dec-11 03:00 PM, 1.3.3 SUB ESTACION ELECTRICA
20.3d 14-Oct-11
1.3.3.1 SISTEMA DE PUESTA A TIERRA Y DESCARGA ATMOSFERICA 11-Nov-11
03:00 PM05:00
20.3d
PM 0% 6.8d 11-Nov-11 05:00 PM, 1.3.3.1 SISTEMA DE PUESTA A TIERRA Y DESCARGA ATMOSFERICA
1.3.3.1.CIV CIVIL 20.3d 14-Oct-11
11-Nov-11
03:00 PM05:00
20.3d
PM 0% 6.8d 11-Nov-11 05:00 PM, 1.3.3.1.CIV CIVIL
EXCAVACIN PARA MALLA A TIERRA 4.0d 14-Oct-11
18-Oct-11
03:00 PM05:004.0d
PM 0% 11.0d EXCAVACIN PARA MALLA A TIERRA
EXCAVACION PARA PODIO DE PARRARAYO 1.0d 19-Oct-11
19-Oct-11
06:00 AM03:001.0d
PM 0% 11.0d EXCAVACION PARA PODIO DE PARRARAYO
EXCAVACION PARA POZOS A TIERR A 1.0d 19-Oct-11
20-Oct-11
03:00 PM12:001.0d
PM 0% 29.0d EXCAVACION PARA POZOS A TIERRA
RELLENO CON TIERRA DE CHACRA EN MALLA 2.0d 18-Oct-11
19-Oct-11
08:00 AM03:002.0d
PM 0% 31.0d RELLENO CON TIERRA DE CHACRA EN MALLA
RELLENO DE POZO A TIERRA 1.0d 20-Oct-11
21-Oct-11
12:00 PM10:001.0d
AM 0% 31.0d RELLENO DE POZO A TIERRA
RELLENO COMPACTADO CON MATERI AL PROPIO EN MALLAS
2.0d 10-Nov-11
11-Nov-11
10:00 AM05:002.0d
PM 0% 11.0d RELLENO COMPACTADO CON MATERIAL PROPIO EN MALLAS
1.3.3.1.CON CONCRETO 2.3d 21-Oct-11
25-Oct-11
10:00 AM12:002.3d
PM 0% 8.5d 25-Oct-11 12:00 PM, 1.3.3.1.CON CONCRETO
COLOCACION DE ACERO EN PODIO DE PARRARRAYO1.0d 21-Oct-11
22-Oct-11
10:00 AM08:001.0d
AM 0% 11.0d COLOCACION DE ACERO EN PODIO DE PARRARRAYO
ENCOFRADO PARA PODIO DE PARRARAYO 1.0d 22-Oct-11
22-Oct-11
08:00 AM05:001.0d
PM 0% 11.0d ENCOFRADO PARA PODIO DE PARRARAYO
COLOCACION DE CONCRETO EN PODIO DE PARRARAYO
1.0d 24-Oct-11
24-Oct-11
06:00 AM03:001.0d
PM 0% 11.0d COLOCACION DE CONCRETO EN PODIO DE PARRARAYO
DESENCOFRADO EN PODIO DE PARRARAYO 1.0d 24-Oct-11
25-Oct-11
03:00 PM12:001.0d
PM 0% 11.0d DESENCOFRADO EN PODIO DE PARRARAYO
1.3.3.1.EST ESTRUCTURAS 0.0d 05-Nov-11
07-Nov-11
10:00 AM08:000.0d
AM 0% 8.0d 07-Nov-11 08:00 AM, 1.3.3.1.EST ESTRUCTURAS
MONTAJE DE POSTE PARA PARRARAYOS 1.0d 05-Nov-11
07-Nov-11
10:00 AM08:001.0d
AM 0% 11.0d MONTAJE DE POSTE PARA PARRARAYOS
1.3.3.1.ELE ELECTRICA 3.8d 04-Nov-11
10-Nov-11
12:00 PM10:003.8d
AM 0% 6.8d 10-Nov-11 10:00 AM, 1.3.3.1.ELE ELECT RICA
TENDIDO DE CONDUCTOR DE COBRE DESNUDO Y VARILLA
2.0d 07-Nov-11
08-Nov-11
08:00 AM03:002.0d
PM 0% 11.0d TENDIDO DE CONDUCTOR DE COBRE DESNUDO Y VARILLA
SOLDADURA CADWELD EN MALLA PT 2.0d 08-Nov-11
10-Nov-11
03:00 PM10:002.0d
AM 0% 11.0d SOLDADURA CADWELD EN MALLA PT
INSTALACION DE PARARRAYO PDL INCL. DETALLES 1.0d 04-Nov-11
05-Nov-11
12:00 PM10:001.0d
AM 0% 11.0d INSTALACION DE PARARRAYO PDL INCL. DETALLES
1.3.3.2 ALIMENTACION SUBESTACION MOVIL 13.3d 05-Nov-11
24-Nov-11
10:00 AM10:00
13.3d
AM 0% 8.5d 24-Nov-11 10:00 AM, 1.3.3.2 ALIMENTACION SUBESTACION MOVIL
1.3.3.2.ELE ELECTRICO 13.3d 05-Nov-11
24-Nov-11
10:00 AM10:00
13.3d
AM 0% 8.5d 24-Nov-11 10:00 AM, 1.3.3.2.ELE ELECT RICO
TENDIDO DE CABLE MINERO 8 KV 15.0d 05-Nov-11
19-Nov-11
10:00 AM10:00
15.0d
AM 0% 13.0d TENDIDO DE CABLE MINERO 8 KV
CONEXIONADO DE ENCHUFE 8 KV 4.0d 19-Nov-11
23-Nov-11
10:00 AM12:004.0d
PM 0% 13.0d CONEXIONADO DE ENCHUFE 8 KV
TIE-IN ELECTRICO 1.0d 23-Nov-11
24-Nov-11
12:00 PM10:001.0d
AM 0% 13.0d TIE-IN ELECTRICO
1.3.3.3 CASA DE FUERZA 20.0d 21-Nov-11
17-Dec-11
08:00 AM12:00
20.0d
PM 0% 8.0d 17-Dec-11 12:00 PM, 1.3.3.3 CASA DE FUERZA
1.3.3.3.ELE ELECTRICA 11.8d 21-Nov-11
06-Dec-11
08:00 AM03:00
11.8d
PM 0% 8.5d 06-Dec-11 03:00 PM, 1.3.3.3.ELE ELECTRICA
MONTAJE Y CONEXIONADO DE ESTACIONES MOVILES6.0d 21-Nov-11
25-Nov-11
08:00 AM05:006.0d
PM 0% 11.0d MONTAJE Y CONEXIONADO DE ESTACIONES MOVILES
TENDIDO DE CABLE MINERO A TABLEROS DE BOMBAS2.0d 26-Nov-11
28-Nov-11
06:00 AM12:002.0d
PM 0% 11.0d TENDIDO DE CABLE MINERO A TABLEROS DE BOMBAS
TENDIDO DE CABLE PARA ILUMINACION 1.0d 28-Nov-11
29-Nov-11
12:00 PM10:001.0d
AM 0% 12.0d TENDIDO DE CABLE PARA ILUMINACION
AMARILLADO Y ATERRAMIENTO DE CABLES 4.0d 29-Nov-11
02-Dec-11
10:00 AM12:004.0d
PM 0% 12.0d AMARILLADO Y ATERRAMIENTO DE CABLES
CONEXIONADO DE CABLES A 1760-US-16032 1.0d 02-Dec-11
03-Dec-11
12:00 PM10:001.0d
AM 0% 12.0d CONEXIONADO DE CABLES A 1760-US-16032
CONEXIONADO DE CABLES A 1760-US-16033 1.0d 03-Dec-11
05-Dec-11
10:00 AM08:001.0d
AM 0% 12.0d CONEXIONADO DE CABLES A 1760-US-16033
ROTULADO Y TAGGEADO DE CABLES 2.0d 05-Dec-11
06-Dec-11
08:00 AM03:002.0d
PM 0% 12.0d ROTULADO Y TAGGEAD O D E CABLES
1.3.3.3.INS INSTRUMENTACION 8.3d 06-Dec-11
17-Dec-11
03:00 PM12:008.3d
PM 0% 8.0d 17-Dec-11 12:00 PM, 1.3.3.3.INS INSTRUMENTACION
TENDIDO DE CABLE A PLC 1.0d 06-Dec-11
07-Dec-11
03:00 PM12:001.0d
PM 0% 12.0d TENDIDO DE CABLE A PLC
TENDIDO DE CABLE DE CONTROL 2.0d 07-Dec-11
10-Dec-11
12:00 PM08:002.0d
AM 0% 12.0d TENDIDO DE CABLE DE CONTROL
AMARILLADO Y ATERRAMIENTO DE CABLES 2.0d 10-Dec-11
12-Dec-11
08:00 AM03:002.0d
PM 0% 12.0d AMARILLADO Y ATERRAMIENTO DE CABLES
CONEXIONADO DE CABLES A 1760-US-16032 2.0d 12-Dec-11
14-Dec-11
03:00 PM10:002.0d
AM 0% 12.0d CONEXIONADO DE CABLES A 1760-US-16032
CONEXIONADO DE CABLES A 1760-US-16033 2.0d 14-Dec-11
15-Dec-11
10:00 AM05:002.0d
PM 0% 12.0d CONEXIONADO DE CABLES A 1760-US-16033
ROTULADO Y TAGGEADO DE CABLES 2.0d 16-Dec-11
17-Dec-11
06:00 AM12:002.0d
PM 0% 12.0d ROTULADO Y TAGGEADO DE CABLES
1.3.3.4 TABLEROS 47.3d 20-Oct-11
26-Dec-11
12:00 PM03:00
47.3d
PM 0% 7.8d 26-Dec-11 03:00 PM, 1.3.3.4 TABLEROS
1.3.3.4.CIV CIVIL 2.3d 20-Oct-11
24-Oct-11
12:00 PM03:002.3d
PM 0% 24.3d 24-Oct-11 03:00 PM, 1.3.3.4.CIV CIVIL
EXCAVACION DE LOSA PARA TABLERO DE INSTRUMENTACION
3.0d 20-Oct-11
22-Oct-11
12:00 PM05:003.0d
PM 0% 29.0d EXCAVACION DE LOSA PARA TABLERO DE INSTRUMENTACION

Actual Work Critical Remaining Work % Complete Page 3 of 4 TASK filter: All Activities

Remaining Work Milestone Summary (c) Primavera Systems, Inc.


P6_TR3_CEYCA_SEM40_REV1 Classic WBS Layout 12-Oct-11 04:03 PM
Activity ID Activity Name Original Start Finish Remaining Schedule Total September 2011 October 2011 November 2011 December 2011 January 2012
Duration % Float
04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15
Duration Complete
RELLENO EN LOSA 1.0d 24-Oct-11
24-Oct-11
06:00 AM03:001.0d
PM 0% 34.0d RELLENO EN LOSA
1.3.3.4.CON CONCRETO 3.3d 24-Oct-11
27-Oct-11
03:00 PM05:003.3d
PM 0% 23.0d 27-Oct-11 05:00 PM, 1.3.3.4.CON CONCRETO
COLOCACION DE ACERO EN LOSA 1.0d 24-Oct-11
25-Oct-11
03:00 PM12:001.0d
PM 0% 34.0d COLOCACION DE ACERO EN LOSA
ENCOFRADO DE LOSA 1.0d 25-Oct-11
26-Oct-11
12:00 PM10:001.0d
AM 0% 34.0d ENCOFRADO DE LOSA
COLOCACION DE CONCRETO 1.0d 26-Oct-11
27-Oct-11
10:00 AM08:001.0d
AM 0% 34.0d COLOCACION DE CONCRETO
DESENCOFRADO DE LOSA 1.0d 27-Oct-11
27-Oct-11
08:00 AM05:001.0d
PM 0% 34.0d DESENCOFRADO DE LOSA
1.3.3.4.EST ESTRUCTURA 9.3d 24-Oct-11
05-Nov-11
03:00 PM10:009.3d
AM 0% 22.5d 05-Nov-11 10:00 AM, 1.3.3.4.EST ESTRUCTURA
HABILITACION Y FABRICACION DE PERFILES 5.0d 24-Oct-11
28-Oct-11
03:00 PM03:005.0d
PM 0% 34.0d HABILITACION Y FABRICACION DE PERFILES
MONTAJE DE PERFILES ESTRUCTURALES 2.0d 03-Nov-11
04-Nov-11
06:00 AM12:002.0d
PM 0% 34.0d MONTAJE DE PERFILES ESTRUCTURALES
FABRICACION DE VIGAS Y DIAGONALES 3.0d 26-Oct-11
28-Oct-11
10:00 AM03:003.0d
PM 0% 34.0d FABRICACION DE VIGAS Y DIAGONALES
MONTAJE DE VIGAS Y DIAGONALES 2.0d 03-Nov-11
05-Nov-11
03:00 PM10:002.0d
AM 0% 34.0d MONTAJE DE VIGAS Y DIAGONALES
PINTURA BASE Y ACABADO DE PERFILES 2.0d 28-Oct-11
31-Oct-11
03:00 PM10:002.0d
AM 0% 34.0d PINTURA BASE Y ACABADO DE PERFILES
1.3.3.4.ARQ ARQUITECTURA 0.0d 05-Nov-11
07-Nov-11
10:00 AM08:000.0d
AM 0% 24.3d 07-Nov-11 08:00 AM, 1.3.3.4.ARQ ARQUITECTURA
MONTAJE DE COBERTURA TR4 1.0d 05-Nov-11
07-Nov-11
10:00 AM08:001.0d
AM 0% 34.0d MONTAJE DE COBERTURA TR4
1.3.3.4.ELE ELECTRICA 10.3d 28-Nov-11
12-Dec-11
12:00 PM03:00
10.3d
PM 0% 7.8d 12-Dec-11 03:00 PM, 1.3.3.4.ELE ELECTRICA
MONTAJE DE TABLEROS ELECTRICOS 3.0d 28-Nov-11
30-Nov-11
12:00 PM05:003.0d
PM 0% 11.0d MONTAJE DE TABLEROS ELECTRICOS
CONEXIONADO DE TABLEROS 4.0d 01-Dec-11
05-Dec-11
06:00 AM08:004.0d
AM 0% 11.0d CONEXIONADO DE TABLEROS
TENDIDO DE CABLE A BOMBAS 2.0d 06-Dec-11
07-Dec-11
06:00 AM12:002.0d
PM 0% 11.0d TENDIDO DE CABLE A BOMBAS
TENDIDO DE CABLE A BOTONERAS 2.0d 07-Dec-11
10-Dec-11
12:00 PM08:002.0d
AM 0% 11.0d TENDIDO DE CABLE A BOTONERAS
ROTULADO Y TAGGEADO DE CABLES DE BOMBAS 1.0d 10-Dec-11
10-Dec-11
08:00 AM05:001.0d
PM 0% 11.0d ROTULADO Y TAGGEAD O D E CABLES DE BOMBAS
ROTULADO Y TAGGEADO DE CABLES DE BOTONERAS1.0d 12-Dec-11
12-Dec-11
06:00 AM03:001.0d
PM 0% 11.0d ROTULADO Y TAGGEADO DE CABLES DE BOTONERAS
1.3.3.4.INS INSTRUMENTACION 10.0d 12-Dec-11
26-Dec-11
03:00 PM03:00
10.0d
PM 0% 7.8d 26-Dec-11 03:00 PM, 1.3.3.4.INS INSTRUMENTACION
MONTAJE DE TABLEROS (PLC PANEL INSTRUMENTACIN)
2.0d 12-Dec-11
14-Dec-11
03:00 PM10:002.0d
AM 0% 11.0d MONTAJE DE TABLEROS (PLC PANEL INSTRUMENTACIN)
CONEXIONADO DE TABLEROS 3.0d 14-Dec-11
16-Dec-11
10:00 AM03:003.0d
PM 0% 11.0d CONEXIONADO DE TABLEROS
TENDIDO E INSTALACION DE CABLE A INSTRUMENTOS2.0d 16-Dec-11
19-Dec-11
03:00 PM10:002.0d
AM 0% 11.0d TENDIDO E INSTALACION DE CABLE A INSTRUMENTOS
CONEXIONADO INTERNO DE CABLES A INSTRUMENTO3.0d
S 19-Dec-11
21-Dec-11
10:00 AM03:003.0d
PM 0% 11.0d CONEXIONADO INTERNO DE CABLES A INSTRUMENTO S
ROTULADO Y TAGGEADO DE CABLES 2.0d 21-Dec-11
23-Dec-11
03:00 PM10:002.0d
AM 0% 11.0d ROTULADO Y TAGGEADO DE CABLES
PRUEBAS DE INSTRUMENTACION 3.0d 23-Dec-11
26-Dec-11
10:00 AM03:003.0d
PM 0% 11.0d PRUEBAS DE INSTRUMENTACION
1.3.3.5 GESTION DE CIERRE DE SISTEMA 4.0d 26-Dec-11
30-Dec-11
03:00 PM03:004.0d
PM 0% 10.0d 30-Dec-11 03:00 PM, 1.3.3.5 GESTION DE CIERRE DE SISTEMA
CAMINATAS DE CONSTRUCCION 3.0d 26-Dec-11
29-Dec-11
03:00 PM08:003.0d
AM 0% 15.0d CAMINATAS DE CONSTRUCCION
CAMINATAS NARANJA 2.0d 29-Dec-11
30-Dec-11
08:00 AM03:002.0d
PM 0% 15.0d CAMINATAS NARANJA
1.3.4 TRABAJOS PERIMETRALES 33.0d 02-Nov-11
17-Dec-11
08:00 AM12:00
33.0d
PM 0% 19.8d 17-Dec-11 12:00 PM, 1.3.4 TRABAJOS PERIMETRALES
1.3.4.1 LINEA DE IMPUL SION-1 13.0d 02-Nov-11
19-Nov-11
08:00 AM10:00
13.0d
AM 0% 20.3d 19-Nov-11 10:00 AM, 1.3.4. 1 LINEA DE IMPULSION-1
1.3.4.1.CIV CIVIL 13.0d 02-Nov-11
19-Nov-11
08:00 AM10:00
13.0d
AM 0% 20.3d 19-Nov-11 10:00 AM, 1.3.4. 1.CI V C IVIL
EXCAVACION DE ZANJA 2.0d 02-Nov-11
03-Nov-11
08:00 AM03:002.0d
PM 0% 29.0d EXCAVACION DE ZANJA
COLOCACION DE CAMA DE ARENA 3.0d 03-Nov-11
07-Nov-11
03:00 PM08:003.0d
AM 0% 29.0d COLOCACION DE CAMA DE ARENA
RELLENO Y COMPACTACION 2.0d 15-Nov-11
16-Nov-11
10:00 AM05:002.0d
PM 0% 30.0d RELLENO Y COMPACTACION
ELIMINACION DE MATERIAL EXCEDENTE 3.0d 17-Nov-11
19-Nov-11
06:00 AM10:003.0d
AM 0% 30.0d ELIMINACION DE MATERIAL EXCEDENTE
1.3.4.1.TUB TUBERIAS 8.8d 07-Nov-11
17-Nov-11
08:00 AM03:008.8d
PM 0% 20.3d 17-Nov-11 03:00 PM, 1.3.4.1.TUB TUBERIAS
TENDIDO DE TUBERIAS HDPE SDR9 16" 7.0d 07-Nov-11
12-Nov-11
08:00 AM03:007.0d
PM 0% 29.0d TENDIDO DE TUBERIAS HDPE SDR9 16"
PRUEBAS HIDROSTATICAS, FLUSHING, UT 2.0d 12-Nov-11
15-Nov-11
03:00 PM10:002.0d
AM 0% 29.0d PRUEBAS HIDROSTATICAS, FLUSHING, UT
EJECUCION DE TIE-IN 1.0d 15-Nov-11
16-Nov-11
10:00 AM08:001.0d
AM 0% 29.0d EJECUCION DE TIE-IN
ROTULACION Y TAG GEADO DE TUBERIAS 2.0d 16-Nov-11
17-Nov-11
08:00 AM03:002.0d
PM 0% 29.0d ROTULACION Y TAG GEADO D E TUBERIAS
1.3.4.2 CERCO PERIMETRICO 16.3d 17-Nov-11
10-Dec-11
03:00 PM05:00
16.3d
PM 0% 20.0d 10-Dec-11 05:00 PM, 1.3.4.2 CERCO PERIMETRICO
1.3.4.2.CIV CIVIL 6.3d 17-Nov-11
25-Nov-11
03:00 PM05:006.3d
PM 0% 20.0d 25-Nov-11 05:00 PM, 1.3.4.2.CIV CIVIL
EXCAVACION PARA POSTES 9.0d 17-Nov-11
25-Nov-11
03:00 PM05:009.0d
PM 0% 29.0d EXCAVACION PARA POSTES
1.3.4.2.CON CONCRETO 3.3d 22-Nov-11
26-Nov-11
03:00 PM03:003.3d
PM 0% 20.0d 26-Nov-11 03:00 PM, 1.3.4.2.CON CONCRETO
COLOCACIN DE CONCRETO PARA POSTES 5.0d 22-Nov-11
26-Nov-11
03:00 PM03:005.0d
PM 0% 29.0d COLOCACIN DE CONCRETO PARA POSTES
1.3.4.2.EST ESTRUCTURAS 15.5d 18-Nov-11
10-Dec-11
12:00 PM05:00
15.5d
PM 0% 20.0d 10-Dec-11 05:00 PM, 1.3.4.2.EST ESTRUCTURAS
HABILITACION Y FABRICACION DE POSTES 9.0d 18-Nov-11
26-Nov-11
12:00 PM03:009.0d
PM 0% 34.0d HABILITACION Y FABRICACION DE POSTES
INSTALACION Y MONTAJE DE POSTES 5.0d 26-Nov-11
01-Dec-11
03:00 PM03:005.0d
PM 0% 29.0d INSTALACION Y MONTAJE DE POSTES
HABILITACION DE PARANTES Y DIAGONALES 6.0d 22-Nov-11
26-Nov-11
06:00 AM03:006.0d
PM 0% 34.0d HABILITACION DE PARANTES Y DIAGONALES
INSTALACION DE MALLAS DE SEGURIDAD 3.0d 01-Dec-11
05-Dec-11
03:00 PM08:003.0d
AM 0% 29.0d INSTALACION DE MALLAS DE SEGURIDAD
INSTALACION DE ALAMBRE DE PUAS 3.0d 05-Dec-11
07-Dec-11
08:00 AM12:003.0d
PM 0% 29.0d INSTALACION DE ALAMBRE DE PUAS
HABILITACION Y MONTAJE DE PORTONES 3.0d 07-Dec-11
10-Dec-11
12:00 PM05:003.0d
PM 0% 29.0d HABILITACION Y MONTAJE DE PORTON ES
1.3.4.2.ELE ELECTRICAS 0.8d 09-Dec-11
10-Dec-11
10:00 AM05:000.8d
PM 0% 20.0d 10-Dec-11 05:00 PM, 1.3.4.2.ELE ELECTRICAS
ATERRAMIENTO DE CERCO PERIMETRAL 2.0d 09-Dec-11
10-Dec-11
10:00 AM05:002.0d
PM 0% 29.0d ATERRAMIENTO DE CERCO PERIMETRAL
1.3.4.3 GESTION DE CIERRE SISTEMA 5.0d 12-Dec-11
17-Dec-11
06:00 AM12:005.0d
PM 0% 19.8d 17-Dec-11 12:00 PM, 1.3.4.3 GESTION DE CIERRE SISTEMA
CAMINATAS DE CONSTRUCCION 3.0d 12-Dec-11
14-Dec-11
06:00 AM10:003.0d
AM 0% 29.0d CAMINATAS DE CONSTRUCCION
CAMINATAS NARANJA 2.0d 16-Dec-11
17-Dec-11
06:00 AM12:002.0d
PM 0% 29.0d CAMINATAS NARANJA
1.3.5 CIERRE DE OBRA GENERAL 0.0d 13-Jan-12
13-Jan-12
03:00 PM03:000.0d
PM 0% 0.0d 13-Jan-12 03:00 PM, 1.3.5 CIERRE DE O
A23290
ENTREGA DE OBRA A MYSRL 0.0d 13-Jan-12 03:000.0d
PM 0% 0.0d ENTREGA DE OBRA A MYSR L

Actual Work Critical Remaining Work % Complete Page 4 of 4 TASK filter: All Activities

Remaining Work Milestone Summary (c) Primavera Systems, Inc.